State Data Center (SDC) ProjectsUpdate for the
CTS Customer Advisory Council Meeting
January 07, 2015
Agenda• Update on SDC Projects• Customer Communications• Q&A
2
SDC Projects
SDC Projects Timeline
4
Firewall Migrations
CTS has approximately 102 firewalls to decommission or migrate from OB2 to the new firewall solution in the SDC.
• The first migration was in March 2013.
• The project is scheduled to complete March 2015.
• Each migration has been a coordinated effort with the
CTS customer(s).
• We have completed 84 of the 102 migrations to date.
5
Firewall Migrations
6
CTS Private Cloud Status
7
The project has completed.
A service announcement for the CTS Private Cloud Service was posted in December.
DR - VTL ProjectThe scope of the Virtual Tape Library (VTL) Project was redefined in order to minimize transformation in flight and help ensure migrations complete on time.
• The IBM tape backups in OB2 will be replaced by virtual backups in SDC. • The Unisys tape service will be migrated to a newer, smaller Unisys tape
system in the SDC.
8
CTS Move Phase 1 - Recap
• 517 of 517 virtual servers in OB2 were moved or decommissioned. 264 of 264 physical servers in OB2 were moved or decommissioned
• Completed migration of the messaging environment• Completed numerous projects to migrate CTS security
systems, including 8 change events supporting the migration of SAW and Fortress customer test and production
• Completed several telephony systems migrations• Establish provider/carrier presence in the SDC• Completed Unisys Mainframe migration and the
stand-up of the IBM Mainframe to the SDC
9
SDC Move Ph 2- ScopeSDC Move Phase 2 moves the remaining systems out of OB2 into the SDC.
In Scope: • Equipment supporting CTS services such as:
• CTS internal support systems• Security systems• Telephony system• Network systems
• Customer agencies in OB2 A la Carte
10
SDC Move Ph 2- Next 90 Days
11
SDC Move Ph 2- CTS Devices
12
CTS teams are working to remove any/all remaining equipment in OB2 by the end of the project.
Any equipment that will not be migrated to the SDC will be decommissioned.
SDC Move Ph 2- Security
13
SDC Move Phase 2
CTS Devices
Security
Telephony
Network
Customer Migrations
The Enterprise Security Services team is working to migrate remaining security services from OB2 to SDC.
The remaining services to migrate include:• Web Services Gateways• VPN Services• Load Balancer• “Secman” - Out of Band Management
SDC Move Ph 2– Telephony
14
Migrations complete!
SDC Move Ph 2– Network
15
The Telecommunications Services Division team is working to migrate remaining services from OB2 to SDC.
The remaining systems/services to decommission from OB2 include:
• T1s• Vendor Trunks• NGN MSPP• PBX remote sites• WAN Carriers / Providers
SDC Move Ph 2 - CustomersCTS is working with customers to migrate out of OB2:
• There were twenty A la Carte customers with equipment in OB2.
• All customers have completed orientation sessions and the last High Level Design Consult will be in Jan.
• Six customers have removed 100% of their gear.• One customer will migrate to CTS Server Hosting.• Three large customers with multiple migrations have
completed setup and have started migrations.• Additional migrations for remaining customers are
scheduled to occur until June 2015. CTS has also supported two non-OB2 customers to
move into SDC (WSP and OAH). In talks with add’t.
16
CTS Service Announcement
A service announcement for sunsetting the OB2 Data Center was posted.
OB2 Equipment RoomDES, CTS, and DSHS have been meeting to discuss the requirements, plan, and design or the future state of vacated data center space in OB2. Some telephony equipment (PBX) will need to stay in OB2 to support DSHS.
18
Customer Communications
Implementation CoordinatorsDue to the volume of CTS migrations impacting numerous systems and customers, CTS has asked each agency to identify an Agency Implementation Coordinator (AIC) to act as an agency single-point-of-contact for collaboration on the SDC Projects. Typically, the AIC:
• Oversees all communication / activities with CTS
• Is responsible for internal agency coordination in support of customer readiness activities
• Gathers, validates, and communicates agency requirements and readiness
• Coordinates deliverables with project team
• Develops and supports project schedule, management and reporting
• Identifies and escalates project risks, issues and actions items as needed
• Serves as an advocate of change
Customer Communications• The SDC Projects website provides information regarding project
background, status, meeting information, and migration resources.• The SDC Migration Calendar provides a calendar view of migration
information linking back to the Technical Bulletins.• Technical Bulletins notify customers of upcoming changes regarding SDC
project-related changes.• The SDC Project ASK website provides online document collaboration
regarding agency migrations out of OB2.• Monthly AIC meetings provide an opportunity to hear status presented
and ask questions.• Migration project meetings are scheduled with specific customers as
needed to prepare for their migrations.
21
SDC Project Website
22
The SDC Projects website provides current information about the status of the projects.
See also: Customer Readiness website
Migration Calendar Updates
SDC Migrations
Calendar
23
SDC Project ASK Website
24
The SDC Projects ASK website enables customer and CTS collaboration regarding the migrations.
Note: Site access is provided to current migration customers.
The Migration Guide
25
The Migration Guide is available on the ASK site.
Q&A