spdo report

20
SPDO report Richard Schilizzi and Peter Dewdney US SKA Consortium Meeting Madison, 17 November 2008

Upload: hinto

Post on 08-Jan-2016

18 views

Category:

Documents


0 download

DESCRIPTION

SPDO report. Richard Schilizzi and Peter Dewdney US SKA Consortium Meeting Madison, 17 November 2008. International SKA context PrepSKA SPDO and WP2, WP3 WPs 4, 5, 6, 7 SPDO team WP2 program (Peter Dewdney). Contents. Top-level specifications in SKA Memo 100 - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: SPDO report

SPDO report

Richard Schilizzi and Peter Dewdney

US SKA Consortium MeetingMadison, 17 November 2008

Page 2: SPDO report

Contents

International SKA context PrepSKA SPDO and WP2, WP3 WPs 4, 5, 6, 7 SPDO team

WP2 program (Peter Dewdney)

Page 3: SPDO report

specifications

Top-level specifications in SKA Memo 100

Sensitivity (Aeff/Tsys) 12000 (max) FoV

single pixel feed 1 sq. deg. (21 cm), 4 sq. deg. at z=1phased array feed 20 sq. deg.aperture array 20 sq.deg.

Survey speed figure of merit (Aeff/Tsys)2.FoV 2x1010 (max)

Continuum sensitivity 20 nJy (10 hours)

Page 4: SPDO report

Costs Target construction cost: 1.5 billion € for

Phase 1+2 Expected operating costs: 100+ million

€/year Energy costs a big contributing factor

Currently funded SKA R&D (2007-2012) via national and regional projects: 140 M€ PrepSKA (FP7) funds the SPDO engineers Design Studies (FP6 SKA Design Study, US Tech Dev Program) Pathfinders (ASKAP, MeerKAT, LOFAR, Apertif, ATA, MWA, LWA, EVLA, eMERLIN, eEVN)

Page 5: SPDO report

Key dates

2008-2012 costed system design 2012 site selection2012-2013 agreement on construction

funding2012-2016 Phase 1 implementation2016 early science with Phase 12016-2021 construction of full array at

low and mid-frequencies

Page 6: SPDO report

06 | 08 | 10 | 12 | 14 | 16 | 18 | 20 | 22 | 24 |

System DesignSystem Design Full SKA mid + low Full SKA mid + low construction and construction and commissioningcommissioning

SKA-high SKA-high ConstructionConstruction

Sites short-listed

EC-FP7: PrepSKA

System design Verification Programs

Funding Governance

Site Selection

Preliminary SKA specs External

Engineering Review of design

Reference Design selected

Pathfinder Suite Construction

SKA-mid+lowSKA-mid+lowCompleteComplete

Phase 1 Phase 1 funding funding approvalapproval

System System design design SKA-hiSKA-hi

Pathfinder science

Phase 1 complete

Concept Concept DesignDesign

SiteSelect

Concept design for Concept design for SKA-highSKA-high

SKA timeline

Prod. Readiness

Review

Early Science SKA mid+low

SKA Operations

Phase 2 funding approval

Phase 1 Prod. Eng. & Tooling

Phase 1 Construction

Page 7: SPDO report

Solar power array in Portugal

2550 elements each 150 m2

Spread over an area 2km in diameter

Azimuth rotation

Erected in one year

Page 8: SPDO report

Artist’s impression of the SKA

1000- 1500 dishes (15m) in the central 5 km 2000-3000 total+ dense and/or sparse aperture arrays

Page 9: SPDO report

Alternatively…….

