specification for construction of manholes,

Upload: wan-mahiram

Post on 02-Apr-2018

232 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 Specification for Construction of Manholes,

    1/23

    T-2

    Specification for Construction of manholes, Joint Box and Laying of Ducts

    ____________________________________________________________________________________________

    SPECIFICATION FOR CONSTRUCTION OF MANHOLES,

    JOINT BOXES AND LAYING OF DUCTS

    1.0 GENERAL

    This section of the Specification describes and specifies requirements

    for the supply, delivery, installation, testing, commissioning,

    handing over in approved working order and maintenance during the

    Defects Liability Period of the manholes, joint boxes and ducts all in

    accordance with the Specification, Supplementary Notes, Bill of

    Quantities, Conditions of Contract, Drawings etc.

    2.0 STANDARDS AND APPROVAL

    The installation works shall comply with the latest relevant British

    Standard Specification and Syarikat Telekom Malaysia Berhad (STM)

    specification and requirements. All material used shall be of thetypes approved by STM and acceptance by the S.O.s Representative.

    Samples of materials shall be submitted to the S.O.s Representative

    for approval prior to installation. Sample of the materials which have

    been approved by the S.O.s Representative for use in the Works shall

    be displayed at the site office for reference.

    3.0 WORK PROGRAMME

    The Contractor shall submit to the S.O.s Representative detail work

    programme for approval within two weeks after acceptance of tender of

    such shorter period as required by the S.O.s Representative. If the

    work programme submitted is not acceptance by the S.O.s

    Representative, the Contractor shall amend and resubmit the programme

    for final approval.

    4.0 SITE DIARY

    The Contractor shall keep at the work site a site diary, to which the

    S.O.s Representative shall have access at all times during working

    hours. The Contractor shall keep the site diary posted up to date,

    entering therein all measurements on the day on which they are taken

    and details of any deviations or extra work. Records of works shall be

    submitted daily to the S.O.s Representative for verification. All

    entries in the said shall be considered to be, and shall remain, theproperty of the S.O.s Representative.

  • 7/27/2019 Specification for Construction of Manholes,

    2/23

    T-2

    Specification for Construction of manholes, Joint Box and Laying of Ducts

    ____________________________________________________________________________________________

    5.0 SAFETY

    Adequate approved traffic warning signs and lamps shall be provided

    and displayed by the Contractor at all time. The form, placing and

    light of the warning signs must comply with all local and national

    regulations and safety codes for road works. The Contractor shall take

    all necessary precautions and follow the correct procedures to avoid

    accidents due to presence of explosive gases, asphyxiating gases and

    toxic gases in the underground network. The Contractor shall take all

    necessary measures to ensure the safety of the workmen, members of the

    public, plant or property, especially when carrying out any works in

    manholes or joint boxes.

    6.0 QUALITY OF MATERIALS

    6.1 CONCRETE

    Concrete shall be of quality A,B,C,F or G as provided by this

    Specification and the proportions of the ingredients shall be as

    follows :-

    Concrete

    Mixture

    Parts by Measure

    Cement Sand Aggregate

    Usage

    Quality A

    Quality B

    Quality C

    Quality F

    Quality G

    Cement

    Mortar

    1 2 4

    1 2 7

    1 3 9

    1 2 3

    1 1 3

    1 4 3

    1 3 -

    All Jointing

    Chamber, Plinth.

    Placed between

    two sets of plant

    if separation

    clearance is

    152mm or less.

    For supporting

    protecting or

    filling in

    purpose.

    Concrete Troughs.

    Filling in

    Manholes covers

    3E & 7E.

    Encasement of

    Ducts.

    Dummy ducts in

    jointing chamber,

    repairing damaged

    or split ducts.

    The concrete used for encasing ducts shall be relatively dry and

    having the consistency of wet sand. In no circumstances shall the

    water content be increased appreciably as this will result in a weak

    concrete. The cement used for encasing ducts shall be rapid-hardening

    type.

  • 7/27/2019 Specification for Construction of Manholes,

    3/23

    T-2

    Specification for Construction of manholes, Joint Box and Laying of Ducts

    ____________________________________________________________________________________________

    Concrete mixing shall be done manually or by machine. Ready mixed

    shall be the first preference if available. In the process of mixing

    the concrete, the ingredients shall be repeatedly turned over and

    mixed in a dry state on mixing boards, after which water from the nose

    of a watering can shall be added and the materials shall than again be

    turned over sufficiently to ensure thorough mixing. The mixing boards

    shall be sufficiently large to give ample room for turning over the

    ingredients entirely from one place to another and shall be so

    arranged or constructed that liquid cement shall not escape through

    the joints. When mixed by machine the water shall be poured in first

    and the ingredients shall be put into the machine dry without prior

    mixing.

    The standard of cleanliness of water for mixing is that it shall be

    fit for drinking. The quantity used shall be sufficient to effect the

    proper hydration of cement to obtain a plastic mixture. The S.O.s

    Representative may reject concrete which is, in his opinion, so over

    watered that it would be deficient in ultimate strength.

    The concrete shall be deposited carefully in its intended position as

    quickly as possible after being mixed and all concrete footings and

    foundations shall be tamped and carefully leveled. All concrete shall

    be compacted by the used of a poker type vibrator until a dense solid

    mass without voids is obtained. Under no circumstances must the

    vibrator be used longer than is necessary to obtain compaction nor

    left unattended in the concrete, otherwise segregation of the mixture

    will occur.

    Concrete which has become hard, dry, dirty or not placed within 30

    minutes after being mixed shall not be used, and of any earth fall on

    top of any concrete after laying and before the work is completed, it

    shall be carefully removed.

