spmp online photo gallery

Upload: sumit-kumar

Post on 03-Mar-2016

43 views

Category:

Documents


0 download

DESCRIPTION

what is online photo gallery? all these questions solved in these document.

TRANSCRIPT

  • Sumit Kumar (1310013) Software Engineering Lab (BTCS-606)

    1

    7. FLOW CHART 11

    8. DFDS 12

    8.1 Context level 12

    8.2 Level 1 13

    8.3 Data Dictionary 14

    9. UML DIGRAMS 15

    9.1 Use Case diagram 15

    9.2 Class and Object diagram 16

    9.3 Sequence diagram 17

    9.4 Collaboration diagram 18

    9.5 Activity diagram 19

    9.6 State diagram 20

    9.7 Deployment diagram 21

    9.8 Component diagram 22

    TABLE OF CONTENTS PAGE NO.

    1. INTRODUCTION 2

    1.1 Objectives 2

    1.2 Major Function 2

    2. PROJECT ESTIMATE 4

    2.1 Estimation technique used 4

    2.2 Effort, Resource, Cost and Project duration estimate 4

    3. SCHEDULE 5

    3.1 Task Network Representation 5

    3.2 Gantt chat 5

    3.3 PERT chart 6

    4. PROJECT RESOURCE 7

    4.1 People/Staff 7

    4.2 Hardware and Software 7

    4.3 Special resource 7

    5. STAFF ORGANIZING 8

    5.1 Team Structure 8

    5.2 Management reporting 8

    6. RISK MANAGEMENT PLAN 9

    6.1 Risk Analysis 9

    6.2 Risk Identification 10 6.3 Risk Estimation

  • Sumit Kumar (1310013) Software Engineering Lab (BTCS-606)

    2

    1. INTRODUCTION

    The SPMP (Software Project Management Plan) is created for the e-Hotel Project. The Purpose of this

    document is to ensure that SWOT analysis have properly been done with respect to the cost and benefit

    analysis for the Online Photo Gallery project.

    1.1 Objectives

    Used to store photos for lifetime.

    Can be shared with public or private.

    Visitors belonging to access category which has access permission "Write" or Read are allowed: to

    post or download photos.

    1.2 Major Functions

    User can download or share photos.

    Guest can view photos which marked as public.

    User can comment or like any of photos.

    Report on Online Photo Gallery:

    Online Photo Gallery is an online application, which is used to display and Download photos of users. Users

    can register online for being a member in the photo gallery and each user can upload the photo of their photo

    under the respective categories. They can host their photo sell for fixed price. Photo lovers have to go to the

    photo exhibition to collect their favorite photos. But now-a-days they are not getting enough time to get

    surfing websites for downloading his/her favourite photos.

    Online Photo Gallery is application software and it is very helpful for the photo lovers and others who want to

    know the addresses where this kind of photos will we sold. This application helps the end-users to search their

    photos and they can purchase the selected photos. The end-user can also get the information about the photo

    exhibition and the respective information about user.

    Photo Gallery brings you an opportunity to view online categorized photos at our Online Photo Gallery we

    bring you details of all photos. The Online Photo Gallery is updated daily, so the user can view and buy the

    latest collection of contemporary photo online from anywhere in the world. You can view and buy the latest

    photo collection available at the premium section.

    Proposed system is an Image Gallery. According to designate we can create an account. Our proposed system

    has the following advantages:

    User friendly Interface

    Fast access to database

  • Sumit Kumar (1310013) Software Engineering Lab (BTCS-606)

    3

    Less error

    Storage Capacity

    Some Specifications of project:

    User should be able to register and log in.

    Once user logged in, his Homepage should be seen.

    On Homepage user should see:

    o Albums

    o Specials

    o Menu

    o Identification

    On clicking any of his album user should see album details and images in particular album.

    On clicking any of the image should be shown with greater resolution and user can download image

    also.

    Image and album should have remove option. On clicking it album or image should be removed from

    database (Only by Admin).

    Registration: Users can register within a minute and upload their photos. And creates own albums.

    Login: Users can login after registration or also login via Facebook or Google+ securely with our

    authorization application.

    Share: User also shares their photos on Facebook, Twitter, Tumbler and Google+. By clicking on their

    buttons.

    Privacy: User can publish their photos Private or Public. Private photos only visible to the uploader and

    Public visible to all users.