Page 10: SPDO report

PrepSKAFormal PrepSKA partners

Agencies STFC (UK), NWO (NL), CNRS (FR), INAF (IT),

DIISR (AU), NRF (ZA), NRC-HIA (CA) Institutes

ASTRON (NL), Cornell/NAIC (USA), CSIRO (AU), IT (PT), JIVE (Europe), MPIfR (DE), OBSPAR (FR), RuG (NL), UCal (CA), UK (UCam, UMan, UOxf), UOrl (FR),

Other organisations involved in studyNSF(USA), AUI(USA), FG-IGN(EC), VR(SE),

SKA Program Development Office (SPDO)

7 Work Packages

Page 11: SPDO report

PrepSKA organisation

Page 12: SPDO report

WP2

Deliverables(Peter Dewdney “Guiding Principles, Activities and Targets for

WP2”)

Technology selection System Design

including operational – construction tradeoffs

Science Performance vs Reference Science Mission Total cost estimate for Baseline Design (incl.

contingency) Risk assessment Design and deployment plan Top-level build schedule Upgrade paths

Page 13: SPDO report

WP2 approach Streamline WP2 Description of Work

Move from 40 technology development tasks, including an ill-defined ‘IVS’ to assembly and verification of large SKA sub-systems

Easily evaluated by EC and Funding Agencies/Governments

Dish Verification Program

PAF Verification Program

AA Verification Program

Signal transport Verification Program

…..

+

MoAs with organisations and institutes

Page 14: SPDO report

WP3 – Additional Site Studies

Inform decision-making process for site selection

– Carry out further RFI measurements (in progress)

– RQZ (in progress)– Investigate infrastructure deployment

costs and timescales– Detailed risk analysis– Array configuration (in progress)– Ionosphere (in progress)– Tropospheric water vapour

Page 15: SPDO report

WP4, WP5

WP4 – Governance and Legal Framework (led by NWO, NL)Study of options for viable models of governance and a

legal framework for SKA during construction and operation

Interim legal entity for SPDO during PrepSKA?

WP5 – SKA Procurement and industrial involvement (led by INAF, Italy)Lay out options for procurementInvestigation of the optimum way to involve industry in

the global, regional and national contexts

Page 16: SPDO report

WP6, WP7 WP6 – Developing the funding model

(led by STFC, UK)Investigate all aspects of the financial model for lifetime

costs of the SKAIssues: phasing of SKA and ELTs

what constitutes a “mature” project? post-PrepSKA funding

how to value in-kind contributions pre-construction

Investigate options for loan from European Investment Bank and other similar bodies to provide a smooth funding profile

WP7 – Implementation plan (led by Co-ordinator)Investigate socio-economic and knowledge impact of the

SKAIntegrate output of all other partners to produce a

detailed, costed design for Phase 1 of the SKA and an implementation plan for the full SKA.

Page 17: SPDO report

SPDO TeamProject Director Richard SchilizziProject Engineer Peter Dewdney Project Scientist Joe LazioExecutive Officer Colin GreenwoodSystem Engineer Kobus Cloete Domain Specialist Receptors Neil Roddis Domain Specialist Signal Transport Roshene McCool Domain Specialist Computing & Softw Duncan Hall

(starting January)Domain Specialist Signal Processing not yet filledSite Engineer Rob Millenaar Project Management Officer Billy Adams

(starting January)Industry Relations Manager to be advertisedOutreach Officer Ian MorisonOffice Manager Lisa Bell

Support Engineers (4-5x) to be advertised

Page 18: SPDO report
Page 19: SPDO report

In –kind contributions Call for submissions – deadline 31 October

2008 7 responses (ASTRON, CSIRO, INAF, JPL,

McGill/Laval Universities, NRAO, NRC Canada)

Contributions Audit CommitteePaul Mantsch (chair, Spokesperson for Pierre Auger Collaboration)Ethan Schrier (US)Jim Ulvestad (US)Arnold van Ardenne (Europe)Wim Brouw (Europe)Lewis Ball (Australia)Faranah Osman (South Africa)

Audit Committee to make recommendations to SSEC by February 2009

Page 20: SPDO report

Issues How is the in-kind contributions register

going to be used by the Funding Agencies?

What is the “value” to the international SKA program of the submissions to the in-kind register?

Should we only consider contributions in the PrepSKA era?and/or

Only those contributions that made mention of the SKA in the original proposals?