    6.2 CEMENT

    All cement used shall comply with the relevant British Standard

    Specification. The cement shall be fresh, fine, smooth, loose and warm

    and the S.O.s Representative reserves the right to reject the cement

    which is found unsatisfactory. The Contractor may employ generally

    rapid hardening Portland cement or high alumina cement in lieu of

    ordinary Portland cement for his convenience and acceleration of

    progress. Before high alumina cement is used, all tools and plants

    shall be cleaned. High alumina cement shall not be used with P.V.C.

    ducts. The Contractor shall ensure that all cement is protected

    adequately against moisture while being transported and stored. Theused of cement aids where an additive is added to ordinary Portland

    cement to render it rapid hardening is not recommended and permission

    for its use shall first be obtained from the S.O.s Representative who

    shall also determine the amount of additive to be used.

  • 7/27/2019 Specification for Construction of Manholes,

    4/23

    T-2

    Specification for Construction of manholes, Joint Box and Laying of Ducts

    ____________________________________________________________________________________________

    6.3 SAND

    All sand to be used shall be river sand. It shall be clean, sharp,

    gritty and free from loam or other impurities. If the sand is found to

    contain more than 5 percent by volume of silt, the sand shall not be

    used. The sand used shall be course and the grains graded in size to 5

    mm.

    6.4 AGGREGATE

    The aggregate for concrete shall be cleaned screened river ballast,

    gravel, stone or other materials as approved by the S.O.s

    Representative. The aggregate shall be of the nature of cubes, not of

    flakes and graded in size and free from dirt, floury stoned duct,

    loam, earth or any other impurities. Clinkers, brick sandstone or

    other porous stone shall not be used.

    The maximum size of aggregate for each of the qualities of mixtureincluded in Section 6.1 shall be as follows :-

    A ..20mm, B40mm, C..any size suitable for work, F&G 10mm, for

    encasement of ducts .6mm. Any portion which will pass a 5mm mesh

    shall be used as sand.

    6.5 BRICKS

    The bricks used shall be best quality hard burned common bricks,

    either wire cut or plastic pressed, or selected hard hand-made, stock

    bricks or other hard or over-burned hand-made bricks of comparable

    quality. They shall be of good shape, free from visible particles or

    lime and from serious cracks, and shall not absorb more than 12

    percent of their weight when immersed in water for 24 hours. Five

    bricks from each batch delivered at site shall be tested and all shall

    be required to pass the test. The dimensions of bricks described as

    type 2 and 3 in B.S. 657 shall be regarded as standard.

    6.6 CEMENT MORTAR

    The cement mortar shall consist of one measure of cement and three

    measure of sand. The materials after being gauged shall be thoroughly

    mixed in a dry state and then thoroughly mixed with sufficient water

    to form a stiff mortar. Water, cement and sand shall not be added

    after mortar has one been mixed and set. If mortar has once begun toset and excess water has been used for mixing, further quantity of

    sand and cement not be added but the whole mortar shall be rejected.

  • 7/27/2019 Specification for Construction of Manholes,

    5/23

    T-2

    Specification for Construction of manholes, Joint Box and Laying of Ducts

    ____________________________________________________________________________________________

    6.7 STEEL, IRONWORK AND HARDCORE

    All structural steel shall be in accordance with British Standard

    Specification. All invoices for steel shall be inspected by the S.O.s

    Representative.

    If the Contractor cannot procure such reinforcing steel in the

    Imperial sizes as described in the Drawings but can obtain such steel

    in the Metric sizes and the dimensions approximating to those in the

    following table, then the Contractor shall forthwith obtain the

    approval of S.O.s Representative before such steel are ordered.

    Imperial size (ins) 5/16 3/8 5/7 7/8

    Metric size (mm) 6 8 10 12 16 20 22

    Imperial size (ins) 1 11/8 1.25 1.5

    Metric size (mm) 25 28 32 40

    Bolts, nuts, rivets and other accessories shall be in accordance withthe relevant British Standard Specification. All invoices for iron

    shall be inspected by the S.O.s Representative. All hardcore shall

    consist of hard brick, concrete or stone graded down to a minimum of

    80mm. Sufficient hardcore material under the sizes of 80mm shall be

    added up to fill voids and aid consolidation.

    7.0 EXCAVATION

    The Contractor shall carefully segregate the surface and foundation

    material from the lower sub-soil. Sub-soil shall be protected whilst

    above ground from weathering action which could cause a damaging

    increase in the natural moisture content of soil leading to the

    formation of voids and/or settlement after back-filling. Sub-soil

    which is damages shall be removed and replaced by undamaged sub-soil.

    Except where otherwise provided, the excavation shall include all

    necessary/timbering and shoring.

    Mechanical excavator shall be used in a manner as to fulfill the

    requirements of excavation work. A timber base support or platform

    shall be placed under the fees of the excavation machine as a

    protection to prevent the carriageway surface being marked when the

    machine is in operation.

    Pneumatic drills or other power driver appliance shall be fitted with

    efficient silencing devices and the compressor machine shall be

    maintenance in an efficient condition so as to avoid undue noise.

    The Contractor shall obtain prior approval of the S.O.s

    Representative to dig pilot holes and excavation of trenches. Pilot

    holes shall be dug at positions selected by the S.O.s Representative,

    normally one per sectional length to ascertain the most suitable

    position for the work.

    Timber support for excavation shall be so designed and placed as to

    permit wherever possible withdrawal of such timber and consolidation

    of the space it occupied.

  • 7/27/2019 Specification for Construction of Manholes,

    6/23

    T-2

    Specification for Construction of manholes, Joint Box and Laying of Ducts

    ____________________________________________________________________________________________The routes of the trench shall be marked out and approved by the

    S.O.s Representative before excavation. The width of trench excavated

    shall not be greater than is necessary for satisfactory execution of

    the work. The routes of the excavated trench shall be as straight as

    possible and any bends or curves shall be of the maximum radius

    possible. Where ducts are to be encased in concrete the width of

    trench shall be dependent upon the number of ducts to be laid in a

    horizontal direction. In unstable ground, timbering shall be used to

    support the trench and to act as a former for the concrete.

