specifications for electrical
TRANSCRIPT
8/2/2019 Specifications for Electrical
http://slidepdf.com/reader/full/specifications-for-electrical 1/25
PROPOSED CHURCH, PRIEST HOUSE AND BOUNDARY FENCE ON
PLOT No. LR 1/564 KILIMANI
FOR
ETHIOPIAN ORTHODOX CHURCHP.O. BOX 76025
NAIROBI
ELECTRICAL ENGINEERING SERVICES SUB - CONTRACT
CONDITIONS, SPECIFICATIONS AND BILLS OF QUANTITIES.
NAME OF TENDERER: .....................................................................….
........................................................................................................................
ELECTRICAL ENGINEER PROJECT MANAGER
SYNCHROCONSULT ASSOCIATES GADO CONSULTING ENGINEERS
P. O. BOX 79626 00200 P.O. BOX 54400NAIROBI NAIROBI
8/2/2019 Specifications for Electrical
http://slidepdf.com/reader/full/specifications-for-electrical 2/25
JULY 2005
INSTRUCTIONS TO TENDERERS
1. Tenders shall be submitted on the form of tender attached and all blanks in thisspace are to be filled.
2. The tenderer and all other recipients of this document are to treat it as private and
confidential.3. The employer does not bind himself to accept the lowest or any tender and will not
be responsible for paying any expenses of losses which may be incurred by any
tenderer in the preparation of his tender.4. The tender and all accompanying documents shall be enclosed in a plain sealed
envelope marked : Proposed Church, Priest House and Boundary fence on plot No.
Lr 1/564 Kilimani
5. The sub-contract will deem to have been awarded when formal notice is given tothe tenderer that the employer has accepted the tenderers proposals.
6. The tender must be received at the address given below not later than 12.00 noon
on the day stated in the covering letter :-
ETHIOPIAN ORTHODOX CHURCH
P.O. BOX 76025NAIROBI.
2
8/2/2019 Specifications for Electrical
http://slidepdf.com/reader/full/specifications-for-electrical 3/25
FORM OF TENDER
ELECTRICAL SERVICES
TO : ETHIOPIAN ORTHODOX CHURCH
P.O. BOX 48231 00100
NAIROBI
1. I/We understand that works, the subject of this Tender, are covered by a prime cost
of provisional sum in the main contract entered into by the main contractor.
I/We shall become a Nominated sub-Contractor, that is to say, a sub-contractor nominated by the interior designers under the terms and conditions of the current
form of agreement and schedule of conditions , of Building Contract published by
the interior designers Sural Association of Kenya (latest edition with quantities).
2. It is confirmed that I/we have notice of all the provisions of the main contract
including the detailed prices of the contract in the schedule and Bill of Quantities.
I/We undertake in accordance with the particulars set out in the preliminaries and tothe satisfaction of the interior designers, to execute and complete the sub-contract
works as described in the specification and drawings for the sum of KENYA
SHILLINGS ............................................................................................................................... only (KSH............................................/=)
3. I/We confirm that this Tender is subject to adjustments by any variation ordered bythe interior designers in accordance with the terms of the main contract.
4. I/We undertake to commence the works within 7 days from the date of official
confirmation of the acceptance of the Tender.
5. I/We further undertake to complete the work in accordance with the Main
Contractors programme.
6. I/We agree that this Tender shall be open for acceptance by the interior designers
within 90 days from the date given below.
7. I/We understand that you are not bound to accept the lowest or any Tender.
For and on behalf of :
..........................................................................................................................……………..
................................................................................................................................................
......................................................................................................................................……..
Signature/Official Stamp : …….............................................................................……....
Date :.......................................................................………………………………………..
3
8/2/2019 Specifications for Electrical
http://slidepdf.com/reader/full/specifications-for-electrical 4/25
..........................................................................................................................................…..
CLAUSE DESCRIPTION PAGE
1.00 PART A: CONTRACT PRELIMINARIES & CONDITIONS
1.01 descriptions 7-9
1.02 Imported fittings 10
1.03 Sub-Contract Agreement 10
1.04 Firm Price Contract 101.05 Prime Cost & Provisional Sum 10
1.06 Guarantee 101.07 Storage of Materials on site 10
1.08 Principal Contractor's Liability 10
1.09 Labour 10
1.10 Supervision 10
1.11 Facilities for Inspection 10
1.12 Discrepancies 10
1.13 Variations 10
1.14 Ordering of Materials 111.15 Faulty Work or Materials 11
1.16 Final Account 11
1.17 Validity of Tender 111.18 Existing Property 11
1.19 Samples 11
1.20 Site Conditions 11
1.21 Materials, Tools, Plants 11
1.22 Insurance 111.23 Casing Up and Protection 11
1.24 Defect Liability Period 11
1.25 Bond 11
1.26 Damages For Delay 11
1.27 Clear Away on Completion 11
1.28 Security 11
1.29 Measured Work 11
1.30 Setting Out 12
1.30A Taxes and duty 13
1.31 Fair Wages 131.32 Government ordinance and regulations 13
1.33 Scope of Contract 13
1.34 Housing 13
1.35 Duration of Contract 13
1.36 Documents to be checked 13
1.37 Water, Electricity and Telephone 132.00 PART B: GENERAL SPECIFICATION FOR ELECTRICAL WORKS
2.01 Regulations and Standards Applicable 142.02 Scope 14
2.03 As Installed Drawings 14
2.04 Contract Drawing 14
2.05 Working Drawings 142.06 Materials 14
2.07 Labels 14
2.08 Galvanising 15
2.09 Cleaning and Painting 152.10 Fire Precautions 15
2.11 Radio Interference 15
2.12 Padlocks 15
2.13 Tool 15
4
8/2/2019 Specifications for Electrical
http://slidepdf.com/reader/full/specifications-for-electrical 5/25
2.14 Expansion Joint 15
2.15 MV Switchboard and Switchgear 15
CLAUSE DESCRIPTION PAGE
2.16 Circuit Breakers 15
2.17 Fuse Switches 15
2.18 Farthing and Bonding 152.19 Neutral Bars 16
2.20 Switch Fuses 162.21 Distribution Boards 16
2.22 Consumer Units 16
2.23 Labelling of Switchgear and Distribution Boards 16
2.3.00 CABLES 16
2.3.01 P.V.C. 1 Cable 16
