sr 252 section dsr pa 252 (palmers mill road bridge) over ... · replace bridge over spillway and...

27
Marple and Upper Providence Township Meetings || SR 0252, Section DSR Bridge Replacement Project || January 24, 2019 SR 252 Section DSR PA 252 (Palmers Mill Road Bridge) over Springton Reservoir Bridge Replacement Project Presented by Pennsylvania Department of Transportation Gannett Fleming, Inc.

Upload: others

Post on 04-Apr-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SR 252 Section DSR PA 252 (Palmers Mill Road Bridge) over ... · Replace bridge over spillway and roadway barrier along NB shoulder/length of dam • Maintain 2 lanes of traffic during

Marple and Upper Providence Township Meetings || SR 0252, Section DSR Bridge Replacement Project || January 24, 2019

SR 252 Section DSRPA 252 (Palmers Mill Road Bridge) over

Springton ReservoirBridge Replacement Project

Presented by

Pennsylvania Department of TransportationGannett Fleming, Inc.

Page 2: SR 252 Section DSR PA 252 (Palmers Mill Road Bridge) over ... · Replace bridge over spillway and roadway barrier along NB shoulder/length of dam • Maintain 2 lanes of traffic during

Marple and Upper Providence Township Meetings || SR 0252, Section DSR Bridge Replacement Project || January 24, 2019

Purpose of Presentation

• Update the community on the Springton Dam Bridge Replacement

• Share response to community concerns

Page 3: SR 252 Section DSR PA 252 (Palmers Mill Road Bridge) over ... · Replace bridge over spillway and roadway barrier along NB shoulder/length of dam • Maintain 2 lanes of traffic during

Marple and Upper Providence Township Meetings || SR 0252, Section DSR Bridge Replacement Project || January 24, 2019

Project Description• Replace bridge over spillway and roadway

barrier along NB shoulder/length of dam

• Maintain 2 lanes of traffic during construction

• Provide temporary roadway and bridge for staged construction

• Provide permanent retaining wall for construction staging and future maintenance activities

Page 4: SR 252 Section DSR PA 252 (Palmers Mill Road Bridge) over ... · Replace bridge over spillway and roadway barrier along NB shoulder/length of dam • Maintain 2 lanes of traffic during

Marple and Upper Providence Township Meetings || SR 0252, Section DSR Bridge Replacement Project || January 24, 2019

Bridge Project Area

Page 5: SR 252 Section DSR PA 252 (Palmers Mill Road Bridge) over ... · Replace bridge over spillway and roadway barrier along NB shoulder/length of dam • Maintain 2 lanes of traffic during

Marple and Upper Providence Township Meetings || SR 0252, Section DSR Bridge Replacement Project || January 24, 2019

Existing Bridge Approach

• View traveling Southbound

Page 6: SR 252 Section DSR PA 252 (Palmers Mill Road Bridge) over ... · Replace bridge over spillway and roadway barrier along NB shoulder/length of dam • Maintain 2 lanes of traffic during

Marple and Upper Providence Township Meetings || SR 0252, Section DSR Bridge Replacement Project || January 24, 2019

Existing Bridge Approach

• View traveling Northbound

Page 7: SR 252 Section DSR PA 252 (Palmers Mill Road Bridge) over ... · Replace bridge over spillway and roadway barrier along NB shoulder/length of dam • Maintain 2 lanes of traffic during

Marple and Upper Providence Township Meetings || SR 0252, Section DSR Bridge Replacement Project || January 24, 2019

Existing Bridge Elevation

BRIDGE ABUTMENT

SPILLWAYTRAININGWALL

SPILLWAYINVERT

42’ SPAN(ALONG C ROADWAY)L

22’-10” VERTICALCLEARANCE

Page 8: SR 252 Section DSR PA 252 (Palmers Mill Road Bridge) over ... · Replace bridge over spillway and roadway barrier along NB shoulder/length of dam • Maintain 2 lanes of traffic during

Marple and Upper Providence Township Meetings || SR 0252, Section DSR Bridge Replacement Project || January 24, 2019