    The depth of trenches shall comply with the specification and as

    directed by the S.O.s Representative. The floor of the trench shall

    be leveled and shall not follow surface irregularities. The bottom of

    the trench shall be normally leveled with 50mm of sand and rammed.

    In passing from footway to carriageway and vice versa or where ducts

    enter jointing chambers below standard depth or in any other

    circumstances where it is necessary to change level, the bottom of the

    trench shall rise or fall gradually as directed by the S.O.s

    Representative.

    The Contractor shall dispose of the water in the trench so as to

    prevent any risk of the ducts, cables and other materials to be laid

    in it being detrimentally affected. He shall provide all pumps and

    appliances required and shall carry out the necessary pumping and

    bailing.

    8.0 DUCTS LAYING

    8.1 GENERAL PROCEDURES

    The routes of ducts shall be kept as possible. In the case of 4-ways

    ducts or more, the lines shall break joint by approximately half the

    duct length in alternative lines, horizontally and vertically.

    Unless otherwise permitted by the S.O.s Representative, no ducts

    shall be laid and covered up in the absence of the S.O.s

    Representative.

    All ducts laid direct in the ground shall be kept well clear of water

    mains, service pipes, sewers, subways, manholes, joint boxes etc.

    belonging to others. In order to permit the use of tapping machine

    on water mains, a minimum clearance of 152mm shall be given wherever

    possible. This clearance shall also be given, if practicable, to the

    other service mentioned above. In no case shall the clearance be less

    than 25mm, where the two services cross each other, the minimum

    vertical clearance shall be 50mm.

    The following minimum separating distance between the electrical

    supply cables and lines of ducts shall be provided :-

    (a) High-voltage single-core cables (exceeding 650 volts)Standard minimum clearance .460mm

    No exception to this requirement will be permitted.

    (b) High-voltage multi-core cables (exceeding 650 volts)

  • 7/27/2019 Specification for Construction of Manholes,

    7/23

    T-2

    Specification for Construction of manholes, Joint Box and Laying of Ducts

    ____________________________________________________________________________________________Standard minimum clearance . 300mm

    If difficult cases a reduced clearance shall be permitted. Where

    it is impossible to provide a greater clearance than 150mm, a

    layer of quality B concrete, not less than 50mm thick and of a

    width to overlap the electrical services by 50mm on each side,

    shall be placed between the two services. Where the two service

    cross each other, the length of the layer of concrete shall not

    be less than the width of the telephone services.

    (c) Low and medium-voltage cables (not exceeding 650 volts)

    Standard minimum clearance .50mm

    Where the two services cross each other no exception to this

    requirement shall be permitted. At other points a clearance down

    to 25mm shall be allowed in difficult cases. Wherever the

    clearance is 50mm or less, the spare between the two services

    shall be filled with a layer of quality B concrete.

    In all cases the concrete shall overlap the electrical services by

    50mm on each side, and at crossing, the length of the layer of

    concrete shall nor be less than the width of the telephone services.

    The Contractor shall cut and bend the ducts according in the

    requirements of the work. Inside edges of cut ducts shall be

    thoroughly rounded off to prevent damages to cables from the edges.

    The trench bottom shall be filled with a layer of sand 50mm thick and

    holes shall be taken out of the bottom of the trench at all points

    where sockets occur so that the barrels of the ducts rest on solid

    ground. In rocky soils, the trench shall be bedded with 80mm thick

    sand on which the ducts are laid.

    On completion of the ducts line between any two jointing chambers of

    sites, a cylindrical brush connected to the following end of a mandrel

    shall be passed twice through each way to clean the duct and to remove

    any foreign matter which may have entered.

    All test shall be carried out in the presence of the S.O.s

    Representative. If any obstruction or other defect be discovered, it

    shall be rectified to the satisfaction of the S.O.s Representative.

    A hardwood plug shall be inserted at the ends of each way in a line of

    ducts until the length has been tested and passed.

    When jointing chambers are provided on an existing duct routes or when

    any disturbance takes place which may affect the alignment of the

    ducts, a test mandrel of appropriate dimensions shall be drawn through

    each of the spare ways. The Contractor shall take all reasonable stepsto prevent damage to the paving by his plants.

  • 7/27/2019 Specification for Construction of Manholes,

    8/23

    T-2

    Specification for Construction of manholes, Joint Box and Laying of Ducts

    ____________________________________________________________________________________________8.2 GALVANISED IRON PIPES

    All galvanized iron pipes shall comply with STM Specification Lines D

    0010. Galvanized iron pipes shall be provided in nominal lengths of 6m

    and provided with screwed socket at one end.

    The procedures of laying galvanized iron pipes shall be as specified

    in Section 8.0. Where one line of ducts is laid over the lower line of

    ducts and carefully rammed to form a bedding of 50mm in thickness for

    the top ducts. Sand shall also be rammed between the ducts laid said

    by side in the same trench. The ducts shall break joint by

    approximately half the length in alternative lines, horizontally and

    vertically.

    Joints shall be made by positioning the threaded end of the pipes to

    the screwed socket of the other pipe end. One of the pipes shall be

    turned until it cannot be turned any more and the thread of the

    threaded end cannot be seen.

    Pipes shall be cut where necessary at right angle to the bore only.The inside edges shall be filed so that there can be no possibility of

    damages to cables from the edges.

    To ensure the alignment of the ducts, a working mandrel of 457mm in

    length and 83mm in diameter shall be drawn through as the ducts are

    laid.

    The test mandrel used for testing and cleaning shall be 457mm in

    length and 83mm in diameter, the cylindrical brush shall be 108mm in

    diameter.

    8.3 P.V.C. DUCTS

    P.V.C ducts shall be supplied in 6m lengths. The ducts shall be stored

    away from the direct rays of the sun. A solvent cement shall be used

    for the process of jointing. The ducts shall comply with STM

    Specification Lines D 0011. The trench shall be scooped out at all

    points where the spigot rest, so that the duct lies upon rammed sand.

