specification of works for installation of new door …

66
DOO SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR ENTRY SYSTEMS Prepared by: Brighton & Hove City Council The Housing Centre Unit 1 Fairway Trading Estate Eastergate Road Brighton BN2 4QL This specification is the current (Jan 2014) standard in place for new Door Entry System (DES) Installations i.e. when the existing system is deemed beyond repair. Contractors will be required to complete a works/pricing schedule for each site. These list the components required for each site upgrade and act as an asset schedule for each site as well as a detailed specification for cost/quality monitoring purposes. These only need to be completed at the time the works required have been identified, once the contract is in place i.e. you are not required to complete this schedule at the ITT stage. This detailed DES specification should be used in conjunction with the more general electrical specifications in the main ITT document. The works/pricing schedule for each site will be based on the tendered costs in Pricing Schedule PF1 of the main ITT documents. However, PF1 does not detail the individual components of a complete Door Entry System. The works/pricing schedule required for each site will list the individual components required and a cost must be attributed to each component part and labour costs identified in order to provide transparency of costs and prove value for money. The works/pricing schedule must be agreed with the BHCC Contract Manager prior to any works being carried out on site.

Upload: others

Post on 02-Jan-2022

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

DOO

SPECIFICATION OF WORKS

FOR INSTALLATION OF NEW DOOR ENTRY SYSTEMS

Prepared by: Brighton & Hove City Council The Housing Centre Unit 1 Fairway Trading Estate Eastergate Road Brighton BN2 4QL This specification is the current (Jan 2014) standard in place for new Door Entry System (DES) Installations i.e. when the existing system is deemed beyond repair. Contractors will be required to complete a works/pricing schedule for each site. These list the components required for each site upgrade and act as an asset schedule for each site as well as a detailed specification for cost/quality monitoring purposes. These only need to be completed at the time the works required have been identified, once the contract is in place i.e. you are not required to complete this schedule at the ITT stage. This detailed DES specification should be used in conjunction with the more general electrical specifications in the main ITT document. The works/pricing schedule for each site will be based on the tendered costs in Pricing Schedule PF1 of the main ITT documents. However, PF1 does not detail the individual components of a complete Door Entry System. The works/pricing schedule required for each site will list the individual components required and a cost must be attributed to each component part and labour costs identified in order to provide transparency of costs and prove value for money. The works/pricing schedule must be agreed with the BHCC Contract Manager prior to any works being carried out on site.

Page 2: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Materials & Workmanship DOOR ENTRY SYSTEM

Standard DES Nov 2013

SECTION 2

PREAMBLES

DEFINITIONS AND DESCRIPTION OF

MATERIALS AND WORKMANSHIP

Page 3: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2.00 DEFINITIONS 2.01 Figures Figures in descriptions are millimetres unless qualified by a unit of measurement or by a work

or phrase indicating a reference, e.g. BS, pipe, grade, or are associated with a dash, e.g. rebates - 2. A figure associated with a dash gives the number of times the condition described occurs.

2.02 Stored Existing materials to be refixed in the works are described in the items as “stored” and this

description includes selecting, cleaning removing from store to the appropriate location and fixing.

2.03 Included elsewhere The term “included elsewhere” qualifying any part of a description means that provision is

made elsewhere in this specification for the part so qualified. 2.04 Holes The provision of holes is deemed to be included in work described to be fixed with screws. 2.05 Plugging The term “plugging” means the provision and fixing of approved proprietary plugs or, at the

Contract Administrator’s discretion, fixing by approved mechanical means. 2.06 Preparation of surfaces Description of finishing’s applied to new surfaces are deemed to include the preparation of

these surfaces to receive the finishing. 2.07 Proprietary brands Where materials or articles are specified as proprietary brands or makes, these are to be used

and/or fixed in accordance with the manufacturer’s printed or written instructions.

The Contractor shall supply the manufacturers with all relevant details and afford them every facility for inspecting the work during progress in order to ascertain that their products are being used correctly and allow them to take samples of materials from the site if so desired.

2.08 British Standards Where materials, articles and/or workmanship are specified to be in accordance with a British

Standard Specification and/or British Standard Code of Practice, this is to be deemed to mean the latest issue of the British Standard Specification or British Standard Code of Practice together with any amendments.

2.09 Generally “Remove” shall mean demolish and clear away together with all ancillary and incidental items

attached hereto. “Set aside for later re-use” shall mean clean, cover, protect and move about as necessary. “Make good” shall mean reinstate with materials and workmanship to match in every respect

the surrounding work and properly bonded thereto.

Page 4: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

“Cut and form opening” shall include cutting opening to required size, quoining of jambs and generally leaving ready to receive new work and all necessary making good on completion.

New Door Entry Systems Installation A door entry system is to be installed at the address as indicated in the particular specification and as listed the appendixes using the equipment and manufactured items as below: Equipment shall be as manufactured by Entrotec Limited with integrated KMS proximity access control and supplied & installed as a complete working system by the winning installation contractor. All equipment required for the integrated systems shall be purchased from Entrotec with the exception of any magnetic locks that shall be supplied pre fitted in the new door via the door manufacturer Multisteel. The installation contractor shall employ Entrotec Limited to fully connect & commission the entire system. Installer shall purchase, install and fix all the equipment, connecting the room terminal in the dwellings. Brighton and Hove City Council insist that all installers if not a current Entrotec approved installer shall employ Entrotec to carry out manufacturers commissioning. If the contractor is a current Entrotec approved installer they may install and commission the entire systems completely themselves. They must prove to Brighton & Hove that they are current Entrotec approved installers and this shall be confirmed with Entrotec. All Blocks shall be fitted with an integrated pre-programmed KMS 10,000 capacity Simplekey controller. The KMS controller shall be connected to the KMS Hosting Cloud via a KMS GPRS Modem connected to the controller for administration at: The Estates Department C/O Les Barnes Brighton & Hove City Council The Housing Centre Unit 1, Fairway Trading Estate Eastergate Road Brighton BN2 4QL The KMS controller shall be connected to a GPRS modem and shall use a contract Vodafone data only SIM card (SIM card provide by the client and issue by the CA on request for the contractor to fit and connect on site. The KMS equipment shall be integrated within the Entrotec door entry Sarel enclosure. Where controllers are required as satellite boxes these shall be fitted in Sarel IP66 boxes with a Sarel hasp and staple and fitted with the KA1 IFAN lock. Cabinet shall also be fitted with a traffolite label “fob Equipment”. All KMS controllers shall be supplied by the door entry equipment manufacturer. SIM card free issue to the contractor by Brighton & Hove City Council CA for fitting with in the GPRS modem. All system controllers shall have new Shark tooth tokens colour coded to the Brighton & Hove City Council standard supplied via Entrotec pre-programmed in to the controller and on the KMS SimpleKey Web System cloud.

Page 5: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

DOOR ENTRY PERFORMANCE SPECIFICATION FOR EQUIPMENT & INSTALLATION INDEX 1.0 GENERAL 2.0 SCOPE OF WORKS 3.0 DOOR ENTRY & PROXIMITY ACCESS CONTROL SYSTEMS 4.0 DOOR ENTRY SYSTEM INSTALLATION

5.0 VIDEO DOOR ENTRY 6.0 EARTHING AND BONDING 7.0 TESTING AND COMMISSIONING OF ELECTRICAL INSTALLATION 8.0 LABELLING AND IDENTIFICATION 9.0 TRAINING 10.0 RECORD DOCUMENTATION

Page 6: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

1.0 GENERAL The Contractor shall visit site prior to the submission of tender to familiarise themselves

with the site and local conditions. Site visits shall be by prior appointment with Brighton & Hove City Council.

Supervision of Labour The Contractor shall employ one or more competent representatives to superintend the carrying out of the works on the site. The said representative(s) shall be present on site during all working hours, and any orders or instructions which Brighton & Hove City Council or its representative/agent may give to the said representative shall be deemed to have been given to the Contractor. The Contractor shall prevent all site staff from trespassing beyond the limits of the designated work areas. Protection of Existing Equipment All existing plant equipment and furniture, which is to be retained, shall be adequately protected from mechanical damage. The Contractor shall also allow for each area to be thoroughly cleaned before handover to the client. Protection of Materials All materials shall be suitably protected against the weather. Plant motors and materials whether fixed or unfixed shall be protected from the ingress of dirt or moisture by means of polythene covers or other approved method. Protection against mechanical damage by other trades shall be provided where necessary. Electrolytic Action Where copper and non-ferrous pipe work or equipment are connected together non-metallic fittings or joint rings shall be incorporated to prevent contact between the two metals and the setting up of electrolytic action. Discrepancies in Documentation Where discrepancies exist between information contained within the specification and on the drawings, the Works Contractor shall clarify the differences before submitting his tender. Any cost or expense arising from the works contractor’s failure to comply with this clause will be the responsibility of the works contractor. Electrical Supplies Electrical supplies shall be as follows: 400 volt 3 phase 50 Hz 230 volt 1 phase 50 Hz All equipment covered by the specification and drawings shall, unless otherwise specified, be suitable for operation at these voltages and shall operate satisfactorily when the voltage is ± 10% of these nominal voltages.

Page 7: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

Workmanship All work shall be installed in a neat and professional manner, with due consideration to the design intention. The tradespersons employed on the work shall have received appropriate training and be a fully qualified to be employed on such work. Where, in the opinion of the Brighton & Hove City Council or its representative/agent, any operative is not suitably qualified, the Contractor shall replace them with a tradesperson whose skill and experience is appropriate to the work. The proportion of skilled and unskilled labour employed on the work shall be as approved by National Agreement. If, in the opinion of the Engineer, any member of the Contractors staff is considered undesirable due to conduct or other misdemeanour, the Contractor will be required to remove this person from site immediately. Interference All the Contractor's equipment shall where necessary be fitted with suppressers to limit radio interference as prescribed in BS800.

Radio and Television / Satellite TV / Cable TV Equipment

Aerials, cables and equipment, including satellite dishes, likely to impede or suffer damage as a result of the specified works are to be carefully removed and temporarily re-rigged by the Contractor to maintain the quality of the signal reception to the users satisfaction. Cables interfering with door and window replacement works are to be carefully unclipped and repositioned so as to pass between the new frame and the masonry opening, sealed and re-clipped internally and externally.

The Contractor is to make all arrangements and pay all fees and charges required by British

Telecom/British Cable TV/NTL, Sky, their agents, subsidiaries or successors for similarly removing and refixing their equipment, cables, wiring, bracket fixtures and fittings as required to facilitate the works. Connections to Equipment Service connections shall conform to the items of equipment to which connections are to be made. Before any service is first operated, the Contractor shall confirm safe operating pressures and temperatures with the manufacturer. Builders Work Builder's work drawings shall detail the construction of concrete bases, the building in of steel works, all holes greater than 150mm dia. or 150mm square, all holes through beams, columns or structural elements. The builders work drawings shall be prepared and issued for approval three weeks before the holes are required to accept services. The Contractor shall supply two copies of each drawing. The depth of all chases shall be at least equal to the external diameter of any pipes or tubes installed in them to allow plaster cover to the normal thickness. Where chases are to be pre-cast the Contractor shall supply any necessary detailed drawings.

Page 8: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/1

No horizontal or diagonal chases shall be permitted and vertical chases shall be in approved locations, not back to back. The Contractor shall drill and plug any necessary holes in floors, walls, ceilings and roofs for securing services and equipment. Prior approval shall be obtained from the engineer for all fixings into concrete walls, floors, ceilings, roofs or other structural surfaces. Plant and materials shall not be deposited on roadways, footpaths or in corridors without prior permission.

The Contractor shall be responsible for all builders work. Cutting of ways through landings, brick walls, concrete floors etc. shall be carried out using masonry drills. Comply with restrictions on the cutting of holes, chases, notches, etc. and methods of attachment to the building fabric as specified in section. Where mini trunking is required all appropriate fixtures and associated bends, junctions and tee bars shall be used. All mini trunking shall be screw fixed. Self addevise mini trunking shall not be acceptable. All conduit and trunking shall be galvanised steel and used with all appropriate fixtures and associated accessories. All exposed conduit and trunking lids shall be secured using suitable security screws. Maintenance Manuals and Record Drawings As part of the works the Contractor shall provide record drawings of and maintenance manuals for the complete installation and plant. The record drawings of the installations shall detail the following: 1. Positions of plant and equipment. 2. Routes, sizes and types of all trunking, tray, ducts, cable and conduit. 3. Invert levels for all underground services. 4. Reference numbers of all electrical circuits. 5. All underground joint boxes and earth electrodes. All record drawings shall be submitted to the Brighton & Hove City Council or their representative/agent for approval

Maintenance manuals shall contain full operating and maintenance instructions sufficient to enable the plant to be operated, maintained, dismantled, reassembled and adjusted. Three sets of the maintenance manuals shall be provided, following submission to and approval by the Engineer. Manuals shall be A4 size, loose-leaf type, having stiff clothbound or approved plastic covers. The Manuals shall include a detailed index and ready means of reference.

Page 9: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/2

Systems shall be dealt with systematically and the following details included: 1. Overview of all systems. 2. Plant and nameplate details. 3. Safety procedures. 4. Automatic control items with sensor set points. 5. Lubrication details. 6. Wiring diagram of equipment and control panels. 7. Procedures for emergency operation where applicable. 8. Manufacturers information and contact telephone numbers. 9. Procedures for faultfinding. 10. Circuit schedules. 11. List of essential spares. 12. List of record drawings. 13. Testing schedules. 14. Completion & test certificates. Manufacturers commissioning certificate if not a current approved installer The production of Maintenance Manuals and Record Drawings are an essential part of the works, which shall not be considered complete until approved copies of manuals and drawings have been received. In the event of Practical Completion or Sectional Completion being accepted before the production of the Maintenance Manuals and Record Drawings monies will be retained from the Contract payments to cover the cost of preparing such drawings and manuals by others. The amount retained may be released in stages to the Contractor as evidence of production of the necessary drawings and manuals is offered and approved. In the event of the Contractor failing to product any evidence of the production of the drawings and manuals within one month of handover of the works or any section of the works the Brighton & Hove City Council or its representative/agent may at their discretion instruct others to carry out these works the costs of which will be charged to the Contractor. Materials, Installations and Designs All materials shall comply with the current relevant British Standard Specification unless otherwise specified and Installations shall comply with the relevant code of practice. Materials, Installations and designs shall comply with all Acts of Parliament, statutory rules and regulations, Gas Safety Regulations, Insurance Company requirements and BS7671.

Page 10: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/3

Contractor to Inform Himself fully The Contractor shall be deemed to have examined the site, if access has been available to them. If any particulars required cannot be obtained from this examination together with the Conditions of Contract, Specification, Schedules and Drawings, application for the information shall be made to the Brighton & Hove City Council or its representative/agent. The Contractor shall have no claim because of want of knowledge in any respect of the Contract. Recycling of Waste Arising From Works All rubbish resulting from the works, including glass and components removed, is to be cleared from the premises at the end of each working day. All entrance paths and steps giving to the dwelling are to be kept clear at all times

Rubbish removed from the premises is to be stored in skips enclosed or within the

Contractor’s compound for bulk disposal. The Contractor is to obtain the consent of the Executive Director of Environment Development and Housing of the Council before placing rubbish skips or containers upon the public highway, pavements and streets.

