special provisions blank master€¦ · web viewsecure each cabinet in an upright position when...

21
SP XXXX-XX Insert Date DELETE WHEN DONE: Statements in red are guidelines or instructional in nature. Remove these notes before completing the spec. When appearing at the top left of a provision, it pertains to the paragraph immediately beneath the note, as well as any indented items following it. All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting. DIVISION SS Table of Contents SS-1 (2565) TEMPORARY SIGNAL SYSTEM........................................1 SS-1.1 GENERAL................................................................ SS-1.2 MATERIALS.............................................................. SS-1.3 CONSTRUCTION REQUIREMENTS.............................................. SS-1.4 MEASUREMENT AND PAYMENT............................................... SS-2 (2565) EMERGENCY VEHICLE PREEMPTION SYSTEM...........................17 SS-2.2 MEASUREMENT AND PAYMENT............................................... SS-1 (2565) TEMPORARY SIGNAL SYSTEM This work consists of furnishing and installing materials and electrical equipment and installing Department furnished materials as specified herein, all to provide a complete operating temporary full-traffic- actuated traffic control signal system at the intersection of T.H. ___ and ___________ in _________, ________ County in accordance with the applicable provisions of MnDOT 2565; with the Plans; with the current edition of the National Electrical Code; and as follows: SS-1.1 GENERAL A Cast Aluminum Pipe Fittings Cast aluminum pipe fittings are not permitted for mounting vehicle and pedestrian heads. All locknuts, nipples, lock nipples, gaskets, washers, and all other hardware, used to fasten vehicle and pedestrian heads to signal bracketing and pipe fittings and to signal head mounts must not be fabricated of aluminum. B Contractor Initiated Change In Quantities Any change initiated by the contractor resulting in an increase in materials, quantities, or work is considered incidental to the pay item "TEMPORARY SIGNAL SYSTEM". C Temporary Signal System Staging The temporary traffic control signal consists of separate temporary signal systems utilized during the various stages of roadway construction. 1-SS

Upload: others

Post on 24-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Special Provisions Blank Master€¦ · Web viewSecure each cabinet in an upright position when transporting to the job site. Ensure that each cabinet being transported will not tip

SP XXXX-XXInsert Date

DELETE WHEN DONE: Statements in red are guidelines or instructional in nature. Remove these notes before completing the spec. When appearing at the top left of a provision, it pertains to the paragraph immediately beneath the note, as well as any indented items following it.All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

DIVISION SS

Table of ContentsSS-1 (2565) TEMPORARY SIGNAL SYSTEM...................................................................................................... 1

SS-1.1 GENERAL.........................................................................................................................................................SS-1.2 MATERIALS.....................................................................................................................................................SS-1.3 CONSTRUCTION REQUIREMENTS...................................................................................................................SS-1.4 MEASUREMENT AND PAYMENT...................................................................................................................

SS-2 (2565) EMERGENCY VEHICLE PREEMPTION SYSTEM.............................................................................17SS-2.2 MEASUREMENT AND PAYMENT...................................................................................................................

SS-1 (2565) TEMPORARY SIGNAL SYSTEMThis work consists of furnishing and installing materials and electrical equipment and installing

Department furnished materials as specified herein, all to provide a complete operating temporary full-traffic-actuated traffic control signal system at the intersection of T.H. ___ and ___________ in _________, ________ County in accordance with the applicable provisions of MnDOT 2565; with the Plans; with the current edition of the National Electrical Code; and as follows:

SS-1.1 GENERAL

A Cast Aluminum Pipe Fittings Cast aluminum pipe fittings are not permitted for mounting vehicle and pedestrian heads.

All locknuts, nipples, lock nipples, gaskets, washers, and all other hardware, used to fasten vehicle and pedestrian heads to signal bracketing and pipe fittings and to signal head mounts must not be fabricated of aluminum.

B Contractor Initiated Change In Quantities Any change initiated by the contractor resulting in an increase in materials, quantities, or work is

considered incidental to the pay item "TEMPORARY SIGNAL SYSTEM".

C Temporary Signal System Staging The temporary traffic control signal consists of separate temporary signal systems utilized during

the various stages of roadway construction.

