spdo report
DESCRIPTION
SPDO report. Richard Schilizzi and Peter Dewdney US SKA Consortium Meeting Madison, 17 November 2008. International SKA context PrepSKA SPDO and WP2, WP3 WPs 4, 5, 6, 7 SPDO team WP2 program (Peter Dewdney). Contents. Top-level specifications in SKA Memo 100 - PowerPoint PPT PresentationTRANSCRIPT
SPDO report
Richard Schilizzi and Peter Dewdney
US SKA Consortium MeetingMadison, 17 November 2008
Contents
International SKA context PrepSKA SPDO and WP2, WP3 WPs 4, 5, 6, 7 SPDO team
WP2 program (Peter Dewdney)
specifications
Top-level specifications in SKA Memo 100
Sensitivity (Aeff/Tsys) 12000 (max) FoV
single pixel feed 1 sq. deg. (21 cm), 4 sq. deg. at z=1phased array feed 20 sq. deg.aperture array 20 sq.deg.
Survey speed figure of merit (Aeff/Tsys)2.FoV 2x1010 (max)
Continuum sensitivity 20 nJy (10 hours)
Costs Target construction cost: 1.5 billion € for
Phase 1+2 Expected operating costs: 100+ million
€/year Energy costs a big contributing factor
Currently funded SKA R&D (2007-2012) via national and regional projects: 140 M€ PrepSKA (FP7) funds the SPDO engineers Design Studies (FP6 SKA Design Study, US Tech Dev Program) Pathfinders (ASKAP, MeerKAT, LOFAR, Apertif, ATA, MWA, LWA, EVLA, eMERLIN, eEVN)
Key dates
2008-2012 costed system design 2012 site selection2012-2013 agreement on construction
funding2012-2016 Phase 1 implementation2016 early science with Phase 12016-2021 construction of full array at
low and mid-frequencies
06 | 08 | 10 | 12 | 14 | 16 | 18 | 20 | 22 | 24 |
System DesignSystem Design Full SKA mid + low Full SKA mid + low construction and construction and commissioningcommissioning
SKA-high SKA-high ConstructionConstruction
Sites short-listed
EC-FP7: PrepSKA
System design Verification Programs
Funding Governance
Site Selection
Preliminary SKA specs External
Engineering Review of design
Reference Design selected
Pathfinder Suite Construction
SKA-mid+lowSKA-mid+lowCompleteComplete
Phase 1 Phase 1 funding funding approvalapproval
System System design design SKA-hiSKA-hi
Pathfinder science
Phase 1 complete
Concept Concept DesignDesign
SiteSelect
Concept design for Concept design for SKA-highSKA-high
SKA timeline
Prod. Readiness
Review
Early Science SKA mid+low
SKA Operations
Phase 2 funding approval
Phase 1 Prod. Eng. & Tooling
Phase 1 Construction
Solar power array in Portugal
2550 elements each 150 m2
Spread over an area 2km in diameter
Azimuth rotation
Erected in one year
Artist’s impression of the SKA
1000- 1500 dishes (15m) in the central 5 km 2000-3000 total+ dense and/or sparse aperture arrays
Alternatively…….
PrepSKAFormal PrepSKA partners
Agencies STFC (UK), NWO (NL), CNRS (FR), INAF (IT),
DIISR (AU), NRF (ZA), NRC-HIA (CA) Institutes
ASTRON (NL), Cornell/NAIC (USA), CSIRO (AU), IT (PT), JIVE (Europe), MPIfR (DE), OBSPAR (FR), RuG (NL), UCal (CA), UK (UCam, UMan, UOxf), UOrl (FR),
Other organisations involved in studyNSF(USA), AUI(USA), FG-IGN(EC), VR(SE),
SKA Program Development Office (SPDO)
7 Work Packages
PrepSKA organisation
WP2
Deliverables(Peter Dewdney “Guiding Principles, Activities and Targets for
WP2”)
Technology selection System Design
including operational – construction tradeoffs
Science Performance vs Reference Science Mission Total cost estimate for Baseline Design (incl.
contingency) Risk assessment Design and deployment plan Top-level build schedule Upgrade paths
WP2 approach Streamline WP2 Description of Work
Move from 40 technology development tasks, including an ill-defined ‘IVS’ to assembly and verification of large SKA sub-systems
Easily evaluated by EC and Funding Agencies/Governments
Dish Verification Program
PAF Verification Program
AA Verification Program
Signal transport Verification Program
…..
+
MoAs with organisations and institutes
WP3 – Additional Site Studies
Inform decision-making process for site selection
– Carry out further RFI measurements (in progress)
– RQZ (in progress)– Investigate infrastructure deployment
costs and timescales– Detailed risk analysis– Array configuration (in progress)– Ionosphere (in progress)– Tropospheric water vapour
WP4, WP5
WP4 – Governance and Legal Framework (led by NWO, NL)Study of options for viable models of governance and a
legal framework for SKA during construction and operation
Interim legal entity for SPDO during PrepSKA?
WP5 – SKA Procurement and industrial involvement (led by INAF, Italy)Lay out options for procurementInvestigation of the optimum way to involve industry in
the global, regional and national contexts
WP6, WP7 WP6 – Developing the funding model
(led by STFC, UK)Investigate all aspects of the financial model for lifetime
costs of the SKAIssues: phasing of SKA and ELTs
what constitutes a “mature” project? post-PrepSKA funding
how to value in-kind contributions pre-construction
Investigate options for loan from European Investment Bank and other similar bodies to provide a smooth funding profile
WP7 – Implementation plan (led by Co-ordinator)Investigate socio-economic and knowledge impact of the
SKAIntegrate output of all other partners to produce a
detailed, costed design for Phase 1 of the SKA and an implementation plan for the full SKA.
SPDO TeamProject Director Richard SchilizziProject Engineer Peter Dewdney Project Scientist Joe LazioExecutive Officer Colin GreenwoodSystem Engineer Kobus Cloete Domain Specialist Receptors Neil Roddis Domain Specialist Signal Transport Roshene McCool Domain Specialist Computing & Softw Duncan Hall
(starting January)Domain Specialist Signal Processing not yet filledSite Engineer Rob Millenaar Project Management Officer Billy Adams
(starting January)Industry Relations Manager to be advertisedOutreach Officer Ian MorisonOffice Manager Lisa Bell
Support Engineers (4-5x) to be advertised
In –kind contributions Call for submissions – deadline 31 October
2008 7 responses (ASTRON, CSIRO, INAF, JPL,
McGill/Laval Universities, NRAO, NRC Canada)
Contributions Audit CommitteePaul Mantsch (chair, Spokesperson for Pierre Auger Collaboration)Ethan Schrier (US)Jim Ulvestad (US)Arnold van Ardenne (Europe)Wim Brouw (Europe)Lewis Ball (Australia)Faranah Osman (South Africa)
Audit Committee to make recommendations to SSEC by February 2009
Issues How is the in-kind contributions register
going to be used by the Funding Agencies?
What is the “value” to the international SKA program of the submissions to the in-kind register?
Should we only consider contributions in the PrepSKA era?and/or
Only those contributions that made mention of the SKA in the original proposals?