Bridge Area

Page 9: SR 252 Section DSR PA 252 (Palmers Mill Road Bridge) over ... · Replace bridge over spillway and roadway barrier along NB shoulder/length of dam • Maintain 2 lanes of traffic during

Marple and Upper Providence Township Meetings || SR 0252, Section DSR Bridge Replacement Project || January 24, 2019

Existing Section

Page 10: SR 252 Section DSR PA 252 (Palmers Mill Road Bridge) over ... · Replace bridge over spillway and roadway barrier along NB shoulder/length of dam • Maintain 2 lanes of traffic during

Marple and Upper Providence Township Meetings || SR 0252, Section DSR Bridge Replacement Project || January 24, 2019

Proposed Bridge Section

Page 11: SR 252 Section DSR PA 252 (Palmers Mill Road Bridge) over ... · Replace bridge over spillway and roadway barrier along NB shoulder/length of dam • Maintain 2 lanes of traffic during

Marple and Upper Providence Township Meetings || SR 0252, Section DSR Bridge Replacement Project || January 24, 2019

Proposed Roadway Section

Page 12: SR 252 Section DSR PA 252 (Palmers Mill Road Bridge) over ... · Replace bridge over spillway and roadway barrier along NB shoulder/length of dam • Maintain 2 lanes of traffic during

Marple and Upper Providence Township Meetings || SR 0252, Section DSR Bridge Replacement Project || January 24, 2019

Proposed Bridge Elevation

Page 13: SR 252 Section DSR PA 252 (Palmers Mill Road Bridge) over ... · Replace bridge over spillway and roadway barrier along NB shoulder/length of dam • Maintain 2 lanes of traffic during

Marple and Upper Providence Township Meetings || SR 0252, Section DSR Bridge Replacement Project || January 24, 2019

Method of Construction

• Maintain one lane of vehicular traffic in each direction during construction

• Maintain access to local residences

Page 14: SR 252 Section DSR PA 252 (Palmers Mill Road Bridge) over ... · Replace bridge over spillway and roadway barrier along NB shoulder/length of dam • Maintain 2 lanes of traffic during

Marple and Upper Providence Township Meetings || SR 0252, Section DSR Bridge Replacement Project || January 24, 2019

Utility Coordination• Aerial – Poles/wires relocated prior to, and during

construction• PECO Electric, Comcast, Crown Castle, Verizon

• Underground• PECO Gas: new future line, partially installed

during construction• Verizon: ductbank and manhole abandoned and

removed• Marple Township: traffic signal removed during

construction, new signal provided to Township for its reinstallation

Page 15: SR 252 Section DSR PA 252 (Palmers Mill Road Bridge) over ... · Replace bridge over spillway and roadway barrier along NB shoulder/length of dam • Maintain 2 lanes of traffic during

Marple and Upper Providence Township Meetings || SR 0252, Section DSR Bridge Replacement Project || January 24, 2019

Stage 1 Construction

• Maintain one lane each way• Upgrade shoulders• Construct retaining wall, and

temporary roadway and bridge

Page 16: SR 252 Section DSR PA 252 (Palmers Mill Road Bridge) over ... · Replace bridge over spillway and roadway barrier along NB shoulder/length of dam • Maintain 2 lanes of traffic during

Marple and Upper Providence Township Meetings || SR 0252, Section DSR Bridge Replacement Project || January 24, 2019

Stage 2 Construction• Maintain one lane each way• Shift NB traffic to temporary

bridge• Shift SB traffic to existing NB lane• Replace west side of bridge

Page 17: SR 252 Section DSR PA 252 (Palmers Mill Road Bridge) over ... · Replace bridge over spillway and roadway barrier along NB shoulder/length of dam • Maintain 2 lanes of traffic during

Marple and Upper Providence Township Meetings || SR 0252, Section DSR Bridge Replacement Project || January 24, 2019

Stage 3 Construction• Maintain one lane each way• Shift SB and NB lanes to new portion of

bridge• Replace east side of existing bridge and

roadway barrier along length of dam

Page 18: SR 252 Section DSR PA 252 (Palmers Mill Road Bridge) over ... · Replace bridge over spillway and roadway barrier along NB shoulder/length of dam • Maintain 2 lanes of traffic during