    The condition for duct laying as detailed in Section 8.1 shall be

    applied. Where one line of ducts is laid over another in the same

    trench, sand shall be filled in and over the lower lone of ducts and

    carefully rammed to form a bedding of 50mm in thickness for the top

    ducts. Sand shall also be rammed between the ducts laid side by side

    in the same trench. The ducts shall break joint by approximately half

    the duct length in alternative lines, horizontally and vertically.

    If it is necessary to deflect from a straight line or to vary the

    depth, sets shall be given to the joints but deflections shall not be

    greater than 12mm per 610mm run of the single ducts. Short ducts not

    less than 610mm in length, shall be built into the track in order to

    ensure the required deviation.

    Ducts shall be cut when necessary, at right angles to the bore only,

    preferably with a saw in a simple cutting guide. The inside edges of

  • 7/27/2019 Specification for Construction of Manholes,

    9/23

    T-2

    Specification for Construction of manholes, Joint Box and Laying of Ducts

    ____________________________________________________________________________________________the ducts shall be trimmed so that there shall be no possibility of

    damages to cables from the edges.

    The spigot of the ducts shall be wiped clean. The solvent cement shall

    be applied to the spigot as well as the end of another duct. The end

    of the ducts where the solvent cement ware applied shall be positioned

    and pressure applied for the two ducts to be jointed. In no

    circumstances shall dirt or grit be allowed to enter the joint.

    To ensure the alignment of the ducts, a working mandrel of 457mm in

    length and 83mm in diameter shall be drawn through as the ducts are

    laid.

    When the construction of the jointing chamber is deferred, the last

    joint of each duct shall be tested on completion of the jointing

    chamber by means of the working mandrel mentioned above.

    The test mandrel used for testing shall be 457mm in length and 83mm in

    diameter, the cylindrical brush shall be 108mm in diameter.

    8.4 ENCASING IN CONCRETE

    The method of encasing ducts in concrete in the layer by layer method

    where each duct is completely surrounded by concrete.

    To install P.V.C ducts around curves, the rigid ducts shall be bent to

    avoid obstacles or to negotiate curves.

    The ducts shall be cold bent around stakes for radii above 10.6m. To

    provide favourable cable hauling conditions, the radii should be as

    large as possible. Cold bending in situ to the curve required is

    achieved by provision of stakes to form the ducts to the required

    shape. The stakes must be spaced at intervals not greater in length

    than 1/20th of the radius of curvature or alternatively as indicated in

    the Table below.

    Bend

    Radius

    11.6m

    -

    11.2m

    12.2m-

    15.2m

    15.2m-

    18.2m

    18.2m-

    21.3m

    21.3m-

    24.3m

    24.3m

    -

    27.4m

    27.4m

    -

    304m

    Support

    Spacing

    53.3

    cm

    61.0

    cm

    76.2

    cm

    91.5

    cm

    106.7

    cm

    122.0

    cm

    137.2

    cm

    Concrete cover above the top duct of a complete tier is to be a

    minimum of 51mm.

    After the initial set of concrete has occurred and before it sets

    hard, all stakes shall be withdrawn by applying a lifting and turning

    action to the stakes. Where additional ducts are to be installed abovethe first nest, the stakes shall be withdrawn until approximately

    305mm remain embedded.

  • 7/27/2019 Specification for Construction of Manholes,

    10/23

    T-2

    Specification for Construction of manholes, Joint Box and Laying of Ducts

    ____________________________________________________________________________________________

    8.5 FIXING DUCTS TO BRIDGES

    The following two methods shall be used for fixing ducts to bridges :-

    (i) fixing to steel R.S.Js or fabricated beams.(ii) Fixing to reinforced concrete bridge beams and masonry walls.It should be noted that extra care shall be taken when it is necessary

    to make holes for fixing bolts in existing bridge beams. All bridge

    fittings shall be thoroughly cleaned and painted with one coat of

    bituminous paint.

    Where it is necessary for duct to pass through abutment walls, the

    masonry or brickwork shall be arched over the pipe, the diameter of

    the hole thus formed shall be at least 13mm more than the external

    diameter of the duct. The space between with masonry or brickwork and

    the pipe shall then be filled with bitumen to provide a cushion of

    bitumen to the perimeter of the pipe at least 13mm thick.

    8.6 DUMMY DUCTS

    One length of P.V.C ducts shall be positioned, in a wall of the

    chamber or above the row of ducts terminated at a jointing chamber.

    When it is necessary to increase the number of ways, the new ducts

    shall be jointed to the dummy ducts and the ducts shall be made

    available by breaking the mortar seal that was set previously in

    position when the ducts and chamber were constructed.

  • 7/27/2019 Specification for Construction of Manholes,

    11/23

    T-2

    Specification for Construction of manholes, Joint Box and Laying of Ducts

    ____________________________________________________________________________________________

    9.0 JOINTING CHAMBERS

    9.1 TYPE OF MANHOLES

    The standard types and sizes of manholes with code reference are shown

    in the following tables :-

    Reinforced Concrete Construction

    Throughout

    Internal Dimensions

    Code STM

    Standard

    Drg. No.

    Figures Length

    (cm)

    Breadth

    (cm)

    Height

    (cm)

    RO

    RIA

    RIB

    R2Bmod

    fr

    RI3

    RI3

    mod.

    R2A

    R2B

    R2A-

    E

    R2A

    Mod.

    R4

    R6

    R7

    SM.

    No.1

    SM.No.2

    SM.