The transition from one stage of temporary signal system to another stage of temporary signal system can occur only when directed by the Engineer.

The State, by its own forces, will make all necessary revisions in the intersection traffic control signal cabinet and control equipment when the transition from one stage of temporary signal system to another stage of temporary signal system occurs.

For each stage of temporary signal system, make all necessary field lead connections in the intersection traffic control signal cabinet as directed by the Engineer and make the temporary signal system operational.

1-SS

Page 2: Special Provisions Blank Master€¦ · Web viewSecure each cabinet in an upright position when transporting to the job site. Ensure that each cabinet being transported will not tip

SP XXXX-XXInsert Date

SS-1.2 MATERIALS

A Department Provided Materials

The Department provides to the Contractor (at no expense to the Contractor) the following materials and electrical equipment for the Contractor to install:

(1) One (1) traffic control signal cabinet each complete with actuated controller unit and all required signal control equipment.

(2) Four (4) sets of anchor rods, nuts, and washers to mount the Department provided traffic control signal cabinet (one set = one anchor rod, nut, and washer).

(3) One (1) 4-section rubber gasket to be installed between the bottom of each traffic control signal cabinet and the concrete foundation.

(The following language is to be used for required warning stickers on the backside of sign panels being installed on the signal system project. See additional verbiage under construction requirements. The Specification Writer must include the appropriate contact person and phone number to the following paragraph).

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

(4) Warning stickers on new sign panels shall be in accordance with 2564.3 H. The quantity required must be coordinated with the Engineer.

Add the section below if video detection is going to be used.There should be companion verbiage in the construction requirements section below also. The video detection system should be state supplied. The detection systems are on State contract. The traffic signal control public interest finding (PIF) covers this type of detection so State supplying it should not be a problem.The Auto scope Vision uses 4 conductor 18 AWG microwave and sonic detector cable 3815.2 C.14The Gridsmart system uses an Ethernet cable with power over Ethernet. Ethernet Cable (Outside Plant) 3815.2 C.6.dThe Iteris Vantage Next system uses an Ethernet cable with power over Ethernet. Ethernet Cable (Outside Plant) 3815.2 C.6.d.

The video detection system to be installed and used at the intersection should be decided at the signal design phase so the correct cable can be call for and shown on the plan. Either Cat 5 E or 4/C 18 AWGUse the language when appropriate based on the plan and as directed in RED text.

All RED text must be removed from the special provisions prior to the special provisions being submitted for project letting.

(5) Video Detection

Obtain traffic control video detection cameras and mounts from MnDOT Electrical Services Section (ESS) at least 30 business days in advance of planned signal turn on.

B ConduitPlace a section of liquid tight flexible non-metallic conduit and conduit fittings in accordance with

MnDOT 3804 from each metal junction box to each signal bracket.

Use a weather head service entrance type fitting with knockouts (unused knockouts must not be opened) for conduits terminating near the top of wood poles.

2-SS

Page 3: Special Provisions Blank Master€¦ · Web viewSecure each cabinet in an upright position when transporting to the job site. Ensure that each cabinet being transported will not tip

SP XXXX-XXInsert Date

Temporary Cabinet Base

Provide a MnDOT approved temporary cabinet base as listed on MnDOT’s Approved Products List for Signals:http://www.dot.state.mn.us/products/index.html

C Arc-Flash Hazard Warning LabelsProvide 4 in H x 6 in W vinyl or polyester labels meeting the following:

(1) White background,(2) Orange background behind the WARNING text,(3) Black text,(4) Self-adhesive,(5) Machine printed letters and numbers, and(6) Water-resistant.

Figure 1 is for information and reference only.

The following order form must be filled out by the special provisions writer before inclusion in the final set of special provisions. The order form should be left as separate pages so they can be removed.All RED text must be removed from the special provisions prior to the Special Provisions being submitted for project letting.