2.3.02 P.V.C. SWA P.V.C. Cables 16
2.3.03 Mineral Insulated Cables 16
2.4.00 WIRING SYSTEMS 16
2.4.01 Method of Wiring 162.4.02 System A - Cables Enclosed in Concealed Steel Screwed Conduit or Trunking
2.4.03 System B - Cables Enclosed in Steel Screwed Conduit or Trunking Fixed to the
Surface or Walls and Ceilings
16
2.4.04 System C - PVC Insulated Cables with Insulated Earth Continuity Conductor Enclosed
in Concealed Non-Metallic Conduit or Trunking
17
2.4.05 System D - PVC Insulated Cables with Insulated Earth Continuity Conduct Enclosed
in Non-Metallic Conduit or Trunking Fixed to the Surface of Walls and Ceilings 17
2.4.06 System E - Mineral Insulated Copper Sheathed Cables 172.4.07 Steel Conduit 17
2.4.08 Steel Trunking 18
2.4.09 Non-Metallic Conduit 18
2.4.10 Flexible Conduit 18
2.4.11 Cable Trays 19
5
8/2/2019 Specifications for Electrical
http://slidepdf.com/reader/full/specifications-for-electrical 6/25
CLAUSE DESCRIPTION PAGE
2.5 Socket Outlets 19
2.6 Fused Connection Units 20
2.7 Lighting Switches 202.8 Ceiling Roses 20
2.9 Lampholders 202.10 Lighting Fitting 20
2.11 Flexible Cords 21
2.12 Earthing 21
2.13 P.M.E. System 22
2.14 Commissioning 22
3.00 PART C: PARTICULAR SPECIFICATIONS
3.01 Location of the Site 22
3.02 Description of the Project 22
3.03 Extent of the Work 223.04 Consumer Units and Distribution Boards 22
3.05 Wiring System 22
3.06 Earthing System 22
4.00 PART D: CONTRACT DRAWINGS, BILLS OF QUANTITIES 23
4.01 Contract Drawings 23
4.02 Bills of Quantities D1-D9
6
8/2/2019 Specifications for Electrical
http://slidepdf.com/reader/full/specifications-for-electrical 7/25
SUB-CONTRACT PRELIMINARIES AND CONDITIONS
1.00 PART A
1.01 DEFINITIONS
Throughout the sub-contract document units of measurement and
terms are abbreviated and shall be interpreted as follows:
EMPLOYER: ETHIOPIAN ORTHODOX CHURCH
P.O. BOX 48231 00100
NAIROBI
PROJECT MANAGER : GADO CONSULTING ENGINEERS
P.O. BOX 54400
NAIROBI.
ELECTRICAL ENGINEER: SYNCHROCONSULT ASSOCIATES
P.O. Box 79626 00200,
NAIROBI.
CONTRACTOR: The person or persons, partner- ship, firm or company whose
tender for the main contract works has been accepted and
who has entered into a contract with the employer
SUB-CONTRACT: The term ‘Sub-contract’ whereas used hereinafter and in all
sub-contract documents shall mean the person or persons, partnership, firm or company whose tender for the sub-
contract works has been accepted and who has or have
entered into a sub-contract Agreement with the contractor for
the execution and completion of the sub-contract works and
shall include his or their heirs, executors, administrators,
assigns, successor and duly appointed representative
7
8/2/2019 Specifications for Electrical
http://slidepdf.com/reader/full/specifications-for-electrical 8/25
SUB-CONTRACT AGREEMENT: The term Sub-Contract Agreement whereas used
hereinafter and in all the sub-contract documents shall meanthe latest edition of the Agreement and schedule and
Building sub-contract published by the Kenya Association of Building and Civil Engineering Contractors with the sanction
of the East Africa Institute of INTERIOR DESIGNERS as
particularly noted or amended hereafter. For the purpose of
the sub-contract works, the sub-contract Agreement shall be
read and construed together the sub-contract under the terms
of the sub-contract Agreement will be required to indemnify
the contractor against all claims and obligation in respect of
the sub-contract as those for which the contractor is liable in
respect of his contract with the employer.
SITE: The term site wherever used herein after and in all the sub-contract documents shallmean the land or other places in which the sub-contract
documents shall mean the land or other places in which the
sub-contract works are to be executed or carried out and any
other lands or places provided by the employer for the
purposes of the main contract. The sub-contractor should refer
to the main contract specification for detailed description of
the site.
mm: Shall mean millimetres.
M: Shall mean metres.
Kg: Shall mean kilogramme mass.
N: Shall mean Newtons.
B. S: Shall mean the current British Standard Specification
(pertaining to the relevant topic) published by the British
Standards Institutions.
I.E.E. Shall mean the Institute of Electrical Engineers and references
to the I.E.E. Regulations shall mean the 14th Edition of the
Institution of Electrical Engineers wiring Regulations for
Buildings, with the latest amendments.
C.P Shall mean the current British Standard Code of Practice published by the Council for codes of Practice British
Standards Institution.PROVIDE: The term ‘provide’ shall mean the supply, delivery to site of
all necessary materials and labours, installation, testing and
commissioning at site.
SPECIFICATION: The term ‘specification’ shall mean the whole of the sub-
contract document including but no restricted to:-
a) This document comprising sub-contract preliminaries,General specifications and bills of quantities.
b) The contract drawings.
8
8/2/2019 Specifications for Electrical
http://slidepdf.com/reader/full/specifications-for-electrical 9/25
BILLS OF QUANTITIES: Where the term ‘Bill of Quantities’ bears any relation to the
Sub-contract it shall mean the specification and priced or other
schedules contained herein.
CONTRACT DRAWINGS: The term ‘Contract Drawings’ shall mean those drawings listedas referred to in and forming part of the specification.
TENDER DRAWINGS: The term ‘Tender Drawings’ shall mean those drawingswhich were enclosed with and formed part of the dub-
contractor’s tender for the sub-contractor works.WORKING DRAWINGS: The term ‘Working Drawings’ shall mean those drawings
required to be prepared by the sub-contractor as hereafter
described.
RECORD DRAWINGS: The term ‘Record Drawings’ shall mean those drawings
required to be prepared by the sub-contractor showing the ‘as
installed’ and other records of the sub-contract works as
hereinafter described.
9
8/2/2019 Specifications for Electrical
http://slidepdf.com/reader/full/specifications-for-electrical 10/25
ITEM NO DESCRIPTION KSHS CTS
1.02 IMPORTED FITTINGS AND EQUIPMENT - The sub-contractor is deemed to have taken into
account the need of importation of fittings and equipment. Delay in doing so should not affect
the contract period. The interior designers must be informed of the items to be imported and
must first approve the importation of the same if they are to utilized for this project.
