status of tasks in the program of works
DESCRIPTION
The whole of the lightning protection system installation is to be visually inspected to ensure proper joints of copper tapes with accessories and earth electrodes in the earth pitsTRANSCRIPT
Sheet 1
Week Report Of Activities in The Program Of WorksProject Hotel-Ambassador- G&I 5* Hotel
Ground, Technical & Mezzanine Floors
Issue11-10-2010To15-10-2010
Trade Tasks Status % Complete
Civil WorksGF and MF
Shop DraiwingsMasonry & Problem solving (Wall Prenetration ... Etc)POP ( Meeting Room ,Adm offices & Toilets – GF)Tiling on Floor ( GF & MF BOH)False Ceiling Structure ( GF & MF BOH)Tiling on To FinishFalse ceiling Panel ( GF FOH )Laundry Water proof,pads &Tile on WallECG connection and electrical room ( Milestone)Mechanical Rooms ( Milestone)Voids Inpections
onon
Not startNot startNot start
onStopStop0nonon
Fire/Chilled Water
Maine Line FinishingFM2000 Position & Fire Fitghting SystemFuel Supply piping From pumps room to daily TanksPipe insulation
onNot Start
onon
VAC Plenum Installation & flexible PipesDucts installation ( GF Kitchen Area & BOH to Finish )Fixing & Connection MufflersIron Ducts (Tech Fl)Air Handling Units Drainage &Signals InstallationFan coil Final To Fix
ononononon
Finished
Electrical Caling (Power, Data, Alarms , AV...Etc ( Ballroom)Finish Electrical Cabling above Ceiling
Not Starton
Carpentry Wood Subframe ( Restaurant ) Not Start
Aluminium Work
Aluminium Curtain Wall on
Sheet 2
Week Report Of Activities in The Program Of WorksProject Hotel-Ambassador- G&I 5* Hotel
1st Typical Floor
Issue11-10-2010To15-10-2010
Trade Tasks Status Note
CorridorVoid Closure InspectionCompletion of missing items after 1st InspectionDar Void Closure InspectionFalse Ceilling Panels in Corridors
onononon
BedroomsSecond Fix ElectricalFinal Fix smoke detectorFinish Tile in Rooms
ononon
Bedroom Entrance
Install Wardrobe-TechmanInstall frame and architraveDAR inspectionVOID inspectionFirst Coat paint
onononon
Toilets VOID inspectionDAR inspectionFalse Ceilling PanelsInstall Architrave and Door - Techman
onononon
2nd typical FloorTrade Tasks Status Note
CorridorVoid Closure InspectionCompletion of missing items after 1st InspectionDar Void Closure Inspection
ononon
BedroomsSecond Fix ElectricalFinal Fix smoke detectorFinish Tile in Rooms
ononon
Bedroom Entrance
Install Wardrobe-TechmanInstall frame and architraveDAR inspectionVOID inspectionFirst Coat paint
ononononon
Toilets VOID inspectionDAR inspectionInstall Architrave and Door - Techman
ononon
3rd Typical Floor
Sheet 3
Trade Tasks Status Note
CorridorVoid Closure InspectionCompletion of missing items after 1st InspectionDar Void Closure Inspection
ononon
BedroomsSecond Fix Electrical2nd Fix smoke detectorFinish Tile in Rooms
ononon
Bedroom Entrance
Install Wardrobe-TechmanInstall frame and architraveDAR inspectionVOID inspectionFirst Coat paintBMS
Not StartNot Start
onon
Not Starton
Toilets VOID inspectionDAR inspectionInstall Architrave and Door - Techman
ononon
4th Typical Floor
Trade Tasks Status Note
CorridorVoid Closure InspectionCompletion of missing items after 1st InspectionDar Void Closure Inspection
ononon
BedroomsWall adjustmentsFirst Coat PaintFinish Tile in Rooms
onNot Start
Stop
Bedroom Entrance
Wall penetrationsDAR inspectionVOID inspectionBMS
onononon
Toilets Masonry- Walls problems solvingPlaster -Finishing EMP worksTiling & Install marble tresholdFalse Ceiling Structure
ononon
Stop
5th typical Floor
Sheet 4
Trade Tasks Status Note
CorridorVoid Closure InspectionCompletion of missing items after 1st InspectionDar Void Closure Inspection
ononon
BedroomsWall adjustmentsFirst Coat PaintFinish Tile in Rooms
Not StartStop
Bedroom Entrance
Wall penetrationsDAR inspectionVOID inspectionBMS
Stopononon
Toilets Masonry- Walls problems solvingPlaster -Finishing EMP worksTiling & Install marble tresholdFalse Ceiling Structure
ononon
Not Stsrt
Executive Floor
Trade Tasks Status Note
CorridorFinishing small shaftCable TraysFire Pipe Lines
Not starton
Stop
BedroomsWall adjustmentsTilingMasonry- plaster
onNot start
on
Bedroom Entrance
TilesAir DuctsFire branch Lines
Not startNot startNot start
Toilets Masonry- Walls problems solving on
Executive Lounge
Masonry- Walls problems solving 0n
Presidential Floor
Sheet 5Trade Tasks Status Note
CorridorAir DuctsCable TraysFire Pipe LinesPlaster in Corridors
Stopon
Stop
BedroomsEntrance
Fire branch LinesChiller supply & return –Pipe lineAir Ducts
Not startNot start
Stop
Bedroom Masonry - wallsMasonry- plaster
onon
Toilets Masonry- Walls problems solving on
Presidential Rooms
Masonry- Walls problems solving on
Roof FloorTrade Tasks Status Note
Civil WorksLouvers installationsAlucobondMain signageScreedingWater proofingWall penetrationsOffice area mechanical room buildingConcrete wall of stair cases opening
Not startNot start
StopStopon
StopStop
EMPAir handling units ducts connectionInstruments installationIron ducts installationAir handling signals installationPumps power supplyPumps power supplyVent pipes terminationChillers test and start upOffices air handling unit ducts connectionStair case pressurization ducts connectionPipe insulationAir handling power supplyRoof power connection
Not startNot startNot start
ononon
Not startNot startNot start
ononon
External WorksTrade Tasks Status Note
All Activities On Progress