Accessible Pedestrian Signal (APS)ORDER FORM

(Fill out one form per intersection)Intersection:

System I.D. ___________ T.E. No. ___________ Total Number of Pedestrian Push Buttons _____ Field Wiring Interface Board: One needed for each intersection Qty: 1

CCU (Central Control Unit): One needed for each intersection Qty: 1

Push Button and Sign Braille Information

3-SS

Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1Figure 1 ARC-Flash Warning Label Category 1

Page 4: Special Provisions Blank Master€¦ · Web viewSecure each cabinet in an upright position when transporting to the job site. Ensure that each cabinet being transported will not tip

SP XXXX-XXInsert Date

Button Arrow Direction R/L Street Name(Street Being Crossed)

PB2-1 PB2-1PB2-2 PB2-2PB2-3 PB2-3PB2-4 PB2-4PB4-1 PB4-1PB4-2 PB4-2PB4-3 PB4-3PB4-4 PB4-4PB6-1 PB6-1PB6-2 PB6-2PB6-3 PB6-3PB6-4 PB6-4PB8-1 PB8-1PB8-2 PB8-2PB8-3 PB8-3PB8-4 PB8-4

Custom Voice Message Details

Voice on Location and Walk Message(s) Please give phonetic pronunciation on difficult street names so that the message will be recorded correctly. *Note that unless Street, Drive, Avenue etc.…are absolutely necessary for intersection identification, it is recommended to not include them in the verbal message. 

4-SS

Page 5: Special Provisions Blank Master€¦ · Web viewSecure each cabinet in an upright position when transporting to the job site. Ensure that each cabinet being transported will not tip

SP XXXX-XXInsert Date

5-SS

PB2-1Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

PB2-2Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

PB2-3Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

PB2-4Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

Page 6: Special Provisions Blank Master€¦ · Web viewSecure each cabinet in an upright position when transporting to the job site. Ensure that each cabinet being transported will not tip

SP XXXX-XXInsert Date

6-SS

PB4-1Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

PB4-2Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

PB4-3Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

PB4-4Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

Page 7: Special Provisions Blank Master€¦ · Web viewSecure each cabinet in an upright position when transporting to the job site. Ensure that each cabinet being transported will not tip

SP XXXX-XXInsert Date

7-SS

PB6-1Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

PB6-2Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

PB6-3Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

PB6-4Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

Page 8: Special Provisions Blank Master€¦ · Web viewSecure each cabinet in an upright position when transporting to the job site. Ensure that each cabinet being transported will not tip

SP XXXX-XXInsert Date

8-SS

PB8-1Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

PB8-2Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

PB8-3Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

PB8-4Wait Message: Wait to Cross at

(Street Being Crossed) (Intersecting Street)Walk Message: Walk sign

is on to cross

(Street Being Crossed) (Street Being Crossed)

Page 9: Special Provisions Blank Master€¦ · Web viewSecure each cabinet in an upright position when transporting to the job site. Ensure that each cabinet being transported will not tip

SP XXXX-XXInsert Date

Walk Interval MessagesModel message for the walk interval, applicable to most intersections.“Howard. Walk sign is on to cross Howard.”

Pushbutton Informational MessagesModel message for pushbutton intersection identification information.“Wait to cross Howard at Grand.”All RED text must be removed from the special provisions prior to the Special Provisions being submitted for project letting.

D Service EquipmentPlace service equipment including meter socket on the wood pole where indicated in the Plans in

accordance with MnDOT 3837 using a circuit breaker load center.

Provide and install circuit breakers in the new load center as follows:

(1) One (1) 2-pole 100 amp main circuit breaker.(2) One (1) 1-pole, 30 amp circuit breaker for signal system.(3) Two (2) 1-pole, 15 amp circuit breakers for roadway lighting.

E Metal Junction Boxes on Wood PolesPlace a metal junction box with terminal blocks on each wood pole with vehicle signal heads in accordance with the provisions of MnDOT 3838.2B.

If the district is going to install the pole base connectors the spec writer will need to select one of the following paragraphs but not usually both.

All RED text must be removed from the special provisions prior to the special provisions being submitted for project letting.

Provide MnDOT approved 14AWG pole base connectors in accordance with MnDOT 2565.2Y and as follows:

Use pole base connectors in each metal junction box for terminating signal conductors to vehicle signal indications, pedestrian signal indications, and EVP confirmatory lights in accordance with the detail in the Plan.

The following language needs to be included if “terminal blocks” are being used as conductor termination devices. The district must use either Pole Base Connectors or Terminal Bocks but not both.

