stabcon tie in

4
STABCON ® Tie-in System The Stab and Connect Connection System (STABCON ® ) is designed to install and connect Rigid and Flexible Flowlines, Umbilicals and Rigid Spools in deep and ultra-deep waters in two modes. In Mode-1, a hinged stab on the termination head enters a receptacle on the subsea structure before the termination head is moved into horizontal position for connection by the ROV carried Connector Actuating Tool (CAT). In Mode-2, the Termination Heads with stabs, are used for docking and connection of Horizontal Spools.

Upload: von18

Post on 25-Nov-2015

274 views

Category:

Documents


15 download

DESCRIPTION

Tie in system

TRANSCRIPT

  • STABCON Tie-in System

    The Stab and Connect Connection System (STABCON) is designed to install and connect Rigid and Flexible Flowlines, Umbilicals and Rigid Spools in deep and ultra-deep waters in two modes. In Mode-1, a hinged stab on the termination head enters a receptacle on the subsea structure before the termination head is moved into horizontal position for connection by the ROV carried Connector Actuating Tool (CAT). In Mode-2, the Termination Heads with stabs, are used for docking and connection of Horizontal Spools.

  • Tie-in of Flexible Line and Umbilical

    Tie-in of Rigid Horizontal Spool

    Lifting Yoke to provide the interface with the Termination Head for lifting the Spool during installation.

    Optional Guide Wires and Anchors for initial guidance and docking of the Termination Head on the Tie-in Porch. For deep water installation, the Guide Wires are deployed locally by the ROV with tension maintained by buoyancy elements. For shallow water installation, the Guide Wires can be run from a surface vessel or drilling rig if required.

    Stroking and connection of the Termination Head to the Inboard Hub is carried out using the Connector Actuation Tool (CAT) System, a connection tool system that is deployed and operated by ROV.

    The tool system includes various ROV operated tools for inspection and cleaning of the Inboard Hub and the seal face in the Connector.

    Main system components

    Tie-in Porch with an Inboard Hub permanently installed on each structure to provide the connection point for the Termination Head at each end of the spool/flowline.

    Termination Head on each end of the spool/flowline, in Monobore configuration or Multibore configuration for a Well Jumper. The Termination Head has an orientation key and a Heavy Stab that locates in a receptacle on the Tie-in Porch during docking.

    Protection Caps to protect the seal faces on the Inboard Hub and in the Connector before connection of the Sea-line.

    Technical Description

    The STABCON Tie-in system has the advantage of being designed to perform a series of tie-ins and connections without returning the CAT to the surface. The connection system ( CAT ) is very compact, requires minimal mobilisation, and is air transportable world-wide.

    STABCON Tie-in System

  • Lifting Yoke

    Buoyanci Element

    GuideWire

    GuideWire

    Anchor

    Carrier Pipe

    ColletConnector

    Seal Plate

    HeavyStab

    Inboard Hub

    Key

    Hinge

    CatLockdown

    Point

    Steel Pipe

    Location for Electrical

    Connectors(Well Jumper only)

    Key Slot

    Guide Wire Anchor Receptacle

    Stab Receptacle, heavy

    High Pressure Cap

    Inboard HubProtection Cap

    Flying Interface

    Connector Actuation Tool

    (ROV Deployed)

    Hoses from ROV

    Stab, 4L 345 bar

    Cat Seal Test Stab

    Outboard Hub Protection Cap

    Specifications

    Termination Head Dimensions: Length: 2,500 mm (98.5) Width: 1,300 mm (51) Height, Light Stab: 1,100 mm (43.5) Height, Heavy Stab: 1,700 mm (67)

    Lifting Yoke Dimensions: Width: 1,300 mm (51) Height: 2,000 mm (79)

    Approximate Weight of Termination Head:In air: 4,500 kg (9,900 lb) In water: 3,700 kg (8,140 lb)

    Approximate Weight of Lifting Yoke: In air: 520 kg (1,144 lb) In water: 454 kg (999 lb)

    Stab Hinge Angle relative to vertical: +90 to -3 degrees

    Lifting Yoke Maximum Hook Load: 510 kN (114,650 lbf)

    Maximum Water Depth: 3,000 m (10,000 ft)

    Lifting Yoke hydraulic supply from ROV via Stab, 4 Line, 345 Bar.

  • Deepwater installation of a Rigid Spool up to 30 OD

    A Lifting Yoke is locked to each Termination Head and the Spool is hooked up to the spreader beam.

    The Spool is deployed and lowered to within a few metres above the target areas on the subsea structures.

    For GL operation, the Guide Wire and buoyancy element is de-ployed at each end of the Spool and the Guide Wire Anchors are connected to the receptacle on each Tie-in Porch.

    The Spool is lowered until the stab on the first Termination Head enters the stab receptacle on the Tie-in Porch.

    The second Termination Head will align horizontally as the Spool continues to be lowered until the stab enters the stab receptacle and lands on the Tie-in Porch.

    The Lifting Yoke is unlocked and released from each Termination Head by the ROV.

    The Lifting Yokes and Guide Wires (if used) are recovered to the surface with the spreader beam.

    The Connector Actuation Tool (CAT) is landed and locked on the first Termination Head by the ROV.

    The Termination Head is levelled and locked in the horizontal position.

    The Protection Caps are removed from the Connector and the Inboard Hub.

    The Termination Head is stroked against the Inboard Hub and the Connector is closed.

    A pressure test is carried out to verify the integrity of the

    Connector seal.

    The CAT is unlocked and lifted from the Termination Head and Inboard Hub.

    The connection procedure is repeated to connect the second Termination Head to the Inboard Hub without returning the CAT to the surface vessel.

    Installation/Handling

    www.fmctechnologies.com/subsea

    FMC TechnologiesP.O. Box 1012NO-3601 KongsbergNorwayPhone: +47 3228 6700

    FMC Technologies1777 Gears RoadHouston TX 77067USAPhone: +1 281 591 4000

    FMC Technologies A

    ugust 2006 - 3D illustrations by ID

    - print by Prinfo Vanberg