Description AwardedBid AmountRs. in Crs.
1
Construction of Sripada Sagar Project acress Godavari river at Yellampally (V), Ramagundam(M), Karimnagar Dt.
(Stage-I)
SCANSKA Cementation Ltd. 408.85
2
Excavation of approach channel Construction of pump house, Supply and commissioning of pumping machinery to lift 8.5 TMC, Transformers, sub-stations, Pressure mains Supply and layers of pipelines from Barrage to NTPC Balancing Reservoir.
M/s.Subhash
Projects &
Marketing(P) Ltd.
98.92
3
Stage-II, Phase-I of Sripada Sagar Project- supply, installation and commissioning of pumping machinery, transformers, sub-stations, pressure mains including construction of pump house all civil structures to irrigate 2.00 Lakh acres in upland areas of Karimnagar (Dist.)
M/s. IVRCL-SEW-
Navayuga (JV)1737
TOTAL 2244.77
SRIPADA SAGAR PROJECT
1 Project Profile : i) Construction of Sri Padasagar Project across river Godavari (St-I) Ph-I
ii) Supply of 8.5 TMC of water to NTPC (St-I, Ph-II)
iii) Lifting 12 TMC to irrigate 2 Lakh Acres (St-II, Ph-I)
2 Administrative Sanction : G. O. Ms. No. 71, I & CAD (PW) GVI, Dt: 16-7-2004 for Rs. 900 Crores
3 No. of EPC Packages : 3 Nos.
4 Agt. Value of 3 Pkgs : Rs. 2244.77Crs.
5 Budget Provision for 2006-07 (For GWUA) : Rs. 1240 Crs.
6 Expenditure of the Project
2004-05 : Rs. 20.44 Crs.
2005-06 : Rs. 202.07 Crs.
TOTAL : Rs. 222.51 Crs.
7 Utilisation ( Stg-I, Ph-I, Ph-II & Stg-II,Ph-I) : 20.5 TMC
Ultimate : 180.50 TMC
8 Ayacut New Ayacut : 2,00,000 acres
SRIPADASAGAR L. I. SCHEME
9 Lift-I Lift Height : 96 M
No. of Pumps : 4 Nos.
Total pumps capacity : 10.8 MW
10 Lift-II
Lift Height : 120 M
No. of Pumps : 4 Nos.
Total pumps capacity : 13 MW
11 Lift-III Lift Height : 80 M
No. of Pumps : 4 Nos.
Total pumps capacity : 5,25 MW x 2, 8.26 MW x 2
12 Lift-IV
Lift Height : 50 M
No. of Pumps : 2 Nos.
Total pumps capacity : 0.50 MW
13 Power required (Stg-I, Ph-II) – water supply to NTPC
: 9 MW
14 Power required (Stg-II, Ph-I) – Irrigation 2L Acs : 137 MW
SRIPADASAGAR L. I. SCHEME
15 Land Acquisition
Required : 15,981 acres
Acquired : 430 acres
Requisitioned : 15,981 acres
16 Est. Cost for LA : Rs. 222.00 Crores
17 Est. Cost for R & R : Rs. 500.00 Crores
18 Mobilisation Advance : PaidRecovered
2004-05 : Rs. 20.44 Crs.
2005-06 : Rs.106.05 Crs. 3.31 Crs.
Total : Rs. 126.49 Crs. 3.31 Crs.
19 Target date for completion : 10/2007
SRIPADASAGAR L. I. SCHEME
Package No. 1 : (Stg-I Ph-I) Construction of Sripada Sagar Project across Godavari river at Yellampally (V), Ramagundam(M), Karimnagar Dt. to store 20 TMC at FRL + 148M.
Name of the Contractor : ITD Cementation India Ltd.
Agreement Amount : Rs. 408.85Crs.
Agreement Date : 07-11-2004/17-2-2005
Period of Completion : 36 Months(10 milestones)
Date of completion : 06-11-2008
SRIPADASAGAR PROJECT
Survey work : Completed Designs : Alignment of barrage - FINALISED
Earth bunds approved by CE/CDO; Spillway under approval in CE/CDO
Execution : Drilling of exploratory bore holes
in river for spill way & earth bund : Completed Excavation of Cutoff trenches for
right side & left side earthen
bunds : Completed Exc. of Cutoff trenches for spillway : In progress Qty. of Earthwork done : 2.43 L Cum against 3.062 L Cum. Expenditure : Rs. 63.59 Crores. (including Mob. Advance
Rs.36.04Crs.) against Rs. 408.85 Crores.
