State Route 58 Hinkley Expressway Project Project Overview New Batch Plant Locaon: For more informaon about this project, please go to caltrans8.info for news re- lease/commuter alerts. Follow us on Twier at www.twier.com/caltrans8. California Department of Transportaon San Bernardino County, California District 8 — SBD — SR58 — Post Mile 22.2 to 31.1 February 2016 The California Department of Transportaon (Caltrans) project to widen a poron of State Route 58 from a two-lane convenonal high- way to a four-lane expressway, is now in the construcon phase. The improvements to State Route 58 extend from approximately 2.8 miles west of Hidden River Road to approxi- mately 0.7 miles east of Lenwood Road, near the unincorporated Community of Hinkley, in San Bernardino County. The expressway would include: 12-foot standard traveled way lanes; 10-foot standard shoulder widths; and a 78-foot-wide median. Two interchanges will be constructed; one at Hinkley Road and the other at Lenwood Road. This realigned roadway would be con- structed on a fill secon (elevated secons of a roadway). Start Concrete Paving New Hwy 58 - April 2016 New Batch Plant - April 2016 Complete import of fill - April 2016 Open Hinkley Road - May 2016 Open Lenwood Road - February 2016 Open New Hwy 58 Expressway - November 2016 Permanent Closure of Existing Hwy 58 to Through Traffic (West of Valley View Rd) - November 2016 Start Asphalt Overlay on Existing Hwy 58 - November 2016 Finish Asphalt Overlay on Existing Hwy 58 - December 2016 Open Lenwood WB Exit Ramp - February 2017 Planned Construction Duration - Early 2017 Public Information Officer Philip Havins (909) 383-6799 [email protected] Resident Engineer Shaine Shahidi Project Manager Jim Robinson http://www.dot.ca.gov/dist8/Project-SR-58-Hinkley.html Project Construcon Schedule * Project Contacts *Please note that the above dates are initial estimates and subject to change through out the duration of construction. Project schedule updates will be available from Caltrans project contacts.

Upload: others

Post on 28-May-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: State Route 58 - Caltrans District 8 | Home Pagedistrict8.dot.ca.gov/documents/sr58/04351_Fact_Sheet_for... · 2016-02-11 · (Caltrans) project to widen a portion of State Route

State Route 58 Hinkley Expressway Project

Project Overview

New Batch Plant Location:

For more information about this project, please go to caltrans8.info for news re-lease/commuter alerts.

Follow us on Twitter at www.twitter.com/caltrans8.

California Department of Transportation San Bernardino County, California District 8 — SBD — SR58 — Post Mile 22.2 to 31.1 February 2016

The California Department of Transportation (Caltrans) project to widen a portion of State Route 58 from a two-lane conventional high-way to a four-lane expressway, is now in the construction phase. The improvements to State Route 58 extend from approximately 2.8 miles west of Hidden River Road to approxi-mately 0.7 miles east of Lenwood Road, near the unincorporated Community of Hinkley, in San Bernardino County. The expressway would include: 12-foot standard traveled way lanes; 10-foot standard shoulder widths; and a 78-foot-wide median.

Two interchanges will be constructed; one at Hinkley Road and the other at Lenwood Road. This realigned roadway would be con-structed on a fill section (elevated sections of a roadway).

Start Concrete Paving New Hwy 58 - April 2016

New Batch Plant - April 2016

Complete import of fill - April 2016

Open Hinkley Road - May 2016

Open Lenwood Road - February 2016

Open New Hwy 58 Expressway - November 2016

Permanent Closure of Existing Hwy 58 to Through Traffic (West of Valley View Rd) - November 2016

Start Asphalt Overlay on Existing Hwy 58 - November 2016

Finish Asphalt Overlay on Existing Hwy 58 - December 2016

Open Lenwood WB Exit Ramp - February 2017

Planned Construction Duration - Early 2017

Public Information Officer

Philip Havins

(909) 383-6799

[email protected]

Resident Engineer

Shaine Shahidi

Project Manager

Jim Robinson

http://www.dot.ca.gov/dist8/Project-SR-58-Hinkley.html

Project Construction Schedule*

Project Contacts

*Please note that the above dates are initial estimates and subject to change through out the duration of

construction. Project schedule updates will be available from Caltrans project contacts.