    Freeware: Users can download or save picture which shared as public. And feel free to comment or

    rate pictures.

    Categories: Default pictures categorized in different-different manners such as Games, Nature and

    Babies etc.

    Platforms: Website also accessible from smart phones and Tablets with compact features.

    Premium: Some pictures categorized as specials which guests cant download they have to register

    first and then login.

    Resolutions: Pictures available in different resolutions such as different for HDTv, Desktops and for

    Smart Phones.

    User Interface: Online photo gallery website provides users a simplify interface which also provides

    features such as search. With the help of search user can easily find his favourite photos.

  • Sumit Kumar (1310013) Software Engineering Lab (BTCS-606)

    4

    2. PROJECT ESTIMATE

    2.1 Estimation techniques used

    The COCOMO cost estimation model is used by thousands of software project managers, and is based on a study of hundreds of software projects. Unlike other cost estimation models, COCOMO is an open model, so all of the details are published, including:

    The underlying cost estimation equations Every assumption made in the model (e.g. "the project will enjoy good management") Every definition (e.g. the precise definition of the Product Design phase of a project) The costs included in an estimate are explicitly stated (e.g. project managers are included, secretaries

    aren't)

    2.2 Effort, Resource, Cost and Project duration estimate

    The basic COCOMO equations take the form: Suppose size is 200 KLOC,

    Organic 2.4(200)1.05

    = 626 staff-months

    Semi-Detached 3.0(200)1.12

    = 1,133 staff-months

    Embedded 3.6(200)1.20

    = 2,077 staff-months

    Duration = 75% * 12.1 Months=9.1Months

    Effort Adjustment Factor = EAF = 1.34*1.09 * 1.43 = 2.09

    Effort = 2.94 * (2.09) * (8)1.0997 = 60.4 Person-Months

    Average staffing = (60.4 Person-Months) / (9.1 Months) = 6.7 people

  • Sumit Kumar (1310013) Software Engineering Lab (BTCS-606)

    5

    3. SCHEDULE

    3.1 Task network representations

    A task network, also called an activity network, is a graphic representation of the task flow for a project. It is sometimes used as the mechanism through which task sequence and dependencies are input to an automated project scheduling tool.

    Name February March April

    Survey

    Requirements

    Diagrams Flow charts

    DFD diagrams

    UML diagrams

    Report created

    1.2

    Requirement Analysis

    1.3

    Feasibility Study

    1.1

    Cost Estimated

    1.4

    Time Duration

    1.5

    Flowchart 1.7

    Risk Analysis

    1.6

    DFDs 1.8

    UML Diagrams

    1.9

    Finish

    H/w and S/w Resources

    1.3.1

    3.2 Gantt chat

    Gantt chart is a special type of bar chart where each bar represents an activity. The bars are drawn along a

    time line. The length of each bar is proportional to the duration of time planned for the corresponding activity.

    It is mainly used to allocate resources to activities. The resources allocated to activities include staff,

    hardware, and software.

  • Sumit Kumar (1310013) Software Engineering Lab (BTCS-606)

    6

    3.3 PERTT Chart A PERT chart is a graphic representation of a project's schedule, showing the sequence of tasks, which tasks

    can be performed simultaneously, and the critical path of tasks that must be completed on time in order for

    the project to meet its completion deadline.

    The PERT chart of this application is:

    Requirements

    Analysis

    2,5,6

    Implementation

    5,10,15

    Feasibility

    study

    2,4,6

    Information

    gathered

    3,4,5

    Flow chart

    4,5,6

    Finish

    10,15,20

  • Sumit Kumar (1310013) Software Engineering Lab (BTCS-606)

    7

    4. PROJECT RESOURCE

    These are those resources which are used to develop this online project.

    4.1 People/Staff Project managers cannot, and must not, do everything. They must rely on the project team to complete the project work. They are rely on their resources the major one is Human Resource and some others are machines, printers a room for meetings (to what to do or not), Internet connectivity and servers. 4.2 Hardware and Software

    Hardware specifications are:

    One monitor

    One keyboard

    One mouse

    Hard disk

    1GB Hard Disk Space

    Software specifications are:

    O.S. Platform Windows XP /Vista/7/8/8.1

    C.MS. Tool Piwigo

    .Net Framework 3.5 or Later

    Web Browser like Mozilla Firefox

    4.3 Special resource

    Additional resources:

    Internet

    One domain name

    Hosting from any Internet domain registrar website.