Marple and Upper Providence Township Meetings || SR 0252, Section DSR Bridge Replacement Project || January 24, 2019

Stage 3 Construction• Maintain one lane each way• Shift SB and NB lanes to new

portion of bridge• Replace east side of existing

bridge and roadway barrier along length of dam

• Temporary traffic signal at PA 252 and Palmers Mill Road intersection

Page 19: SR 252 Section DSR PA 252 (Palmers Mill Road Bridge) over ... · Replace bridge over spillway and roadway barrier along NB shoulder/length of dam • Maintain 2 lanes of traffic during

Marple and Upper Providence Township Meetings || SR 0252, Section DSR Bridge Replacement Project || January 24, 2019

Aesthetics

Existing Bridge Barrier

Page 20: SR 252 Section DSR PA 252 (Palmers Mill Road Bridge) over ... · Replace bridge over spillway and roadway barrier along NB shoulder/length of dam • Maintain 2 lanes of traffic during

Marple and Upper Providence Township Meetings || SR 0252, Section DSR Bridge Replacement Project || January 24, 2019

Aesthetics-Bridge Barrier

Stone-Faced Barrier

Page 21: SR 252 Section DSR PA 252 (Palmers Mill Road Bridge) over ... · Replace bridge over spillway and roadway barrier along NB shoulder/length of dam • Maintain 2 lanes of traffic during

Marple and Upper Providence Township Meetings || SR 0252, Section DSR Bridge Replacement Project || January 24, 2019

Aesthetics-Bridge Barrier

Existing Bridge and Barrier

BRIDGE ABUTMENT

BRIDGE ABUTMENT

ROCK ARMORINGROCK ARMORING

EXISTINGSPILLWAYWALLS

EXISTINGSPILLWAYWALLS

EXISTINGSPILLWAYWALLS

42’ SPAN(ALONG C ROADWAY)L

Page 22: SR 252 Section DSR PA 252 (Palmers Mill Road Bridge) over ... · Replace bridge over spillway and roadway barrier along NB shoulder/length of dam • Maintain 2 lanes of traffic during

Marple and Upper Providence Township Meetings || SR 0252, Section DSR Bridge Replacement Project || January 24, 2019

Aesthetics-Bridge Barrier

Proposed Concrete Bridge with Stone-Faced Barrier

Page 23: SR 252 Section DSR PA 252 (Palmers Mill Road Bridge) over ... · Replace bridge over spillway and roadway barrier along NB shoulder/length of dam • Maintain 2 lanes of traffic during

Marple and Upper Providence Township Meetings || SR 0252, Section DSR Bridge Replacement Project || January 24, 2019

Retaining Wall

Page 24: SR 252 Section DSR PA 252 (Palmers Mill Road Bridge) over ... · Replace bridge over spillway and roadway barrier along NB shoulder/length of dam • Maintain 2 lanes of traffic during

Marple and Upper Providence Township Meetings || SR 0252, Section DSR Bridge Replacement Project || January 24, 2019

Existing Condition

Page 25: SR 252 Section DSR PA 252 (Palmers Mill Road Bridge) over ... · Replace bridge over spillway and roadway barrier along NB shoulder/length of dam • Maintain 2 lanes of traffic during

Marple and Upper Providence Township Meetings || SR 0252, Section DSR Bridge Replacement Project || January 24, 2019

Existing Condition

New Retaining Wall Rendering(Large-Scale Random Ashlar Stone)

Page 26: SR 252 Section DSR PA 252 (Palmers Mill Road Bridge) over ... · Replace bridge over spillway and roadway barrier along NB shoulder/length of dam • Maintain 2 lanes of traffic during

Marple and Upper Providence Township Meetings || SR 0252, Section DSR Bridge Replacement Project || January 24, 2019

Project Schedule

Project Let: October 4, 2018

Contractor: JD Eckman, Inc.

Construction NTP: November 19, 2018

Construction Completion Date: Oct 18, 2021