    No.3

    13359/1

    SHTI&4

    }13359/1

    }SHT&4

    }19488/0}

    }

    19658/0

    }

    }13359/1

    }SHT3&4

    19636/0

    19632/0

    19634/0

    19614/1

    19615/1

    }

    }

    }10750/2

    }

    }

    }

    }

    }}

    }

    Rectangular

    152

    152

    152

    152

    305

    132

    305

    305

    305

    366

    410

    140

    144

    305

    305

    106

    122

    122

    122

    122

    122

    122

    122

    152

    182

    305

    213

    122

    244

    244

    152

    168

    198

    198

    182

    182

    192

    182-244

    182

    182

    182

    305

    182

    213

    213

    TABLE 1 (Contd.)

  • 7/27/2019 Specification for Construction of Manholes,

    12/23

    T-2

    Specification for Construction of manholes, Joint Box and Laying of Ducts

    ____________________________________________________________________________________________

    R3

    R5

    R9

    R9 MOD.

    R10

    R10 MOD.

    R11

    R12

    R13

    R14

    R15

    R16

    19633/0

    19609/1

    19578/2

    19649/0

    19579/2

    19652/0

    19580/0

    19588/0

    19594/0

    19638/0

    19637/0

    19635/0

    A

    S

    S

    O

    R

    T

    E

    D

    S

    H

    A

    P

    E

    S

    &

    S

    I

    Z

    E

    See STM Drawing

    19650/0 for size and

    shape

    Table 1 (Contd.)

    Reinforced Concrete Internal Dimensions

    Code STM Standard

    Drg No.

    Figure Length Breadth Height

    RT88 19485/0

    19482/0

    SHT.1&2

    19484/1

    19486/0

    D A D

    B B

    F

    A B C

    117cm 107cm 244cm

    F

    274cm 182cm

  • 7/27/2019 Specification for Construction of Manholes,

    13/23

    T-2

    Specification for Construction of manholes, Joint Box and Laying of Ducts

    ____________________________________________________________________________________________

    9.2 TYPE OF JOINT BOXES

    The standard types and sizes of joint boxes are shown in the following

    table :-

    TABLE 2

    Item Code STM

    Standard

    Drawing

    Number

    Length Breadth Internal

    Depth

    Carriag

    eway

    Joint

    Box

    Carriag

    ewayJoint

    Box

    Carriag

    eway

    Joint

    Box

    to

    accommo

    date

    L.P.

    200 pr

    JC9

    Mod.

    JC9C

    Mod.

    19647/1

    19646/1

    19540/0

    157cm

    182cm

    244cm

    66cm

    97cm

    97cm

    107cm

    144cm

    108cm +

    61cms.H

    Note: Normal depths are indicated and shall be measured from the carriageway

    of footway surface to the top of the floor in each case. They may

    however be varied to suit the depths of the ducts.

    All jointing chambers whether built of brick or reinforced concrete

    shall be of waterproof construction. Ducts shall enter manholes at

    such a depth to ensure a clearance of at least 460mm between the top

    of the barrel of the uppermost ducts and the underside of the roof of

    the manhole. Except where a duct seal is provided, when a clearance of

    203mm is required clearance of 152mm depending on type of manhole,

    shall be given between the outside of the barrel of the ducts and the

    adjacent wall, and a minimum clearance of 460mm between the undersideof the lowest duct duct and the floor.

    Where the duct capacity of any proposed manhole is not fully utilized,

    the space shall be fitted with dummy ducts for future duct growth by

    laying initially at standard depth. The dummy ducts shall be sealed

    with cement mortar inside the chamber wall. To ensure that cables can

    easily be housed in manholes with a minimum bending, the ducts shall

    be splayed over the last length to enter the manhole equally on either

    side.

  • 7/27/2019 Specification for Construction of Manholes,

    14/23

    T-2

    Specification for Construction of manholes, Joint Box and Laying of Ducts

    ____________________________________________________________________________________________

    9.3 MANHOLE CONSTRUCTION

    The ground shall be excavated to the required dimension, the sides of

    the excavation shall be supported by poling boards or by other means

    if there is any likelihood of the earth falling in. The foundation

    shall taken leveled and rammed. Soft ground shall be dug out, filled

    in with hardcore and consolidated.

    Two light wooden template, slotted (not drilled) to receive the

    reinforced bare shall be set up. The lower template shall be fitted

    about 305mm above the foundation and shall be supported on four small

    pegs at its corners. The upper template shall be fixed to correspond

    with the lower template, but about 305mm below the position of the

    roof of the manhole.

    In the process of erecting the floor of manhole, shuttering for the

    sump hole shall be set up and concrete laid over the foundation to a

    thickness of 38mm.

    The ends of side-wall-to-floor corner reinforcement shall be placed so

    that horizontal portions are just covered by the concrete. The

    vertical portions shall pass through the slots in this template and be

    set so as to obtained 19mm cover from the outside face of the walls

    when these are erected. Additional concrete shall next be laid until

    the level is 19mm less than the concrete level for the floor. This

    shall be done as soon as possible after placing the first layer of

    concrete, so that the two layers units thoroughly. Anchor irons shall

    be set in the floor in accordance with the relevant STM Standard

    Drawings. The interior wall reinforcement shall be placed with the

    horizontal portions flush with the surface of the concrete in the

    floor and the vertical portions passing through the slots of both

    template as to obtain 19mm cover from the interior face of the walls

    when these are erected. To remaining 19mm layer of concrete shall than

    be laid to reach the specified floor level.

    The erection of the walls shall be commenced when the floor has been

    left for at least 12 hours. The portion of the floor on which the

    walls will be erected shall be cleaned and rendered with a 7mm

    thickness of neat cement., well trowelled and placed in position, just

    before wall concreting is commend. The wall shall as far as possible

    be erected continuously to their full height, but if during erection a

    break of 2 hours or more is unavoidable, the existing work shall be

    cleaned and rendered as previously described.

    The horizontal bars and side-to-end-wall corner reinforcement shall be

    placed as walls are built up. Steps, manholes, bolts and cable bearersshall than be set in the walls. The template shall be removed when

    work reaches such a stages that they impede the placing of the

    concrete.

