sp-1024 rev 1

36
 ABU DHABI MARINE OPERATING COMPANY  Document Ref.: SP-1024 Control Sheet ADMA-OPCO STANDARD ENGINEERING DOCUMENTS PAGE Page 1 of 36 D O C U M E N T DESIGNATION SP-1024 SPECIFICATION FOR CONCRETE WE IGHT COATING OF SUBSEA PIPELINE TITLE AUTHORITY NAME TITLE B.UNIT / DIV SIGNATURE DATE TECHNICAL CUSTODIAN Mohamed Yehia SPE P&E/ DED TECHNICAL Amr Mohamed Azouz SPETL P&E/ DED STANDARDS Khaled Tawfik Hendy ESQASL P&E/ DED APPROVAL Hisham Awda MDE P&E/ DED ENDORSEMENT Ali Ghanim Bin Hamoodah SVP-PE P&E CONTROL STAMP The soft copy of this document on ADMA-OPCO Web is Controlled. When printed, it is considered Uncontrolled 1 07/2011 Issued for Implementation Rev. DATE DESCRIPTION/TE XT AFFECTED SF / General / 001 Rev.0 sheet 1 of 1 COPYRIGHT © ABU DHABI MARINE OPERATING COMPANY - ADMA-OPCO  All rights reserved. The information contained in this document is regarded as confidential. Recipient(s) other than ADMA- OPCO's employees undertake both during the continuance of their services to ADMA-OPCO and after termination to maintain in safe custody and not to use any such information for any purpose other than a purpose falling within the scope of the Agreement or Contract under which this document was supplied. Recipient(s) further agree not to dispose of, make copies, in whole or in part of such information or permit the use or access of the same by any Third Party unless the prior written  permissio n of ADMA-OPCO Manager Disciplines Eng ineering is obtained.

Upload: nicholas-waters

Post on 11-Oct-2015

52 views

Category:

Documents


0 download

TRANSCRIPT

  • ABU DHABI MARINE OPERATING COMPANY

    Document Ref.:

    SP-1024 Control Sheet

    ADMA-OPCO STANDARD ENGINEERING DOCUMENTS PAGE

    Page 1 of 36

    D

    O

    C

    U

    M

    E

    N

    T

    DESIGNATION SP-1024

    SPECIFICATION

    FOR

    CONCRETE WEIGHT COATING OF

    SUBSEA PIPELINE

    TITLE

    AUTHORITY NAME TITLE

    B.UNIT

    /

    DIV

    SIGNATURE DATE

    TECHNICAL CUSTODIAN

    Mohamed Yehia SPE P&E/

    DED

    TECHNICAL Amr Mohamed Azouz SPETL

    P&E/

    DED

    STANDARDS Khaled Tawfik Hendy ESQASL P&E/

    DED

    APPROVAL Hisham Awda MDE P&E/

    DED

    ENDORSEMENT Ali Ghanim Bin Hamoodah SVP-PE P&E

    CONTROL STAMP

    The soft copy of this document

    on ADMA-OPCO Web is

    Controlled. When printed, it is considered

    Uncontrolled

    1 07/2011 Issued for Implementation

    Rev. DATE DESCRIPTION/TEXT AFFECTED

    SF / General / 001 Rev.0 sheet 1 of 1

    COPYRIGHT ABU DHABI MARINE OPERATING COMPANY - ADMA-OPCO

    All rights reserved. The information contained in this document is regarded as confidential. Recipient(s) other than ADMA-

    OPCO's employees undertake both during the continuance of their services to ADMA-OPCO and after termination to maintain

    in safe custody and not to use any such information for any purpose other than a purpose falling within the scope of the

    Agreement or Contract under which this document was supplied. Recipient(s) further agree not to dispose of, make copies, in

    whole or in part of such information or permit the use or access of the same by any Third Party unless the prior written

    permission of ADMA-OPCO Manager Disciplines Engineering is obtained.

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    2

    SF / General / 002 Rev.0 sheet 1 of 1

    Liability for utilization by personnel/organizations outside ADMA-OPCO Whilst every effort has been made to ensure the accuracy of this document, neither ADMA-OPCO nor its employees will assume liability for any application or use outside ADMA-OPCO premises/assets.