All RED text must be removed from the special provisions prior to the special provisions being submitted for project letting.

Provide MnDOT approved terminal blocks in accordance with the provisions of MnDOT 2565.2GG

Coat all terminal blocks with a MnDOT approved Pole Base Terminal Block Coating listed on MnDOT’s Approved/Qualified Products List for Signals:

http://www.dot.state.mn.us/products/index.html

Spray coat the block, terminal connections, and the exposed wire ends where crimped to the spade connector.

SS-1.3 CONSTRUCTION REQUIREMENTS

A Installation of Department Provided MaterialsInstall the Department provided traffic control signal cabinet(s) complete with controller unit and

all required traffic control signal equipment.

9-SS

Page 10: Special Provisions Blank Master€¦ · Web viewSecure each cabinet in an upright position when transporting to the job site. Ensure that each cabinet being transported will not tip

SP XXXX-XXInsert Date

Provide and install all additional materials and electrical equipment for a complete operating traffic control signal cabinet installation (which includes, but is not limited to):

(1) Temporary cabinet base including mounting bolts, nuts, and washers.(2) Grounding electrodes.(3) All bonding and grounding materials and connections.(4) Make all field lead connections in the traffic control signal cabinet as directed by the

Engineer to make the temporary traffic control signal system fully operational.

The following paragraph needs to be modified to give contractor specific location to deliver the pallet back to MnDOT.

All RED text must be removed from the special provisions prior to the Special Provisions being submitted for project letting.

Protect the Department provided cabinet pallet from damage and return the pallet to MnDOT Central Electrical Inventory Center at the address specified herein, or MnDOT’s District Headquarters.

B Pick Up Department Provided Materials Pick up materials and electrical equipment described above at MnDOT’s Electrical Services

Section, 6000 Minnehaha Avenue, St. Paul, MN. 55111- 4014. Follow these requirements:

(1) Request from MnDOT’s Electrical Services Section the materials and electrical equipment listed above.

(2) Direct the Electrical Services Section to the T.E. Request No. ______. (3) Request Department provided materials at least 30 business days in advance of needing

the material on the project. (4) Notify MnDOT Electrical Services Section at least 3 business days in advance of intention

to pick up materials and electrical equipment. (5) Contact:

Electronic Maintenance Supervisor 651 366 5759Stockroom 651 366 5720Transportation Program Supervisor 651 366 5753

(6) Pick up the Department provided materials and electrical equipment at the above specified location and transport them to the job site.

(7) Secure each cabinet in an upright position when transporting to the job site. Ensure that each cabinet being transported will not tip and be damaged.

(8) Notify the Engineer in advance of contacting MnDOT’s Electrical Services Section.

Add the text below if the signal system has video detection.There should be companion verbiage in the materials section above also. Use the language when appropriate based on the plan and as directed in RED text.

All RED text must be removed from the special provisions prior to the special provisions being submitted for project letting.

C Video Detection Systems Construction RequirementsInstall traffic signal high definition video detection systems at the locations shown on

the Plan and the following:

(1) Aim each camera for optimal field of view and detector placement at each specific approach,

(2) Install continuous unspliced Cat 5 E cable, or microwave and sonic detector cable(3) Zoom and focus the cameras to provide proper imaging of the approaches

10-SS

Page 11: Special Provisions Blank Master€¦ · Web viewSecure each cabinet in an upright position when transporting to the job site. Ensure that each cabinet being transported will not tip

SP XXXX-XXInsert Date

(4) Program video image detection zones as shown on the Plan, and(5) Verify with MnDOT’s district traffic office:

(a) Aim each camera for optimal field of view and detector placement at each specific approach,

(b) Detection zones are working correctly, and(c) Live video images show the detection zones properly overlaid and operating

(6) Remove, reinstall, and aim cameras for optimal field of view and proper detector overlay placement when different stages of the project require intersection configuration changes.

D Arc-Flash Hazard Warning Labeling

Calculate available fault current in accordance with 2545.3X and 2565.3 CC.

Establish available fault current and apply the appropriate label as follows.

Use the current edition of NFPA 70E “Standard for Electrical Safety in the Workplace” to determine the required PPE category and personal protective equipment.

