status of tasks in the program of works

7
Sheet 1 Week Report Of Activities in The Program Of Works Project Hotel-Ambassador- G&I 5* Hotel Ground, Technical & Mezzanine Floors Issue 11-10-2010 To 15-10-2010 Trade Tasks Status % Complete Civil Works GF and MF Shop Draiwings Masonry & Problem solving (Wall Prenetration ... Etc) POP ( Meeting Room ,Adm offices & Toilets – GF) Tiling on Floor ( GF & MF BOH) False Ceiling Structure ( GF & MF BOH) Tiling on To Finish False ceiling Panel ( GF FOH ) Laundry Water proof,pads &Tile on Wall ECG connection and electrical room ( Milestone) Mechanical Rooms ( Milestone) Voids Inpections on on Not start Not start Not start on Stop Stop 0n on on Fire/ Chilled Water Maine Line Finishing FM2000 Position & Fire Fitghting System Fuel Supply piping From pumps room to daily Tanks Pipe insulation on Not Start on on VAC Plenum Installation & flexible Pipes Ducts installation ( GF Kitchen Area & BOH to Finish ) Fixing & Connection Mufflers Iron Ducts (Tech Fl) Air Handling Units Drainage &Signals Installation Fan coil Final To Fix on on on on on Finishe d Electrical Caling (Power, Data, Alarms , AV...Etc ( Ballroom) Finish Electrical Cabling above Ceiling Not Start on

Upload: pisourie25

Post on 12-Jul-2016

3 views

Category:

Documents


0 download

DESCRIPTION

The whole of the lightning protection system installation is to be visually inspected to ensure proper joints of copper tapes with accessories and earth electrodes in the earth pits

TRANSCRIPT

Page 1: Status of Tasks in the Program of Works

Sheet 1

Week Report Of Activities in The Program Of WorksProject Hotel-Ambassador- G&I 5* Hotel

Ground, Technical & Mezzanine Floors

Issue11-10-2010To15-10-2010

Trade Tasks Status % Complete

Civil WorksGF and MF

Shop DraiwingsMasonry & Problem solving (Wall Prenetration ... Etc)POP ( Meeting Room ,Adm offices & Toilets – GF)Tiling on Floor ( GF & MF BOH)False Ceiling Structure ( GF & MF BOH)Tiling on To FinishFalse ceiling Panel ( GF FOH )Laundry Water proof,pads &Tile on WallECG connection and electrical room ( Milestone)Mechanical Rooms ( Milestone)Voids Inpections

onon

Not startNot startNot start

onStopStop0nonon

Fire/Chilled Water

Maine Line FinishingFM2000 Position & Fire Fitghting SystemFuel Supply piping From pumps room to daily TanksPipe insulation

onNot Start

onon

VAC Plenum Installation & flexible PipesDucts installation ( GF Kitchen Area & BOH to Finish )Fixing & Connection MufflersIron Ducts (Tech Fl)Air Handling Units Drainage &Signals InstallationFan coil Final To Fix

ononononon

Finished

Electrical Caling (Power, Data, Alarms , AV...Etc ( Ballroom)Finish Electrical Cabling above Ceiling

Not Starton

Carpentry Wood Subframe ( Restaurant ) Not Start

Aluminium Work

Aluminium Curtain Wall on

Page 2: Status of Tasks in the Program of Works

Sheet 2

Week Report Of Activities in The Program Of WorksProject Hotel-Ambassador- G&I 5* Hotel

