stanford university information technology services research data centers- stanford phil reese,...

6
STANFORD UNIVERSITY • INFORMATION TECHNOLOGY SERVICES Research Data Centers- Stanford Phil Reese, Stanford University [email protected] CSG Meeting, June 16, 2011 University of Minnesota

Upload: edgar-blake

Post on 13-Jan-2016

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: STANFORD UNIVERSITY INFORMATION TECHNOLOGY SERVICES Research Data Centers- Stanford Phil Reese, Stanford University preese@stanford.edu CSG Meeting, June

STANFORD UNIVERSITY • INFORMATION TECHNOLOGY SERVICES

Research Data Centers- Stanford

Phil Reese, Stanford University

[email protected]

CSG Meeting, June 16, 2011

University of Minnesota

Page 2: STANFORD UNIVERSITY INFORMATION TECHNOLOGY SERVICES Research Data Centers- Stanford Phil Reese, Stanford University preese@stanford.edu CSG Meeting, June

STANFORD UNIVERSITY • INFORMATION TECHNOLOGY SERVICES

6/16/2011 Research Data Centers- Stanford page 2

Research Data Center Plans

Stanford’s Board of Trustees have approved the first step in the project, ‘Concept and Site’ approval.

Two more visits to the BOT are needed before ground breaking.

Next visit is projected for October, with the final visit in December, ground breaking shortly there after.

Plan calls for 3MW of server load, .5MW for SLAC, 1MW for School of Med, and 1.5MW for the other campus schools.

Page 3: STANFORD UNIVERSITY INFORMATION TECHNOLOGY SERVICES Research Data Centers- Stanford Phil Reese, Stanford University preese@stanford.edu CSG Meeting, June

STANFORD UNIVERSITY • INFORMATION TECHNOLOGY SERVICES

6/16/2011 Research Data Centers- Stanford page 3

Speed and Feeds…

Site is on SLAC land, roughly 3 miles from campus.

Locating it on SLAC land has pro and cons.

Redundant fiber paths to campus planned.

Modularity and Flexibility are key design factors.

Page 4: STANFORD UNIVERSITY INFORMATION TECHNOLOGY SERVICES Research Data Centers- Stanford Phil Reese, Stanford University preese@stanford.edu CSG Meeting, June

STANFORD UNIVERSITY • INFORMATION TECHNOLOGY SERVICES

6/16/2011 Research Data Centers- Stanford page 4

Speed and Feeds… (continued)

Average rack density of 20kW/rack.• More than one research group has already approached and said

they will need >30kW/rack on day one.

Primarily ambient air cooled.• Weather data for the past 6 years suggest temps of more than 85 F

occur less than 2% of the year.

Auxiliary 200 Ton (~700kW) chiller planned for those racks that can’t be ambient air cooled.• Chilled water headers will be available from this chiller in all the row

lineups.

Power protected by a medium voltage UPS with 10 minutes of full load run time. (servers and mechanical on the UPS)

Page 5: STANFORD UNIVERSITY INFORMATION TECHNOLOGY SERVICES Research Data Centers- Stanford Phil Reese, Stanford University preese@stanford.edu CSG Meeting, June

STANFORD UNIVERSITY • INFORMATION TECHNOLOGY SERVICES

6/16/2011 Research Data Centers- Stanford page 5

Speed and Feeds… (continued)

No generator anticipated, though transfer switch and generator pad planned.• Backup option #1: dual transmission grade power feeds from local

but diverse substations. (no cost to project, 3-5 years away however)

• Backup option #2: energy storage system (significant capital cost, could be recouped quickly by buying power at night and selling power during day/peak times)

Phase II plans include doubling in size and/or incremental growth via containers or similar options.

Page 6: STANFORD UNIVERSITY INFORMATION TECHNOLOGY SERVICES Research Data Centers- Stanford Phil Reese, Stanford University preese@stanford.edu CSG Meeting, June

STANFORD UNIVERSITY • INFORMATION TECHNOLOGY SERVICES

6/16/2011 Research Data Centers- Stanford page 6

Business model, how to get Researchers in? Three models planned, hosting only, hosting and sys

admin for stand alone cluster, hosting and cluster condo model (with Provost provided uplift racks).

Models include funding for a Program Director and a Research Application Specialist as a start.• Plan to offer quality support to researchers as they plan grants and

to support their transition to using the facility. Reviewing code and algorithms. Over time, these services can be charged for and staffing will grow, if demand is there.

Campus senior admins are most concerned about how to get old gear out of the facility.