  • Sumit Kumar (1310013) Software Engineering Lab (BTCS-606)

    8

    5. STAFF ORGANIZING

    The staff hierarchy, in which the departments are revenue consumers, and their managers are responsible for activities that support line functions (such as maintenance, designing). While both hierarchies have their own chains of command, a manager may have direct control over staff employees but a staff manager may have no such power over the line employees. In modern practice, however, the difference in the two hierarchies is not so clear-cut and jobs often have elements of the both types of functions. 5.1 Team Structure

    Team structure refers to the composition of an individual team or of a multi-team system. Team

    structure is an integral part of the teamwork process. A properly structured patient team is an

    enabler for and the result of effective communication, leadership, situation monitoring, and mutual

    support. A website designer might be working with business managers and network specialists to

    create a application for presenting internal management information on sales - both as part of the

    same project.

    5.2 Management reporting

    Management reporting is the process of providing agency management with timely, accurate and

    relevant information that is designed to assist the strategic and operational management of an

    agency.

    Project Manager

    System Administrator Technical

    Hardware

    Software

    Maintenance

    Enhancements Conversion

    Testing

    Interfaces

  • Sumit Kumar (1310013) Software Engineering Lab (BTCS-606)

    9

    6. RISK MANAGEMENT PLAN

    A Risk Management Plan is a document that a project manager prepares to foresee risks, estimate impacts, and define responses to issues. It also contains a risk assessment matrix. A risk is "an uncertain event or condition that, if it occurs, has a positive or negative effect on a project's objectives."

    6.1 Risk Analysis

    Risk analysis is a technique used to identify and assess factors that may jeopardize the success of a

    project or achieving a goal.

    In the project, theres a table where you can analyses the risks:

    List the potential risks Assign a probability to each risk (1 is low, 5 is high) Assess the severity should the risk occur (1 is low, 5 is high) Give each risk a score (probability times severity)

    6.2 Risk Identification

    In the project plan template, theres a table where you can analyses the risks:

    List the potential risks Assign a probability to each risk (1 is low, 5 is high) Assess the severity should the risk occur (1 is low, 5 is high) Give each risk a score (probability times severity)

    6.3 Risk Estimation

    When estimating a project it is important to understand what stage the project is in as this will

    determine the level of project estimation accuracy required. For example, if the project is in the

    initiation stage, the project estimate may have an accuracy of 50%. Determine the specific effect that

    each risk may have on your projects product, schedule, and resource performance. When evaluating these

    effects, do the following:

    Consider the effect of a risk on the total project rather than on just part of it. Taking one

    week longer than you planned to complete an activity may cause you to miss intermediate

    milestones (and cause the personnel waiting for the results of that activity to sit idle).

    Consider the combined effect of related risks. The likelihood that your schedule will slip is

    greater if three activities on the same critical path have a significant risk of delay rather than

    just one.

  • Sumit Kumar (1310013) Software Engineering Lab (BTCS-606)

    10

    RISK FACTOR

    QUALITATIVE RISK RANKING GUIDELINES

    LOW

    MEDIUM

    HIGH

    TECHNOLOGY - Conventional/off-the- shelf

    - Extensive previous facility application

    - Little or no testing required

    - Proven state of the art

    - Some previous facility or site application

    - Some proof of application testing required

    - Unproven/new

    - Little or no previous facility or site application

    - Extensive proof of principle testing required

    - Complex/highly engineered

    INTERFACES - Little or no impact from other site programs

    - Established and mature interfaces and working relationships used

    - Potential impact from other site operations, programs or contractors

    - Some new interfaces must be established and managed

    - Potential MAJOR impact from other site operations, or contractors

    - Multiple and/or complex interfaces required which may include competing objectives

    TIME/SCHEDULE - No known schedule constraints

    - Predecessor and successor actions are simple and clearly identified and understood.

