status of atf/atf2 and machine schedule in this fall impact of the earthquake recovery status,...
Post on 20-Dec-2015
213 views
TRANSCRIPT
Status of ATF/ATF2 and machine schedule in this fall
• Impact of the earthquake• Recovery status, alignment• Schedule in this fall
N. Terunuma, KEK
Recovery History for Test BeamMar11 14 21 28
Apr4 11 18 25
May2 9 16 23 30
Jun6 13 20 27
Jul4
KEK MW 1.7 2 / 5 MW (day/night) 24 MW 20
Power line recovery
Rough Alignment (LINAC)
RF
Blackout ½ power
Vacuum
ATF2 Shield
Cooling Water
(BT) (DR)
Su
mm
er S
hu
tdo
wn
Test BeamKEKRequested Standbyat Home Power
Distri-bution
ATF Shield
Rad
iati
on
Saf
ety
ATF LINACQM2L table was backed to the original.Chambers were exchanged.
QD10L bellows was exchanged.
All were repaired in March!
Beam TransportFallen Pb blocks were cleared.Ceramic of the CT monitor and a bellows were exchanged.
Repaired in April.
ATF2 beam line
Repositioning Dust on the IP-BSM Optics
Dust on the FD mover
Magnet Mover
Outside of ATF2 end
10 cm slide
A test beam passes all beamline
2011/5/25Injector
2011/5/26LINAC
5/31DR 1st turn
Single bunch, 0.78 Hz, 0.3 x 1010 e/bunch DR&ATF2
5/27 BT end
6/2DR storage
6/2 MS1X6/3 MS1FF6/3 MS2FF
6/3 MSPIP
2011/06/03 N.Terunuma
Stored beam in DR (x1010 e/bunch)A stored beam was delivered to the dump of ATF2.No critical damage on the accelerator was found.
6/1 6/3 6/8 6/10 6/13 6/17 6/24 6/30
0.5x1010
1.0x1010
3 trains
XSR
read
y
Compton2-mirror
FON
T
3 trains
Cavity BPMsFFTB moverHAPS
Freq. A
djust
V-emittance
(XSR
) ~30pm
DR rough alignment for checkout was continued in daytime.
Insp
ectio
n of
the
radi
ation
saf
ety
Status of AlignmentAll in the ATF building was shaken (10 cm or more?) by Great East Japan Earthquake.
Linac/BT • Lift up the downstream section close to the BT/DR level. It will reduce the
workload of DR tuning.
DR• ¾ of DR has been re-aligned.
East arc will be done in this week.• Expanded North-South about 1.5
mm Rematch the optics
ATF2: Just surveyed. Waiting the alignment work in October.
Alignment: LINAC/BT levelcomments
Measured after earthquake
Re-aligned LINAC TableRe-aligned Cavity
LINAC’s drop to end and jump to BT had been known since the DR startup. It might be caused by the DR construction after LINAC alignment. It brought a troublesome tuning to us. We corrected these by using a power-recovering long shutdown after the earthquake.
BT was re-aligned but plots were not yet prepared.
DR displacement (Enlarged image)
after earthquakeRough alignment in May
• 1.5 mm wider(N-S) than the original design. When??
• New design was defined as wider but same circumference.
Alignment: DR levelaligned in June, aligned in summer
Verti
cal (
mm
)
-0.5
0.0
-1.0
0.5
North West Arc South
East Arc is under realignment.
Target: |x|< 90 um
Alignment: DR
Hor
izont
al (m
m)
-0.5
0.0
1.0
0.5
Long
itudi
nal (
mm
)
-0.5
0.0
-1.0
1.0
0.5
aligned in summerOthers aligned in May
North West Arc
South East Arc is under realignment.
Target: |x|< 90 um
Waiting for alignment: ATF2
Floor of ATF2 sank about 1.5 mm.
Level of the EXT-ATF2 magnets
EXT FF
Verti
cal (
mm
)
QD0 mover is OFF
QF1 mover is ON
FFTB movers are “zero” position.
Target: +-0.1 mm
-1.0
0.0
-2.0
-3.0
ATF2 Q-magnet Setup
Concrete Base Stand (KEK)
FFTB mover
(SLAC)
QBPM
(Cavity BPM)
(KEK,PAL)
Q magnet (KEK,SLAC,IHEP)
QBPM electronics
(SLAC)
(2008/6)
Waiting for alignment: ATF2
Horizontal
EXT FF
Target: +-0.1 mm
-1.0
0.0
-2.0
-3.0
0.0
-1.0
-2.0
-3.0
-4.0
1.0(mm)(mm) Longitudinal
EXT FF
Datum on floor
We are checking the definition of the datum on the floor used at the ATF2 construction. Offset?
Waiting for alignment: ATF2
Roll of magnets (mrad)1.0
- 1.0
0
EXT
Target: +-0.1 mrad
Pitch (mrad)1.0
- 1.0FF
Schedule (draft for discussion)Sep.26
Oct.3 10 17 24 31
Nov.7 14 21 28
Dec.5 12 19 26
Beam
DR
Checkout of beam instruments
EXT-FF
Low emittance,Compton and Others
ATFR&D
ATF2R&D
Alignment
DR survey
ATF2 &TBmeeting
Recovery of 10 pm (DR)
Recovery of 300 nm Goal-1 and others
extraction
survey survey
2012 Schedule (draft for discussion)2012Jan.2 9 16 23 30
Feb6 13 20 27
Mar.5 12 19 26
Apr2 9 16 23 30
May7 14 21 28
Jun4 11 18 25
New
IP
-BP
M i
nst
alla
tio
n a
t IP
Low emittance,Compton and Others
Goal-1? and others Goal-2? and others
Su
mm
er S
hu
tdo
wn
GD
E m
eeti
ng
?JP
S m
eeti
ng
Alignment: DRAfter earthquake, aligned in June, aligned in summer
- 2.0 mm
+2.0 mm
Horizontal Longitudinal
all
B
Q
Sx
- 2.0 mm
+2.0 mm
Hardware updates 1/?Pol e+ Compton: Upgrade of the 2-mirror system to 4-mirror system is underway. (Hiroshima, KEK)• Old 2-mirror system in DR was
replaced with a dummy chamber in August.
• New 4-mirror system is under testing beside the beamline.
• Installation will be done in the maintenance week after the full checkout of the optical system. It will be in October or later.