statestreet - library mall - pim #1 042313...public information meeting #1 april 23, 2013 april 23,...
TRANSCRIPT
Public Information Meeting #1gApril 23, 2013
April 23, 2013 1State Street 700/800 Blocks & Library Mall
Project Sitej
April 23, 2013 2State Street 700/800 Blocks & Library Mall
Project InformationjProject Website: cityofmadison.com/engineering/statest
Facebook: https://www.facebook.com/CityofMadison
Ci f M di Wi i G
Twitter: @cityofmadison
Project Email Updates:
City of Madison, Wisconsin Government
Project Email Updates: my.cityofmadison.com/subscriptions Chris Petykowski, P.E., Engineering
Bill Fruhling, AICP, [email protected]
G B PLA FASLA UW M diGary Brown, PLA, FASLA, UW-Madison [email protected]
Jason DiPiazza, P.E., MSA
April 23, 2013 3State Street 700/800 Blocks & Library Mall
Meeting Agenda• Project Background
– History of Library MallHi f S S
g g
– History of State Street• Breakout Session - Input• Wrap-up & Next StepsWrap up & Next Steps
April 23, 2013 4State Street 700/800 Blocks & Library Mall
Meeting Agenda• Project Background
– History of Library MallHi f S S
g g
– History of State Street• Breakout Session - Input• Wrap-up & Next StepsWrap up & Next Steps
April 23, 2013 5State Street 700/800 Blocks & Library Mall
Project Team IntroductionsjCity of Madison
Engineering & Planning
UW-MadisonFacilities Planning &
State Street Design Facilities Planning &
Management
MSA P f i l S i
Oversight Committee
MSA Professional Services
Ken Saiki Design SmithgroupJJR Jill Sebastian
ZebradogStudio KJWW
April 23, 2013 6State Street 700/800 Blocks & Library Mall
Project Schedulej
Final DesignConstruction Documents
and Bidding ProcessStakeholder
InputPreliminary Design Construction
Jan Feb Mar Apr May Jun Jul Aug Sep
2014
g
Sep Oct Nov Dec
2013
Jun
p
Jul AugApr May
April 23, 2013 7State Street 700/800 Blocks & Library Mall
Stakeholders
Mayor & AlderpersonsWisconsin FoodWisconsin
Historical Society
Food Vendors
State Street 700-800 Block & Library Mall
City Agencies & Emergency
General Public & Library Mall & g cy
Responders
Businesses & Business Associations UW Staff &
Students
Religious & Campus Centers
April 23, 2013 8State Street 700/800 Blocks & Library Mall
Students
Meeting Agenda• Project Background
– History of Library Mall
Hi f S S
g g
– History of State Street• Breakout Session - Input• Wrap-up & Next StepsWrap up & Next Steps
April 23, 2013 9State Street 700/800 Blocks & Library Mall
Historical Timeline• Lower Campus Added (1891)
– Uses included:• Athletic• Social gatheringg g• Political
• Historical Society Opens (1900)– Library Mall concept introduced and
included:• Gravel, diagonal paths
1850 1950 2013
, g p• A large circular, gravel space in the center• Controversy over Library Mall design
begins
April 23, 2013 10State Street 700/800 Blocks & Library Mall
1900 2000 2016
Historical Timeline• Simonds Campus Master
Plan Introduced (1906)– Simonds’ Arched Roadway
Installed in front of State Historical Society (Early 1900’s)
– Preserved open space including Library Mall
• Hagenah Plan for Murray Mall and Lower Campus Introduced (1945)
– Plan anchored Library Mall
1850 1950 2013
Plan anchored Library Mall with Historical Society and Memorial Library
April 23, 2013 11State Street 700/800 Blocks & Library Mall
1900 2000 2016
Historical Timeline• Quonset Huts Installed (1946)
– Accommodated increased post-war population
– Eliminated athletic use of d c s oLibrary Mall
• Memorial Library Opens (1953)– Controversy continues as
plans for Library Mall move f dforward
1850 1950 2013
April 23, 2013 12State Street 700/800 Blocks & Library Mall
1900 2000 2016