All rubbish is to be bagged and lowered to ground level. On no account is anything to be

thrown from the roof, scaffold or any other platform.

The disposal of all rubbish shall be in accordance with the requirements of the Environmental Protection Act 1990 and where necessary appropriate documentation for such disposal will need to be provided by the contractor upon request. Responsibility for Works The Contractor shall be responsible for all sections of the works whether in use, under test, or in construction until such sections of the works are formally taken over (save as provided in the conditions of contract). Handover On completion of the works to the satisfaction of the Brighton & Hove City Council or its representative/agent a formal meeting will be arranged to hand over the installations to the Employer and a certificate of practical completion issued. Documentation Hand over to the CA at Practical Completion: Copies of manufacturers' operating and maintenance instructions for all fittings and apparatus. As-installed drawings showing all circuits and their ratings and the locations of all fittings and apparatus.

Variations No variations shall be carried out to the works unless the Contractor has received a Contract Instruction. No Contract Instruction will be placed without an appropriate quotation.

Page 11: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/4

Final Adjustment The Contractor shall adjust Time Switches to the complete satisfaction of the Contract Administrator. The Contractor shall ensure that the correct fuse elements, fuse links or circuit breakers have been installed.

Application for Payment In order for the Contract Administrator to certify payment on practical completion the Contractor shall be required to submit a Test and Completion Certificate. Site Visit The Contractor shall visit the site before submitting the schedule of works to establish the particular problems associated with the works. No claim on the grounds of insufficient or inaccurate information shall be entertained. Summary of Costs The Contractor shall complete the works/pricing schedules as stated on the front page of this document for each block requiring a new DES upgrade.

Programme Prior to commencing the works on each site the Contractor shall present to the Contract Administrator a programme of works for each site. NICEIC Approval The Contractor nominated to carry out the works shall provide evidence of membership to the NICEIC or associated body prior to commencing work on site. Each of the company’s engineers shall provide current certification. Lock Up Accommodation Lock-up accommodation and storage of materials and plant shall be the sole responsibility of the Contractor, who shall ensure the protection of new materials/equipment against rough treatment, dust, grit or damage in other ways. The sighting of any such accommodation shall be agreed with the CA. Insurance The Contractor shall be deemed to have insurance cover for damage against the Council or Council's tenants' properties in case of accidents occurring during the progress and execution of the works. Removal of Existing Equipment The contractor shall allow to remove all existing equipment and furniture which is not to be reused. (If fitted) The contractor shall offer the removed equipment back to the client for uses as maintenance spares.

Regulations A representative list of regulations and guidelines, for the purpose of illustration only, is given below but it is not exhaustive and it is the responsibility of the Trade Contractor to identify and ensure compliance with all applicable and updated regulations and amendments and to obtain all necessary permissions and approvals:

• The Health and Safety at Work Act and all associated regulations and requirement of the Health and Safety Executive.

Page 12: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/5

• The Building Regulations.

• The Offices Shop and Railway Act.

• The Clean Air Act.

• EC Directives and associated Codes of Practices.

• County and Local Authority Byelaws.

• Local Planning Authority Requirements.

• Petroleum Regulations.

• Local Authority and other Byelaws applicable to the site area.

• Electricity at Work Regulations.

• The Electricity at Work Act.

• The COSHH Regulations.

• The Model Water Byelaws.

• The Noise at Work Regulations.

• The Fire Precautions Act

• The Pressure Vessel Regulations.

• The Gas Safety Regulations.

• The Fire Precautions (Place of Work) Regulations.

• The CDM Regulations 2005.

• BS7671 – 2008 (17th Edition of the IEE Regulations)

• CIBSE Codes and recommendations

• BS8300:2009+A1:2010

Copies of all Certificates and approval documents shall be passed to the Client, as they are obtained but not later than at practical completion. Copies shall be included within the record documentation.

2.0 SCOPE OF WORKS This part of the Engineering Services Specification details the electrical engineering

installation, the door installation and requirements for the project. It must be read in conjunction with all other parts, sections and appendixes of the Tender Documents.

` The Contractor shall be responsible for the execution of the work described herein and

shown on the tender drawings. The scope of work shall comprise the whole of the labour and all materials necessary to

form a complete installation and such tests, adjustments and commissioning as are described in subsequent clauses as may otherwise be required to give an effective working installation to the satisfaction of the Engineer.

Page 13: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/6

The words ‘complete installation’ in the above clause shall mean not only the major items of plant and equipment conveyed by the Specification, but shall include all the incidental sundry components necessary for the complete execution of the works and for the proper operation of the installation with their labour charges, whether or not these sundry components are mentioned in detail in the tender documents issued is connection with the Contract. The scope of work for the project shall include the following: - Door Entry System Works as described in Pricing Schedule Annexe(s). 1. Installation of new door entry systems. 2. Production of working drawings and builders work drawings as required. 3. Builders work as required. 4. Earthing. 5. Testing and Commissioning. 6. Training. 7. Production of Record Documentation.

3.0 DOOR ENTRY CONTROL SYSTEMS General

The following works describe the installation of a new Entrotec door entry system for all blocks as listed in the appendixes: Including all associated builders work.

The Entrotec door entry system will serve all flats in the block as indicated in Pricing Schedule

Annex(s). The system shall be complete with trade’s facility. Unless otherwise stated the following particular preambles for Controlled Door Entry

Systems shall be read in conjunction with and shall incorporate the materials and workmanship clauses of the electrical and other sections of the preambles as applicable. Door Entry System Equipment Manufacturer and Supplier The door entry equipment shall be obtained under OJEU framework agreements from Entrotec Ltd, Access House, 5 Ashwood Court, Oakbank, Livingston, West Lothian, EH53 0TL.

Tel: 01506 886230 Fax: 01506 886233 [email protected] www.entrotec.co.uk

(See below for variations of equipment conditions) Entrotec equipment has been subjected to an OJEU framework equipment tender and supply chain framework agreement and is considered best value for quality, price, service and on-going maintenance. The council has standardised on product across the housing stock and equipment shall not be deviated from.

• The manufacturer & installer must not be the same company or group of

Page 14: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/7

companies.

• The Equipment shall be EMC tested and all equipment shall carry the CE mark.

• The Equipment shall be manufactured in line with Current EEC directives.

• The Manufacturer shall be a BS EN ISO 9001 company.

• The Manufacturer shall be a member of Construction Line.

• WEEE Compliance. If the contactor wishes to vary from the nominated equipment manufacture he must complete the tender return using equipment as per the specification. If the contractor wishes for an alternative equipment manufacturer to be considered then he must provide, on a separate sheet, a costing break down showing a like for like alternative in a similar format to that of the tender return. He shall provide a detail letter explaining why he wishes to deviate from named manufacturers with a list of advantages, a full specification of the alternative manufacturer, together with the manufactures literature and samples, so the CA can consider and if deemed to be a suitable replacement. The door entry equipment shall be commissioned by the manufacturer Entrotec Limited. A Current Entrotec Approved installer shall be able to commission the entire system, themselves. Non Current Entrotec Approved installers shall employ the manufacturer or manufacturer’s agent to commission the systems.

The installer shall prove to the CA that the engineers carrying out the installation and

commissioning, have themselves been Entrotec trained and on demand show the engineer training certification. The engineers shall also prove that they are familiar with both PAC and KMS proximity control system and have a high level of understanding of both product ranges and remote administration packages including Pac EasiNet residential and KMS simple key. If deemed insufficient the installer shall employ Entrotec commissioning engineers/Agents to carry out the full commission of bot DE and the Proximity system.

The installer shall first fix all equipment and run all necessary cable and containment to this

specification and Entrotec’s requirements. The installer shall connect each handset at the dwelling to the colour code and Entrotec wiring

details. Entrotec or the Entrotec approved installer shall connect all other supplied door entry equipment and proximity access control equipment.

Or equal and approved (see below for variation of equipment).

Variation of Equipment If the contactor wishes to vary from the nominated equipment manufacture or specialist they must complete the tender return using Entrotec equipment as per the specification. If the contractor wishes for an alternative equipment manufacturer or specialist to be considered then they must provide, on a separate sheet, a costing break down showing a like for like alternative in a similar format to that of the tender return. They shall provide a detail letter explaining why they wish to deviate from Entrotec with a list of advantages, a full specification of the alternative manufacture, if deemed a suitable replacement.

A contactor can only put an alternative equipment manufacture forward at in full agreement with the Client and the Contract Administrator.

Page 15: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/8

Equipment to be provided The contractor shall obtain a quotation from Entrotec Limited to supply and commission `the entire system.

The equipment to be provided shall be as authorised by the Electrical Engineer from Brighton and Hove City Housing Department at tender stage in relation to make, size, manufacturer's installation number, etc. At no stage shall a contractor install any item of equipment other than as specified without consent from the Electrical Engineer of the Brighton and Hove City Housing Department.

The equipment to be provided shall comprise of readily available components to facilitate ease of maintenance. Spare parts shall be readily available for a minimum of 10 years.

Door Entry Equipment Specification The controlled door entry system shall provide, each dwelling within the block with a means of accepting in the dwelling a call from each entrance door call panel, a means of conversing with the caller from the dwelling unit, and admitting entrance to the block, all without the need to leave the dwelling.

The Entry Phone System shall be designed and installed in accordance with the

specification attached and in conjunction with this brief to provide an integrated access controlled audio only door entry system.

The system and equipment shall be designed and manufactured of materials such that the

unit present a high degree of resistance and protection to vandalism and provide durability. The controlled entry system shall be a system with full duplex speech. Type of system to be

suitable for size to each block. (see size of system). The Entry Phone System should be in line with the EEC directive 89/336/EEC and all

equipment should carry the CE mark. Therefore all equipment should be EMC tested. The manufacturers should be a BS EN ISO

9001- 2000 company. General Operation The controlled door entry system shall provide,:-

1. Each dwelling within the block with a means of accepting in the dwelling a call from each

entrance door call panel. 2. A Means of conversing with the caller from the dwelling unit and admitting entrance to

the block, all without the need to leave the dwelling. 3. The design and operation of the system is to be designed to achieve a high level of

protection to the equipment from vandalism and provide durability. 4. The equipment shall be manufactured of materials such that the unit present a high

Page 16: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/9

degree of resistance to vandalism. 5. The controlled entry system shall be a system with full duplex speech. Type of system to

be suitable for size to each block. (See size of system) 6. Provide a KMS networked proximity access control system using the KMS Simplekey

10,000 controllers linking to the Council’s office KMS Hosting Cloud using a GPRS modem link using a Vodafone SIM card. SIM card free issue to contractor for site installation by Brighton & Hove CA.

Door Entry System Description The Contractor is to supply and install a controlled entry system, which is to provide the following facilities: 1. Visitors to ring from the entrance panel a selected dwelling and hold a private two-way

conversation. 2. Allow the occupant of the dwelling to be able to operate an electric door release or

magnetic lock on the entrance door, with the admittance of an audible warning to indicate to the visitor that the lock has been activated.

3. Allow for Tradesman's entry, during a selected period, by providing a button on the

control panel, controlled by an Automatic summer winter seven-day digital time correction time clock with six on off times per day.

4. In the event of a total power failure the lock release shall revert to fail-safe. 5. The system shall be so arranged in order that extension handsets, buzzers or xenon

beacons and inductive couplers can be incorporated in the event that a tenant suffers from deafness.

6. It will be the Contractor's responsibility to check all dwelling numbers etc. before the

main panels are engraved. 7. The system shall be capable of self-cancelling after a specified time period,

irrespective of whether a call has been answered or not.

8. The system shall be wired so that no individual dwelling, if faulty or vandalised, shall

cause the system to malfunction, and the wiring shall be so arranged that an individual dwelling can be removed from service without having to gain access to the dwelling by use of plug in connectors.

9. The system shall be able to activate the lock only when the handset has been

answered and the lock release button on the dwellings handset has been activated. The lock release circuit will not operate if the handset has not been picked up. Only the lock at the call panel that the call has been generated shall be released.

10. The system shall incorporate an anti lock down circuit to stop residents jamming the

handset lock release button down to allow access to the building by just calling that particular handset.

Page 17: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/10

11. It shall be the contractor who is ultimately responsible for the design of the system and not that of the manufacturer. If the contactor feels that the design is not suitable he shall inform the Manufacturer and the client in writing with he views and suggestions.

12. Tenants shall gain entry through the main entrance by use of KMS proximity access

control key fobs. Solid colour as required to match the standard Brighton & Hove colour code.

4.0 DOOR ENTRY SYSTEM INSTALLATION

The installer shall supply and fit all components and installation materials necessary to complete and make the door entry system work. All work on individual blocks as per Pricing Schedule Annex(s). The proposed door entry systems shall comprise the following:

1. High gain room terminal with timed privacy & LED indication. Type ED4+. 2. Privacy of speech. Room Terminals are not to become operational until individually

called. 3. Vandal resistant push button control panel with bezelled back box. 4. Vandal resistant Pressure sensitive buttons (not touch sensitive or moving buttons). 5. Equipment cabinets IP 66 Sarel cabinets with LK 1242E Sarel lock and chassis

plates. 6. Each Sarel cabinet shall be fitted with a factory fitted Sarel 10mm hasp and staple.