  • 7/27/2019 Specification for Construction of Manholes,

    15/23

    T-2

    Specification for Construction of manholes, Joint Box and Laying of Ducts

    ____________________________________________________________________________________________

    When the walls have been built to the requisite height, shuttering for

    the roof shall be set up and the boards being arranged to form a

    recess at the position of the roof beams. A 26mm thickness of concrete

    shall then be laid throughout the roof area, including the recess of

    the beams. The beam reinforcement which have been previously assembled

    by threading and wiring of stirrups to the bars may now be laid and

    the main reinforcing bars shall be set to obtain 26mm cover. The

    remainder of the roof reinforcement shall be laid and to give the

    correct cover of 19mm and the rods shall be just visible above the

    surface of the concrete. The alternate bent bars shall be conveniently

    supported by a single wire fixing at the point where they enter the

    beam reinforcement. The concrete in the roof shall than be made up to

    the necessary thickness and finally the roof-to-wall corner

    reinforcement shall be embedded.

    The correct cover of 19mm to the roof shall be checked by a wood

    spike. Correction at each end of the horizontal part of the rod shall

    ensure that the vertical portion has the correct cover throughout its

    length. The upper face of the beams shall be spade-finished and theroof given a slight slope to the sides to avoid accumulation of water

    on the roof.

    The shuttering shall be struck and the floor shall be rendered with a

    19mm cement mortar, with a fall to the sump hole on all sides and the

    manhole frame shall then be fitted.

    The arrangement of reinforcement for each type of manhole are as shown

    pictorially in the relevant STM Standard Drawings as listed in Table

    1.

    The minimum concrete curing time for jointing chamber after completion

    of concreting shall be as shown in the following table :-

    TABLE 3 : Manholes Built In The Carriageway/Foot Way

    Type of

    Cement

    Used

    Minimum Period from Completion of Concreting

    (a) to removal (b) before commencing c)before

    of shuttering commencing allowing

    reinstatement passenger

    of traffic

    Portland

    Cement orits

    equivalent

    Rapid-

    Hardening

    Cement

    High

    Alumina

    Carriage-

    way

    5days

    2days

    10hrs

    Foot-

    way

    5days

    2days

    10hrs

    Carriage

    -way

    7days

    3days

    24hrs

    Foot-

    Way

    5days

    2days

    24hrs

    Carriage-

    way

    7days

    3days

    24hrs

    Foot-

    way

    7days

    3days

    24hrs

  • 7/27/2019 Specification for Construction of Manholes,

    16/23

    T-2

    Specification for Construction of manholes, Joint Box and Laying of Ducts

    ____________________________________________________________________________________________Cement

    The striking of the shuttering shall be commenced before the

    expiration of 12 hours and the concrete shall be prevented from

    becoming dry at any time by watering it within 24 hours of mixing.

    9.4 JOINTING CHAMBER FITTINGS

    The following fittings in the jointing chamber shall be hot-dip

    galvanized and the following requirements shall be followed :-

    (a) Grating for sump holes shall be fitted to the sump holes of allmanholes.

    (b) Anchor iron shall be fitted in accordance with the relevantdrawing.

    (c) Steps shall be installed in the position shown in the relevantdrawings for the manholes. The steps shall also be used in

    entrance shafts for all manholes.

    (d) Steel ladders shall be used in all type of manholes. The laddersshall be fixed in accordance with the relevant drawings to suitthe different heights of the manholes.

    (e) Bolts shall be fitted for the attachment of cable bearers. Inall types of manholes, the bolts required for the walls shall be

    fixed temporarily in the shuttering during the construction of

    the manhole to ensure that they shall remain in their correct

    position while the concrete is setting. The positions for holes

    in the shuttering shall be obtained by using the cable bearer as

    a template.

    (f) The cable bearers shall be fixed to the walls as described in(e).

    (g) The brackets for cable bearers shall be in accordance withrelevant drawing and the initial provision shall be 2 per Cable

    bearer, e.g. in a R2A type manholes, where the cable bearers are

    fitted 3 to a wall making a total of 6 cable bearers, the number

    of brackets provided shall be 12.

    (h) The pins locking and cable bearer shall be designed tofacilitate the removal of brackets.

    9.5 FITTING OF MANHOLE COVERS

    Manholes Cover No.3E shall be fitted in all classes of manholes inaccordance with the relevant drawings. Manholes Covers No. 7E shall be

    fitted in all classes of joint boxes in accordance with the relevant

    drawing.

    (a) Where the manhole is to be set at the minimum depth (as shown onthe standard manhole drawings), one course of brickwork shall be

    laid between the manhole roof and frame.

  • 7/27/2019 Specification for Construction of Manholes,

    17/23

    T-2

    Specification for Construction of manholes, Joint Box and Laying of Ducts

    ____________________________________________________________________________________________(b) Where, due to anticipated alternations in level, the manhole is

    to be set at an increased depth, one or more additional course

    of brickwork shall be laid. This is particularly important in

    the case of manholes built in the footway where there is

    possibility of the frames and covers being installed to

    carriageway level at a later date. Cement mortar shall be used

    both for setting the brickwork and for bedding the manholes

    frame.

    (c) 24 hours must elapse after the building of a jointing chamberbefore the frame and cover are installed. The water used in the

    concrete shall not exceed 643 litres per cubic metres.

    The frame shall be positioned accurately in relation to the cover

    before being filled so that the cover is flush and level with the

    surrounding carriageway. Two methods of filling and setting may be

    employed :-

    (i) In-situ filling The frame shall be embedded on a layer ofstiff cement mortar, care being taken to ensure that the frameis fully supported along all the four side.