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    3

    SF / General / 002 Rev.0 sheet 1 of 1

    TABLE OF CONTENTS

    1. INTRODUCTION ....................................................................................................................... 5

    1.1 SCOPE ........................................................................................................................................ 5 1.2 COVERAGE ............................................................................................................................... 5 1.3 EXCLUSIONS ............................................................................................................................ 5 1.4 REFERENCES ............................................................................................................................ 5 1.5 ABBREVIATIONS ..................................................................................................................... 6 1.6 DEFINITIONS ............................................................................................................................ 6 1.7 USE OF LANGUAGE ................................................................................................................ 6 1.8 UNITS ......................................................................................................................................... 7 1.9 LESSONS LEARNED ................................................................................................................ 7 1.10 SITE CONDITIONS & DATA ................................................................................................... 7

    2. QUALITY ASSURANCE .......................................................................................................... 8

    2.1 QUALITY ASSURANCE SYSTEM .......................................................................................... 8 2.2 QUALITY PLAN ........................................................................................................................ 9 2.3 INSPECTION AND CERTIFICATION REQUIREMENTS ..................................................... 9

    3. CONCRETE WEIGHT COATING MATERIALS AND REINFORCEMENT ............. 10

    3.1 CEMENT .................................................................................................................................. 10 3.2 AGGREGATES ........................................................................................................................ 10 3.3 WATER ..................................................................................................................................... 11 3.4 CONCRETE MIXING .............................................................................................................. 12 3.5 REINFORCEMENT ................................................................................................................. 12 3.6 CURING COMPOUND ............................................................................................................ 12

    4. PROPERTIES OF THE CONCRETE WEIGHT COATING ........................................... 13

    4.1 CONCRETE MIX DESIGN ..................................................................................................... 13 4.2 BATCHING PLANT ACCURACY ......................................................................................... 13

    5. APPLICATION ......................................................................................................................... 13

    5.1 PIPE LENGTH PREPARATION ............................................................................................. 13 5.2 INSTALLATION OF REINFORCEMENT ............................................................................. 14 5.3 PLACING OF THE CONCRETE WEIGHT COATING ......................................................... 15

    6. TESTING AND INSPECTION OF CONCRETE ................................................................ 17

    6.1 TESTING .................................................................................................................................. 17 6.2 INSPECTION ............................................................................................................................ 20 6.3 QUALIFICATION TESTS ....................................................................................................... 20 6.4 INSPECTION AND TEST PLAN ............................................................................................ 20

    7. REPAIRS AND CAUSES OF REJECTION ......................................................................... 21

    7.1 REPAIR OF SPALLING .......................................................................................................... 21 7.2 CRACKING .............................................................................................................................. 21 7.3 CAUSES FOR REJECTION ..................................................................................................... 22

    8. DOCUMENTATION AND REPORTING ............................................................................ 23

    8.1 PRODUCTION AND TEST REPORTS ................................................................................... 23

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    4

    SF / General / 002 Rev.0 sheet 1 of 1

    9. MARKING OF CONCRETE WEIGHT COATED PIPE .................................................. 24

    9.1 COLOUR IDENTIFICATION .................................................................................................. 24

    10. STORING AND HANDLING CONCRETE WEIGHT COATED PIPE ......................... 24

    10.1 HANDLING OF PIPE AFTER COATING .............................................................................. 24 10.2 HANDLING OF PIPE FOR LOAD-OUT ................................................................................ 24 10.3 PIPE HANDING OVER CERTIFICATION ............................................................................ 24

    11. CATHODIC PROTECTION (SACRIFICIAL ANODES) ................................................. 25

    11.1 ANODES ................................................................................................................................... 25 11.2 METHOD OF ATTACHMENT ............................................................................................... 25 11.3 TESTING AND INSPECTION ................................................................................................ 26 11.4 STORING, STACKING AND HANDLING OF PIPE WITH ANODES FITTED ................. 26

    APPENDIX-A: CALCULATION OF NEGATIVE BUOYANCY .............................................. 27

    A1 FORMULA FOR COMPUTING "AS APPLIED" NEGATIVE BUOYANCY FOR CONCRETE FITTED PIPE ............................................................................................................. 27

    A2 FORMULA FOR COMPUTING "AS APPLIED" NEGATIVE BUOYANCY FOR ANODE FITTED & CONCRETED PIPES .................................................................................... 29

    APPENDIX-B: CONCRETE COATING DATA SHEET ............................................................ 32

    APPENDIX-C: ABBREVIATIONS ................................................................................................. 33

    APPENDIX-D: DEFINITIONS ........................................................................................................ 34

    APPENDIX-E: REFERENCED DOCUMENTS............................................................................ 35

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    5

    SF / General / 002 Rev.0 sheet 1 of 1

    1. INTRODUCTION

    1.1 Scope

    This Specification is intended to provide & highlights the minimum basic

    requirements for materials and application of uniform concentric reinforced concrete

    weight coating for ADMA-OPCO subsea pipelines and shall not relieve the

    Contractor of his contractual obligations. Any deviation from this Specification shall

    be identified by Contractor and shall require written approval from ADMA-OPCO.