Hasp and staple to be fitted with an IFAN KA1 padlock issued by the client. 7. Low voltage power supply. 8. Inter-linking multi-core telephone CW type cabling. CW1308 & CW1600. 9. Conduit / trunking / mini-trunking system. 10. Door monitoring circuit to turn on Green LED on handset when the door is open. 11. EMC tested equipment complete with CE mark. 12. Full System isolation and exchange principle. 13. Proximity access control key system including controllers and PSU 14. Residents Colour coded Pre-Programmed KMS tokens (3 per dwelling). 15. Double Pole, double throw Fireman’s switches (one per main entrance door). 16. Installer to provide one year’s on-site maintenance for complete installation. 17. Entrance door and screen (Where indicated by Multisteel). 18. Double pole, double throw push to exit switches (if using magnetic locks). 19. Full Duplex Speech. 20. Trades Facility with digital automatic summer/winter time correction time clock. 21. Battery back up of Door entry and Proximity Access Control systems. 22. Door locking devices (See type of Locking Device). 23. Manufactures equipment defects 2-year warranty for parts only. Installer to fit. 24. Local connection boxes (if required). 25. Entrotec Manufacturers on site connect & commissioning service or commissioned by

a current Entrotec approved installer. 26. Entrotec Limited manufacturer commissioning certificate or Entrotec approved

installers certificate. 27. KMS 10,000 pre-programmed GPRS ready Simplekey controller 28. KMS GPRS Modem and Vodafone data only SIM card (per block) (SIM Card Provided

by Brighton & Hove CA). 29. Disability Discrimination act friendly system 30. Audio/Visual display indication on door panel

Page 18: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/11

31. Pictorial systems to indicate functions on handsets for door open, lock release and privacy on.

32. Yellow contrasting rings on call buttons to aid the visually impaired. Note Battery back up complete with batteries shall be provided to all door entry equipment and access control equipment. The Contractor shall contain all door entry control equipment and access control equipment within an IP 66 Sarel cabinet(s) with Sarel a LK1242E key operating a Sarel lock. Equipment fitted on to a purpose made pre drilled chassis plate’s. Each Sarel cabinet shall be fitted with a factory fitted Sarel 10mm hasp and staple. Hasp and staple to be fitted with an IFAN KA1 padlock issued by the client and fitted to each cabinet by the installer. Installer shall request padlocks from the client. It shall be the installing contractor’s responsibility to provide a mains supply to the door entry equipment from the landlords supply. The installation shall be designed to operate from a 230 Volt 50Hz supply. All system functional voltages shall be designed to operate around 12V DC. Equipment to be Provided The contractor shall obtain a current quotation from Entrotec limited to meet the full specification. It shall be the contractor’s responsibility to inform the manufacturer of the particular site requirements to be able to receive a quotation to match the requirement. It shall be the installer’s responsibility to ensure that the quotation contains all necessary equipment to meet the client’s requirements for the site and that to match the performance and particular specification 100% The equipment to be provided shall comprise of readily available components to facilitate ease of maintenance. Spare parts shall be readily available for a minimum of 10 years. System type The systems shall be:- A Type “A”

Entrotec Fully functional integrated access controlled audio entry system designed to work with individual pressure sensitive push buttons on a functional entrance panel(s) with up to a maximum of 8 dwellings with space ready for KMS controller, GPRS modem an panel reader cut out with stainless steel blank or

B Type “B”

Entrotec Fully functional integrated access controlled audio entry system designed to work with individual pressure sensitive push buttons on a functional entrance panel(s) with up to a maximum of 8 dwellings with integrated KMS access control or

Page 19: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/12

C Type “C”

Entrotec Digital integrated access controlled audio entry system designed to work with a digital keypad series of push buttons on a digital entrance panel(s) with dwellings numbering 9 and greater. The pressure sensitive call buttons are to be restricted to No's 0-9 and any other buttons necessary for making or cancelling calls to dwellings with intergraded KMS access control.

Type A system shall be fitted where existing doors are installed using mechanical key entry – up to 5 dwellings Type B+C system shall be fitted where existing and new doors are secured by magnetic locking systems and electronic key fob entry is required or is on existing. REQUIREMENTS FOR EQUIPMENT Abbreviations

• MED – Main Entrance Door. (Outer & Inner Doors). • SED – Sub Entrance/Landing Controlled Door. • RED – Rear/residents Entrance Door. • EOD – Exit Only Door • FED – Fire Exit Door • VEG – Vehicle Entry Gate • PED – Pedestrian Entry Door/Gate • BIN – Bin Store Door

• CYCLE – Cycle Store Door Door Entry System

• The installer shall supply, fit and commission a complete working door entry and proximity access control system to the flowing performance specification.

Functional Systems

• Functional systems are deemed blocks with up to 8 dwellings with call panels having a dedicated button per dwelling.

Digital systems

• Digital systems are deemed blocks with 9 or above dwellings with a call panel with a standard number matrix keypad. Dwelling numbers are entered on the keypad and the call button is pressed to call said dwelling.

Mains 230V equipment supply

• It shall be the installing contractor’s responsibility to provide a suitable mains supply to both the door entry and proximity access control equipment from the landlords supply from a dedicated MCB.

• The installer shall supply a 6 amp unswitched fused spur at each location. Where a 13 amp socket is installed within the door entry or proximity access control

equipment the installer shall connect this to a separate 13 amp supply.

Page 20: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/13

CALL PANELS

Functional Entry Panels

The following requirements for equipment apply: -

• The entry control panel(s) shall comprise of a manual/functional audio system with call buttons for each dwelling up to a maximum of 8 dwelling. The button arrangement shall have a maximum of two columns (up to 6 rows) with separate buttons for tradesmen and to include a DDA proximity reader with a raised tactile key symbol. Type EPR or reader cut out with Stainless steel blank plate defined if type A or B system

Digital Entry Panels Functional & Digital Call Panel LCD Display

• The entry control panels shall comprise an audio digital display and a standard key keypad lay out of push buttons (0-9) with separate buttons for call, cancel (either side of the No “0” button) and tradesmen facilities. Designed for use on building with 9 dwellings and greater. No “5” button to incorporate a raised pimple to aid the blind. Panel to include a DDA proximity reader with a raised tactile key symbol. Type EPR.

• Provide LCD message panel display screen • Protected by minimum 5mm thick Lexan. • LCD Message Display with White or Green display • LCD Protected by minimum 5mm thick Lexan. • Numerals not less than 12mm high and be colour Black, message text in title &

sentence case.

• Include message “Door Open” to include Audible Alarm. • Include message “Flat Calling” to include reassurance ring tone. • Include message “System Busy” to operate if system is busy multi panel systems

only.

• Include message “Speak Now” to operate when a handset has been lifted in a dwelling. To indicate to a deaf person the call has been answered.

• Include message “ Call Hung up in Flat”

• Include Message “ Handset on Privacy”

General • Whole assembly to be fully sealed against ingress of moisture, adverse weather and vandalism.

• All components to be of modular design to permit easy maintenance. • Panel to be minimum 2.5mm Stainless Steel BS316 marine grade brushed

stainless steel.

• All call panels to be both audible and visual indication LCD display as described above for functional and digital systems.

Engraving • Operating instructions to be clear, concise and arranged in sequence. These shall either be engraved on the call panels or part of the LCD text.

• All Engraving to be sentence case 6mm (24 point) minimum.

• On a functional call panel each button shall have the relevant dwelling number engraved to the left of each button.

• Flat numbering shall start at the top left button and work left to right cascading down the call panel

• On a digital style call panel the numbers shall be engraved on each of the 10 No. Call buttons.

• All engraving to be machine engraving in filled with enamel paint or laser etched in black.

• All block names to be engraved at the top of the call panel in Title case 6mm (24 point) minimum. E.G “1 – 15 Kirk House”

Page 21: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/14

• Trades button with DDA yellow ring engraved, “Trades” for trades.

Back Box • Flush fitted galvanised steel or zink back box incorporating BS 316 marine grade stainless steel mitred bezel 12 SWG 2.5mm stainless steel.

• Fix to structure of building with non-ferrous screws. • Provide concealed conduit installation without cables entering the top of the back

box.

• Back box sealed by installer to side screen or wall using suitable mastic at the top and sides leaving the bottom free to allow any water to drain out of the box.

Push Buttons with DDA Yellow Contrasting Ring

• BS316 marine grade Stainless Steel, • No moving Pressure Sensitive (Not Touch sensitive). Moving buttons shall not

be acceptable.

• Ability to engrave on the button faces. • IP68 • Vandal Resistant. • Capable of withstanding heavy impact without adverse affects. • Flush fitted with external shoulder for a tactile feel to aid the visually impaired to

be able to locate the position of the button.

• To contrast the stainless steel of the call button and that of the call panel and to aid the partially sighted distinguish the call button shall have a milled yellow contrasting ring on the button.

• Contacts to be stainless steel with removable connector for termination on each call button.

Microphone Loudspeaker/ Amplifier Unit

• Be mounted in upper section of fascia plate. • Protected by holes not slots. • Further protection by a mesh infill to prevent insertion of any device. • Fixed by studs welded to rear of fascia plate. • Operate efficiently over a frequency range of 8 Hz to 200 Hz with fully integrated

circuit.

• Sensitive to maintain speech clarity/audibility over all ambient noise levels without distortion or lessening effect.

• Amplification to be adjustable in both directions with separate controls for adjustment of microphone and speaker levels for speech clarity/audibility in both internal and external environments due to location of panels.

Installation of Entry Panel

• The flush mounted entry panel shall be inserted in the new side screen final positioning to be agreed on site.

• The face of the panel shall be finish flush with the surrounding surface. Securing of the back box is to be achieved by suitable multiple fixings to prevent any travel or movement and be able to withstand the pressure exerted by any external levers.

• Care shall be taken to consider the disability act with regards the height and position of the door entry call panel.

• The entrance panels must be earthed to meet the current statutory electrical regulations BS7671 2008 (or later) and amendments.

• All cables entering the entrance panel must enter via glands, grommets or conduit locking rings and bush to protect the cable against sharp edges and shall be installed so that water cannot run down them and on to any components.

• No cable shall enter any back box via the top of the box. • The installer shall seal ALL back boxes to the wall or side screen to prevent any

water ingress Mounting • Mount panel to BS 8300:2009+A1:2010 sit within a zone of 900mm and

Page 22: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/15

Location/ Height

1050mm above FFL as part M and BS8300:2009 +A1:2010 with in 200mm of the doorframe or aperture, where there is a glazed facade, and adequately illuminated.

• Call panels shall be located on the latch side of the door.

Integral DDA Entrotec Proximity Reader Type EPR Fitted with in Call Panels

• Where Proximity access control (FOB) Readers are mounted within entrance panels they shall be: -

• Be flush mounted in lower section of fascia plate. • Reader incorporating a key symbol. • Reader incorporating a DDA Yellow back ground and a black key Logo. • Fixed by studs welded to rear of fascia plate. • The call panel shall include Standard English Braille. (Grade II).

English Standard Braille (Grade II)

999a

9 9 9 a

9 9 9 a

To be confirmed and instructed by CA.

• On functional panels Standard English Braille (grade II) is NOT REQUIRED • The ‘Trades’ button shall not be engraved in Braille. • On Digital panels shall have a Standard English Braille dimple on the number

five button with the call and cancel buttons either side of the “0” button as per the standard keypad layout to aid the visually impaired. All call buttons when pressed shall emit a bleep to indicate the button has been pressed.

• The contractor shall allow for engraving in STANDARD ENGLISH BRAILLE the words “CALL” & “CANCEL”

• The ‘Trades’ button shall not be engraved in Braille. • On a digital system if Braille is required and the system is an alpha system the

manufacturer shall include for Braille alpha letters. • The installer shall price as an option for Braille Instructions to be engraved on

the call panels for both functional and digital panels.

Proximity Access Control (fob) Standalone Readers. Rear/Residents Entrance Doors (RED’s)

General • Where Proximity access control (FOB) Readers are not mounted within entrance panels they shall be installed with a concealed conduit installation. Theses are generally rear/resident entrance doors. (RED’s).

Type Fascia Plate

• DDA Panel mounted EPR Reader

• Flush mounted unit with welded 2.5mm BS 316 marine grade stainless steel mitred bezel back box. Type EPR/BZ.

• Reader incorporating a key symbol. • Readers incorporating a DDA Yellow background and a black key Logo. • Carry 2 year guarantee • Fixed by studs welded to rear of fascia plate. • Rear door readers to be wired to the internal reader buzzer to give both audio and

visual indication on operation.

• 2.5mm Stainless Steel BS 316 marine grade brushed stainless steel plate fixed with a minimum of 4 no. Vandal resistant screws.

Back Box Mounting Height

• Flush mounted galvanised steel box. • Fix box through back with non-ferrous screws. • Provide concealed conduit installation.

● Mount reader to BS8300:2009+A1:2010 between 900mm and 1050mm to FFL as part M

POWER SUPPLY UNIT

General • The controlled entry system shall be served from a power supply control unit.

Page 23: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/16

• All enclosures shall be fitted with in a suitable cupboard. Door Entry control enclosures, KMS controller enclosures and marshalling boxes shall only under extreme circumstances be fitted in a vulnerable area and only with full advanced approval of location by the CA.

Enclosure • IP 66 Steel cabinet fixed to structure of building with non-ferrous screws. • Cabinet door, reversible to suit cupboard it is fitted with in. • Cabinet door locked with LK1242E security barrel lock(s). • All enclosures shall be fitted with in a suitable lockable cupboard. • If a suitable cupboard is not available the contractor shall consult the CA priory to

equipment enclosures being fitted in a corridor or an exposed area.

• The enclosure shall be fitted with a hasp and staple in addition to the standard Steel cabinet lock.

• The installer shall supply padlocks and fit one per cabinet. This shall be a suited as Brighton & Hove standard pad lock, IFAN KA1. Obtained from Brighton & Hove City Council, Estates Department, The Housing Centre, Unit 1 Fairway Industrial Estate, Eastergate Road, Brighton, BN2 4QL

• All containment & wiring systems to enter the cabinet via the entry plate, not top or rear entry.

Requirements • To incorporate a 6 amp double pole MCB for the incoming mains supply • Whole control unit to be pre-wired with plug and socket PCB connector on the

modular circuit boards for all incoming connection.

• Complete LED status and fault indicators. • Fused protection on input and output circuits. • Switched mode modular power supplies. Minimum 60 watt. • Battery back up facility. • Digital seven-day automatic summer/winter time correction trades clock with a

minimum of six on off times.

• Provide engraved Traffolite label fitted to cabinet door. Engraved “Door Entry System”

Door Entry Equipment

• Whole unit to consist of detachable modular printed circuit boards fitted to removable

steel chassis plates.

• Each circuit to be individually isolated and fuse protected. • Complete LED status and fault indicators. • Cabinet earthed to current IEE wiring regulations. • In the event of mains failure the system shall have full battery back up.

Under normal operation the system will automatically operate a built in battery charging circuit, this shall ensure optimum life performance of the backup facility should mains failure occur.

Adjustable Timers

• 0 - 60 seconds for lock release

• 0 - 60 seconds to call flats • 0 - 90 seconds for time to call dwellings

Installation • Locations as indicated on drawings in appropriate rooms. • Not in public areas. • Agree arrangement with Contract Administrator prior to installation. • Provide complete system of PVC cable, trunking to enclose all interconnecting cables.

Trades Time Clock

• Located with in main door entry controller/PSU enclosure. • Digital 7 day GMT/BST time correction clock. (Dallas chip controlled time clocks shall

not be acceptable).

• 6 on/off time settings.

Page 24: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/17

Trades Time Clock Settings

• Generally trades clock times to be set as below, agreed, confirmed and submitted to CA at time of commissioning. Certain installations shall have site-specific time setting as determined by the CA. Monday – Friday – On 7.00 am Off 12.00 am. Saturday – On 7.00 am Off 12.00 am. Sunday – On 7.00 am Off 12.00 am. Time settings to be agreed with Brighton & Hove City Council and are to be determined on site.

STANDBY BATTERIES

General • Provide battery back up supply to maintain both the Controlled Entry System and Access Control system and all doors in complete operation for a minimum of 4 hours on loss of main electrical supply.

Requirements • Automatic charging with LED status indicators. • Nickel Cadmium or sealed lead acid batteries. • Automatic changeover on loss, or restoration, of mains supplies. • Fitted with in door entry and/or access control enclosure. • Charging rate set to provide the battery 13.8 volts.

MARSHALLING BOX

General • The individual cabling to each dwelling telephone location shall emanate from a Marshalling Box/Hub Distribution Unit.

