spheres iss flight preparation & hardware status 08 july 2002 steve sell ([email protected])...
TRANSCRIPT
SPHERES
Payload Systems Inc
ISS Flight Preparation & Hardware Status
08 July 2002
Steve Sell ([email protected])
Stephanie Chen ([email protected])
SPHERES
Payload Systems Inc2
Agenda
• Payload Systems activities
• Mission description and logistics
• Integration activities
• Hardware build status
SPHERES
Payload Systems Inc3
Payload Systems Activities
SPHERES
Payload Systems Inc4
Payload Systems Activities
• Design and construct SPHERES flight hardware– Spheres– Beacons– Laptop hardware
• Conduct NASA International Space Station integration activities– Safety review process– Develop experiment procedures– Conduct crew training– Create Graphical User Interface (GUI)– Conduct training of ISS crews
• Conduct hardware analyses and testing– Safety verification analysis– Flight certification testing
• Vibration• EMI acoustic
SPHERES
Payload Systems Inc5
Mission Description and Logistics
SPHERES
Payload Systems Inc6
Major Components
SPHERES Satellites
Laptop Assembly
Ultrasound Beacon
(5 Total)
SPHERES
Payload Systems Inc7
Hardware Components
• SPHERES consists of three “satellites”, eight inches in diameter
– Each satellite is self-contained with power (AA batteries), propulsion (CO2 gas), computers, and navigation equipment
– The satellites communicate with each other and an ISS laptop through a low-power wireless (RF) link
• Five ultrasound beacons located in the SPHERES work envelope act as a navigation system
– Each beacon is self-contained and uses two AA batteries
– A single beacon is approximately the size of a pager
– Operational volume is 6’ x 6’ x 6’ (up to 10’ x 10’ x 10’ is possible)
PADS beacon
Satellite
SPHERES
Payload Systems Inc8
SPHERES Satellite
+ Z
- Y
- XUltrasonic receivers
CO2 tank
Adjustable regulator
Pressure gauge
Thruster
Satellite body axes
Diameter 8 in (0.2 m)
Mass 7.85 lb (3.56 kg)
Thrust(single thruster)
<1 oz (0.2 N)
CO2 Capacity 6 oz (170g)
SPHERES
Payload Systems Inc9
Operational Configurations
• Mode 1: Single satellite operations– Long term station-keeping– Minimum propellant maneuvers
through pre-determined profiles• Isolated multidimensional rotation,
multidimensional translation• Combined rotation & translation
• Modes 2 and 3: Multiple satellite operations (two or three satellites)– Docking– Topological orientations
• Independent control• Collision avoidance• Hierarchical control (leader-follower)• Distributed control (consensus)
Example configurations on the KC-135
SPHERES
Payload Systems Inc10
Satellites perform formation flying maneuver
Uplink protocols to OPS LAN prior to SPHERES ops
Each satellite calculates position from PADS
beacons
Appropriate thrusters fire
Transfer protocol/commandsvia wireless link to satellites
Data continuously downloaded to laptop
Downlink experiment data to ground after SPHERES ops
Control loop
ISS Laptop
ISS Laptop
Typical Test Session
SPHERES
Payload Systems Inc11
Typical Crew Operations
Load tanks & battery packs
into satellites
Upload protocols from laptop to
satellites
Run protocols from laptop
Unstow equipment
Satellites out of gas / power?
Setup test area(position US beacons)
NO
YESTest session over?