1st Typical Floor

Issue11-10-2010To15-10-2010

Trade Tasks Status Note

CorridorVoid Closure InspectionCompletion of missing items after 1st InspectionDar Void Closure InspectionFalse Ceilling Panels in Corridors

onononon

BedroomsSecond Fix ElectricalFinal Fix smoke detectorFinish Tile in Rooms

ononon

Bedroom Entrance

Install Wardrobe-TechmanInstall frame and architraveDAR inspectionVOID inspectionFirst Coat paint

onononon

Toilets VOID inspectionDAR inspectionFalse Ceilling PanelsInstall Architrave and Door - Techman

onononon

2nd typical FloorTrade Tasks Status Note

CorridorVoid Closure InspectionCompletion of missing items after 1st InspectionDar Void Closure Inspection

ononon

BedroomsSecond Fix ElectricalFinal Fix smoke detectorFinish Tile in Rooms

ononon

Bedroom Entrance

Install Wardrobe-TechmanInstall frame and architraveDAR inspectionVOID inspectionFirst Coat paint

ononononon

Toilets VOID inspectionDAR inspectionInstall Architrave and Door - Techman

ononon

3rd Typical Floor

Page 3: Status of Tasks in the Program of Works

Sheet 3

Trade Tasks Status Note

CorridorVoid Closure InspectionCompletion of missing items after 1st InspectionDar Void Closure Inspection

ononon

BedroomsSecond Fix Electrical2nd Fix smoke detectorFinish Tile in Rooms

ononon

Bedroom Entrance

Install Wardrobe-TechmanInstall frame and architraveDAR inspectionVOID inspectionFirst Coat paintBMS

Not StartNot Start

onon

Not Starton

Toilets VOID inspectionDAR inspectionInstall Architrave and Door - Techman

ononon

4th Typical Floor

Trade Tasks Status Note

CorridorVoid Closure InspectionCompletion of missing items after 1st InspectionDar Void Closure Inspection

ononon

BedroomsWall adjustmentsFirst Coat PaintFinish Tile in Rooms

onNot Start

Stop

Bedroom Entrance

Wall penetrationsDAR inspectionVOID inspectionBMS

onononon

Toilets Masonry- Walls problems solvingPlaster -Finishing EMP worksTiling & Install marble tresholdFalse Ceiling Structure

ononon

Stop

5th typical Floor

Page 4: Status of Tasks in the Program of Works

Sheet 4

Trade Tasks Status Note

CorridorVoid Closure InspectionCompletion of missing items after 1st InspectionDar Void Closure Inspection

ononon

BedroomsWall adjustmentsFirst Coat PaintFinish Tile in Rooms

Not StartStop

Bedroom Entrance

Wall penetrationsDAR inspectionVOID inspectionBMS

Stopononon

Toilets Masonry- Walls problems solvingPlaster -Finishing EMP worksTiling & Install marble tresholdFalse Ceiling Structure

ononon

Not Stsrt

Executive Floor

Trade Tasks Status Note

CorridorFinishing small shaftCable TraysFire Pipe Lines

Not starton

Stop

BedroomsWall adjustmentsTilingMasonry- plaster

onNot start

on

Bedroom Entrance

TilesAir DuctsFire branch Lines

Not startNot startNot start

Toilets Masonry- Walls problems solving on

Executive Lounge

Masonry- Walls problems solving 0n

Presidential Floor

Page 5: Status of Tasks in the Program of Works

Sheet 5Trade Tasks Status Note

CorridorAir DuctsCable TraysFire Pipe LinesPlaster in Corridors

Stopon

Stop

BedroomsEntrance

Fire branch LinesChiller supply & return –Pipe lineAir Ducts

Not startNot start

Stop

Bedroom Masonry - wallsMasonry- plaster

onon

Toilets Masonry- Walls problems solving on

Presidential Rooms

Masonry- Walls problems solving on

Roof FloorTrade Tasks Status Note

Civil WorksLouvers installationsAlucobondMain signageScreedingWater proofingWall penetrationsOffice area mechanical room buildingConcrete wall of stair cases opening

Not startNot start

StopStopon

StopStop

EMPAir handling units ducts connectionInstruments installationIron ducts installationAir handling signals installationPumps power supplyPumps power supplyVent pipes terminationChillers test and start upOffices air handling unit ducts connectionStair case pressurization ducts connectionPipe insulationAir handling power supplyRoof power connection

Not startNot startNot start

ononon

Not startNot startNot start

ononon

External WorksTrade Tasks Status Note

All Activities On Progress