1.03 SUB-CONTRACT AGREEMENT - As defined under definition of terms.
1.04 FIRM PRICE CONTRACT - Unless otherwise specifically stated in the preliminaries, this is a
firm price contract and the sub-contractor must allow in his tender for any increase in the cost
of labour and/or materials during the currency of the sub-contractor. No claim for increased
costs will be entertained accepting only increased costs arising from fluctuations in duties as
defined in condition No 30 of the conditions of contract. No claim will be allowed for currencyfluctuations. All prices shall be Kenya shillings and cents.
1.05 PRIME COST AND PROVISIONAL SUMS - These sums are allowed to cover the cost of special items. All these sums will be omitted from the sub-contractor initially and added only
through instruction by the INTERIOR DESIGNERS or Engineer. Any item detailed to be
supplied out of a provisional sum any be purchased direct by the employer and supplied to the
sub-contractor on a non-basis. Alternatively, the sub-contractor may be asked to purchase such
items direct from the suppliers. If required and instructed by the Engineer, the sub-contractor
nominated by the engineer, to supply and install any equipment covered by provisional sums.
1.06 GUARANTEE - The whole of the work shall be guaranteed for a period of six months form the
date of Engineer’s certificate of completion and under such guarantee the contractor shallremedy at his expense all defects in material and apparatus due to faulty design, construction or
workmanship which may develop in that period.
1.07 STORAGE OF MATERIAL ON SITE - Space for storage will be provided on the site by the
Main Contractor but the Sub-contractor will be responsible for the provision of any lock-up
sheds or stores required.
1.08 PRINCIPAL CONTRACTOR’S LIABILITY - Space for theses shall be as stated in the latest
edition of the Contract Agreement published by the Kenya Association of Building and Civil
Engineering Contractors.1.09 LABOUR - The work shall be executed under the direction and to the entire satisfaction in all
aspects of the interior designers. The working hours shall be those worked by good
employers in the industry.1.10 SUPERVISION - The Sub-contractor shall constantly keep on the site a literate Agent or
Representative competent and experienced in the kind of work involved, who shall give his
whole time to the super-intendance of the Sub-contractor works. Such Agent or Representative
shall receive on behalf of the Sub-contractor directions and instructions from the Contractor and
such directions and instructions shall be deemed to be given to the Sub-contractor in accordance
with the conditions of the Sub-contract agreement.
1.11 FACILITIES FOR INSPECTION - The Engineer shall at all t imes during normal working
hours have access to the Sub-contractor works and to the yards and work-shops of the Sub-
contractors or other places where work is being prepared for the Sub-contract works.
1.12 DISCREPANCIES - The Sub-contractor is not expected to deviate from the specifications and
drawings. Unless expressly permitted to do so by the interior designers in writing. Any
discrepancies which are not approved will be replaced before the works are accepted as
practically complete.1.13 VARIATIONS - Variations which have a financial implication to the Sub-contract will be
priced per the priced schedules. The Sub-contractor must obtain a site instruction signed by the
Engineer and countersigned by the interior designers before additional works are
10
8/2/2019 Specifications for Electrical
http://slidepdf.com/reader/full/specifications-for-electrical 11/25
commenced. Where site instructions have a financial implication, the Sub-contractor must
ensure that the interior designers has raised a Variation order for the same.
1.14 ORDERING FOR MATERIALS - All materials used in the execution of the works shall be of
the best quality and description. Any materials for the works condemned by the interior
designers shall immediately be removed and replaced with accepted materials at the site
ITEM NO DESCRIPTION SHS CTS
at the Sub-contractor’s expense. Ordering of materials which are therefore an alternative to the
specified should only be done with the written approval of the interior designers.
1.15 FAULTY WORK OR MATERIAL - The whole of the works shall be carried out to the
satisfaction of the interior designers who shall have the right to reject any material or
workmanship which is in his opinion unsatisfactory and to instruct the Contractor to rectify
such bad workmanship forthwith at Sub-contractor’s expenses. In the event of any undue
delay, the interior designers shall have the right to employ others to supply and deduct the
cost from the contract value. In the case of poor workmanship, the interior designers may
direct that it be done otherwise and the cost thereby incurred shall be recoverable as liquidated
damages in money.
1.16 FINAL ACCOUNT - The final account shall be prepared only at the end of the defects liability period. The final retention money will only be released when the interior designers is
completely satisfied with all the works under the Main Contract unless he expressly approves
separate completion. The Sub-contractor is expected to liaise with the Engineer throughout the
contact term so that undue claims may not arise at Final Account stage.
1.17 VALIDITY OF TENDER - The Tender validity period shall be 90 days from the date of tender
opening. The interior designers may, however, request the Sub-Contractor to extend validity
for a short period if the 90 days expire before acceptance
1.18 EXISTING PROPERTY - Every care shall be exercised by the Sub-contractor to avoid damage
to all existing property. Any damage caused to the existing property during execution of this
Sub-contract will be entirely the responsibility of the sub-contractor and it will be made good
to the satisfaction of the Engineer.1.19 SAMPLES - The Sub-contractor shall furnish at his own cost any sample materials or
workmanship that may be called for by the interior designers for his approval and anyfurther samples in the case of rejection until such samples are approved by the interior designers. The interior designers may reject any materials or workmanship not in his
opinion up to the approved samples.
1.20 SITE CONDITIONS - It will be deemed that the Sub-Contractor visits the site before entering
into the Sub-contract Agreement. It shall further be deemed that he satisfies himself with
regard to access to the site, the risk of injury or damage to the property on or adjacent to the site
or to the occupiers of such property, the supply of labour and materials. It shall be deemed that
these extremities are covered in the pricing and knowledge in this respect.
1.21 MATERIALS, TOOLS, PLANTS - As described under item numbers 1.07, 1.14 and 1.15.1.22 INSURANCE - The Sub-contractor shall take out all insurance policies as required under the
terms of the Sub-contract Agreement clauses 5 and 6.
1.23 CASING UP AND PROTECTION - The Sub-contractor shall be responsible for casing up or
otherwise protecting to the satisfaction of the Engineer all parts of the Sub-contract works liableto damage and for removing such protection and making good at completion.
1.24 DEFECT LIABILITY PERIOD - The defect liability shall be six months from the date of
completion of the Contract as certified by the interior designers.
1.25 BOND -All Tenderers will submit the name of an approved surety who will be willing to be
bound to the main contractor in an amount equal to 10% of the Sub-contract amount as clause
31 of the Sub-contract Agreement.