Historical Timeline• Current Library Mall Design
installed (1955), followed by Hagenah Memorial Fountain and Vegetation (1958)V g ( )
– Incorporated design components from previous plans dating back to 1900
• 700-800 Blocks of State Street are Closed for Trial Testing (1971-72), followed by Permanent Closure and Pedestrian Mall installation in
1850 1950 2013
and Pedestrian Mall installation in 1975
April 23, 2013 13State Street 700/800 Blocks & Library Mall
1900 2000 2016
Historical Timeline• East Campus Mall
Master Plan is updated (1996)
– Proposed removal ofProposed removal of Hagenah Fountain
• East Campus Mall (formerly Murray Mall) Master Plan is updated (2004)(2004)
– Hagenah Fountain is retained
– Construction of the first piece starts
1850 1950 2013
p(Regent to Dayton)
April 23, 2013 14State Street 700/800 Blocks & Library Mall
1900 2000 2016
East Campus Mallp
• University Square (2008)
• University Club/Chazen (2012)
• Gordon Commons (2013)1850 1950 2013
• Regent to Dayton (2004)
April 23, 2013 15State Street 700/800 Blocks & Library Mall
1900 2000 2016
East Campus Mallp
• Memorial Union & Alumni Park (2015)
1850 1950 2013• Library Mall (?)
April 23, 2013 16State Street 700/800 Blocks & Library Mall
1900 2000 2016
Meeting Agenda• Project Background
– History of Library MallHi f S S
g g
– History of State Street
• Breakout Session - Input• Wrap-up & Next StepsWrap up & Next Steps
April 23, 2013 17State Street 700/800 Blocks & Library Mall
Historical Timeline
J h N l ’ 1911 Ci Pl 200 Bl k 1913D Pl f 1836 John Nolen’s 1911 City Plan 200 Block 1913Doty Plat of 1836
1850 1950 2013
400 Block 1929 200-300 Blocks 1935
April 23, 2013 18State Street 700/800 Blocks & Library Mall1900 2000 2016
Historical Timeline
200 Block 1939
1850 1950 2013
800 Block 1940s200 Block 1950s
April 23, 2013 19State Street 700/800 Blocks & Library Mall1900 2000 2016
Historical Timeline
600 Block 1960s
1850 1950 2013
200 Block 1970s 800 Block 1960s
April 23, 2013 20State Street 700/800 Blocks & Library Mall1900 2000 2016
Historical TimelineThe 700-800 Block Traffic Experiment, 1971
1850 1950 2013
April 23, 2013 21State Street 700/800 Blocks & Library Mall1900 2000 2016
Historical Timeline
1850 1950 2013
April 23, 2013 22State Street 700/800 Blocks & Library Mall1900 2000 2016
Historical TimelineDesign Principles:• Flexibility• Timelessness• Long Lasting/Easy to Maintain
S i bili• Sustainability
Strategic Plan 1999 Design Plan 2001
1850 1950 2013
200 Block 1980/90s
April 23, 2013 23State Street 700/800 Blocks & Library Mall1900 2000 2016
Historical TimelineCurrent Conditions
1850 1950 2013
April 23, 2013 24State Street 700/800 Blocks & Library Mall1900 2000 2016
Meeting Agenda• Project Background
– History of Library MallHi f S S
g g
– History of State Street• Breakout Session - Input
• Wrap-up & Next StepsWrap up & Next Steps
April 23, 2013 25State Street 700/800 Blocks & Library Mall
What Do We Want To Learn?
April 23, 2013 26State Street 700/800 Blocks & Library Mall
What Do We Want To Learn?
Consider the current 700-800 blocks of State Street.
April 23, 2013 27State Street 700/800 Blocks & Library Mall
What Do We Want To Learn?
Consider the current 700-800 blocks of State Street. • What aspects of the streetscape work well in your estimation?What aspects of the streetscape work well in your estimation?
April 23, 2013 28State Street 700/800 Blocks & Library Mall
What Do We Want To Learn?
Consider the current 700-800 blocks of State Street. • What aspects of the streetscape work well in your estimation?What aspects of the streetscape work well in your estimation?• What are the problems?