    1.2 Coverage

    This Specification covers concrete coating application, inspection, repairs, coated

    pipes handling and storage at coating plant.

    1.3 Exclusions

    This Specification excludes coated pipes transportation and any intervention works

    outside the coating plant.

    1.4 References

    1.4.1 General

    The latest edition (at the time of the contract award) of the reference documentation

    as listed in Appendix-E shall be read as an integral part of this Document.

    The latest edition/revision of ADMA-OPCO Standard Engineering Documents as

    indicated in Status List SL-001 shall be utilized.

    1.4.2 Equivalent Standards

    Standard Documents equivalent to those referred to herein shall not be substituted

    without written approval from ADMA-OPCO. Approval of equivalent Standard

    Documents will not, in any way, release/relieve responsibility from the Contractor to

    meet the best practices and/or requirements of the Standard Engineering Documents

    referred to herein, in the event of conflict.

    Where differences and/or conflicting issues occur between the referenced documents

    themselves or the requirements of this document, the requirements of this document

    shall overrule unless otherwise advised by ADMA-OPCO. However, major conflicts

    shall be reported in writing to the ADMA-OPCO Standards Authority/Technical

    Custodian nominated in the front sheet of this document for determination.

    The following hierarchy of adherence to standards shall be followed:

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    6

    SF / General / 002 Rev.0 sheet 1 of 1

    a. Whenever ADMA-OPCO Standard Engineering Documents (SEDs) relevant to the system, service and/or equipment design are available, the same shall be

    utilized first.

    b. ADMA-OPCO Shareholder SEDs (tailored to suit ADMA-OPCO needs) shall be utilized next in the hierarchy, if the relevant subject is not covered by

    ADMA-OPCO Standards.

    c. National or International standards (tailored to suit ADMA-OPCO needs) shall

    be utilized, if the required subject is not covered either by ADMA-OPCO or

    Shareholder SEDs.

    The Contractor shall equip himself with copies of all the referenced Standard

    Engineering Documents referred in Appendix-E of this Document and shall make

    them readily available to all ADMA-OPCO, or nominated representative, personnel

    involved in the work.

    1.5 Abbreviations

    The abbreviations used in this Specification are listed in Appendix-C.

    1.6 Definitions

    The definitions used in this Specification are listed in Appendix-D.

    1.7 Use of Language

    Throughout this document, the words will, may/can, should and shall/must, when used in the context of actions by ADMA-OPCO or others, have specific

    meanings as follows:

    a. Will is used normally in connection with an action by ADMA-OPCO and / or nominated representative, rather than by a Contractor or Vendor.

    b. May / Can is used where alternatives / action are equally acceptable.

    c. Should is used where provision is preferred.

    d. Shall / Must is used where a provision is mandatory / vital.

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    7

    SF / General / 002 Rev.0 sheet 1 of 1

    1.8 Units

    Units shall be in accordance with ADMA-OPCO STD-00, Part-1.

    1.9 Lessons Learned

    Upon completion of works related to the scope of this document, a descriptive

    summary of lessons learned shall be prepared and made available by the

    Contractors/Consultants/Job Officer and shall be forwarded to ADMA-OPCO

    Lessons Learned System as appropriate.

    1.10 Site Conditions & Data

    Site Conditions & Data of existing ADMA-OPCO facilities (Umm Shaif and Zakum

    fields) shall be in accordance with ADMA-OPCO STD-00, Part-2. For new Fields

    development, project specific requirements should be followed or refer to ADMA-

    OPCO.

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    8

    SF / General / 002 Rev.0 sheet 1 of 1

    2. QUALITY ASSURANCE

    2.1 Quality Assurance System

    2.1.1 All activities and services associated with the scope of this Specification shall be

    performed by Contractors/Vendors approved by ADMA-OPCO.

    2.1.2 The Contractor/Vendor shall operate Quality Management Systems (QMS) within

    his organizations, which ensure that the requirements of this Specification are fully

    achieved.

    2.1.3 The Contractor/Vendors Quality Management System shall be based on ADMA-OPCO Specification SP-1009 or the latest issue of ISO 9001 Series and accredited by

    an international certifying agency.

    The Contractors Quality Manual shall provide details for the preparation of a Quality Plan, which shall include provisions for the QA/QC of services activities.

    Where an approved Contractor/Vendor revises their Quality Management System

    that affect the ADMA-OPCO approved Quality / Inspection and Test Plan, then the

    revised Quality Plan / Inspection and Test Plan shall be submitted for ADMA-OPCO

    approval before initiating any service activities.