Enclosure • IP 66 Sarel cabinet fixed to structure of building with non-ferrous screws. • Cabinet door, reversible to suit cupboard it is fitted with in. • Cabinet door locked with LK1242E security barrel lock(s). • All enclosures shall be fitted with in a suitable lockable cupboard. • If a suitable cupboard is not available the contractor shall consult the CA priory

to equipment enclosures being fitted in a corridor or an exposed area.

• The enclosure shall be fitted with a hasp and staple in addition to the standard Sarel cabinet lock.

• The installer shall obtain suitable padlocks from BHCC Estates Department and fit one per cabinet.

• ALL boxes are to be fitted with a hasp and staple and locked with a padlock. (IFAN KA1)

• Provide engraved Traffolite label fitted to cabinet door. Engraved “Door Entry System”

Door Entry Equipment

Requirements • Whole unit to consist of detachable modular printed circuit boards fitted to removable steel chassis plates.

• Each circuit to be individually isolated and fuse protected. • Ensure breakdown from any individual dwelling does not affect any other sector

of system.

• Complete LED status and fault indicators. • Ensure complete secrecy of conversation so that all conversations are private. • Ensure all connections are of a plug in connector type. • The cabinet shall be fitted with a hasp and staple • Provide written label fitted to the inside cabinet door. Detailing the dwellings

connected and the related marshalling port the dwelling cable is connected to.

Page 25: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/18

• THE CHASSIS PLATE MUST BE REMOVED PRIOR TO DRILLING ANY HOLES TO THE CABINET.

Locations for installations

• Locate in concealed areas e.g. Store Room / risers / false ceilings (relative to floor served where possible).

• Not in public areas.

ROOM TERMINALS General • Provide each dwelling with a room terminal receiver unit to accept calls from

the entry control panel and release the appropriate entry door panel. • If the dwelling has an existing handset the contractor shall remove said handset.

If the new handset position does not cover the position of the existing handset fully the contractor shall provide a plastic plate to cover any Re decoration.

Requirements • ABS resistant impact plastic. • White in Colour. • Privacy/secrecy of speech • Timed privacy switch (On/Off button) with Red LED display & adjustable time

cancel facility to switch the room terminal back on (adjustable 5 Minutes to 8 hours).

• Green LED display indicating live Door Open/Door status. • Adjustable DC sounder/Call tone generated ring tone. Ringing tones adjustable

in each individual handset. If adjustable call tone volume is required for individual handsets then the ED9 handset shall be used in place of the ED4.

• Permanent marked operating pictorial symbols on room terminal moulding to indicate privacy switch, lock release button and door monitoring LED.

• Full discrete unlocking of entry door with anti lock down circuit. • Wall mounted with non-ferrous screws. • Contain knockouts to accept PVC mini trunking at any position. • Capable of accepting disabled aids, i.e. arthritic handles, hearing amplification,

Inductive couplers, strobe lights, extension handsets and sounders with out the need to extra cabling entering the dwelling.

Audio Handset Type

• Full Duplex two-way simultaneous speech. • Large soft touch 20mm lock release button. • Handset cover fixed to handset base with screws top and bottom. (Handsets

covers held to the handset base using clips shall not be acceptable).

• Handset easy to remove and replace on cradle. • Position and secure handset in vertical position. • Option to add secondary extra button for Concierge or operation of peripheral

devices

Video Handset Type

• Full Duplex two-way simultaneous speech. • 4” LCD TFT Colour video screen. • Adjustable call tone volume switch. • Engineer adjustable pots for Contrast, Brightness, Colour and Tint. • Illuminated buttons for Privacy On and Door Open. • Handset easy to remove and replace on cradle. • Position and secure handset in vertical position. • Option to add secondary extra button for Concierge or operation of peripheral

devices

Full Duplex Apartment

• Full Duplex two-way simultaneous speech, based on Digital Signal Processing (DSP) & Digital Echo cancellation (DEC) Technology. Half or simulated duplex

Page 26: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/19

Station using technology such as noise gates shall not be acceptable. • Single button press to answer and open bi directional speech. • Optional wireless remote control unit for DDA users.

• Surface and Semi flush fitting back boxes. • Illuminated buttons for Privacy On and Door Open. • Secondary extra button for Concierge or operation of peripheral devices included

as standard. • Audio and Audio Visual versions available in same housing. • Video version with LCD TFT Colour screen. • Capability through Echo cancelling to mix systems with handsets and apartments

stations.

Apartment Station Remote control

• Where requested the apartments station shall be controlled using a black 4 button remote control device allowing the user to fully answer the call, close the call, open the door and use a peripheral button to operate other equipment as required or call the concierge.

Location & Installation

• Generally positioned with in 5 meters with in Hallway, in close proximity to lounge and kitchen where possible in a position where the handset shall not be damaged by moving furniture in and out of the flat.

• Positions to be confirmed by CA on site. • Sited to prevent injury to user and unit from damage. • Close proximity where possible to Lounge and Kitchen. • Mounted at 1200 FFL to top of handset as per part M, BS8300:2005 and DDA

requirements.

• Provide PVC mini trunking installation to enclose cables. • Allow complying with any individual tenant's needs in sighting the handset, i.e.

elderly or infirm tenants may require lowering of mounting height and a different location from the norm.

Operating instructions

• Demonstrate the use of the handset to each tenant.

• Provide clear, concise printed operating instructions and hand to tenant when installing the handset.

FIRE SWITCH

General • Provide each main front entrance door & any other side/rear doors as indicated on the drawings and with in the schedules with a double pole fire override switch to momentary disengage and cut the power to the electric lock release or magnetic lock while the switch is operated and key is inserted and held also provide a time entry when the switch is momentarily operated at.

• The contractor shall also check with the CA to ascertain whether a fire drop key switch shall be required at any other location such as RED’s.

Type • (FS4/BZ) • Drop key design FS4 type double pole, double throw. • The fire switch shall be a three-section switch with three parts. Back box,

removable switch assembly and face plate. Switch • Double pole with two separate switch connections to provide normally open

going closed and normally closed going open with two separate commons. • The Fire switch shall comprise of three separate parts. The back box, the

removable switch assembly and the faceplate, so the switches can be connected and the cables dressed to avoid the key fowling the cables. The faceplate shall then be fitted after the switch has been tested.

Fascia plate • 2.5mm Stainless Steel BS 316 marine grade brushed stainless steel front plate with vandal resistant screws.

Page 27: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/20

• The switch shall have a tube producing by 1mm. This shall stop the key, when being operated scratching the faceplate.

Engraving • Front plate (115 x 115) to be engraved “Fire Switch”. • The Plate shall be fixed with minimum of 4 No. Vandal resistant screws. • Engraving to be 12mm high. Engraving to be machine engraving in filled with

enamel paint, Red infill.

Back box Fire key Mounting height Position Wiring

LOCKING DEVICES General Magnetic Lock Type

• Flush galvanised steel box. (120 x 120 including welding) • Fix box through back with non-ferrous screws.

• Provide concealed conduit installation. • Fire switch shall not have conduit or cabling leaving the bottom of the fireman’s

back box to enter the top of the call panel or stand alone reader back box. • All conduit and cable entry shall be from the side to avoid any water being able

to run down conduit or cabling and entering the call panel. All conduit and cabling shall be side entry.

• The door entry control panel back box and the fireman’s switch shall be linked using flush mounted 20mm galvanised conduit with no junction boxes or inspection elbows along the route.

• The fireman’s switch back box shall be solely for this purpose, and shall not be used as a through box.

• The installation contractor shall NOT directly link the cables from the bottom of the fireman switch to the top of the call panel. The cables shall leave the bottom of the fireman switch and enter the call panel from the bottom to make a drip loop.

• Allow for One (1) Fire Drop key per contract or phase of works to be. Key to be issued to Brighton & Hove City Council Mechanical & Electrical engineer at handover or delivery of O & M Manual(s).

• High level with top of door, above the call panel or reader fitted between 1900mm - 2000mm from FFL.

• Positioned directly above the door entry call panel. • Position as if the timed circuit fails the button can be depressed and held

depress while opening the door.

• The switch shall be wired to break the positive feed to the lock to open the door when the key is operated and held. This is a fail-safe method of entry. Under no circumstance shall the negative feed be discounted to open the door.

• The switch shall also be wired to provide a timed release, when the drop key momentarily operates the switch.

• Each entry door where ever possible shall be outward opening, except those for those indicated in the schedule or where the opening width will not allow for the use of magnetic locks. These locks shall be supplied by the door entry manufacturer and handed/free issued to the door manufacturers as described elsewhere for construction into the door frames or by Multisteel and shall be: -

• Securitron Magnalock M32 series • Two Per door • MED’s & SED’s - 1 No. M32SC – 12NM fitted with an internal monitoring switch

and 1 No. M32-12NM per door. RED’s - 2 No. M32-12NM per door.

Page 28: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/21

Lock Release Type

• Where the structural opening does not provide for a clear door opening of 900mm or doors are inward opening the following may be incorporated in lieu of magnets or on inward opening doors.

• Where the the doors are not controlled using Proximity access control then Bell 208 high security lock releases shall be fitted with all associated lock cases and half set lever furniture. The installer shall also supply suited mastered cylinders with three keys per flat.

• In the event the bell208 lock applications wont work due to fitment, the use of An ASSA high security monitored 5331A/ lock release shall be fitted with an ASSA 8761 emergency night latch with dead locking latch, ASSA 640 lever ASSA 20A half set and blind rose shall be used, or where a pull knob is required ASSA8561 half set with pull knob (ASSA496).

• No 16 face plate for timber doors • No. 24 face plate for steel doors

• Where indicated on smaller blocks in the blocks appendixes showing a particular spec the ASSA Medium Security lock release shall be used. MED’s fitted 5114A/ and RED’s fitted with together with suitable face plate to suit lock case either 5,10, 510 or 505.

Magnetic lock Installation

• Provide one monitored & one unmonitored Securitron magnetic locks per MED door.

• Provide two unmonitored Securitron magnetic locks per RED door. • Contractor to fit the top monitored magnetic lock and wire the door contact to

door entry monitoring circuit. • Contractor to fit the unmonitored magnetic lock to the bottom. Outward

opening door (unless agreed with CA). Outward opening door (unless agreed with CA).

• Ensure magnet built into vertical jamb ¼ distance from floor ¼ distance from top of frame.

• Locate strike plates onto door and align with magnets (front fix with vandal resistant security Allen key screw with centre pin and retaining box).

• Install in accordance with wiring manufacturer's recommendation. • MED Locks to be powered from Door Entry System, SED & RED Locks powered

from KMS controller. • Minimum cable size to serve locks to be 1.5mm to 2.5mm max if long runs.

Secure By Design Locking Devices

• Where Secure By Design accreditation is required the door manufacturer shall ideally provide the locking devices as named above. Where this is no possible they shall provide the lock that the SBD door has been tested with. Details shall be provided to the door entry manufacturer.

• Multipoint locking devices shall NOT BE ACCEPTABLE on any communal entrance doors. Except on individual flats entrance doors installation where SBD PAS24 Wink Haus AV2E locks shall be fitted to the flat entrance door.

• The Locking devices shall be: 1. Fail Safe 2. 12 Volts DC – Maximum Current 1 amp 3. Monitored

Operation Requirements for Door Release

• Actuation of door button on tenant's handset. • Operation of Access Control System. • Actuation of Push to Exit button. • Operation of Fireman’s Switch.

Page 29: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/22

• Actuation of Tradesman’s button at pre-determined times.

PUSH TO EXIT (PTE) – GENERALLY

General • Provide each door fitted with electromagnet locks with a manually operated push to exit button.

Type • Double pole switching (isolate door by removing the supply to the magnetic lock and activate timer) 10 seconds delay before reset – adjustable 0 to 60 seconds.

• Type – Flush fitted - PTE/EPTE/YR • 2.5mm Stainless Steel BS316 marine grade brushed stainless steel. • Large 25 mm moving button • The Plate shall be fixed with minimum of 2 No. Vandal resistant screws

DDA • The button shall be engraved with DDA yellow contrasting ring.

Mounting Height

• Mount PTE at 900 to underside to 1200 to the top from FFL to underside. To be agreed by CA on site. To BS8300:2009+A1:2010 & Part M.

Position • Position the push to exit so as it is protected and cannot be depress from the insecure side of the door or gate. It cannot be reached easily by using a coat hanger or stick.

• Positioned below or to the side of the door entry call panel back box to minimise the side screen depth.

• Position as if the timed circuit fails the button can be depressed and held depress while opening the door.

Wiring • The switch shall be wired to break the positive feed to the lock to open the door when the button is operated and held. This is a fail-safe method of entry. Under no circumstance shall the negative feed be discounted to open the door.

• The switch shall also be wired to provide a timed release, when the push to exit button momentarily operates the switch.

Engraving • Front plate to be engraved “Push To Exit”. Above the button in Green infill. Below the Button engraved “In Emergency Press & Hold the Button While Opening Door” in Red infill.

• Engraving to be 10mm high, engraving to be machine engraving in filled with enamel paint.

Flush Fitted Back Box

• Flush galvanised steel back box. • Fix with non-ferrous screws. • Provide concealed wiring installation.

If Surface Mounted PTE Back Box

• If a flush fitting box is deemed not practical and agreed with the CA, a surface mounted unit shall be installed.

• Powered coat steel back box GREEN in colour if internal or Stainless steel back box if external.

• Type – Internal back box – BBXPTESMPC. • Type - External back box – BBXPTESMSS. • Plate and switch inset with in the back box, 2.5mm Stainless Steel BS 316

brushed stainless steel. • The Plate shall be fixed with minimum of 2 No. Vandal resistant screws.

Alternative PTE

• On smaller blocks where indicated in the particular spec the PTE can be a PTE/YR as above but with out the extra RED emergency instruction engraving.

DOOR MONITORING

Page 30: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/23

General • The door entry system shall monitor the state of the MED on each system. This shall be via the door entry system door monitoring circuit and a Green LED that shall illuminate ion each hand set when the door is in the open position.

• The top magnetic lock shall be for the door entry system monitoring circuit (as applicable).

• The bottom magnetic lock shall be unmonitored, unless a secondary door contact is required, then this magnetic lock shall also be monitored.

VANDAL RESISTANT SCREWS

General • All accessible fixing screws shall be vandal resistant and tamper proof. Samples shall be provided to the Project Administrator for approval.

Type • Zinc plates with system zero high tongue head. • Be of appropriate size and type to their application to give a ridged fixing.

Screwdrivers • Provide two screwdrivers to the Project Administrator for each size of screw

installed.

General • When the building has a fire alarm or Smoke detection system the door entry

and KMS system controlled doors shall be connected to the FA/SD system.

• The FA/SD system manufacturer shall provide an I/O relay at every required controlled door to disconnect the supply to the lock when operated. The FA/SD system shall not be interfaced with the door entry or proximity access control system and shall only disconnect the lock supply. On activation of the fire alarm/smoke detection unit the door entry/KMS system shall unlock all doors until the fire alarm/smoke detection controller has been reset.

• Final connections to the fire alarm/smoke detection system to be carried out by the fire alarm/smoke detection installer or Maintenance Company.

• I/O relay shall be require a volt free normally open held closed contact going open on activation of the alarm that shall open all doors until the fire alarm/smoke detection controller has been reset.