1.26 DAMAGES FOR DELAY - Liquidated and Ascertained damages as stated in the main
Contract Agreement will be claimed against the main Contractor for any unauthorized delay in
11
8/2/2019 Specifications for Electrical
http://slidepdf.com/reader/full/specifications-for-electrical 12/25
completion. The Sub-contractor will be held for the whole or a portion of these damages
should be cause delay in completion.
1.27 CLEAR AWAY ON COMPLETION - The Sub-contractor shall upon completion of the works,
at his own expense remove and clear away all plant equipment, rubbish and unused materials,
and shall leave the whole of the works in a clean and tidy state to the satisfaction of the
interior designers. On completion, the whole of the works shall be delivered up clean,
complete and perfect in every respect to the satisfaction of the interior designers.
1.28 SECURITY -Security on site shall be the responsibility of the Main Contractor as per the
contract Agreement. The Sub-contractor is however expected to lock up his store and be
responsible for all his tools, plant etc.1.29 MEASURED WORK - These will be as per the Main Contract Agreement. All Sub-contract
works are deemed to final measurement when completed to the satisfaction of the interior
designers.
ITEM NO DESCRIPTION SHS CTS
1.30 SETTING OUT - The Sub-contractor shall set out the works in accordance with the dimensions
and levels shown on the contract drawings and shall be responsible of the correctness of all
dimensions and levels so set out by him. He will be required to amend all errors arising from
inaccurate setting out at his own cost and expenses. In the event any error or discrepancies
must be reported by the Contractor to the interior designers for his immediate consideration.
1.30A TAXES AND DUTY - The Sub-contractor shall be required to pay import duty on all items of
equipment, fittings, plant, whether imported or locally manufactured. Provision should beallowed for Value Added Tax at the prevailing Government rate and the VAT will have to be
inbuilt in the rates and is not to done separately.
12
8/2/2019 Specifications for Electrical
http://slidepdf.com/reader/full/specifications-for-electrical 13/25
ITEM NO DESCRIPTION SHS CTS
1.31 FAIR WAGES - These shall be as clause 30 of the sub-contract Agreement.
1.32 GOVERNMENT ORDINANCE AND REGULATIONS - Provisions of the FactoriesOrdinance 1950, Regulations of the Electrical Equipment of Buildings, relevant British
Standards and Codes of Practice and current Government regulations must be complied with by
the Sub-contractor and allowance must be made by him in his Tender. The Sub-contractor shall
obtain from the relevant authority fullest information regarding all such regulations at his own
expense and no claim for want of knowledge in this connection will be entertained.
1.33 SCOPE OF CONTRACT - It will be deemed that the Sub-Contractor allowed in the Sub-
contract sum for everything necessary for the proper and satisfactory execution to completion of
the works in accordance with the specification and Contract Drawings taken together and to theapproval of the Engineer. Any claims based upon qualifications included in any document
introduced by the Sub-contractor to accompany his tender will not be entertained.
The bonus for discovering any differences that may exist between the Contract Drawings and
the text of the specification shall be taken to rest with the Sub-contractor. Any such differences
should be brought to the attention of the Engineer for clarification before tenders are returned
for opening. It shall be deemed that no such discrepancy exist or that the Sub-contractor has
priced for them in the document should he not seek the clarification as stated.
Should any difference be found between the Contract Drawings and the Specification after
submission of the tender, the engineer will at his absolute discretion and without prejudice tothe employer decide the procedure to be followed and no claim based upon the Engineer’s
decision will be entertained.
It will be deemed that the Sub-contractor prior to submitting his tender for the executing and
completion of the Sub-contract works obtained all particulars, information, clarification and
explanation from the Engineer for complete and correct preparation of the tender. No claim
based on lack of knowledge in these respects will be entertained.1.34 HOISTING - This shall be as clause 25 of the Sub-contractor Agreement
In addition all casing, cutting and making good Builder’s works will be done by the Main-
Contractor after markings done by the Sub-contractor.
1.35 DURATION OF THE CONTRACT - This will be in keeping with the Main Contractor period.
1.36 DOCUMENTS TO BE CHECKED - It shall be deemed that all tender documents have beenfully checked by the Sub-contractor. The interior designers may disqualify any tender which in
his opinion has incorrect and insufficient documents.1.37 WATER, ELECTRICITY, TELEPHONE - These will be availed by the Main Contractor. The
Sub-contractor shall be liable for the cost of any services provided by the Main Contractor for
their own use, as stated in the Main Contract Agreement.
Total carried forward to price summary page : …………………………………………………………………
……………………………………………………………………………………………………………………….
13
8/2/2019 Specifications for Electrical
http://slidepdf.com/reader/full/specifications-for-electrical 14/25
Signed (as in Tender) ………………………………………………………………………………………………..
………………………………………………………………………………………………………………………...
Date : …………………………………………………………………………………………………………………
Stamp : ……………………………………………………………………………………………………………….
2.00 PART B - GENERAL SPECIFICATIONS FOR ELECTRICAL WORK
2.01 REGULATIONS AND STANDARDS APPLICABLE
The Sub-contractor works shall comply with the provisions of the following documents:-
1. General conditions of contract for sub-contract works.
2. Government Electrical specification Number 1.3. Government Electrical specification Number 2.
4. Electrical Power Act and the rules made thereunder.
5. The current edition of the ‘Regulations for the Electrical Equipment of Buildings’ issued
by the Institution of Electrical Engineers of Great Britain (with Kenya Amendment).
6. Kenya Power and Lighting Company Ltd. By-laws.
The Sub-contract shall comply with all the requirements of the Kenya Power and lighting
Company Ltd. and Kenya Posts and Telecommunication.
2.02 SCOPE - The Sub-contractor shall supply all materials and install, fix, connect, test, label,commission and deliver the electrical work, clean , complete and working in every detail as
described elsewhere in the specifications and any related specifications and drawings listed in
the schedule of drawings and to the satisfaction of the interior designers.
2.03 AS INSTALLED DRAWINGS - On completion of the work to be carried out under this
contract the electrical sub-contractor shall submit to the interior designers record or ‘As
installed drawings’. These shall be reproduced in the form of a negative (preferably plastic
film) from the original contract drawings which the contractor shall bring up to date with anyalteration made during the progress of the work. The size and scale of any drawing shallgenerally be the same as the original contract drawing unless otherwise specified by the interior
designers. On completion of the drawing they shall be endorsed as a true record of the
installation and signed by the Contractor.