    2.1.4 The effectiveness of the Contractors Quality Management System may be subject to monitoring by ADMA-OPCO or its representative and may be audited following an

    agreed period of notice.

    2.1.5 The Contractor/Vendor shall make regular QA audits on all their Sub-

    Contractors/Suppliers. Details of these audits shall be made available to ADMA-

    OPCO when requested.

    2.1.6 The Contractor/Vendor shall maintain sufficient Inspection and Quality Assurance

    staff, independent of the service provider management, to ensure that the QMS is

    correctly implemented and that all related documentation is available.

    2.1.7 Using Sub-Contractors is not allowed for services/functions carried out by a

    Contractor without ADMA-OPCO approval.

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    9

    SF / General / 002 Rev.0 sheet 1 of 1

    2.2 Quality Plan

    2.2.1 Contracted activities shall be performed in accordance with an approved Quality Plan

    (QP).

    2.2.2 The level of detail required in the Quality Plan shall be commensurate with the scope

    of services provided.

    2.2.3 The quality of works is an essential factor in carrying out all services & activities

    covered by this Document.

    2.2.4 During services/activities, Quality Assurance/Quality Control issues are the

    responsibility of the Contractor, and shall be approved and certified by TPA.

    2.2.5 Conflicts between Contractor & TPA shall be reported in writing to ADMA-OPCO

    for resolution.

    2.3 Inspection and Certification Requirements

    Inspection and certification requirements for material shall be certified to ADMA-

    OPCO CP-102 and BS EN 10204.

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    10

    SF / General / 002 Rev.0 sheet 1 of 1

    3. CONCRETE WEIGHT COATING MATERIALS AND REINFORCEMENT

    3.1 Cement

    All cement used for the preparation of the concrete shall comply with the following

    requirements:

    a. Certified by the supplier to be in compliance with the requirements of ASTM C150 Type V.

    b. The cement shall be adapted for sea water hardening and shall resist the effects of sulphates.

    c. Identified with the following information on the certification and delivery documents for each shipment of cement:

    c1. Cement producer's name and location,

    c2. Product description including type and classification of cement,

    c3. Year and month of production.

    d. Handled, transported and stored in compliance with the cement manufacturer's recommendations and the applicable standards.

    e. No more than six months from the date of manufacture, unless it is retested and proven to be in compliance with the original standard.

    f. Cement shall be stored in covered areas or covered by plastic sheeting if supplied in bags. Bulk cement shall be stored in water proof containers.

    g. Cement that has hardened, partially hardened or become lumpy shall be rejected.

    h. Test certificates from the cement manufacturer shall be supplied for every cement delivery to site.

    3.2 Aggregates

    3.2.1 Sand (Silica Type)

    Sand aggregates used shall be round grained and shall be obtained by sieving. Sand

    shall be free of injurious amounts of salt, alkali, deleterious substances, or organic

    impurities. Natural sand and aggregate shall conform to BS EN12620 or ASTM C 33

    requirements.

    Sand grading shall be within the range of values as shown in Table 3.2.1 herein under

    Mesh size, as per

    ASTM C 33

    Per Cent Passing

    Minimum Maximum

    4.75 mm -- 100

    2.36 mm 80 100

    1.18 mm 50 100

    600 microns 25 60

    300 microns 5 30

    150 microns 0 10

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    11

    SF / General / 002 Rev.0 sheet 1 of 1

    3.2.2 Heavy Aggregate

    Heavy aggregates made of crushed iron ore or barites shall conform to BS EN 12620

    or ASTM C 33 requirements.

    A maximum size of 9.52mm aggregate shall be added to the mixture to achieve the

    required negative buoyancy after submersion in sea water.

    The aggregate gradation shall be within the range of values shown in Table 3.2.2

    below:-

    Mesh size, as per

    ASTM C 33

    Per Cent Passing

    Minimum Maximum

    9.52 mm 100 -

    4.75 mm 100 -

    2.36 mm 80 100

    1.18 mm 50 85

    600 microns 10 30

    300 microns 5 30

    150 microns 0 10

    Table 3.2.2 Aggregate Grading

    N.B:

    a. The heavy aggregate shall be clean and free of clay, organic and deleterious

    materials.

    b. The cleanliness of the aggregate shall be controlled by screening at the crusher.

    c. The aggregate shall be stored on paved area to avoid its contamination.

    3.3 Water

    Water used in the production of concrete shall comply with BS EN 1008. The water

    shall be clean and free from oils, acids, alcohols, salts or organic materials. Water that

    is potable does not require further testing for compliance.