If the available fault current is ≤ 25,000 amps then provide a label with the following information shown in Example 1.

If the available fault current is ˃ 25,000 amps:

Determine PPE requirements in accordance with the current edition of NFPA 70E Standard for Electrical Safety in the Workplace

Provide a label with the following information shown in Example 2. Fill in the ___ (blank) with the required arc-flash PPE category and arc-flash boundary distance

11-SS

Example 1

Warning Arc Flash HazardAppropriate PPE RequiredArc Flash Boundary 19 inches Arc Flash PPE Category ____1____Working Distance 18 Inches Arc Flash Personal Protection Equipment (PPE)

List required clothing, Min Arc Rating of 4 cal/cm², and protective equipment in accordance with the PPE Table from the current edition of NFPA 70E Standard for Electrical Safety in the Workplace

Equipment ID

Page 12: Special Provisions Blank Master€¦ · Web viewSecure each cabinet in an upright position when transporting to the job site. Ensure that each cabinet being transported will not tip

SP XXXX-XXInsert Date

Install labels on the front of the dead front door of the electric service cabinet at eye level.

The following Section should only be included in projects when the contractor is going to be required to do excavation work.

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

E Maintenance of Existing Electrical Systems

Maintain and keep in operation new and existing electrical systems in accordance with 2565.3B and as follows:

The Contractor is responsible for locating underground facilities of existing traffic control signal systems including temporary, and newly constructed signal systems within the limits of the construction project, for the duration of the construction project in accordance with the applicable provisions of MnDOT 1514 and in accordance with Minnesota State Statute 216D.

The responsibility for locating underground traffic control signal system facilities shall be transferred to the Contractor on the project start date as shown on the proposal.

MnDOT’s locating group will provide an initial locate of the underground traffic control signal system facilities within the project limits at the request of the Contractor at the start of the project. The request for the initial locate must be submitted to MnDOT’s Locating Office a minimum of 4 business days prior to the project start date.

Locate requests that are within the construction project limits will continue to be received by MnDOT’s Locating Office. These locate tickets will be forwarded to the Contractor’s representative responsible for coordinating locate requests within the projects limits. The locate tickets will be forwarded via e mail or fax. Confirmation of receipt of the locate ticket must be sent by the Contractors representative back to MnDOT’s locating office within 2 hours of MnDOT’s sending the Contractor’s representative the locate request.

The Contractor responsible for locating underground traffic control signal system facilities will repair damage as the result of improperly located or unmarked underground traffic control signal system facilities within the project limits.

12-SS

Example 2

Warning Arc Flash HazardAppropriate PPE RequiredArc Flash Boundary ____Feet Arc Flash PPE Category ________Working Distance 18 Inches Arc Flash Personal Protection Equipment (PPE)

List required clothing, Min Arc Rating of ___ cal/cm², and protective equipment in accordance with the PPE Table from the current edition of NFPA 70E Standard for Electrical Safety in the Workplace

Equipment ID

Page 13: Special Provisions Blank Master€¦ · Web viewSecure each cabinet in an upright position when transporting to the job site. Ensure that each cabinet being transported will not tip

SP XXXX-XXInsert Date

The repair the damaged underground traffic control signal system facilities in accordance with 2545.3A, 2565.3B and RTMC design and construction requirements.

Until final written acceptance of the project by the Engineer (MnDOT 1716), locate underground traffic control signal facilities as required in this section. This Work is included in the Pay Item Traffic Control Signal System.

It is the Contractor’s responsibility to notify MnDOT’s Locating Office to provide contact information and establish the contractor has assumed responsibility for locating MnDOT’s underground traffic control signal system facilities within the project limits. The form in this section is filled out by the Contractor’s representative and provided to the Engineer at the pre-construction meeting. A copy of the completed form sent to the following:

Electrical Services Dispatch Phone: (651)366-5750Fax: (651)366-5742E mail: [email protected] Minnehaha Ave. St. Paul, MN 55111-4014AndLocating Supervisor Phone: (651)755-9061Fax: (651)366-5742E mail: [email protected] Minnehaha Ave. St. Paul, MN 55111-4014