    The level of the frame shall be adjusted to the level of the

    surrounding road surface by pieces of mild steel packing

    approximately 152mm x 51mm and of appropriate thickness. The

    cover shall than be placed in the frame. When the cover is

    correct suited, the edges of the frame and the cover shall be at

    the same level. If any irregularly can be felt by running the

    finger along the joint, or if the cover rocks, the frame shall

    be packed up until the edges are at the same level and the cover

    is free from rocking. The cover and the frame shall then be

    filled with concrete of Quality G, or an asphalt and granite

    mixture. Great care shall be taken when filling the frame to

    ensure that no voids are left, the concrete in each pocket shall

    be thoroughly tamped with to reinforcing rod. Finishing shall be

    done with a trower the concrete in the cover compartments being

    left slightly proud but not more than 3.2mm at the edge to 6.4mm

    crown in the center of the cover to allow for shrinkage, wear

    and to protect the metal webs. The lettering on the plate

    bearing the STM marking shall be left clear.

    (ii) Where in-situ filling is not possible, the frame shall be placed

    on a level surface with a piece of building paper beneath it to

    prevent concrete adhering to the floor. The leveling of the

    frame and cover, and the concrete filling shall then be done as

    described in method (i). The frames and covers must be left

    undisturbed for a minimum of 3 days. When the frame isinstalled, it shall be bedded on stiff 1:3 cement mortar.

  • 7/27/2019 Specification for Construction of Manholes,

    18/23

  • 7/27/2019 Specification for Construction of Manholes,

    19/23

    T-2

    Specification for Construction of manholes, Joint Box and Laying of Ducts

    ____________________________________________________________________________________________Shuttering shall be struck as follows :-

    (i) For carriageway joint boxes, after the lapse of time given in

    Table 3 of section 9.3 of this specification.

    (ii) For footway joint boxes, after 24 hours, irrespective of the

    type of cement used. A 20mm cement mortar rendering shall be

    applied to level the floors or they shall be built up to give

    25mm drainage fall where required.

    Manhole cover No.7E shall be fitted to all joint boxes and the method

    as described in Section 9.5 of this specification shall apply.

    9.7 PROTECTION OF CABLES AND ASSOCIATED EQUIPMENT

    The Contractor shall take such measures, to protect cables and

    associated equipment during the cutting of duct entries into existing

    structures or the demolition and rebuilding of jointing chambers. Such

    measures may include any or all of the following :-

    (a) A ladder must be provided by the Contractor for the access ofmanhole excavation. Under no circumstances shall cable, joints

    and associated equipment be used for climbing, standing or

    sitting on.

    (b) Sufficient pumping capacity shall be made available to ensurethat when cables are removed from their bearers they shall not

    be immersed in water at any time.

    (c) All cables shall be protected at duct entries by packing withfoam rubber to act as cushion when any movement occurs.

    (d) During demolition of the roof of a manhole the Contractor shallerect a deck of timber between the cables and the roof of the

    manhole to protect the cables etc. from falling debris in the

    following manner :-

    (i) A minimum of three 229mm x 76mm timber upright shall be

    evenly spaced against each long wall of the manhole with

    the 229mm side against the wall. The length of the upright

    shall be such that the terminate approximately midway

    between the uppermost cables and the roof. Further length

    of horizontally on top of the uprights and between the

    uprights at the bottom, all positions shall be wedged and

    blocked to the satisfaction of the S.O.s Representative.

    Lengths of poling boards or other similar timber shallthen be placed on top of the horizontal supports.

    (ii) When the manhole roof and walls have been demolished down

    to the level of the timber decking and all debris and

    decking removed, the cables and other associated equipment

    shall be suspended from beams on the surface of the ground

    to the satisfaction of the S.O.s Representative.

  • 7/27/2019 Specification for Construction of Manholes,

    20/23

    T-2

    Specification for Construction of manholes, Joint Box and Laying of Ducts

    ____________________________________________________________________________________________(iii) Cables and joints and other equipment shall be protected

    by wrapping (not tying) with several layers of sacking

    while timber decking is being erected or dismantled.

    (e) During rebuilding operations, cables shall be supported on

    wooden benches with cushions of sacking or similar

    material once the floor has been laid and the concrete

    allowed to set.

    9.8 BONDING AT JOINTING CHAMBERS FOR EARTHING FACILITIES

    Where metal pipes are laid and terminated at jointing chambers, the

    break in continuity shall be made good by embedding 51mm x 3.2mm G.I.

    strips of required lengths in the walls of the jointing chambers

    during construction. The ends of the G.I. strips shall be welded to

    the pipes.

    10.0 INTERIM RESTORATION, BACKFILLING AND PERMANENT REINSTATEMENT OF ROADSAND OTHERS

    10.1 INTERIM RESTORATION

    The Contractor shall execute interim restoration of all trenches and

    ducts in accordance with the provisions and specification laid down by

    JKR and other relevant authorities. A layer of sand shall first be

    laid on the bed of the trench and hand punned to a thickness of not

    less than 50mm before ducts are laid. All ducts shall be covered by a

    layer of sand and hand punned to a thickness of not less than 50mm.

    10.2 BACKFILLING

    The spaces outside the walls of jointing chambers and surrounding area

    shall be completely filled with sand free from stones in 230mm layers

    and rammed. Care shall be taken such that the ramming shall not

    disturb any recently completed work.

    All materials shall be replaced in 150mm layers in the reverse order

    to which they were excavated. The remaining 300mm top of the trench

    shall be backfilled with good quality red earth and the materials

    previously excavated shall be placed on top and the gaps filled with

    quarry dust. All backfilling shall be thoroughly compacted at each

    layer using a mechanical rammer. If mechanical rammer is impracticable

    and hand ramming is employed, there shall be at least three persons

    ramming to one filling. Where S.O.s Representative required

    backfilling of trenches completely with sand or quarry duct, allexcavated materials shall be removed from site, and backfilling shall

    be carried out as described in the following paragraph.