The Contract will not be considered complete until ‘As installed’ drawings have been produced
and accepted by the INTERIOR DESIGNERS.
2.04 CONTRACT DRAWINGS - The contract shall be based on the drawings listed in the schedule
of the Drawings given elsewhere in this specification.
It should be noted that the contract drawings do not purport to show every detail and the
Electrical Sub-contractor shall allow for all the fittings, fixing, accessories, etc., normally
provided and required to form a complete and working installation where not specificallyshown on the tender drawings or mentioned in this specification. No deviations shall be made
form the contract drawings unless with written approval from the interior designers. Any suchdeviations will be rectified at the expense of the Contractor.
2.05 WORKING DRAWING - The Sub-contractor shall prepare working drawings as may be
necessary for the proper execution of the works including conduit layouts, switch-gear
arrangements and cable routing. Three prints of working drawings must be submitted to the
Engineer before commencement of work. One set will be signed by the Engineer and returned
for use by the Sub-contractor. The other set will be returned to the contractor and other Sub-contractors, to ensure that other services are not interfered with. In preparing working
drawings, the Sub-contractor is expected to liase closely with other contractors and allow of
their services. Alterations which may later arise due to lack of liaison will be at the Sub-
14
8/2/2019 Specifications for Electrical
http://slidepdf.com/reader/full/specifications-for-electrical 15/25
contractor’s expense.
2.06 MATERIALS - All materials required for completion of the Sub-contract works must be
supplied by the electrical Sub-contractor unless stated otherwise these materials must confirm
to both the specifications and the contract drawings.
The manufacturer’s catalogue numbers and trade names are quoted only as a guide to the type
and standard of equipment required. Equipment, similar type and standard may be used subject
to the prior approval of the interior designers in writing.2.07 LABELS - All switchgears, distribution boards, etc., shall be clearly and properly labelled in
accordance with clause 32 of GES no 1 Fuseways and circuit breakers feeding final sub-circuits
shall be labelled to show whether light or power etc. the area served and the circuit number as
given by the contract drawing. This shall be done by writing neatly on the label normally
provided with a ball-pen (not a pencil or felt tip) If no label is provided, the Sub-contractor shall
fix a specially made label of the ‘Traffolyte’ tape (Dynotape will not be accepted).
2.08 GALVANIZING - Galvanizing shall be applied by the process and shall consist of a smooth
clear zinc coating free from defects and be in uniform thickness. The thickness shall not be less
than 610gms of zinc per square meter of surface and tested in accordance with the requirements
of B.S. 729 where applicable. Sherardise or other alternative processes shall not be used
without approval in writing of the Engineer. The preparation for galvanizing and the
galvanizing itself shall not adversely affect the mechanical properties of the coated material.
Surfaces which are normally in contact with oil shall not be galvanized or cadmium plated. Allout-door structures, access ladders, platforms, equipment cubicles shall be galvanized.
2.09 CLEANING AND PAINTING - All equipment shall be cleaned of all dust, oil grease, dirt scale
and rust by power tool operated metal brush or preferably by shot or grit blasting and then
ground smooth where necessary.
Unless otherwise approved, they shall then immediately have applied to them two coats of
approved primer paint. After inspection, any rough surfaces shall be fitted in an smoothed over
and further painting done.
2.10 FIRE PRECAUTIONS - It shall be deemed that the sub-contractor has taken precautionsagainst fire inclusive of insurance cover as per the sub-contract Agreement clause 6.
2.11 RADIO INTERFERENCE - It shall be deemed that the sub-contractor has taken into account
protection against radio interference in installation where stated elsewhere.
2.12 PADLOCKS - The sub-contractor is expected to use approved padlocks to ensure safety of his
store and materials stored therein.
2.13 TOOLS - These should be as described in PART A clause 1.21.
2.14 EXPANSION JOINT - Adequate allowance shall be made for longitudinal expansion andcontraction of conduit under normal working temperature variations.
2.15 MV SWITCHBOARD AND SWITCHGEAR - Main switchboards shall either be of the cubicle
type (e.g. as English Electric Miniform) or of the composite type having a bus-bar chamber and
switchfuses of the MEM type as shown on the contract drawings. They shall have a separate
chamber(s) to install K P & L Co. Ltd incoming service cable, current transformer, meters and
all other such equipment. Ammeters, Voltmeters and other instruments shall be installed where
specified. Before constructing any type of main switchboard sub-main switchboard or
distribution centre, the sub-contractor shall submit for the approval of the interior designers a
fully dimensioned layout drawing. Any switchboard installed without the approval of the
interior designers may have to be removed. All switchboards supplied to the site shall be
complete with all necessary fuses, plugs connections support brackets, etc.2.16 CIRCUIT BREAKERS - These shall be manufactured to B.S. 3871 and of a rating as specified
on the drawings. The circuit breakers shall incorporate both thermal overload and magneticshort circuit tripping, with a trip free-mechanism. Three phase circuits shall be controlled by
integrally manufactured three pole breakers with one common operating lever. An inter-
tripping mechanism shall ensure isolation of all three poles in the event of an overload or short
circuit of any one phase.
2.17 FUSE - SWITCHES - These should be of modern compact design with a performance service,
safety and maintenance features to suit the requirements of low voltage a.c. system . Theyshould meet the requirements of B.S. 5419 with latest amendments and I.E C408 which implies
that they should accept fuse links of appropriate rating to B.S. 88. They should in addition meet
the extra requirements necessary for motor isolating switches.
15
8/2/2019 Specifications for Electrical
http://slidepdf.com/reader/full/specifications-for-electrical 16/25
Only those manufactured by ottermill, MEM Bill, English Electric or equally approved by the
Engineer are to be used.
2.18 EARTHING AND BONDING - Earth electrodes shall be minimum 1.4 metres long by 12mm
diameter hard copper rod, and shall be located not less than 3m apart at a convenient position
6m away from the building. The terminal head of each electrode shall be in a concrete
inspection pit, with cover. If the resistance to earth is not satisfactory with one electrode then
additional electrodes or an earth mat shall be provided as directed by the Engineer. All water pipes, hand-wash basins and exposed metal works must be bonded to earth as per the I.E.E.
regulations.
2.19 NEUTRAL BARS - All switchgear must be equipped with neutral bus-bars to which the service
cable neutrals will be bolted. The neutral bus-bars will be of similar size to the other bus-bars.
All distribution boards will have integral neutral bus-bars with screwed outlets per individual
circuits.2.20 SWITCH FUSES - These are to conform to BS5861, BS5419 and IEC408. In addition they
shall conform to all aspects as fuse switches i.e. clause 2.17.