Brake Glass • Only where indicated shall a green break glass unit be fitted. • Generally these are not fitted on a on general housing blocks of flats. • As agreed on individual project & doors by the CA.

IRS/COMMUNAL ARIAL SYSTEMS

General • When the building has a need for the residents to receive CCTV images via the IRS system on the residents TV, the contractor shall supply a Entrotec Dome camera that shall either be wall or ceiling fixed to look down & across at the MED to see both the caller and area around the door.

• Camera signal linked to buildings CCTV system and recording equipment. • Image only to be sent to the IRS/communal aerial system on activation of the

door entry system.

• Door entry equipment shall be interfaced so that the signal from the camera is switched via a timer relay and only active when the door entry system is in use, limiting the time the image is being shown on the residence television set.

• An interface relay shall close a contact and allow the CCTV image to be sent to the IRS/communal aerial system allowing the image to be viewed on the residents TV. This shall only occur when the door entry system is in use.

• Final connections to the IRS/ communal aerial system to be carried out by the

Page 31: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/24

IRS maintenance or installation company. Please arrange via the CA. • Entrotec require a volt free contact.

PROXIMITY ACCESS CONTROL ENTRY INSTALLATION

PROXIMITY ACCESS CONTROL Variation of Equipment General Requirements

The Proximity Access Control entry system shall be as manufactured by:- Key Management Systems Or equal and approved (see variation of equipment) The KMS equipment shall be purchased and supplied from

Entrotec Ltd, Access House, 5 Ashwood Court, Oakbank, Livingston, West Lothian, EH53 0TL. Tel : 01506 886230 Fax: 01506 886233 [email protected] www.entrotec.co.uk • If the contactor wishes to vary from the nominated equipment manufacture he

must complete the tender return using KMS equipment as per the specification.

• If the contractor wishes for an alternative equipment manufacturer to be considered then he must provide, on a separate sheet, a costing break down showing a like for like alternative in a similar format to that of the tender return. He shall provide a detail letter explaining why he wishes to deviate from KMS with a list of advantages, a full specification of the alternative manufacture, if deemed a suitable replacement.

• A contactor can only put an alternative equipment manufacture forward at a pre contract meeting and only if in full agreement with the client and the contracts administrator.

• All KMS equipment shall be purchased via Entrotec Limited. The installer must and shall not purchase the KMS equipment from another source. Remote programming of the controllers shall be covered elsewhere in this specification.

• Each controlled entry system shall be supported by a proximity access control system as manufactured by KMS Key Management Systems utilising FOB electronic keys.

• The proximity access control system shall also be used for all other controlled access doors that are not directly connected to the Controlled Door Entry System, such as Bin and cycle stores.

• The contractor shall use the type KMS 10,000 GPRS enabled controller specified by the CA.

• KMS controller shall be supplied pre-programmed with resident fobs. • The Contractor shall provide a proximity key reader access system. The access

system shall be a non- contact proximity technology where specified. Residents' access into controlled areas will be via the use of individually coded electronic keys.

• The system shall comprise of Proximity Access Control system controllers for 2 doors with power supplies, battery back up, readers and fobs.

• The Proximity Access Control controller shall be selected to suit the building being controlled.

• Blocks shall be controlled with the KMS SimpleKey controller with a GPRS modem using a SIM card linked to the Councils web based cloud system. SIM card to be provided by B&HCC.

• KMS shall only be installed if there are more than 6 dwellings with the exception

Page 32: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/25

Enclosure Controllers Installation

of blocks using Maglocks on main and rear entrance doors. • All installs shall use the larger sarel box to allow for the larger controller and

modem for future KMS upgrade, should MED/RED be replaced and would incorporate a maglock system.

• All KMS equipment shall be purchased via the door entry manufacturers Entrotec Limited. The contractor shall not provide his own KMS equipment.

• All KMS controllers supplied pre-programmed • Comply with Brighton and Hove’s standard fob colour coding.

Grey/Yellow/Green. Fobs pre-programmed in to controller.

• Ensure interconnections between systems are interfaced by Controlled Entry Manufacturer’s equipment.

• To incorporate a 6 amp double pole MCB for the incoming mains supply. • Incorporate suitable switch mode power supply Minimum 60 watt with battery

back up facility and battery. • The locks for the main entrance door or for any door with a door entry call panel

shall be powered by the door entry controller’s power supplies and not via the KMS lock output.

• In every case an audible indication shall be heard when the door has being released generated by the door entry system. All read entrance doors, shall be powered via the KMS lock outputs.

• GPRS modem power shall be wired to switch on/off via a relay. • Where ever possible where blocks are physically linked, the installer shall

link/network all controllers to a single GPRS modem. • IP 66 Sarel cabinet fixed to structure of building with non-ferrous screws. • KMS controller boxes are NOT ACCEPTABLE. • Cabinet door, reversible to suit cupboard it is fitted with in. • Cabinet door locked with LK1242E security barrel lock(s). • Provide engraved Traffolite label fitted to Controller cabinet door. Engraved “FOB EQUIPMENT”

FOB Equipment

• Where existing cabinet does not house fob equipment but it is then added at a

later date “FOB EQUIPMENT” traffolite shall be added.

• All enclosures shall be fitted with in a suitable lockable cupboard. • If a suitable cupboard is not available the contractor shall consult the CA priory

to equipment enclosures being fitted in a corridor or an exposed area. • The enclosure shall be fitted with a hasp and staple in addition to the standard

Sarel cabinet lock.

• The installer shall supply padlocks and fit one per cabinet. This shall be an IFAN KA1 padlock suited to Brighton & Hove City Council’s Code.

• KMS 10,000 SimpleKey controllers. For networked systems with up to two doors, with the capacity to network via hard wired link to slave KMS controllers. Up to a maximum of 20 controllers can be networked together and linked via a GPRS SIM and modem to a remote KMS SimpleKey Web System.

• Maximum network cable distance 1 K. • KMS 1000 controllers shall not be acceptable. • PAC EasiKey 99, 250, 1000, 512, iPAC & 2000 series controllers shall not be

acceptable.

• Location as indicated on drawing in appropriate room. • Do not mount in public areas. • Group together with standby battery units and where appropriate

Page 33: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/26

GPRS installation for networked controllers High Gain Aerial KMS GPRS Installation Access Control

• Fix to building fabric with non-ferrous screws. • Agree arrangements with CA. • Provide complete system of cable trunking to enclose all interconnecting cables.

• Where requested that the proximity controller shall be network to a remote cloud based PC using a GPRS modem and Data SIM card the contractor shall supply the following.

• Master KMS controller connected to GPRS modem to remote program and manage key fob database.

• Provide KMS GPRS modem fitted next to KMS controller in Entrotec Sarel door entry enclosure.

• Where the Master KMS controller is to be connected to a GPRS modem. The contactor shall liaise with Brighton & Hove City Council for system synchronisation.

• The KMS SimpleKey controller is to be networked to a KMS SimpleKey Web System

• The KMS Controller shall be connected to a GPRS modem. • The contactor shall fit a Vodafone data SIM with in the modems. • Data SIM card to be Free issued by Brighton & Hove City Council CA. • Where a Vodafone signal is not possible the contractor shall liaise with Brighton

& Hove to provide a suitable SIM card by a provider that produces a good signal for the area.

• To provide KMS GPRS modem, fitted with in the Entrotec.

• The installer shall provide and install a high gain aerial fitted to the outside of the building if using a GPRS modem. Not required on PSTN or hard-wired systems.

• The installer shall carry out site surveys and carry out a signal strength test to find the best position for the aerial to gain maximum signal strength. This shall be done in conjunction by consulting Vodaphone mobile and by using a signal strength test meter. Test results shall be provide to the CA before a final position to fit the aerial is agreed and completed.

• Fitted in a high level and secure location.

• The KMS controllers shall be networked to a KMS SimpleKey Web System. • Brighton & Hove City Council has such a PC installed in their head office

controlling several blocks connected to the KMS SimpleKey Web System.

• The contractor shall prepare the systems to have the KMS pre – programmed tokens synchronised with the KMS SimpleKey Web System.

• Where instructed in the particular specification a GPRS modems cannot be used. The Installation contractor shall liaise with Brighton & Hove City Council CA to arrange a dedicated PSTN phone line installation at the required block and office location. Generally where GPRS signal are not available.

• The Installation contractor shall liaise with Brighton & Hove City Council CA to have the KMS system networked to the KMS SimpleKey Web System for controlling the fob access.

• The Installation contractor shall provide pre-programed KMS Controllers for use with the KMS SimpleKey Web System. The contractor shall discuss this process with the client and agree a format and procedure to issue tokens to the client prior to commencing work.

• The main contractor shall install the proximity access control system to the manufactures recommendations. The reader cabling shall use multi-stranded

Page 34: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/27

Cables Disabled, visually impaired, blind, elderly or tenant with special needs (DDA 2004) PC & KMS SimpleKey Web System Notes for issuing keys to estate officers

unscreened six-core cable and the reader shall be capable of operating up to 1,000 metres from its control unit without the need of an additional power supply. Cable from the reader shall be permitted to run next to mains carrying conductors without adverse effect.

• Readers

Up to 200 metres: 0.22 mm2

Up to 500 metres: 0.5 mm2

Up to 1000 metres: 1.0 mm2

• Notes: 1. All cable is 7/0.2 unscreened multi-stranded (intruder alarm style)

cable. 2. If screened cable is used, then reduce distances quoted by 1/3 third.

• In the case of disabled tenants, elderly, visually impaired or blind tenants, the contractor must provide adequate instruction as to how the tenant is to use the access reader.

• The contractor shall explain the raised tactile key symbol and its meaning. • The tenant shall be instructed as to how to show their token and gain successful

entry.

• The lights and sounder functionality of the reader shall be fully explained to the tenant.

• The contractor shall ensure that this additional door open time is suitable for these tenants by means of a live test using wheelchairs/walking frames etc and adjust accordingly.

• The KMS SimpleKey controllers shall be networked to the KMS SimpleKey Web System. The Installation contractor shall liaise with Brighton & Hove CA to have the KMS system networked to the KMS SimpleKey Web System

• Brighton & Hove have such a PC in the Housing center controlling several blocks. This is via the cloud based system and managed by Estate Services.

• The contractor shall allow for having the KMS tokens pre-programmed via the SimpleKey Web System

• Connection SimpleKey Web System remote PC.

• All Proximity keys issued should be identified per flat and grouped together and placed in a polythene bag detailing the flat they are issued to with a copy of a user guide to both the key fob access control system and door entry system. The address of each block should be clearly written on the front of the bag.

• Non-residential keys should be placed in a polythene bag and passed to the nominated CA.

• The system uses “Common Access” Fobs that have been issued to Mears and B&HCC staff that have common access across the city these fobs are colour coded for ease of identification.

• Mears Master Common Access fobs – KMS Shark Tooth – RED. • B&HCC Staff Master Common Access Fobs – KMS shark Tooth – BLUE. • These coloured tokens shall not be issued to residents • All "Master" or "Staff" fobs for the system should be clearly identified and

handed over to the nominated Project Manager, unless written permission to hold onto an editor key after commissioning is granted.

Page 35: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/28

KMS UPGRADE WHEN EXISTING PAC SYSTEMS ARE INSTALLED

• Where Pac controller is fitted with in an Entrotec supplied Sarel enclosure, there

is sufficient space to retro fit a KMS controller within the existing cabinet. It should be installed with the correct display orientation, KMS control shall always be fitted landscape.

• If the KMS controller can not be fitted with in the existing cabinet it shall be fitted in a new Sarel cabinet as described previously in this specification.

• If controller is fitted in existing Pac enclosure, KMS system can be installed on custom chasis plate with PSU, GPRS, modem and MCB as entrotec.Kmsc/lok/gprs/60w/cpo/special

KMS FOB ELECTRONIC KEYS

General Key Fobs and Programming Commisioning

• Provide per block 3 pre-programmed Fob Keys per dwelling complete with solid coloured ID (KMS Shark Tooth Fobs).

• All Residents’ fobs shall be colour coded to easily identify each fob issued to the same apartment.

• Each Fob Key to be colour coded with Key 1: Grey, Key 2: Yellow and Key 3: Green for 1st, 2nd & 3rd issued fobs. Where a 4th fob is required this shall be Black. A 5th shall be Orange and a 6th shall be Purple.

• All keys to be programmed and issued to Housing Management as required during the contract period.

• Each set to be separately packaged. • All KMS tokens to be pre-programmed by KMS, down loaded to the KMS

controller pre supply, numbered and enter on the SimpleKey Web Cloud System.

• The key fobs shall be identified and entered onto the system programming residents issue list as flat number and a coloured fob.

• All key fobs supplied by the Contractor shall be pre-programmed in to the controller labelled and bagged to the flat number.

• Each key fob given to the same property must be easily identified from each other by coloured fobs. A separate colour for each fob issued to the same dwelling. The fobs shall be given to the Resident of each property and a signed receipt obtained.

• All key fobs supplied by the Contractor shall be identified and entered into the system and be allocated to relative readers and controlled doors as required.

• No system shall be put into operation or the doors locked unless all fobs have been issued and all Residents instructed on their use.

• The Contractor shall in addition ensure that every Resident is made aware of the function and operation of the door entry installation before the system is put into operation.

• All the fobs will be entered onto the system / programmed prior to handover to ensure that at the time of handover the system will be fully operational.

• The contractor shall at time of order provide Entrotec a programming list strategy that shall be provided in advance to show which fob shall be allowed to open which door or combination of doors. This shall be in the format of the example spread sheet Annex L.

• The contractor whilst on site shall contact KMS and provide them with the DATA number and confirm with KMS the Sim + Block are online

Page 36: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/29

PERFORMANCE SPECIFICATION FOR INSTALLATION

General: Method of Cable Installation

• The whole of the system wiring shall be in strict accordance with the current addition of the IEE wiring regulations and where possible, be concealed and run in such a manner so as to be as unobtrusive as possible. Where wiring is surface fixed cables shall be run in the following manner:

Electrical Installation Generally

• Install, test and commission the electrical work in accordance with the current IEE

• Regulations, ensuring compliance with design and performance requirements, to provide a safe, well insulated, earth protected system capable of supplying the anticipated maximum demand.

• Installation work to be carried out by qualified electricians fully conversant with the current IEE Regulations.

• Fastenings, bushes, glands, terminals, connectors, clips, clamps and all other minor accessories necessary to complete the installation to be types recommended for the purpose by relevant equipment, accessories, and etc.

• In locations where moisture is present or may occur, use corrosion-resisting fastenings and avoid contact between dissimilar metals.

Steel conduit and trunking installation (communal areas and risers)

• All cables within communal areas and risers shall be installed within surface run steel conduit/trunking to route agreed with CA prior to installation.

• Conduit/trunking shall be of sufficient size to permit easy withdrawal of cables and installation of cables.

• Ends shall be cut clean and square with axis and shall be reamed. • Bends shall be made so as not to alter the diameter of the conduit. • Purpose made elbows, bends or tees shall be used. • All conduits shall be butted inside couplings, boxes and accessories. • All conduit/trunking shall be galvanized. • Steel conduit circular locking rings shall be fitted to each entry to every type of

screwed fitting and to each of running couplings.