YES
NO
Take down and stow equipment
SPHERES
Payload Systems Inc12
SPHERES GUI (Sample)
SPHERES
Payload Systems Inc13
Mission Logistics
• SPHERES manifested on ISS for two increments– Ascent flight ISS-12A.1 (STS-116, June 2003), – Resupply flight ISS-13A (STS-117, September 2003) for replacement of
consumables– Descent flight ISS-15A (STS-119, January 2004)
• Operation Time– Allocated 20 hours operation time (nominally spread over twelve sessions)
• Initial stowage requirements– Three SPHERES satellites– Five US beacons– Laptop transmitter– Consumables (CO2 tanks and battery packs)– Spares TBD
SPHERES
Payload Systems Inc14
Stowage Allocation
• SPHERES is allotted 1.83 Middeck Locker Equivalents (MLEs) over ascent and resupply flights– 1.5 MLE total on ascent flight– 0.33 MLE total on one resupply flight
• Stowage allocated in Cargo Transfer Bags in the SpaceHab Module– Possible to be stowed in any locker location
SPHERES
Payload Systems Inc15
Consumables
• Two approaches were taken to determine consumable estimates: top-down (fixed stowage constraint) and bottom-up (fixed operation hours)
• CO2 tanks– Part of the SPHERES mission investigates
ways to minimize propellant usage– This means that no exact number of tanks
can be determined for total operations– Initial estimate is 94 tanks
• Batteries– Current estimate is 88 battery packs
Replacement CO2 tanks and battery packs
SPHERES
Payload Systems Inc16
ISS Equipment
• Workstation
– SPHERES will use Payload Equipment Restraint System (PERS) as a temporary workstation
– H-Strap interfaces with seat track provide two sides of velcro
• Attach laptop restraint for configurable laptop station
• Belly bag can be used to contain extra hardware (satellites) during test session
H-StrapLaptop Restraint Belly Bag
SPHERES
Payload Systems Inc17
ISS Lapto
p
Handrail clamp
ISS Equipment
• Laptop– SPHERES GUI runs protocols from
laptop • Protocols uplinked to OPS LAN but no
connection is required during testing
– Data stored on laptop until downlinked to ground following test session
• US beacons will attach to seat-track interfaces and/or handrail clamps– Locations will be entered into laptop prior
to operations
SPHERES
Payload Systems Inc18
Operational Scenarios
Envisioned operations in ISS Node 1 Envisioned operations in US Lab
• SPHERES will operate in United States Operational Segments (USOS) only
• Ideal test area is 6’ x 6’ x 6’– Most likely will operate in 5’ x 5’ x 10’, given ISS Node configuration
SPHERES
Payload Systems Inc19
Integration Activities
SPHERES
Payload Systems Inc20
Integration Status & Milestones
• Status– Completed Phase II Safety Review Feb 2002
– Payload Integration Agreement baselined June 2002
– Preliminary draft of crew procedures submitted June 2002
– First test of positioning system in ISS node mockup conducted June 2002
• Upcoming milestones– KC test of engineering Sphere scheduled July 2002
– October 2002 – EMI and Vibe testing
– November 2002 – Payload Training Dry Run
– November 14, 2002 – Phase III Safety Review
– December 2002 – Training Session 1
– January 31, 2003 – Flight hardware delivery to JSC
– June 5, 2003 – Launch on STS-116, 12A.1 to ISS
SPHERES
Payload Systems Inc21
Hardware Build Status
SPHERES
Payload Systems Inc22
Flight Hardware Status
• First unit build is 95% complete: all components are in-house– All structural components completed and assembled– All avionics components completed and assembled– All pressurized components installed– Not all tubing and wiring has been routed– Shell is prototype
• Anticipated 100% complete build in 1-2 weeks
SPHERES
Payload Systems Inc23
Structural Frame
• Aluminum structure – Six laser cut rings– Six sheet metal
brackets – Twelve cross members– Provides stiffness and
mounting points for satellite components
Laser cut rings
Cross members
Metal bracket
SPHERES
Payload Systems Inc24
Structure
SPHERES
Payload Systems Inc25
Electronics Board Locations
• Electronics are divided into two assemblies– PADS and computing
• Signal processing
• Computing
– Propulsion and power• Thruster valve control
• Power distribution
PADS and computation boards
Propulsion and power boards
SPHERES
Payload Systems Inc26
Assembly - Avionics
SPHERES
Payload Systems Inc27
Structural Assembly Stage One
• Electronics assemblies– Electronics are assembled inside a partial structure and wired– Avionics can be tested on the bench top
SPHERES
Payload Systems Inc28
Structural Assembly Stage One
SPHERES
Payload Systems Inc29
Structural Assembly Stage Two
• Remaining sheet metal brackets are attached– Battery packs and regulator/tank assembly can then be
installed
Mounting brackets
SPHERES
Payload Systems Inc30
Structural Assembly Stage Two
SPHERES
Payload Systems Inc31
Structural Assembly Stage Three
• Propulsion system tubing is routed– Tubing is assembled prior to final structural element placing
– Manifolds distribute gas from CO2 tank to twelve thruster nozzles
Tubing manifolds Thrusters
SPHERES
Payload Systems Inc32
Structural Assembly Stage Three
SPHERES
Payload Systems Inc33
Full Assembly• Satellite is fully functional without shell
Aluminum frame
CO2 tank
Thruster
Pressure gauge
Battery pack
Ultrasonic receiver
SPHERES
Payload Systems Inc34
Full Assembly
SPHERES
Payload Systems Inc35
External Shell Structure
• Two part shell assembly– Constructed of polycarbonate
– Secured with four fasteners per side– Hinged door for battery access– Cut-outs for thrusters and sensors
Attachmentscrew
Polycarbonate half shell
SPHERES
Payload Systems Inc36
Schedule Milestones
• July 29 - August 3, 2002 – KC-135 Flights
• October 2002 – EMI and Vibe testing
• November 2002 – Payload Training Dry Run
• November 14, 2002 – Phase III Safety Review
• December 2002 – Training Session 1
• January 31, 2003 – Flight hardware delivery to JSC
• June 5, 2003 – Launch on STS-116, 12A.1 to ISS