    - No assumptions with regard to performance

    - Resources identified, committed and under facility control

    - Some schedule constraints exist by won't affect completion date

    - Assumptions have been validated

    - Multiple schedule constraints/compressed schedule

    - Activities developed only to conceptual level (multiple invalidated assumptions)

    LABOR - Low to moderate skill

    - Readily available

    - Gradual buildup

    - Moderate/high skill

    - Restricted availability

    - Phased buildup

    - Moderate/high skill

    -Severely restricted availability

  • Sumit Kumar (1310013) Software Engineering Lab (BTCS-606)

    11

    7. FLOW CHART:

    A flowchart is a graphical representation of decisions and their respective results mapped out in

    individual shapes that were first developed by Herman Goldstine and John von Neumann in the

    1940's. Flowcharts provide a step-by-step diagram for mapping out complex situations, such as

    programming code or troubleshooting problems with a computer. The picture to the right shows an

    image from Microsoft Visio, a popular program used to design and create flowcharts and diagrams.

    Flow Chart for Online Photo Gallery:

    START

    Online Photo Gallery

    Categories

    Albums

    Specials

    Menu

    Identification

    Retrieve Information

    End

  • Sumit Kumar (1310013) Software Engineering Lab (BTCS-606)

    12

    8. DFDs

    DFD (Data Flow Diagram)

    A data-flow diagram (DFD) is a graphical representation of the "flow" of data through an

    information system. DFDs can also be used for the visualization of data processing (structured

    design).

    On a DFD, data items flow from an external data source or an internal data store to an internal data store or an external data sink, via an internal process.

    Level 0 or Context Level

    A System Context Diagram (SCD) is a diagram that defines the boundary between the system, or

    part of a system, and its environment, showing the entities that interact with it. This diagram is a

    high level view of a system.

    Level 0 for Online Photo Gallery:

    Member Photo Gallery

    0 User

    Admin

  • Sumit Kumar (1310013) Software Engineering Lab (BTCS-606)

    13

    LEVEL 1

    Level 1 DFDs aim to give an overview of the full system. They look at the system in more detail.

    Major processes are broken down into sub-processes. Level 1 DFDs also identifies data stores that

    are used by the major processes. When constructing a Level 1 DFD, we must start by examining the

    Context Level DFD. We must break up the single process into its sub-processes. We must then pick

    out the data stores from the text we are given and include them in our DFD.

    Level 1 DFD for Online Photo Gallery

    Users

    Add Photos

    0.1

    Create Category

    0.2 Change Theme

    0.3

    Delete Comments

    0.4 Post Comments

    0.5

    Remove Users

    0.6

    Admin

    Like Photos

    0.9 Post

    Comments 0.8

    Add Albums

    0.7

  • Sumit Kumar (1310013) Software Engineering Lab (BTCS-606)

    14

    Data Dictionary

    A data dictionary is a collection of descriptions of the data objects or items in a data model for

    the benefit of programmers and others who need to refer to them. A first step in analyzing a

    system of objects with which users interact is to identify each object and its relationship to

    other objects.

    Admin

    Field Name

    Data type Constraint Description

    Admin_id

    Number

    Primary key

    Admin id, Auto generated

    Admin_name

    Varchar

    Not null

    Name of Admin

    Password

    Varchar2

    Not null

    Login Password for Admin

    Contact_no

    Number

    Not null

    Landline or mobile number

    Email_id

    Varchar2 Not null

    Any email id

    User

    Field Name

    Data type Constraint Description

    User_id

    Number

    Primary key

    Admin id, Auto generated

    User_name

    Varchar

    Not null

    Name of Admin

    Password

    Varchar2

    Not null

    Login Password for Admin

    Activation_date

    Date

    Not null

    Starting date

    Contact_no

    Number

    Not null

    Landline or mobile number

    Email_id

    Varchar2 Not null

    Any email id

  • Sumit Kumar (1310013) Software Engineering Lab (BTCS-606)

    15

    9 UML DIAGRAMS

    The Unified Modeling Language (UML) is a general-purpose modeling language in the field of

    software engineering, which is designed to provide a standard way to visualize the design of a

    system.

    9.1 Use Case diagram A use case is a methodology used in system analysis to identify, clarify,

    and organize system requirements.. An actor is a role played by a user with respect to the

    system use. It is possible that the same user may play the role of multiple actors. Each actor can

    participate in one or more use cases.

    Online Photo Gallery

    Registration

    getprofile

    View Gallery

    Search By Name

    Login

    Guest

    Admin

    Member

  • Sumit Kumar (1310013) Software Engineering Lab (BTCS-606)

    16

    9.2 Class and Object diagram

    A class diagram is an illustration of the relationships and source code dependencies among

    classes in the Unified Modeling Language (UML). In this context, a class defines the methods

    and variables in an object, which is a specific entity in a program or the unit of code

    representing that entity. An object diagram in the Unified Modeling Language (UML), is a

    diagram that shows a complete or partial view of the structure of a modeled system at a

    specific time.