2.21 DISTRIBUTION BOARDS - Lighting and power distribution boards shall comply with
B.S.3817, BS5861 and BS214 and shall be of the metal clad pattern flush mounted, except
where otherwise stated on the contract drawings.
Each board shall be fitted with an engraved identification label in black and white, such as
‘Distribution Board D.I’ etc., and all three phase boards shall be labelled in white or red,‘DANGER 415 VOLTS’.
2.22 CONSUMER UNITS - Consumer units are to conform to BS381c. They are to have bus-bars
and be able to carry miniature circuit breakers. They must be as crabtree Dorman Smith MK or
equal and approved by the Engineer.
2.23 LABELLING OF SWITCHGEAR AND DISTRIBUTION BOARDS - These are to be as
clause 2.07
2.3.01 P.V.C. I CABLES - All power and lighting wiring cables shall be 600/1000 volt grades singlecore, PVC insulated, with stranded copper conductors, manufactured in accordance withBS6006. The minimum size on lighting circuits shall be 1.5 sq mm, 4.0sqmm on power spur
circuits and 2.5sqmm on ring mains circuits.
The wiring shall be carried out on the looping-in principle. All joints shall be made at the
terminals of main switches, distribution boards ceiling roses, switches and socket outlets, etc.,
and fixed apparatus only.
2.3.02 PVC/SWA/PVC CABLES - These shall be 600/1000 volt grade to BS6346 or BS6004 having
copper conductors of plain copper wire PVC insulated, PVC sheathed, single wire armoured
and PVC sheathed overall, the cores of four core cables shall be distinctively coloured red,
yellow, blue and black. The sub-contractor shall provide suitable glands and accessories for allarmoured cable terminations and where cables are suspended shall provide the necessary cable
trays, racks, cleats or hanger supports and fixings.
Cables supports and racks shall be made by a recognised manufacturer and shall be to the
approval of the interior designers. All supports and racks shall be arranged as far as is
practicable for the easy removal of any single cable in a multi-cable run without threading
cables through supports and racks. The number of types of support and racks shall be kept to a
minimum commensurate with meeting the requirements of the contract works.2.3.03 MINERAL INSULATED CABLES
2.4.00 WIRING SYSTEMS
2.4.01 METHOD OF WIRING - The system of wiring shall be as specified in particular specification
16
8/2/2019 Specifications for Electrical
http://slidepdf.com/reader/full/specifications-for-electrical 17/25
contract drawing.
2.4.02 SYSTEM A - CABLES ENCLOSED IN CONCEALED STEEL SCREWED CONDUIT OR
TRUNKING - The wiring shall be carried out in approval type of single core, plastic insulated
cable, enclosed in steel screwed conduit or trunking mechanically and electrically continuous
throughout. Conduit shall be buried in the wall and floors of the buildings, and either run in
roof space or buried in structural slabs.
2.4.03 SYSTEM B - CABLES ENCLOSED IN STEEL SCREWED CONDUIT OR TRUNKINGFIXED TO THE SURFACE OF WALLS AND CEILINGS - The wiring shall be carried out in
an approved type of single core, plastic cable enclosed in steel screwed conduit or trunking
mechanically electrically continuos throughout conduit and trunking shall be run on the
surfaces of the walls and ceilings, or in false ceiling spaces. Conduit shall be secured in
position by means of spacer bars saddles. Conduit shall be run horizontally on the walls or
vertically to switches or outlets.
2.4.04 SYSTEM C - PVC INSULATED CABLES WITH INSULATED EARTH CONTINUITY
CONDUCTOR ENCLOSED IN CONCEALED NON-METALLIC CONDUIT OR
TRUNKING - Wiring shall be carried out in an approved type single core, plastic insulated
cable with earth continuity conductor enclosed in high impact, heavy gauge, non-metallicconduit or trunking conduit shall be buried in the walls and floors of buildings and either run in
roof space or buried in structural slabs.
2.4.05 SYSTEM D - PVC INSULATED CABLES WITH INSULATED EARTH CONTINUITY
CONDUCTOR ENCLOSED IN NON-METALLIC CONDUIT OR TRUNKING FIXED TO
THE SURFACE OF WALLS AND CEILINGS - Wiring shall be carried out in approved tape
single core plastic insulated cable with earth continuity conductor enclosed in high, impact,
heavy gauge, non-metallic conduit or trunking conduit and trunking shall be run on the surface
of the walls and ceilings or in false ceiling spaces. Conduit shall be secured in position bymeans of space bar saddles. Conduit shall be run horizontally on the walls or vertically to
switches or outlets.
2.4.06 SYSTEM E - MINERAL INSULATED COPPER SHEATHED CABLES - The wiring shall
be carried out in single core or multi-core mineral insulated copper sheathed cables run on the
surface of walls and ceilings in the roof space or concealed in walls and floors.
2.4.07 STEEL CONDUIT - Not more than four easy sets, or two right angle bends or sets may be
installed between draw-in points. Solid elbows or trees shall not be accepted. Where surfaceconduits are authorised for use, they shall be of the welded heavy gauge steel class B to BritishStandard Specifications B.S.31. No conduits shall be smaller than 20mm diameter. They shall
be electrically and in all cases mechanically continuous throughout. Conduits installed inside
buildings, shall be black enameled finish except where specified otherwise. Conduits installed
outside environment shall be of galvanised finish. All fittings and accessories, such as conduit
boxes, etc., to be used in conjunction with galvanised conduits shall also be galvanised.
Conduits shall be fixed to give not less than 6,, clearances between the conduits and the walls or
other surfaces where they are fixed. Conduits fixing points shall generally not exceed 1200mm
spacing for 20 and 25mm diameter conduits and 1500mm for larger conduits.
Conduits shall be kept at least 150mm clear of steam and hot water pipes and preferably run below the pipes. Where conduits run adjacent to cold water pipes, bell clock or telephone
circuits they shall be kept at 150mm or prevented by spacing or insulation, from coming intocontact with these services. Where there is a possibility of moisture collecting in the conduit a
drain hole of 5mm diameter shall be drilled at the lowest point of the conduit run or box, or
other points as directed by the interior designers and shall be fitted with a suitable drain plug.