  • 7/27/2019 Specification for Construction of Manholes,

    21/23

    T-2

    Specification for Construction of manholes, Joint Box and Laying of Ducts

    ____________________________________________________________________________________________For all road crossing in carriageway, after the bedding of a layer of

    sand in the trench has been satisfactorily carried out, the

    backfilling shall be done with nothing else except sand or quarry duct

    in layers. Each layer shall not be more than 230mm in thickness and

    well rammed with mechanical rammer or watered down before the next

    layer is laid. The top 300mm shall be backfilled with quarry dust

    only. This shall be done in tow layers, one layer to be rammed with

    mechanical rammers before the next layer is laid. The top layer shall

    be rammed with mechanical rammer until it is flushed with the road

    surface.

    Backfilled excavation shall be tested by applying a power frog rammer

    repeatedly over on half a square meter area for a period 3 minutes and

    shall performed by the Contractor as instructed by the S.O.s

    Representative at intervals he considers necessary.

    The compactness shall be considered satisfactory of the test shows no

    measurable change in level, a measurable change in level being a

    depression which cannot be rectified by reshaping the tested area and

    consequently requires additional imported material to restore thesurface of the test to the original level. Should any measurable

    change in level occurred, then the area of faulty compaction, defined

    by the results of this and further tests, shall be rectified by the

    Contractor.

    The reinstatement portions of unpaved footways or other excavations

    shall be maintained by the Contractor and he shall ensure that they

    shall be leveled and turfing shall be replaced to the satisfaction of

    the S.O.s Representative. Any subsidence of other defects arising

    during the Defects Liability Period shall be made good by the

    Contractor.

    10.3 PERMANENT REINSTATEMENT OF ROADS

    Permanent reinstatement shall commence only after the back filling and

    interim restoration has been allowed to settle well and that there is

    no measurable change in level.

    The reinstatement shall be carried out by removing the back filled

    material from the trench to a depth of 300mm which shall then be

    filled with a 250mm crusher-run stone (limestone or granite) not

    exceeding 62mm in size and the voids between the metal filled with

    quarry dust to serve as a bind. Where possible, consolidation by

    rolling shall be carried out with an 8 tonne roller utilizing a

    special hydraulic rolling wheel attachment. Elsewhere consolidation

    shall be effected by means of power driven rammer. The 300mm crusher-run stone base for trenches within carriageway shall be consolidated

    in 2 layers of 150mm each. The foundation of the footway shall be

    consist of a layer of not less than 125mm of quarry dust. The layer of

    quarry dust shall be rolled with a 2 tonne roller or by means of a

    power driven rammer.

  • 7/27/2019 Specification for Construction of Manholes,

    22/23

    T-2

    Specification for Construction of manholes, Joint Box and Laying of Ducts

    ____________________________________________________________________________________________A tack coat cationic bituminous emulsion (40%) must be applied to the

    rolled crusher-run stone base/quarry dust base at the rate of 4.5

    square metre per litre before the premixed asphalt macadam surface is

    laid.

    When the consolidation of the stone foundation is completed, premixed

    asphalt shall be spread evenly over the treated stone surface/quarry

    dust surface and rolled until complete consolidation has been obtained

    and the resultant surface left slightly proud of the existing adjacent

    surface. For carriageway consolidation, an 8 tonne roller shall be

    used and for footpath consolidation, a roller not exceeding 2 tonne

    shall be used. All surplus material shall be removed from site by the

    Contractor on the same day the trench has been backfilled. The

    Contractor shall be responsible for maintaining the backfilled trench

    until the surface reinstatement is complete.

    11.0 WORKING DRAWINGS

    Within three weeks after award of the tender or such shorter period as

    may be required by the S.O.s Representative, the Contractor shallsubmit to the S.O.s Representative for his approval, four sets of

    detailed drawings the positions of manholes/joint boxes and cable

    ducts routes. The drawings submitted shall be modified if necessary as

    required by the S.O.s Representative and submitted for final

    approval. It is to be understood, however, that approval of the

    drawings will not exonerate the Contractor from any responsibility in

    connection with the works.

    12.0 SERVICE AND MAINTENANCE

    During the Defects Liability Period, the Contractor shall perform

    service and maintenance work for the complete installation by skilled

    persons. All works, materials, tools and parts necessary to rectify

    the defects due to manufacturing/installation/construction faults

    shall be supplied/executed by the Contractor at no extra cost to the

    Government.

    The works to be performed shall include but not be limited to the

    following :-

    (a) Replacing and making good all manholes, joint boxes, ducts etc.(b) Making good any damage to roads, buildings, drains, cables,

    pipes, concrete areas, paved areas etc. which had not been

    properly made good.

    (c) All other works as deemed necessary by the S.O.sRepresentative.

    The maintenance work shall be carried out as soon as the

    Contractor has been informed by the S.O.s Representative. If

    the work has not been carried out and completed within a

    reasonable period, the S.O.s Representative reserve the right

    to engage another party to carry out the work in which case, the

    Contractor shall be responsible for all the expenses incurred.

  • 7/27/2019 Specification for Construction of Manholes,

    23/23

    T-2

    Specification for Construction of manholes, Joint Box and Laying of Ducts

    ____________________________________________________________________________________________13.0 AS INSTALLED DRAWINGS

    Within three calendar months after the practical completion of the

    project, one set of true to scale negative (110/115gm sq.m) and four

    sets of prints of the layout of cable duct routes, manholes and joint

    boxes with reference to easily recognizable buildings and structures

    shall be submitted.

    These drawings shall be provided whether or not they are separately

    itemzed in the Bills of Quantities of the Tender Document. The cost of

    all these drawings is deemed to be included in the Tender Price.

    These drawings shall be properly stenciled and shall have at the lower

    right hand corner the Contractors name and address date of

    commissioning, scale, drawings number.

    If the drawings submitted are not acceptable by the S.O.s

    Representative, the Contractor shall amend and resubmit the drawing

    within two weeks from the date of return of the drawings.