    User + Name

    + E-mail

    + PhoneNumber

    + addpost()

    + likepost()

    + commentpost()

    Admin

    + Name

    + E-mail

    +PhoneNumber

    +State

    + editpost() + commentpost() + checkpost() + deletepost() + createcategory() + changetheme()

    User

  • Sumit Kumar (1310013) Software Engineering Lab (BTCS-606)

    17

    9.3 Sequence diagram A Sequence diagram is an interaction diagram that shows how processes operate with one another and what is their order. It is a construct of a Message Sequence Chart. A sequence diagram shows object interactions arranged in time sequence. The lifeline indicates the existence of the object at any particular point of time. The rectangle drawn on the lifetime is called the activation symbol and indicates that the object is active as long as the rectangle exists.

    Browser Login Dashboard Online Photo Gallery

    Login

    View site

    Login

    Add post

    update

    Delete post

    update

    Change theme

    update

    Create Category

    update

    Success

    Update apply

    Website Updated

    Admin

  • Sumit Kumar (1310013) Software Engineering Lab (BTCS-606)

    18

    9.4 Collaboration diagram

    A Collaboration Diagram is a diagram that shows object interactions organized around the objects and their links to each other. Unlike a Sequence Diagram, a Collaboration Diagram shows the relationships among the objects. Sequence diagrams and collaboration diagrams express similar information, but show it in different ways. It is an interaction diagram that shows, for one system event defined by one Use Case, how a group of objects collaborate with one another. Unlike a Sequence Diagram, a collaboration diagram shows relationships among object roles and it does not express time as a separate dimension. Therefore, the messages in a collaboration diagram are numbered to indicate their sequence.

    User

    Admin

    4. verifyLogin() 8. showUserList()

    2. showLogin() 5.showOptions()

    3. Login() 6. selectOption()

    ViewUsersUI

    ViewUsers

    User Admin

  • Sumit Kumar (1310013) Software Engineering Lab (BTCS-606)

    19

    9.5 Activity diagram

    Activity diagrams are graphical representations of workflows of stepwise activities and actions

    with support for choice, iteration and concurrency. In the Unified Modeling Language, activity

    diagrams are intended to model both computational and organizational processes (i.e.

    workflows). Activity diagrams show the overall flow of control.

    The below is the Registration activity diagram for Online Photo Gallery website is to provide

    details about how new user or admin registration to the website.

    [Enter Username and Password]

    Get Details

    [Submit]

    Validate Data

    Rejected

    Error

    Accepted

    yes

    or no

  • Sumit Kumar (1310013) Software Engineering Lab (BTCS-606)

    20

    9.6 State diagram

    A state diagram is a type of diagram used in computer science and related fields to describe the

    behavior of systems. State diagrams require that the system described is composed of a finite

    number of states; sometimes, this is indeed the case, while at other times this is a reasonable

    abstraction. Many forms of state diagrams exist, which differ slightly and have different

    semantics.

    Modified items need uploaded

    New photo to be uploaded

    More new photos

    AddDiscussionBoardPhoto

    UpdateListPhotos

    No new discussion photos. Modified items need uploading

  • Sumit Kumar (1310013) Software Engineering Lab (BTCS-606)

    21

    9.7 Deployment diagram

    The deployment diagram specifies a set of constructs that can be used to define the execution

    architecture of systems that represent the assignment of software artifacts to nodes. Nodes are

    connected through communication paths to create network systems of arbitrary complexity.

    Nodes are typically defined in a nested manner, and represent either hardware devices or

    software execution environments. Artifacts represent concrete elements in the physical world

    that are the result of a development process.

    Workstation Web Server

    Presentation Layer

    Database Layer

    User

    Browser

  • Sumit Kumar (1310013) Software Engineering Lab (BTCS-606)

    22

    9.8 Component diagram The Component Diagram helps to model the physical aspect of an Object-Oriented software system. It illustrates the architectures of the software components and the dependencies between them. Those software components including run-time components, executable components also the source code components.

    Database Server Web Server

    Presentation Layer

    Database Interface

    Web Browser

    MySQL Database

    Log File

    User