(The following Section should be filled out by the specification writer to direct the contractor and project engineer to the correct person in the District.All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

MnDOT District Signal Operations Name: _______________Phone: _______________Fax: _________________E mail: _______________Address: ______________

(The following Section should be left on its own page so the contractor can remove it and use the blank page)All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

13-SS

Page 14: Special Provisions Blank Master€¦ · Web viewSecure each cabinet in an upright position when transporting to the job site. Ensure that each cabinet being transported will not tip

SP XXXX-XXInsert Date

14-SS

Locating Responsibility FormJob S.P. Number __________________________________

Job Type __________________________________

Start Date __________________________________

End Date __________________________________

T.H. __________________________________

Location __________________________________

Lighting/ Signal Inspector __________________________________

Contractor __________________________________

Contractor (24 Hour Contact) __________________________________

Project Manager __________________________________

Phone Number __________________________________

Fax Number __________________________________

Email __________________________________

Electrician __________________________________

Phone Number __________________________________

Locator Area __________________________________

Project Engineer __________________________________

Phone Number __________________________________

Chief Inspector __________________________________

Phone Number __________________________________

Weekly Meeting __________________________________

Page 15: Special Provisions Blank Master€¦ · Web viewSecure each cabinet in an upright position when transporting to the job site. Ensure that each cabinet being transported will not tip

SP XXXX-XXInsert Date

During any periods of authorized work suspension, the contractor is responsible for maintenance of the existing, temporary, and newly constructed traffic control signal systems.

Provide to the Department contact information with the names and telephone numbers for 24 hours a day, 7 days a week maintenance as defined above.

This Work is included in the Unit Prices of the Pay Items that are part of the Traffic Control Signal System.

F Temporary Cabinet Base Install the temporary traffic control signal cabinet base at the location staked by the Engineer.

Install the temporary traffic control signal cabinet base per the Manufacturer’s instructions and to the satisfaction of the Engineer.

G Span Wire Mounted Signal HeadsInstall each one-way span wire mounted vehicle signal head as detailed on the “TYPICAL WOOD

POLE/SPAN WIRE SIGNAL SYSTEM DETAILS” in the Plan to the satisfaction of the Engineer.

H Wood Pole Anchors for Down GuysProvide wood pole anchors for down guys approved by the Engineer before installation and

install where indicated in the Plans at an elevation at least 5 feet below the ground line. Embed the wood pole anchors in a compacted granular material in a manner approved by the Engineer.

I Roadway Lighting on Wood PolesProvide mast arms and luminaires for roadway lights in accordance with the following

specifications:

J Mast Arms(1) Suitable for wood pole mounting; (2) 15 foot in length; (3) Galvanized. (4) The nominal 2 3/8 in diameter slipfitter for the luminaire

K LuminairesProvide MnDOT luminaires shown on the Plan and on MnDOT’s Approved/Qualified Products List

for Lighting:

http://www.dot.state.mn.us/products/index.html

L Photoelectric ControlProvide a MnDOT approved Photoelectric Control as listed on MnDOT’s Approved/Qualified

Products List for Roadway lighting:

http://www.dot.state.mn.us/products/index.html

M WiringProvide a 1-3/C 14 AWG (LUM.) signal control cable from the service equipment circuit breaker

load center to the luminaire as required by the Plans with a 2 A (1.5 inch X .406 inch) fast acting fiber tube cartridge fuse mounted in a watertight inline fuse connector in the ungrounded conductor and located inside each luminaire housing. It is not required that the inline fuse connector be made of rubber.

N Bonding and GroundingAll bonding and grounding must be in accordance with the current edition of the National

Electrical Code; with the Plans; and with the applicable provisions of MnDOT 2565.3H, and as follows:

15-SS

Page 16: Special Provisions Blank Master€¦ · Web viewSecure each cabinet in an upright position when transporting to the job site. Ensure that each cabinet being transported will not tip

SP XXXX-XXInsert Date

Ensure that metal conduits, luminaire mast arm, metal junction boxes, span wire, down guys, service equipment, video detection units, and the traffic control signal cabinet are made mechanically and electrically secure to form a continuous bonded and grounded system. Provide a copper wire, not less than No. 6 AWG as the bonding jumper. Use material compatible grounding clamps and connectors to attach the bonding and grounding jumper to span wires, down guys, conduits, and the ground rod electrode.

