status of wp5- the h ydrogen i ncident and a ccident d atabase update march 2005
DESCRIPTION
Status of WP5- The H ydrogen I ncident and A ccident D atabase Update March 2005. Christian Kirchsteiger, EC – DG JRC [email protected]. Ana Vetere, EC – DG JRC [email protected]. Espen Funnemark, DNV (N) [email protected]. DJPA months 13-30. Objectives - overall: - PowerPoint PPT PresentationTRANSCRIPT
-
Status of WP5- The Hydrogen Incident and Accident Database
Update March 2005
Christian Kirchsteiger, EC DG [email protected] Espen Funnemark, DNV (N)[email protected] Vetere, EC DG [email protected]
-
Objectives - overall:H2 safety: integrate/share experience and knowledgecommon understanding of hydrogen safety and risktool for safety and risk assessmentkeep the industry updated with recent H2 accidents/incidentscommon methodology/format for data collection and storageObjectives months 13-30:Software developmentPopulation of HIAD with dataEfforts:Budget: 13.2 MMFurther specification and programming: JRC & DNVExcel tool for data collection (HIAD_Template_4Users.xls): December 05
DJPA months 13-30
-
HIAD Process
-
Web Application / User Interface
-
Screen Layout
-
Registration /Subscription
-
Global View of Records
-
Technical Solution
-
Data input update (1)COMPLETED HIAD EXCEL FORMS
Thomas Jordan, FZK: 20 events Release: 11 Fire: 6 Explosion: 3
Efthymata Papanikolaou, NCSRD/Demokritos: 8 events Fire: 4 Explosion: 4
Karl Verfondern , Research Center Juelich: 4 events Fire: 1 Fire&Explosion: 3
Nicolas Dechy, INERIS: 1 event Explosion: 1
-
Data input update (2)MISCELLANEOUS ACCIDENT INFORMATION
EIGA: 135 events Air Liquide database: 125 events (in French) ARIA (Barpi) database: 119 events (in French) University of Pisa report : 3 events on H2 transport (in Italian) INASMET: 4 events http://www.fireworld.com: 35 events DNV internal database: 8 events
.MARS? .CUTE? .FACTS? .....DoE?
-
SuccessContributions to Integration
Produce a tool to be shared by the partners in the Consortium Invitation to a joint data collection effort Initiated discussions on how to report to HIAD HIAD on the agenda; common meeting place for risk data
Co-operation with external entities/partners
-
Deviations from DJPA/DoW planning:Software delivery and launching delayed to June 15 2006 (D59)HIAD w/data delayed to October 1 2006Else: None p.t.
Foreseen difficulties:Change of JRC programming staff
Limited attention on collecting data on Excel format More attractive and intuitive tool; update based on feedback Marketing
Status vs Planning
-
WP5 Outlook24 27 31 33 36 39 42Next Steps (DJPA_25-42)HIAD operation, management & supportHIAD integration / internal marketingHIAD on HySafe Website advertisingHIAD external marketingHIAD newslettersHIAD WorkshopHIAD w/data15/6 1/10 1/12WP5.