• The method of terminating steel conduit at all untapped entries shall be by means of a smooth bore brass bush, compression washer, couplings and lock ring.

• Exposed conduit threads inside boxes shall not be permitted. • The conduit/trunking shall be mechanically and electrically continuous

throughout so that cables are fully protected and shall be fixed with round head screws in accordance with current IEE regulations (BS 7671 – 2008 and amendments).

• The trunking shall be complete with all purpose-made accessories including end caps, lids and earth continuity links.

• All bends and tees shall be gusseted. • Site manufactured bends shall not be permitted. • On horizontal runs of trunking, cable-retaining straps shall be fitted at 1.5m

centres. • On vertical runs of trunking, cable supports shall be fitted at 3m centres. • Where any cable trunking passes through a fire barrier, a cable support with fire

stopping material shall be provided.

• Mounting/support: (Conduit shall be supported at regular intervals not exceeding 1000mm on horizontal and vertical runs using vandal resistant screws).

• All conduit/trunking lids to be secured using security screws.

Wiring and cables

• The cabling to the Controlled Entry/Access Control System shall be of a conventional system with each one dedicated to its task.

Page 37: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/30

• Provide 6 pair CW1308 to each handset (include 25% spare pairs for future use and maintenance).

• Twisted multi pair PVC insulated cables CW1308 shall be used. (Copper core).

• All Handset cables shall be 6 Pair CW1308. This shall allow for spare pairs to the Brighton & Hove City Council spare pair policy and also allow for extra cables for future use/allow spares for future use, and upgrade to video systems using a dedicated twisted pair. 4 Pair is not acceptable

• Size not less than 0.5mm² CW1308 conforming to BT specifications. • Ascertain the exact wiring requirement and number of cores (minimum 6 pair)

for each situation. Provide a minimum of 30% spare conductors.

• In selection of cables ensure suitability for correct operation of system. • All cables to be in continuous lengths. • Intermediate joints not allowed. • No wiring connections affecting another area or dwelling to be contained within

a dwelling.

• Terminations shall not contain any crimped or plug-in type connections. • Where KMS controllers are interconnected with cable in conduit appropriate

multi pair CW1308 cables shall be used. Where controllers are linked with cables in underground ducts appropriate multi pair CW1128 cables or armoured cables in line with the current IEE wiring regulations shall be used.

Cabling Generally

• CABLES to be BASEC certified. Select types and sizes to suit operating conditions, ensuring compliance with BS 7671. Obtain approval before proceeding with installation. CABLES to be BASEC certified and of the types listed below. Where not specified, select types and sizes to suit operating conditions, ensuring compliance with BS 7671 – 2008 and Amendments. Obtain approval before proceeding with installation.

• Location/use Cable Ring Circuits 2.5mm Sq PVC insulated and sheathed Lighting 1.5mm Sq PVC insulated and sheathed Metre tails 16mm Sq Double insulated

Cable Routes • Straight, vertical or horizontal and parallel to walls unless shown otherwise.

In approved locations where exposed to view. When not specified otherwise, conceal cables wherever possible.

• Concealed horizontal runs in walls, if unavoidable, to be located within 150 mm of ceiling or between 150 and 300 mm of floor.

• Concealed cable runs to wall switches and outlets to be vertically in line with the accessory.

Installing Cables Generally

• Do not commence internal cabling until the building is sufficiently enclosed to ensure permanently dry conditions.

• Install cables neatly and securely, adequately protected against accidental damage, adverse environmental conditions, mechanical stress and deleterious substances.

• Install cables without joints other than at equipment and terminal fittings. • Do not use junction boxes without approval. • Sleeve cables passing through masonry walls with conduit bushed at both ends. • Do not run cables in spaces where they will be surrounded or covered by

insulation. Where this is not practical, size cables accordingly and inform CA. • Use cable conductors throughout; do not use conduit or trunking as protective

conductors.

• Handle and install carefully to prevent damage to sheath and armouring. • Do not install if cable and ambient temperature are, or have been for the

Page 38: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/31

Protective Conductors

Armoured Cable

previous 24 hours, below 0 °C. • Fit galvanized steel guards where cables are liable to mechanical damage. • Bond armour to equipment and main earthing system.

• Make moisture proof connections to apparatus using sealed glands and PVC shrouds.

• Armoured PVC insulated cables shall be subjected at the manufacturers works to the routine test, detailed in BS6346. Duplicate copies of the test certificates shall be submitted to the Brighton & Hove City Council Electrical Engineer if requested.

• If jointing of cables is required the voltage test detailed in BS6346 clause 16.3 using test voltages to BS6346 table 20, shall be applied to the cable in the presence of the Brighton & Hove Electrical Engineer or his appointed representative.

• A visual check of all conductors, bonds and joints of their measured electrical continuity shall be undertaken.

• The method to testing shall be as given in BS 7430. • Where the building construction steelwork and/or foundation piles are employed

as an integral part of the system resistance and continuity test shall be carried out at each stage of the building construction and the results recorded in the logbook.

PVC Sheathed Cables

• Do not install cables when the temperature is near or below freezing. • Do not install in cavities of external walls. • Fit insulating cable glands at entries to equipment. • Terminate cable sheaths within boxes.

MICC Cables • Neatly and carefully dress cable into position using tools recommended by cable

manufacturer. Avoid corrugating sheath when bending. • Connect to equipment and boxes with PVC shrouded glands. • Fix cables with clips recommended by manufacturer ensuring that cable is fixed

within 150 mm of bends and connections.

• As soon as a length of cable has been installed, fit permanent seals and immediately carry out an insulation test between conductors or between any conductor and cable sheath. Repeat test between 24 and 48 hours later. Only infinity readings will be accepted. Replace any cable, which fails and repeat tests.

Cables Laid Directly in the Ground

• Before laying cables, ensure that bottom of trench is even and free from sharp stones, roots, etc.

• Lay cables on a 75 mm bed of sand. • Where two or more cables are laid in the same trench, set 150 mm apart. • Cover each cable with 75 mm of sand overlaid with cable covers to BS 2484. • Mark each change in direction of cables with a precast concrete slab, size 300 x

300 x 150 mm thick, impressed with 'LV CABLE' and laid level with finished ground level.

Cables in Vertical Trunking/ Ducts

• Support with pin racks or cleats at each floor level or at 5 m vertical centres, whichever is the lesser.

• Provide and fix heat barriers at not more than 5 m centres where fire-resisting barriers are not specified.

Conduit/Trunking/Ducting Generally

• Use conduit/trunking/ducting suitable for the location and use, ensuring adequate: Strength Tolerance of high and low temperatures

Page 39: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/32

Resistance to ingress of solid objects and water Electrical properties Corrosion resistance Resistance to flame propagation.

Steel Conduit and Trunking Installation

• Location/use: [To communal stairwells and corridors] • To BS 4568:Parts 1 and 2 or BS EN 50086-1 and 2-1.Manufacturer and

reference: [Davie Burton in plain thread able rigid conduit no less than 20mm internal diameter]

• Jointing: [Screwed] Size: In accordance with BS 7671 – 2008 and Amendments • Fittings: [Deep boxes, extension rings, expansion coupling should be used at intervals were conduit crosses movement joints • Protection class/finish: [Class 2/ Galvanised] • Other requirements: [All conduit is to be run at least 150mm clear of any

plumbing and mechanical services. Cable running adjacent or parallel to heating pipes are to be located under the pipes]

• Mounting/support: [Conduit shall be supported at regular intervals not exceeding 1000mm on horizontal and vertical runs using vandal resistant screws]

• Use maximum practical lengths to minimise number of joints. Remove burrs from cut ends.

• Use elbows or tees and/or junction boxes at changes of direction. • Fix securely with boxes fixed independently of conduit. • Tightly screw all joints to ensure electrical continuity, with no thread showing.

Use expansion couplings where conduit crosses movement joints in structure. • Make secure connections to boxes, trunking, etc. with screwed couplings and

provide rubber bushes at open ends.

Steel Surface Trunking system Generally

• Location/use: [Riser routes] • To BS 4678:Part 1. • Manufacturer and reference: [Davies Burton or equal and approved] • Size: In accordance with BS 7671. • Fittings: [Screwed couplings and rubber brushes at open ends] • Protection class/finish: [Class 3 / Zinc coated] • Other requirements: [Metal partitions inside trunking] • Mounting/support: [Surface Screwed] • Use proprietary units to form junctions and changes of direction wherever

possible.

• Use mechanical fastenings/fixings; do not weld. • Fit a copper link at each joint to ensure electrical continuity. • Fit grommets, bushes or liners into holes, through which cables pass. • Fit security screws to secure trunking lids.

Installing conduit in concrete

• Fix securely to reinforcement and fix boxes to formwork to prevent displacement.

• Depth of concrete cover to be not less than specified for reinforcement. Drainage of conduit

• Provide drainage outlets at lowest points in conduit installed externally and in locations where condensation may occur.

PVC Surface Trunking System Generally

• For use in Flat/dwelling only To BS 4678:Part 4. • The contractor shall install all cabling with in each dwelling in white MT1 mini

trunking the contractor shall use manufactured bends and ends only.

• Installer to install to CA’s requirements. • Allow 6 meters per dwelling.

Page 40: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/33

• MK Electric Limited, UK Head Office, The Arnold Centre, Paycocke Road, Basildon, Essex, SS14 3EA. Tel: 01268 563 000. Fax: 01268 563 360

• Size: In accordance with BS 7671

• Use maximum practical straight lengths to minimise number of joints. • Use proprietary units to form junctions, changes of direction and trunking entry

to surface boxes. • Site manufactured changes in direction will not be permitted. • Strength: [Heavy] duty. • Colour: [White]

Door Entry System Multi-Core Wiring

• The cabling to the door entry system shall comprise be carried out using standard twisted core PVC insulated and sheathed, screened where necessary, cables complying to the British Telecom Specification CW1308 and rated not less than 80V suitable for internal and external conditions. (0.5mm PVC/PVC) (CW1600 where screen cable is necessary) except where larger cables are required for heavy-duty lock releases, magnetic locks or earthing requirements to meet the current statutory electrical regulations. The conductor cross-sectional areas shall be such that the lengths required for the installation shall not affect the system operation.

• All wiring to include 20% spare pairs. (Not spare cores) i.e. 6 pair CW1308 to Handsets.

• A 25% spare factor shall be allowed for all containment. • The Contractor shall ascertain the exact wiring details required for each

situation, including numbers of cores etc., for the correct operation of the system.

• At no time shall any junction boxes be used to join cables Cable lengths shall be continuous lengths from marshalling boards to Handset. Cable junction boxes will not be permitted.

• All multi strand cables should have the appropriate sized ferruls crimped on for termination

• All cables shall be identified with cable markers. • Type A + B Systems should have 15 pair for Door entry + 6 Pair for reader or

future reader, + 1.5mm2 3 core Flex for supply and earth.

• Reader cables shall be installed on all KMS ready systems for future proofing. • ALL EQUIPMENT IS TO BE EARTHED TO MEET THE CURRENT STATUTORY

ELECTRICAL REGULATIONS BS7671 2008 and Amendments.

Fixings • All screws used in conjunction with the electrical installation, other than those used on the panel facia, shall be of a tamper proof type. The Contractor shall allow in their rates for the supply of and handing to the Contract Administrator 1 No. purpose made screwdriver to suit such screws.

• All conduit box lids and trunking is to be held in place with security screws. EARTHING AND BONDING REQUIREMENTS

General Earthing and Bonding Requirements

• The complete electrical installation and system shall and must be correctly earthed in accordance with B.S. 7671:2008 IEE wiring regulations and in the case of low voltage cables DC circuits grounded at the same potential throughout the installation. In addition where the systems voltage has a potential risk of contact with metallic fixed structures, those items must be supplementary bonded to earth.

• In full accordance with the current IEE wiring regulations (BS 7671 2008). • The installer shall also strictly follow the manufacturers earthing requirements.

Page 41: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/34

Testing of Door Entry and Access Control Systems Once the Contractor has satisfied himself that the system is fully operational, testing shall be carried out in the presence of the Contract Administrator. The testing shall be carried out on sections of the completed installation as necessary to ensure satisfactory operation of the following:- 1. Operation of the call tone, speech and door release system from each dwelling

telephone handset unit.

2. Audibility and clarity of the communication system from each dwelling unit to the entrance porch and vice versa.

3. The tests shall be carried out using a dummy dwelling unit connected to positioned

plug in test connections. On completion of the testing, duplicate signed Test Certificate and Commission Certificate indicating individual flat tests will be handed to the Contract Administrator.

4. Once the system is finally tested. Should any amendments be made to this system

as a result of testing, then the amended copies of the above are to be issued to the Contract Administrator.

5. Key fobs operate the doors correctly 6. Test results shall be submitted in the form of a checklist with a final Test certificate to

the Contract Administrator upon completion The installation contractor MUST and shall be a current Entrotec approved installer. If they are not they Must and shall employ Entrotec Limited to commission the system fully. This shall be in full agreement with the client at tender stage. No other company other than Entrotec or Current Entrotec approved installers shall commission the system. Evidence shall be provided that the system has been commissioned by Entrotec Limited or that the installation contractor a current approved installer.

The entire system shall be tested upon completion by the Contractor, with final testing and commissioning to the satisfaction of the Contract Administrator.

Test results shall be submitted in the form of a checklist with a final Test certificate to the Contract Administrator upon completion. The Contractor shall also provide two copies of operating instructions, manuals, ‘As fitted’ drawings and schedules of equipment. This is to include equipment locations, wiring routes, details of which flats are supplied from which Floor Handset Distribution Unit.

The Contractor must have local maintenance and repair facilities available, especially for

dealing with emergency call outs. The Installer shall be issued an Entrotec commissioning certificate to provide to the client. Entrotec shall be responsible for the upkeep of the system against manufactures defects for a period of one year from the date as indicated on the manufactures commissioning certificate. The installer shall responsible for all other defects.

The Contractor shall also supply the addresses and telephone numbers of Maintenance Departments who will be responsible for servicing the system. One copy of this information

Page 42: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/35

shall be retained at site, a second copy shall be supplied to the Contract Administrator and a third copy will be issued to the relevant estates office.

Inspection and Testing To BS 7671 2008, Part 7 and Appendix 6 of the current IEE Regulations.

Give not less than 24 hours notice before commencing tests. In addition to items required to be, inspected or tested, ensure that labels and signs required by the Regulations are securely fixed in the correct locations. After satisfactory completion of tests submit two copies of inspection and completion certificates to CA. Builders Work in Connection with the Controlled Entry System The builders work is to include all work necessary to install the controlled entry system including: 1. Cutting out or forming holes, chases; 2. Building in equipment; 3. Removal and replacement of ducts, panels, false ceilings, etc., to provide access; 4. Making good all work disturbed and decorating all exposed new metal conduits on

corridors.