April 23, 2013 29State Street 700/800 Blocks & Library Mall
What Do We Want To Learn?
Consider the current 700-800 blocks of State Street. • What aspects of the streetscape work well in your estimation?What aspects of the streetscape work well in your estimation?• What are the problems? • What do you feel is needed as far as a new design?
April 23, 2013 30State Street 700/800 Blocks & Library Mall
700 Block State Street
April 23, 2013 31State Street 700/800 Blocks & Library Mall
700 Block State Street
April 23, 2013 32State Street 700/800 Blocks & Library Mall
700 Block State Street - Lighting At Night
April 23, 2013 33State Street 700/800 Blocks & Library Mall
700 Block State Street
April 23, 2013 34State Street 700/800 Blocks & Library Mall
700-800 Blocks State Street - Stage
April 23, 2013 35State Street 700/800 Blocks & Library Mall
700-800 Blocks State Street - Stage
April 23, 2013 36State Street 700/800 Blocks & Library Mall
700-800 Blocks State Street- Speakers Podium
April 23, 2013 37State Street 700/800 Blocks & Library Mall
700-800 Blocks State Street - Furniture
April 23, 2013 38State Street 700/800 Blocks & Library Mall
700-800 Blocks State Street - Furniture
April 23, 2013 39State Street 700/800 Blocks & Library Mall
800 Block State Street
April 23, 2013 40State Street 700/800 Blocks & Library Mall
800 Block State Street - 3 Forms
April 23, 2013 41State Street 700/800 Blocks & Library Mall
800 Block State Street - Kiosks
April 23, 2013 42State Street 700/800 Blocks & Library Mall
800 Block State Street - Trees
April 23, 2013 43State Street 700/800 Blocks & Library Mall
800 Block State Street - From Bascom Hill
April 23, 2013 44State Street 700/800 Blocks & Library Mall
Circulation
April 23, 2013 45State Street 700/800 Blocks & Library Mall
What Do We Want To Learn?
• Consider the current 700-800 blocks of State Street. • What aspects of the streetscape work well in your estimation?What aspects of the streetscape work well in your estimation?• What are the problems? • What do you feel is needed as far as a new design?
What changes, if any, could you envision for Library Mall?
April 23, 2013 46State Street 700/800 Blocks & Library Mall
Library Mall And Future Site Of Alumni Park
April 23, 2013 47State Street 700/800 Blocks & Library Mall
Library Mall - Wisconsin Historical Societyy
April 23, 2013 48State Street 700/800 Blocks & Library Mall
Memorial Library - Class Of 1932 Flagpole
April 23, 2013 49State Street 700/800 Blocks & Library Mall
Library Mall - UW Memorial Union
April 23, 2013 50State Street 700/800 Blocks & Library Mall
Library Mall
April 23, 2013 51State Street 700/800 Blocks & Library Mall
Library Mall
April 23, 2013 52State Street 700/800 Blocks & Library Mall
Library Mall
April 23, 2013 53State Street 700/800 Blocks & Library Mall
Library Mall - William Hagenah Fountain
April 23, 2013 54State Street 700/800 Blocks & Library Mall
Library Mall - William Hagenah Fountain
April 23, 2013 55State Street 700/800 Blocks & Library Mall
LIBRARY MALL - CLASS OF 1923 CLOCK
April 23, 2013 56State Street 700/800 Blocks & Library Mall
What Do We Want To Learn?
• Consider the current 700-800 blocks of State Street. • What aspects of the streetscape work well in your estimation?What aspects of the streetscape work well in your estimation?• What are the problems? • What do you feel is needed as far as a new design?
What changes, if any, could you envision for Library Mall?
According to the Cultural Landscape Study, the relationship between Bascom Mall the Capitol and the State Streetbetween Bascom Mall, the Capitol, and the State Street Pedestrian Mall/Library Mall is unclear.
April 23, 2013 57State Street 700/800 Blocks & Library Mall
What Do We Want To Learn?