Land Acquisition : Required = 8745 Acres; Acquired=225 Acres Requisitioned = 8456 Acs.
Package No.2 : (Stg-I Ph-II)
i) Excavation of approach channel
ii) Construction of pump house
iii) Supply and commissioning of pumping machinery to lift 8.5 TMC, Transformers, sub-stations
iv) Pressure mains
v) Supply and laying of pipelines to NTPC Reservoir
Name of the Contractor : M/s.Subhash Projects &
Marketing(P) Ltd.
Agreement Amount : Rs. 98.92 Crs.
Agreement Date : 07-04-2005
Period of Completion : 18 Months (6 milestones)
Date of completion : 06-10-2006
SRIPADASAGAR PROJECT Water Supply to NTPC
Survey work : Completed
Designs : Designs for pressure mains submitted to CE/CDO & are under scrutiny
: Designs for pump houses, pumps etc. to be submitted by Agency
Designs of pipelines : Yet to be furnished by the Agency.
Execution : Fabrication Unit erected at site for manufacture of pipes
Alignment of pressure mains, location
of approach channel and intake well : under approval by CE/CDO
Expenditure : Rs.12.48Crs. (incl. Mob. Adv.) against Rs.98.92Crs.
Land acquisition : Required 70 Acres,
SRIPADASAGAR PROJECT (Stg-I, Ph-II) Water Supply to NTPC
1 Expenditure
2005-06 Works : Rs. 7.53 Crs.
Mob. Adv. : Rs.4.95 Crs.
Total : Rs. 12.48 Crs.
2 Land Acquisition
Total Required : 55 acres
Acquired : Nil
Requisitioned : 15 Acres
3Utilization
: 8.5 TMC
4 Lift-I
Lift Height : 50 M
No. of Pumps : 4
Total pumps capacity : 3300 HPs.
5 Power required : 9 MW
SRIPADASAGAR PROJECT STAGE-II, PHASE-I (Irrigation)
SALIENT FEATURES :
1 PROJECT PROFILE Installation and commissioning of pumping machinery, transformers, sub-stations, pressure mains including construction of pump house all civil structures to irrigate 2.00 Lakh acres in upland areas of Karimnagar (Dist.)
2 Admn. Sanction: G. O. Ms. No. 149, I & CAD, Dt: 16-8-
2005 for Rs. 1688.86 Crores
3 Expenditure
2005-06 : Rs.146.44 Crs.
4 Land Acquisition
Total Required : 15,000 acres
Acquired : Nil
Requisitioned : 407 Acres
5 Forest Land : 285 Acres
6 Utilisation : 12 TMC
7 Ayacut New Ayacut : 2 Lakhs acres
Stabilisation :
8 Lift-I
Lift Height : 96 M
No. of Pumps : 4 Nos.
Total pumps capacity : 10.8 MW
9 Lift-II
Lift Height : 120 M
No. of Pumps : 4 Nos.
Total pumps capacity : 13 MW
10 Lift-III
Lift Height : 80 M
No. of Pumps : 4 Nos.
Total pumps capacity : 5,25 MW x 2, 8.26 MW x 2
SRIPADASAGAR PROJECT STAGE-II, PHASE-I
11 Lift-IV
Lift Height : 50 M
No. of Pumps : 2 Nos.
Total pumps capacity : 0.50 MW
12 Power required : 137 MW
13 Mobilisation Advance 2005-06 : PaidRecovered
Rs. 85.50Crs Rs. 3.31Crs.
SRIPADASAGAR PROJECT STAGE-II, PHASE-I
Package No.3 : Stage-II, Phase-I of Sripada Sagar Project- supply, installation and
commissioning of pumping machinery,
transformers, sub-stations, pressure mains
including construction of pump house all civil
structures to irrigate 2.00 Lakh acres in upland
areas of Karimnagar (Dist.)
Name of the Contractor : M/s. IVRCL-SEW-
Navayuga (JV)
Agreement Amount : Rs. 1737Crs.
Agreement Date : 03-04-2005
Period of Completion : 30 Months(10 milestones)
Date of completion : 02-10-2007
SRIPADASAGAR PROJECT
Utilization : 12 TMC (Lifting)
Power Required : 137 MW
Investigation : Pressure mains completed
: Pump house & gravity canal under progress
Designs : Designs of pressure mains and alignment submitted to CE/CDO for approval
Mobilization Advance paid : 85.50 Crores
Mob. Advance recovered : Rs. 3.31 Crs.
Land Acquisition : Required : 2000 Acres; Requisitioned : 437 Acres.
(Rs. 5.00 Crores deposited with Revenue Authorities)