5. Removing and making good of any walls, side screen or pedestal after the removal of any door entry or proximity access control equipment such as Call panels, fire switches or readers

PVC Mini-Trunking

The system wiring to the handsets shall be enclosed within 16 mm x 16mm white PVC mini-trunking – colour white, which shall enter the handsets in purpose made knock-outs and trunking accessories. All changes in trunking direction shall be made with pre-manufactured accessories. All conduit/trunking is to be installed in a neat and tidy manner, with adequate clips and fixings. Allow up to 5 Meters of trunking per dwelling. The trunking shall be fixed using round head screws of adequate length located every metre and within 25mmm from each end, corner or change of direction. All cutting of trunking shall be neat, clean and true. Ragged edges shall be cleaned off. Junctions between sections and accessories shall be made with proprietary trunking accessories. The trunking shall run vertically and horizontally and shall run close to corners of the building structure, architrave’s or where possible within cupboards etc. The trunking shall present an unobtrusive appearance upon completion. All trunking shall run between finite positions, i.e. accessories, walls and ceilings etc. and shall not terminate in mid run. Where necessary trunking shall be extended to the next change of direction of wall/or ceilings.

Page 43: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/36

After final installation all trunking and trunking lids shall be cleaned using a mild detergent. Prior to fitting, a sample shall be provided to the Contract Administrator for approval.

Labels and Diagrams All items of equipment shall be identified with a part number noted on it.

Terminals inside each unit must also be readily identified by engraved or pad printed labelling on the PCB i.e. terminals labelled Ov, +6v, S1, S2 for speaker amp connections. All cables must be clearly labelled with destination i.e. flat cables, flat 24.

The system will be supplied with an instruction manual complete with circuit and schematic diagrams. A copy of which will be left on site with the equipment for ease of maintenance. An instruction sheet and handset connection diagram should be supplied with each handset. The instruction sheet will in each case be left with each user at each handset position

The installer shall provide an idiots guide to each dwelling indicating how to use the door

entry and proximity access control system

Holes etc The Contractor is to allow for making all penetrations for cables. System wiring is to enter the property through a purpose made hole within the building fabric, not the door frame. Cutting of ways through landings, brick walls, etc. shall be carried out by boring using masonry drills and electric hand drills. Holes are to be drilled from the flat outwards so that any blown wall finishes are external. The Contractor shall be required to pull back existing wallpaper, make good the hole with plaster and reinstate the paper on completion. The cutting of holes through concrete floor slabs shall be undertaken by using diamond cutter. Holes to be made good. All holes shall be fire stopped to current BS regulations. All cables running through the building fabric shall be protected against mechanical damage. Cables installed in conduit running between floor levels shall be protected with sleeves. In the event of a valid claim for redecoration being sustained, the cost shall be borne by the Contractor. The work shall be carried out when the flats are occupied and full allowance shall be made for this when pricing. Samples

The successful Contractor shall provide samples of the equipment intended to be used and also off-site demonstration of the equipment working as specified during the tender period. All samples submissions and demonstrations shall be required to meet the approval of the Contract Administrator prior to the work commencing on site.

Maintenance The Contractor tendering must indicate the provision made for the continued maintenance

of the Controlled Entry System.

Page 44: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/37

Where defects occur within the twelve months defects liability period, caused by a malfunction of equipment or workmanship or as a result of direct vandalism, the Contract Administrator will issue to the Contractor a “NOTICE OF DEFECT”. Where the defect relates to the failure of the system to an individual dwelling the Contractor shall attend site and rectify the defect within 48 hours of receiving such a notice. However, where the defect relates to a complete block failure the installation Contractor shall attend within 3 hours of notification.

Failure to attend site within the aforementioned time periods will result in Brighton & Hove City Council instructing their own engineer to attend site and thereafter recover any costs related thereto in full from the Contractor. A copy of the Contractors report will be handed to the Contract Administrator when the works are complete.

Should, in the opinion of the Contract Administrator, the Contractors response to defects be found to be unsatisfactory, the Contract Administrator will issue a final notice. On the Contractors failure to comply with the final notice, the Contract Administrator will arrange for the works to be carried out by others and any cost incurred by the Council will be fully recovered from the Contractor.

The installer shall attend to all defects on site first. If deemed a manufacturers defect then installer shall instruct Entrotec to attend detailing the manufacturers defect and if a dwelling fault contact detail of the resident so that an appointment can be made.

Door Entry and Access Control Mains Power Supply Allow for providing a power supply to each service cupboard or position of the door entry

main equipment power supply control box. Wiring to be in orange Pyroshield cable affixed to rear elevations run from the nearest power source from the landlords meter.

The Contractor shall allow for an electrical spur, 3 amp MK type key switch spur to be provided outside the door entry control cabinet. The contractor shall ensure that the manufacture provides a 3 amp MCB with in the door entry equipment cabinet. Allow for moving and repositioning any external porch lamps that will fowl or inhibit the opening of the front or rear entrance doors to the CA approval.

Allow for providing bulkhead lamps within each service cupboard, where door entry

equipment is fitted where non exist at present. 5.0 VIDEO DOOR ENTRY SYSTEM – Secure By Design/New Build Only

General Where the particular specification requests or on a new build block where Secure by Design (SBD) is required the system shall be a colour video system. The main specification shall be followed in full with the addition with the following, replacing the audio Handset with a LCD TFT colour Video handset and supplying a fitting Security dome camera looking down at the whole door area. The contractor shall allow for all video switching and amplification circuits. All new builds shall be supplied with an Entrotec and KMS system.

Page 45: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/38

Video door entry system Where specified the door entry system shall be a colour video door entry system

• A Camera shall not be fitted with in the call panel. A vandal resistant Dome Colour Camera suitable for wall or ceiling mounting shall be fitted to look down at the door and call panel in line with SBD requirements. The Camera shall be purchased via Entrotec and shall be fitted with a 4.0 - 9.0 mm vari-focal lens. The lens shall be adjusted to view the whole door and call panel area.

• Where outer and Inner call panel doors exist to create a secure lobby the system shall have the call panel and dome camera at both positions Outer and inner doors with suitable CCTV switching between doors and cameras.

• The audio handset shall be replaced in all dwellings with an colour 4” LCD TFT colour video handset.

• Each handset shall be wired individually with a separate 6 pair CW1308 (min) up to 50 meters. A 10 pair CW1308 cable shall be used where cable run are up to 100 meters. Coax to handsets not required. Coax to camera and video amp etc RG59B.

• The system shall have fitted with in each marshalling box video distribution amplifiers. • Each video distribution amp shall have an individual RG59B coax wired from the main video

distribution amp.

• When commissioning the system the commissioning engineer shall set up each monitor. • When multiply call panels are fitted a camera switcher shall switch the relevant picture from

the called door to the handset called.

• All handsets shall be modular in design so as that a screen can replace without having to replace the whole handset.

• The contractor shall ensure that that there are sufficient lighting levels at the door and camera position to allow the colour camera to work to the best ability.

• The camera lens shall be selected so as the residents with in the dwelling shall be able to clearly identify the callers face.

Contractor to supply all necessary BNC connectors. Connectors not supplied by Entrotec commissioning engineers.

• BGU required, ressetable type with plastic hinge cover. Positioned away from the PTE NOT NEXT TO IT

Camera The Dome camera shall be supplied by Entrotec and connected to the video door entry system;- • 12 volt DC version

• High resolution • 450 TV lines • For wall or ceiling mounting as required per block • Colour • Auto Iris to automatically adjust to different light levels • PAL composite video output • 1 Lux sensitivity • Vari-focal 4.0 - 9.0 mm Len’s to suit the picture required dependent on how far away from the

door the camera is positioned. • The camera should be able to monitor the whole of the door and NOT located direct above the

call panel looking directly down.

6.0 EARTHING AND BONDING

The earthing system within the building shall be a ‘protective multiple earthing’ system (PME) in accordance with the requirements of BS 7671 2008 and amendments, BS 7430 and the requirements of the local Regional Electricity Company (REC).

Page 46: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/39

All final circuits installed as part of the Electrical Services Installation shall incorporate a separate earth conductor. Supplementary bonding positions shall be bonded in accordance with BS7671 2008 and the Contractor shall provide a spiral green/yellow supplementary earth cable bond to the items indicated via earthing clamp in accordance with BS 951. The positions indicated are not exhaustive and the Electrical Contractor shall include to provided equipotential and supplementary bonding to the full extent required within BS 7671 2008 and BS 7430.

7.0 TESTING AND COMMISSIONING OF ELECTRICAL INSTALLATION

General This section covers the test and commissioning of all electrical works carried out with in the contract. This does not include or cover the testing and commissioning of the door entry system equipment by the specialist installer or door entry manufacturer. The testing and commissioning of the door entry equipment is covered earlier with in this document. The electrical works shall be inspected and tested both during and after installation. When the installation is completed and before energised it shall be inspected and tested in accordance with the requirements of BS 7671 2008 and as detailed in this part of the specification. Testing shall be carried out in the presence of the Engineer or his appointed representative, who shall be given at least 7 days notice before the tests are to be carried out. It shall be noted that electronic components may sustain serious damage as a result of certain electrical installation test procedures. Conductors and other circuitry shall be tested prior to them being connected to electronic components. Electronic equipment shall be tested in accordance with the manufacturer’s instructions. The presence of electronic components shall be noted clearly on the circuit cards and in operation and maintenance manuals with an indication that testing procedures may result in damage. Test Instruments The Electrical Contractor, for the purpose of testing the works, shall provide all labour and test instruments. Competent persons, trained in the use of the instruments, shall operate the instruments. If, in the Engineers opinion, a particular instrument is not suitable then an acceptable alternative shall be provided. Calibration certificates related to the instruments being used shall be made available for inspection by the Engineer. Visual Inspection A visual inspection of the installation shall be carried out as required by BS 7671 2008 and shall include, but should not be restricted to, the items listed on the Completion Schedule. Test results The following items, where relevant, shall be tested in the sequence indicated and the results tabulated on test schedules, as described in BS7671, copies of which shall be included in the O & M manuals. 1. Continuity of final ring circuit conductors.

Page 47: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/40

2. Continuity of protective conductors, including main and supplementary equipotential bonding.

3. Earth electrode resistance. 4. Insulation resistance. 5. Insulation of site built assemblies. 6. Protection by electrical separation. 7. Protection by barriers or enclosures provided during erection. 8. Insulation of non-conducting floors and walls. 9. Polarity. 10. Earth fault loop impedance. Operation of residual current operated devices. In the event of any test indicating failure to comply, that test and those preceding it, the results of which may have been influenced by the fault indicated, shall be repeated after the fault has been rectified. Certification Following satisfactory completion of the inspection and testing A NICEIC Completion and Inspection certificates shall be issued to the Brighton & Hove City Council or its representative/agent. The NICEIC inspection certificate shall be completed using the results tabulated on the test schedules and the test and completion schedules shall be provided as an appendix to the inspection certificate. A practical completion certificate shall not be issued until both the NICEIC Completion and Inspection certificates are issued together with the completed schedules. The original copies of the certificates and schedules shall be included in the Operation and Maintenance Manuals and two further copies issued to the Brighton & Hove City Council or its representative/agent within 14 days of the tests being carried out. Electrical Installation Commissioning Prior to commissioning, the Electrical Contractor shall satisfy himself that the installation is in a safe and satisfactory condition, that all statutory notices are displayed, and that all necessary arrangements have been made for the installation to be safely commissioned. The commissioning shall comprise the energising of the electrical installation, setting into motion any motor or machinery and verifying the operation of controls, safety devices, alarms and lighting levels in relation to the design requirements. Equipment employing batteries such as emergency lighting, fire alarms, etc. shall be subjected to full performance tests including operation for the prescribed time period with battery re-charge accomplished in the specified time. Equipment fitted with batteries shall be protected to ensure that the battery, battery charger or any other component does not sustain damage during discharge or recharge of the batteries when operating unattended. Records of measurements and settings both as offered for acceptance and finally commissioned, shall be issued to Brighton & Hove City Council or its representative/agent and included in the Operating and Maintenance Manuals.

Page 48: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/41

Adequate time for testing and commissioning shall be properly integrated into the main contractors overall programme of site activities. All commissioning and any necessary demonstrations shall be completed before the installation is accepted for use unless agreed otherwise with the Engineer.

8.0 LABELLING AND IDENTIFICATION

All equipment, materials, components and installation of electrical services shall have signs/labels displayed in accordance with BS5378 Parts 1,2 and 3 and the relevant sections of BS7671 - 2008. The following principle colour co-ordination of signs/labels shall apply: Warning - Yellow background with black lettering Mandatory - Blue background with white lettering General Information - White background with black lettering Emergency - Green background with black lettering Prohibition - White background with red lettering Fire Fighting - Red background with white lettering (except extinguishers which have particular colours) Equipment/Service - Orange bands of tape or where required orange colour routed in common locations with others. All items of equipment or enclosures within which voltages exceeds 250 volts or separate enclosures or items of equipment that allow simultaneous human contact with live parts exceeding 250 volts shall be so arranged that before access may be gained a warning of the maximum voltage present shall be clearly visible i.e. “DANGER 400 VOLTS”. Each switchboard shall have the primary warning triangle sign denoting ‘Caution, risk of electric shock’. Where an isolator leaves any part of equipment or enclosure ‘live’ when in the off position a warning notice shall be used indicating that the equipment is not totally isolated and giving instructions for achieving further isolation. A safety sign shall be fixed to every enclosure associated with a high voltage discharge lamp installation, e.g. inductors, resistors, capacitors and transformers. In addition a supplementary sign shall be located below the warning sign which shall be 10mm x 50mm yellow background with 5mm black lettering stating DANGER plus the highest open circuit voltage to earth (i.e. 5000 volts AC). All LV main switch-rooms shall have a warning sign together with warning notices on all doorways into the switch-room.