Steel work shall not be drilled for fixing of conduits or accessories except where authorised in
writing by the interior designers. Such authorisation shall be limited to the drilling of 3mmholes for hardened self-tapping screws and shall not normally be given when more than two
conduits follow the same route. Conduits and accessories may be fixed to steelwork by means
of purpose made bracket and grader fittings. Details of such brackets or clamps shall be
17
8/2/2019 Specifications for Electrical
http://slidepdf.com/reader/full/specifications-for-electrical 18/25
submitted to the interior designers for approval before being used. Where conduit runs enter
specified areas requiring flame proof equipment barrier boxes shall be inserted immediately
before conduit enters the flame proof area. All conduits and accessories installed within this
area shall be solid drawn galvanised and Buxton certified as suitable for Group 11 hazards.
Equipments shall comply with BS229, BS889 and code of practice CP1003 conduit installed
and buried in walls shall allow a minimum of 10mm cover. These conduits and those cast ‘in
site’ in concrete slabs shall be given one coat of rust prevention paint before installation of conduits and before concrete is poured.
where buried in the ground outside the building the whole of the buried conduit shall be painted
with two coats of approved bitumastic composition before covering up. Where run on the
surface, conduits and accessories shall be painted with two coats of oil bound enamel applied to
rust and grease free metal work.
2.4.08 STEEL TRUNKING - Metal trunking shall be fabricated from mild sheet steel of not less than
18swg and shall have stove enameled finish. All sections of trunking shall be rigidly fixed
together and attached to the framework of fabric of the building at intervals of not less than1200mm. Joints in trunking shall not overhang fixing points by more than 600mm. All
trunking shall be made electrically continuous by means of 25mm x 3mm copper links across
each joint in the system. Connection shall be made by means of electro-tinned bolts (head
inside trough) nuts (6mm diameter minimum) flat washers and spring washers. Where the
trunking is galvanised the galvanising shall be removed within 6mm of the jointing strap, and
the area painted. They shall also be mechanically continuous by being jointed with purpose
made through elbow tee or cross box. All trunking fittings (i.e. bends, tees, etc.) shall leave the
main trough completely clear of obstruction and continuously open except through walls andfloors, at which points suitable fire resisting barriers shall be provided as may be necessary.
Where trunking passes through ceilings and walls the cover shall be solidly fixed 150mm either
side of ceilings and floors and 100mm either side of walls.
Screws and bolts securing covers to trunking, sections of cover together shall be arranged sothat damage to cables cannot occur either when fixing covers or when installing cables in thetrough.
When trunking is used to connect switchgear of fuse-boards such connections hall be made by
trunking fittings manufactured for this purpose and not by multiple conduit couplings. Where
vertical section of trunking are used which exceed 900mm in length, staggered tie, off points
shall be provided at 900mm intervals to support the weight of cables.
All trunking systems shall be painted as for conduit.
Where a wiring system incorporated galvanised conduit and trunking, the trunking shall bedeemed to be galvanished unless specified otherwise.
Cables following the same route shall be found together in groups of not more than 6 cables.
The bindings shall comprise fine strip cords and shall be applied at intervals of not more than
600mm along the run of cable.
The number of cables to be installed in trunking shall be such as to permit easy drawing in
without damage to the cables and shall in no circumstances be such that a space factor of 45%is exceeded.
Conduits shall be terminated at the trunking with a coupling and made bush, passing through a
18
8/2/2019 Specifications for Electrical
http://slidepdf.com/reader/full/specifications-for-electrical 19/25
neat clearance hole. Oversized hole and washers shall not be used. All conduits terminating at
the trunking shall be bonded together and to the trunking but the trunking shall not form part of
the earth continuity conductor.
2.4.09 NON-METALLIC CONDUIT - All non-metallic conduit shall be class ‘A’ heavy gauge, high
impact, PVC complying with BS4606 part 2, type AH.
The minimum size to be used is 20mm external diameter. All conduit installations shall beconcealed in the walls and floors or in structural slabs.
2.4.10 FLEXIBLE CONDUIT - These are to be used as final connections to motors and other fixed
appliances where vibration is prevalent.
Flexible metallic conduit shall comply in all respects with BS731 part 1. Flexible non-metallic
conduit shall comply with BS4607 part 3. Flexible metal conduit shall not be used as the solemeans of providing earth continuity, and a separate earth-continuity conductor complying with
the appropriate requirements shall be provided for every part of a system formed by suchconduit.
2.4.1 1 CABLE TRAYS:
These are to be galvanised and constructed as per the relevant British Standard Specifications.
They are to be supported to the wall at 1M intervals.
2.5.00 SOCKET OUTLETS:
In all areas, general power outlets shall be of the 13 amp 3 pin plug type complying with
BS1363. They shall be flush pattern with white or ivory cover plates unless otherwise specified
on the drawings. Where the circuits are supplied from a common feed, two outlets shall formtwin unit in a common box. The earthing terminal of every socket outlet shall be connected to
the earth continuity conductor of the final sub-conductor. Unless otherwise stated they shall be
mounted at 300 mm above finished floor level.
One fused plug top shall be supplied for each socket outlet installed. Fuses shall be 13 amp
unless otherwise specified.
19
8/2/2019 Specifications for Electrical
http://slidepdf.com/reader/full/specifications-for-electrical 20/25
2.6.00 FUSED CONNECTION UNITS
2.6.01 GENERAL
All fused connection units shall be 13 amp with fuse and neon indicator lamp. Boxes shall be
flush type with white or ivory cover plates and shall be switch type unless otherwise specified
on the drawings.
2.6.02 FUSES
All fused connection units shall be fitted with 13 amp fuses, unless otherwise specified.
2.6.03 LABELLING
The front plate of each fused connection unit shall, unless otherwise specified, be engraved with
he name of the appliance connected to it.
2.7.00 LIGHTING SWITCHES
TYPELighting switches shall be of the all-insulated rocker-operating plate-switch type to B53676 of ample rating. Switch inserts shall be white, set in white or ivory cover plates.
Switches controlling points in bathroom shall be placed outside the bathroom or consist of a
ceiling with operated by a non-conducting cord as specified. Switches mounted outdoor shall
be of weathertight pattern.
Switches shall be one way, two-way or intermediate as specified and where a number of
switches are mounted together, they shall be fitted in a common box.
Ceiling switches shall be white or ivory semi-recessed pattern, and shall only be used wherespecified. Pull cords shall be fitted with shock absorbing springs.
2.8.00 CEILING ROSES2.8.01 TYPE
Ceiling roses, ivory or white, shall be of the 3-plate pattern and fitted at all pendant points. An
earthing terminal shall be provided and connected to the earth continuity conductor of the final
sub-circuit where applicable.