• Consider the current 700-800 blocks of State Street. • What aspects of the streetscape work well in your estimation?What aspects of the streetscape work well in your estimation?• What are the problems? • What do you feel is needed as far as a new design?
What changes, if any, could you envision for Library Mall?
According to the Cultural Landscape Study, the relationship between Bascom Mall the Capitol and the State Streetbetween Bascom Mall, the Capitol, and the State Street Pedestrian Mall/Library Mall is unclear.
• What are your thoughts and ideas about making connections?
April 23, 2013 58State Street 700/800 Blocks & Library Mall
Project Site
April 23, 2013 59State Street 700/800 Blocks & Library Mall
Base Of Bascom Hill - Looking Toward Capital
April 23, 2013 60State Street 700/800 Blocks & Library Mall
State Street - Looking Toward Campus
April 23, 2013 61State Street 700/800 Blocks & Library Mall
Library & State Street Malls – Boundary
April 23, 2013 62State Street 700/800 Blocks & Library Mall
Intersection East Campus, Library And State Street Mallsp y
April 23, 2013 63State Street 700/800 Blocks & Library Mall
Intersection East Campus, Library And State Street Mallsp y
April 23, 2013 64State Street 700/800 Blocks & Library Mall
State Street Mall - Two Views - 180 Degrees
April 23, 2013 65State Street 700/800 Blocks & Library Mall
What Do We Want To Learn?• Consider the 700 & 800 Blocks of State Street :
– What aspects work well? What are the problems?– What are the problems?
– What do you feel is needed as far as a new design?
• Consider the Library Mall:• Consider the Library Mall:– What aspects work well? – What are the problems?
Wh t d f l i n d d f r n d i n?– What do you feel is needed as far as a new design?
• According to the Cultural Landscape Study, the relationship between Bascom Mall, the capitol and the State Street Pedestrian Mall/Library Mall is unclear What are yourcapitol, and the State Street Pedestrian Mall/Library Mall is unclear. What are your thoughts and ideas about making connections?
April 23, 2013 66State Street 700/800 Blocks & Library Mall
Meeting Agenda• Project Background
– History of Library MallHi f S S
g g
– History of State Street• Breakout Session - Input
• Wrap-up & Next StepsWrap up & Next Steps
April 23, 2013 67State Street 700/800 Blocks & Library Mall
Wrap Upp p
Regroup in 10 minutesRegroup in 10 minutesg pg p
Summarize comments and ideasSummarize comments and ideasSummarize comments and ideasSummarize comments and ideas
April 23, 2013 68State Street 700/800 Blocks & Library Mall
Meeting Agenda• Project Background
– History of Library MallHi f S S
g g
– History of State Street• Breakout Session - Input• Wrap-up & Next StepsWrap up & Next Steps
April 23, 2013 69State Street 700/800 Blocks & Library Mall
Wrap upp p
Share and Summarize Comments and IdeasShare and Summarize Comments and Ideas
April 23, 2013 70State Street 700/800 Blocks & Library Mall
Next Stepsp• Collect feedback from public and stakeholder meetings.
S f f f h ll b d h• Summary of information from this meeting will be posted on the project website: cityofmadison.com/engineering/statest
• Develop preliminary design concepts – May 2013.
• Public Meeting #2: Share preliminary design concepts – June 2013g p y g p J
April 23, 2013 71State Street 700/800 Blocks & Library Mall
Project InformationjProject Website: cityofmadison.com/engineering/statest
Facebook: https://www.facebook.com/CityofMadison
Ci f M di Wi i G
Twitter: @cityofmadison
Project Email Updates:
City of Madison, Wisconsin Government
Project Email Updates: my.cityofmadison.com/subscriptions Chris Petykowski, P.E., Engineering
Bill Fruhling, AICP, [email protected]
G B PLA FASLA UW M diGary Brown, PLA, FASLA, UW-Madison [email protected]
Jason DiPiazza, P.E., MSA
April 23, 2013 72State Street 700/800 Blocks & Library Mall
Public Information Meeting #1gApril 23, 2013
THANK YOU!THANK YOU!April 23, 2013 73State Street 700/800 Blocks & Library Mall