Page 49: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/42

The warning sign shall be the yellow triangle with black edging and the electrical symbol within the triangle. The warning notices shall be a yellow background with black lettering stating “NOTICE - AUTHORISED PERSONS ONLY” with “KEEP LOCKED AT ALL TIMES” with a minimum letter size of 25mm high. All electrical equipment shall be labelled to ensure correct identification and give essential operating functions, which relate to each other. All these labels shall conform to a white background with black lettering. Individual switch fuse, MCCB, isolator shall state: The circuit which it controls with a general description of Type of load Rating Phase Outgoing cable size in mm2 and cable type All distribution boards shall have external labels which state: Voltage Maximum Rating of Protective devices uses Type of load connected All distribution boards shall have internal labels which state: Main cable in size in mm2 Phase colour indicator Circuit number* Description of circuit* Circuit protection device rating* Actual circuit current* Circuit cable*. *This applies to all sub-circuits and these labels/circuit charts shall be complete in clear printing in black ink on a white background. The individual phase shall be identified with its colour of Brown, Black & Grey in accordance with BS 7671 2008 Amendment 2. Where a distribution arrangement incorporates contactors, time switches, relay indicator lights and push buttons each of these shall be labelled and indicate its function i.e. “LIGHTING”, “OVERRIDE SWITCH”, “TIMESWITCH FOR EXTERNAL LIGHTING”. These labels shall conform to a white background with black lettering. Local switchgear/isolators and controls gear shall have individual labels, which shall be black lettering on a white background. These labels shall indicate: Equipment title Current Rating, Phase, Voltage Circuit Reference

Page 50: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/43

The ON/OFF functions shall be clearly indicated using an appropriate label where the operating positions are not clearly indicated on the equipment itself. All junction boxes which form a marshalling point and junction point for fire alarm system, security systems and communication systems shall have a label with black lettering and white background. These labels shall indicate the Wiring System enclosed, voltage and circuit references. Other information/identification labels shall include: Particular identification of switch/fused spur outlets. Particular identification of junction boxes. Particular identification of blanked off outlets for future use. Particular identification of communication systems, special circuits. All these shall be individually labelled in black lettering on a white background. Where an item of equipment and or switchgear is designated for emergency operation the labelling shall be white lettering on a green background. The labelling shall clearly indicate the item of equipment/function it performs together with the emergency action required or to be undertaken. Where an item of equipment and/or switchgear is designated for prohibited use i.e.: “Danger switch off when not in use” “Do not switch off” “Emergency stop” This labelling shall be red lettering on a white background. Where a particular item of equipment and/or switchgear is designated for fire fighting use i.e. “a fire alarm switch on a main switchgear panel” then this shall be clearly and differently indicated with a label which shall have white lettering on a red background. The material used for the labelling shall be a composite plastic component with three layers of rigid plastic (040” ABS) materials. The letter colour being the centre element of the composite and when engraved the composite shall then expose the colour. The method shall be as commonly referred to as “TRAFFOLYTE”. All lettering shall be in capitals and generally the height of lettering that shall be used as follows: 6mm for identification labels 12mm for warning notices 12mm for principle working of an emergency sign 6mm for the secondary wording of an emergency sign The fixing used for all labels shall be either bolted with gripping washer or riveted with space washers behind each rivet. Two fixings shall be provided for labels with a height up to 25mm and where labels have a greater height than this four fixings one in each corner of the label shall be provided.

Page 51: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Standard DES Jan 2014

2/44

9.0 BUILDING TRAINING

Upon completion of the Electrical Services Installation the Contractor shall be required to provide a demonstration of the various electrical services systems to the client’s representative. This element of training works shall be carried out under the supervision of the Building Services Consultant. The training shall take place over a period of one half day and the Contractors Tender Bid shall incorporate all attendance cost as necessary.

10.0 RECORD DOCUMENTATION As part of the works the Electrical Contractor shall provide record drawings and maintenance manuals for the complete installation and plant as detailed at the beginning section of this part of the electrical specification. The production of Maintenance Manuals and Record Drawings are an essential part of the works, which shall not be considered complete, until approved copies of manuals and drawings have been received. In the event of Practical Completion being accepted before the production of the Maintenance Manuals and Record Drawings, monies will be retained from the Contract payments, to cover the cost of preparing such drawings and manuals by others. The amount retained may be released in stages to the Electrical Contractor as evidence of production of the necessary drawings and manuals is offered and approved. In the event of the Electrical Contractor failing to produce any evidence of the production of the drawings and manuals within one week of handover of the works or any section of the works, they may be instructed to carry out these works, the costs of which will be charged to the Electrical Contractor.

Page 52: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Schedule of Works DOOR ENTRY SYSTEM

Standard DES Jan 2014

SECTION 3

SCHEDULE OF WORKS

SEE ALSO PRICING SCHEDULE: PF1 (Main ITT Documents) & Schedule 5 for individual site Annexes)

Page 53: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Schedule of Works DOOR ENTRY SYSTEM

Standard DES Jan 2014

3/1

THE FOLLOWING SCHEDULE OF WORKS RELATE TO THE REMOVAL AND DISPOSAL OF THE EXISTING DOOR ENTRY SYSTEM INCLUDING ITS COMPONENTS, WIRING AND CONTAINMENT THROUGHOUT. THEREAFTER SUPPLY AND INSTALL NEW DOOR ENTRY SYSTEM, COMPLETE WITH NEW WIRING AND CONTAINMENT THROUGHOUT AS SPECIFIED. THE CONTRACTORS ATTENTION IS DRAWN TO THE MATERIALS AND WORKMANSHIP CLAUSES WITHIN SECTION TWO AND THE CONTRACT DRAWINGS WHERE APPLICABLE. THE CONTRACTOR IS TO INCLUDE FOR ALL WORKS NECESSARY WHETHER SPECIFIED OR NOT TO ENABLE THE EXECUTION OF ALL ITEMS SCHEDULED. NO CLAIM WILL BE ENTERTAINED FOR ENABLING WORKS REQUIRED DUE TO LACK OF KNOWLEDGE OF THE SITE AND ANY RESTRICTIONS THAT MAY BE PRESENT AND/OR REASONABLY FORETOLD. THE CONTRACTOR IS REQUIRED TO PRICE ALL ITEMS INDIVIDUALLY. ANY ITEM NOT PRICED WILL BE DEEMED TO BE INCLUDED ELSEWHERE.

WHERE CONDUIT OR TRUNKING IS TO BE FIXED TO ASBESTOS CONTAINING

MATERIAL THIS FIXING IS TO BE UNDERTAKEN BY AN APPROVED ASBESTOS CONTRACTOR UNDER CONTROLLED CONDITIONS. PERIODIC AIR TESTS ARE TO BE UNDERTAKEN AND FINDINGS REPORTED TO THE CONTRACT ADMINISTRATOR.

3.01 Strip out in its entirety the existing door entry system including all Trunking / Cable Tray / Cabling / Conduit to individual flats, circulation areas and risers. Remove from site and dispose in accordance with Brighton & Hove City Council’s requirements.

3.02 The new door entry system is to be installed complete with new wiring, containments & riser

trunking, as specified in Section Two of this document, all floors to be diamond drilled as necessary as specified.

3.03 not applicable 3.04 Provision of O & M manuals and as installed drawings – Refer to the following items for

details of required content; Page 2/7 Maintenance Manuals & Record Drawings Page 2/10 Documentation Page 2/51 Records Documentation

The O&M Manual must include all Entrotec commissioning test result and comment sheets as attached in Appendix K, Entrotec Clerk of Works installation check list as attached in Appendix M all duly completed by the installation and commissioning engineers. The O&M Manual is also to include copies of the commissioning sheets for each individual flat as attached in Appendix N, Appendix Q ENTROTEC - KMS GPRS Cloud Fob Programming and Door Name Assignment

and the completed Engraving Specifications Sheet.

Page 54: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Schedule of Works DOOR ENTRY SYSTEM

Standard DES Jan 2014

3/2

This documentation must be submitted within one week of issue of Certificate of Practical Completion by Contract Administrator.

Appendices I & J N & P have been removed from this document as they no longer apply.

Page 55: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Appendix K DOOR ENTRY SYSTEM

Standard DES Jan 2014

APPENDIX K ENTROTEC SYSTEMS COMMISSIONING TEST RESULT AND COMMENT SHEET

Page 56: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Appendix K DOOR ENTRY SYSTEM

Standard DES Jan 2014

COMMISSIONING TEST RESULT AND COMMENT SHEET

The commissioning engineers while commissioning the door entry system shall use the following sheet. These sheets shall be issued to the CA together with the manufactures commissioning certificates when the installation has been completed.

Site Address:

Date:

Engineers Signature

Sheet No. of

Full Call Panel Test

Call panel & FS

Earthed

Equipment cabinet

Earthed

Fireman Switch

tested

Push to exit

operation

Proximity access

controller Test

Proximity access

control token test

Trades operation

Visual display

tested

Camera set up

Trades times set to Mon – Fri: -

Sat : - Sun : -

Flat No.

Handset Full

Function Test in

Marshalling

Call Tone

Privacy Function

Speech Test

Door Monitoring

Lock Release

Monitor Picture

adjusted and

tested

Access Gained

No access gain

Handset Ringing

Comments

Page 57: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Appendix L DOOR ENTRY SYSTEM

Standard DES Jan 2014

APPENDIX L

ENTROTEC - PAC/KMS KEY MANAGEMENT RESIDENTS ISSUING LIST

The following sheet shall be used by the Door Entry commissioning engineers while commissioning the door entry system and programming a PAC/KMS access control system. These sheets are to show the fob issue to the residence/client and shall be issued to the CA together with the residents fobs bagged and labelled with manufactures commissioning certificates when the installation has been completed.

Site Address ENTROTEC LIMITED

KMS KEY FOB ISSUE LIST Page of Date

Date

Issued No Fob

Flat No. Name Signature Type of I.D. Shown

Page 58: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Appendix M DOOR ENTRY SYSTEM

Standard DES Jan 2014

APPENDIX M PRE CONTRACT & ENTROTEC CLERK OF WORKS PRE INSTALLATION CHECK LIST

ITEM YES NO

1. Entrotec Equipment Fitted

2. Systems commissioned by Entrotec or Current Entrotec approved installer. Engineer carrying out commissioning has Entrotec training certificate. Test & Commissioning sheets completed and issued to CA. Engineer’s certificate of carried out commissioning has been seen and verified.

3. Equipment has DDA features, Yellow rings, Audio and visual indications.

4. Battery back up door entry equipment.

5. Battery backup KMS equipment.

6. Sarel IP 66 enclosures installed and fitted with lock LK1242E on all cabinets including marshalling and KMS controllers

7. Sarel cabinet fitted with factory fitted hasp and Staple and fitted with free issued B&HCC KA1 IPAN padlocks

8. Cabinets not fitted in exposed valuable area such as corridor without approval of CA. (if fitted with approval enclosure fitted with hasp & staple and Brighton & Hove padlock. KA1 IFAN Lock.

9. Cabinets cabled accordingly with screw fixed Traffolite Label’s for “Door Entry System” & “Fob Equipment” and mains voltage warning stickers.

10. Power supply output set and adjusted to 13.8 volts when battery fitted.

11. Digital Automatic summer/wintertime correction time clock set to CA’s Approval.

12. ED4+ Handset fitted & Privacy switch individually timed and set to 8 hour time period.

13. Block name engraved on entrance panels in Title Case or on LCD Display.

14. Green LED on all handsets to indicate door open working.

15. Audio and visual reassurance heard when door released on MED and RED’s.

16. Lock release timer adjusted to suitable time.

17. Adjustable call tone time period set to CA requirements (Adjustable per Handset).

18. Timed re-assurance tone on door panel adjusted to suitable sound level to suit. area

19. Adjustable speech time set to CA requirements.

20. Handset cables installed in 6 Pair CW1308.

Page 59: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Appendix M DOOR ENTRY SYSTEM

Standard DES Jan 2014

21. System cabled in CW1308 with 3 core flex to call panel.

22. 20% spare pairs allowed for in all cabling

23. Handset cover min. 2 screw fixings (top and bottom)

24. Handset operating instructions left with occupier

25. Cables marked clearly identifying destination and usage using cable markers. Hand written markings on cables is not acceptable.

26. Fireman’s double pole override switch installed at every main entrance controlled door and any other doors deemed necessary where fire brigade access would be required.

27. Push to Exit Double pole Switch installed at every controlled door using magnetic locks. Switch with 2 commons wired to break power and also provide timed release.

28. Push to exit switch fitted with 25mm button with DDA yellow ring. Engraved “Push to Exit” in Green. Engraved “In emergency press and hold button while opening door”

29. Fire switch and Push to exit Double pole type with 2 commons wired to break positive supply to magnetic locks or fail safe lock release and also connected to provide a timed release.

30. MED/RED Magnalocks powered by door entry controller.

31. System and top magnetic lock or Monitoring devise connected to handset monitoring system.

32. Door monitoring circuits tested and demonstrated.

33. Door panels, Fireman Switch, Push to Exit, System controllers etc all Earthed and bonded to common 0v Earth to IEE Regulations

34. Security screws fitted on all containment, stop end boxes and equipment in common areas

35. KMS controller is 10,000 controller and not 1000 controller.

36. KMS controller supplied pre-programmed with fobs.

37. Fobs programmed and working and programmed to BHCCKey Fob access Strategy. Strategy sheeted issued to CA.

38. Fobs issue to CA with Appendix L. Programming issue sheet.

39. Pre-programmed KMS Fobs supplied bagged and labelled with flat number to correct B&HCC colour code. Grey 1st issued Token. Yellow 2nd issued Token. Green 3rd issued Token.

40. Common access Master fob for Mears staff - Solid Red. Common access master for B&HCC Staff – Blue.

41. GPRS SIM card free issue by B&HCC CA fitted by installer.

Page 60: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

Appendix M DOOR ENTRY SYSTEM

Standard DES Jan 2014

42. GPRS modem installed SIM CARD Communicating with remote PC Established and systems networked.

43. Data number of SIM issued to KMS

44. Door closing correctly (LCN closer adjusted for correct speed and alignment)

45. 2 No. Securitron Magnetic Locks fitted. Top fitted magnetic locks Monitored.

46. Magnetic lock armature plates secured with security allen key screw with centre pin.

47. ASSA Lock release Monitored. If used for MED secondary VR door contact fitted to head of door.

48. System Manuals, drawings and engineers log sheet fitted in cabinet pocket.

49. Maintenance contact telephone numbers left with CA.

50. System demonstrated as working to CA.

51. Appendix K Commissioning test results sheets and residents tick sheets issued to CA.

52. All Containment entry points filed and free from any sharp edges

53. 25% spare spacing factor allowed for all containment

Page 61: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

DOOR ENTRY SYSTEM

Standard DES Jan 2014

Page 62: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

DOOR ENTRY SYSTEM

Standard DES Jan 2014

APPENDIX Q ENTROTEC - KMS GPRS Cloud Fob Programming and Door Name Assignment The following sheet shall be used by the Door Entry installer when ordering the door entry system and KMS proximity system. These sheets are to be approved by the client and show the fob access required per resident key fob to associated doors and the name of the door as shown on the KMS Cloud software. The sheet shall be issued to the client for approval.

Site Address ENTROTEC LIMITED - KMS KEY ISSUE LIST Page of

Date

KMS Controller 1

Door Name/description/location to be entered on Cloud

Flat Number range to be given access

Channel 1

Channel 2

KMS Controller 2

Door Name/description/location to be entered on Cloud

Flat Number range to be given access

Channel 1

Channel 2

KMS Controller 3

Door Name/description/location to be entered on Cloud

Flat Number range to be given access

Channel 1

Channel 2

KMS Controller 4

Door Name/description/location to be entered on Cloud

Flat Number range to be given access

Channel 1

Channel 2

KMS Controller 5

Door Name/description/location to be entered on Cloud

Flat Number range to be given access

Channel 1

Channel 2

KMS Controller 6

Door Name/description/location to be entered on Cloud

Flat Number range to be given access

Channel 1

Channel 2

Approval Name Signature Date

Page 63: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

DOOR ENTRY SYSTEM

Standard DES Jan 2014

Page 64: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

DOOR ENTRY SYSTEM

Standard DES Jan 2014

Page 65: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

DOOR ENTRY SYSTEM

Standard DES Jan 2014

Page 66: SPECIFICATION OF WORKS FOR INSTALLATION OF NEW DOOR …

DOOR ENTRY SYSTEM

Standard DES Jan 2014