(The following language is to be used for required warning stickers on the backside of sign panels being installed on the signal system project. The Specification Writer must include the appropriate contact person and phone number to the following paragraph).

All Red text must be removed from the special provisions prior to the special provisions being submitted for project letting.

O Sign Panel Warning StickersInstall Department furnished warning stickers on new sign panels in accordance with MnDOT

2564.3H. Give 30 days’ advance notice to___________________ at ___-___-____ prior to picking up the Department furnished warning stickers.

P Return of Department Provided EquipmentReturn Department provided materials and electrical equipment following these requirements:

(1) Inform MnDOT’s Electrical Services Section (ESS) the materials and electrical equipment to be returned.

(2) Provide ESS the T.E. Request No. ______ . (3) Notify ESS at least 3 business days in advance of intention to return materials and

electrical equipment. Contact directly one of the following:

Electronic Maintenance Supervisor 651 366 5759Stockroom 651 366 5720

Transportation Program Supervisor 651 366 5753

(4) Deliver the Department provided materials and electrical equipment to:

MnDOT’s ESS6000 Minnehaha AvenueSt. Paul, MN 55111-4014

(5) When transporting cabinets:

(a) Place on MnDOT cabinet pallets(b) Secure in an upright position(c) Prevent damage from tipping over or sliding

(6) Return video detection equipment and mounting hardware in proper working order. Repair or replace video detection equipment and mounting hardware that is not returned or returned in non-working order at no cost to the Department.

(7) Notify the Engineer before contacting MnDOT’s Electrical Services Section for returning Department provided materials and equipment.

SS-1.4 MEASUREMENT AND PAYMENT

A MeasurementProviding and installing materials and electrical equipment and installing Department furnished

materials, as specified herein, to provide a complete operating temporary full-traffic-actuated traffic control signal system at the intersection of T.H. ___and __________in ________, _____ County as

16-SS

Page 17: Special Provisions Blank Master€¦ · Web viewSecure each cabinet in an upright position when transporting to the job site. Ensure that each cabinet being transported will not tip

SP XXXX-XXInsert Date

contained in these Special Provisions and in the Plans is measured as an integral unit complete in place and operating.

B Payment A full-traffic-actuated traffic control signal system is paid for under Item No. 2565.616

(TEMPORARY SIGNAL SYSTEM) at the Contract price per SYSTEM, which price is compensation in full for all costs incidental thereto.

SS-2 (2565) EMERGENCY VEHICLE PREEMPTION SYSTEMThis work consists of providing and installing emergency vehicle preemption (EVP) system at the

intersection of ______ (______) and ______ in ________, _______ County in accordance with the applicable provisions of MnDOT 2565; with the Plans; and as follows:

A MATERIALSProvide Emergency Vehicle Preemption (EVP) equipment in accordance with MnDOT 2565 and

3814.

Phase selectors (or other EVP equipment to be installed in the traffic control signal cabinet) will be installed in the Department furnished cabinet by MnDOT personnel.

Deliver all EVP phase selectors or other required EVP equipment to be installed in the traffic control signal cabinet to the Department at MnDOT’s Electrical Services Section for installation into the Department furnished traffic control signal cabinet.

Provide the equipment at least 30 business days in advance of when the Department furnished traffic control signal cabinet is required on the job site.

B CONSTRUCTION REQUIREMENTSPlace in accordance with 2565.3.

SS-2.2 MEASUREMENT AND PAYMENT

A Measurement

B Providing and installing Emergency Vehicle Preemption (EVP) system at the intersection of T.H. ___ and ______ in ________, _______ County as specified herein is measured as an integral unit complete in place and operating. PaymentProviding and installing Emergency Vehicle Preemption (EVP) system at the intersection of T.H.

___ and ______ in ________, _______ County as specified herein is paid for under Item No. 2565.501 (EMERGENCY VEHICLE PREEMPTION SYSTEM) at the Contract price per LUMP SUM, which price is compensation in full for all costs.

17-SS