Ceiling roses of the white porcelain semi-recessed pattern shall be used for surface installation,and shall be of the all-insulated type for a flush installation.
2.9.00 LAMPHOLDERS
2.9.01 TYPE
20
8/2/2019 Specifications for Electrical
http://slidepdf.com/reader/full/specifications-for-electrical 21/25
Lampholders shall generally be of plastic construction with porcelain interiors and bayonet
fitting.
Lampholders for lamps rated 200 watts and above shall be of the Edison Screw Type.
Batten type Lampholders shall be of the all-insulated bayonet type.
Batten type lampholders shall be of the all-insulated bayonet type.
2.10.00 LIGHTING FITTING
2.10.01 GENERAL
The sub-contractor shall supply and fit all lighting fittings of the type indicated on the drawings
and in the schedules. All fittings shall be suitable for operation on a 240 v 50 cycle supply.Lighting fittings rated other than 240 v will not be accepted. All lighting fittings shall be
supplied with lamps.
2.10.02 FLUORESCENT FITTINGS
Fluorescent fittings shall generally be of the batten type, with control gear contained within the
supporting channel. All fittings shall be supported from conduit boxes, and shall be suspended
by two 20mm conduits to give a clearance of 25mm between the top of the fitting and the
ceiling. In the ceiling, the conduit boxes, to BS31, shall be fitted with dome covers, to which
the suspension conduits shall be joined, so that the lighting fitting hangs vertically below the
conduit boxes. Fittings shall comply with BS3820 or class 1 indoor normal atmospheres.
All fluorescent fittings shall be fitted with radio interferance suppression capacitors and power
factor correction capacitors and shall be earthed.
2.10.03 REFLECTORS
All reflectors for fluorescent fittings shall be made of sheet metal suitably shaped and stiffened,
and shall be of white enamel finish.2.10.04 LAMPS
All fittings shall be supplied complete with lamps of the type and rating specified. Fluorescent
tubes shall be of the white type, except where otherwise stated. Pearly type tungsten lamps
shall be fitted in open fittings.
2.11.00 FLEXIBLE CORDS
2.11.01 TYPE
These shall be 250 volt grade PVC insulated and shall comply with BS7. Flexible cords shall
not be less than 24/20 (23/0076). Flexible cords for pendant fittings shall be circular type, heat
resistant white in colour.2.12.00 EARTHING
2.12.01 Earth electrodes shall be minimum 1.4m long by 12mm diameter hard drawn copper rod, andshall be located not less than 3 apart at a convenient position 6m away from the building. The
terminal head of each electrode shall be in a concrete inspection pit, with cover. If the
resistance to earth is not satisfactory with one electrode, then additional electrodes or earth mat
shall be provide, as directed by the Engineer.
2.12.02 DISTRIBUTION SYSTEM EARTHING
All distribution boards shall be earthed in accordance with the I.E.E. regulations. All metal
work associated with the installation shall be earthed to comply with the regulations currently in
force.
21
8/2/2019 Specifications for Electrical
http://slidepdf.com/reader/full/specifications-for-electrical 22/25
2.12.03 TESTING OF EARTHING SYSTEM
The resistance of the earth continuity system, when measured between the main earthing point
and any other point in the installation, including all conduit and other metal work which may
provide a path or earth, shall not exceed 0.5 ohm, where steel conduit forms part or the whole
of the system, or 1.0 ohm if the earth continuity system is composed entirely of copper, copper
alloy or aluminum.
When the installation is complete, the Sub-contractor shall carry out tests for earth loop
impendance, polarity, insulation resistance, ring circuit continuity and earth electrode
resistance, in the presence of, and to the satisfaction of Engineer and the E.A.P & L Co. The
Sub-contractor shall rectify all work not giving test results within the limits prescribed.
Four copies of all test results shall be forwarded to the Engineer and a Certificate of completion
will not be issued until such test have been approved.
2.13.00 P M E SYSTEM
Provision shall be made for the P M E System at supply intake where applicable).
“P M E” means that system whereby the neutral conductor of the supply network is earthed at a
prescribed number of point along its routes, together with the installation earth continuity
conductor, at each consumer’s installation so providing a metallic path for the flow of earthfault currents. The connections between the neutral conductor of the supply network and the
earth continuity conductor of the installation shall be made by the Supply Authority at the point
of intake only. The connection at the isolators will be made by the sub-contractor in the
presence of the Engineer after completion of all tests.
2.14.00 COMMISSIONING
The whole installation shall be tested to the statutory requirements of the Electricity Authority,I E E Regulations and commissioned in the presence of and to the satisfaction of the Engineer.
Four copies of the test reports shall be provided within seven days of carrying out the test, and
the reports shall include full details of how each test was carried out, and copy of all readings
taken.
PART C - PARTICULAR SPECIFICATION
3.01 LOCATION OF THE SITE
The site is located at Kilimani in Nariobi
3.02 DESCRIPTION OF THE PROJECT
The Project comprises of demolition of existing partitions and construction of a co-operative
center as the drawings comprising of new partitioning, electrical, air conditioning, structural
cabling and plumbing and drainage works
3.03 EXTENT OF WORK
The sub-Contractor is expected to carry out the purchase and installation of electrical
accessories i.e. conduits cables lighting fittings etc. do the installation commissioning and
22
8/2/2019 Specifications for Electrical
http://slidepdf.com/reader/full/specifications-for-electrical 23/25
testing.
The subcontractor is to apply to KPLC for power connection and do the necessary attendance in
addition to supplying all the certificates as required by KPLC and ensure energisation of the
completed installations.
3.04 CONSUMER UNITS AND DISTRIBUTION BOARDS
This shall be as per clause 2.21 and 2.22 of part B of the specification.
3.05 WIRING SYSTEM
This shall be system, C clause 2.4.04 of part B of the specification.
3.06 EARTHING SYSTEM
Earthing to clause 2.12 of part B. It shall be expected that the subcontractor will provide the
right readings and to have priced for provision of extra earth electrodes to achieve correctreadings if required.
4.0 CONTRACT DRAWINGS
4.01 CONTRACT DRAWINGS
SCA/2005/13/EO1 - electrical installations for church hall
SCA/02005/13/EO2 - schematic and legend
23
8/2/2019 Specifications for Electrical
http://slidepdf.com/reader/full/specifications-for-electrical 24/25
PART D
BILLS OF QUANTITIES
24
8/2/2019 Specifications for Electrical
http://slidepdf.com/reader/full/specifications-for-electrical 25/25
25