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    12

    SF / General / 002 Rev.0 sheet 1 of 1

    3.4 Concrete Mixing

    3.4.1 The total amount of chlorides in the concrete mix, calculated as the free calcium

    chloride (CaCl2) shall not exceed 0.15% of the weight of cement.

    3.4.2 The total amount of sulphates in the concrete mix, calculated as sulphur trioxide

    (SO3) shall not exceed 3.5% of the weight of cement.

    3.4.3 The constituent parts of the concrete mix shall be weigh-batched using a weigh-

    batching plant of suitable design. The weigh-batcher shall be accurate to within 2%

    of the indicated values.

    3.4.4 A water gauge accurate to within 3% of the indicated values shall be used for

    adding water to the mix.

    3.5 Reinforcement

    3.5.1 The reinforcement shall be manufactured from high quality billet steel conforming to

    ASTM A 810 or approved equivalent, formed into galvanized wire mesh/fabric

    reinforced type. The wire shall be galvanized before weaving.

    3.5.2 The resultant proportion of reinforcement shall not be less than 0.5% of the cross

    sectional area of the weight coat taken in the plane perpendicular to the longitudinal

    axis of the pipe and shall be not less than 0.08% of the circumferential axis of the

    pipe as given in DNV-OS-F101.

    3.6 Curing Compound

    The curing compound shall be of a type approved by ADMA-OPCO and shall be

    evenly applied over the complete surface of the concrete. The curing compound shall

    be prepared and applied in strict conformity with the manufacturer's written

    instructions.

    The compound performance shall conform with ASTM C 309. Data sheets shall be

    submitted for ADMA-OPCOs approval.

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    13

    SF / General / 002 Rev.0 sheet 1 of 1

    4. PROPERTIES OF THE CONCRETE WEIGHT COATING

    4.1 Concrete Mix Design

    4.1.1 Concrete mixes shall be carried out in such a way that the required densities and

    strengths are obtained. To this end full details shall be furnished as follows:-

    a. The proportion and weights of the respective dry aggregates.

    b. The cement weight per cubic meter of concrete.

    c. The volume of water per cubic meter of concrete.

    d. The results of preliminary tests for water absorption.

    e. The density of the proposed mix.

    4.1.2 The component parts of the concrete shall be properly mixed to provide a

    homogenous and consistent mix. A number of mixes with different gradings, cement

    contents and water ratios shall be tested until the correct mix is attained.

    4.1.3 The proposed composition shall meet the minimum mechanical strengths and water

    absorption specified and shall ensure easy and satisfactory application of the concrete

    coating.

    4.1.4 The water/cement (W/C) ratio should not exceed 0.40 and shall not be less than 0.25,

    the cement content should not be less than 400 kg/m3.

    4.2 Batching Plant Accuracy

    The batching plant and water gauge accuracies should be within 3%. Calibration

    should be checked weekly during production.

    5. APPLICATION

    5.1 Pipe Length Preparation

    5.1.1 Prior to placing of reinforcements and anode bracelets, the whole anti-corrosion

    coating of each pipe length shall be visually inspected and if damages are found, they

    shall be repaired to the ADMA-OPCO approved specification before starting the

    placing of any concrete.

    5.1.2 After repairs, the anti-corrosion coating shall be electrically inspected using a holiday

    detector with minimum 20,000 volts.

    5.1.3 At the beginning of each work period, the length of the detector's spark shall be

    calibrated on sample with a known defect.

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    14

    SF / General / 002 Rev.0 sheet 1 of 1

    5.1.4 The appropriate output voltage shall be established either by:-

    a. Positioning the electrode away from the bare steel, the same distance as the

    coating thickness and increasing the voltage until a spark jumps the gap.

    b. Using a spark gap setter.

    5.1.5 The minimum operating voltage of the detector shall be maintained at or above the

    established level throughout the testing works.

    5.1.6 The maximum operating voltage for the electrode shall be established such that no

    damage to sound coating is caused, and this value shall not be exceeded during the

    testing.

    5.1.7 Pipes requiring mid-section supports, when so required during concrete placing, shall

    be adequately supported to prevent undue flexure during coating.

    5.1.8 The installation of anodes shall be performed in accordance with Clause 11.1.2 prior

    to the placing of concrete.

    5.2 Installation of Reinforcement

    5.2.1 The galvanized wire reinforcement shall be carefully placed around the pipe without

    causing damage to the anti-corrosion coating.

    5.2.2 The resultant proportion of reinforcement shall not be less than 0.5% of the cross

    sectional area of the weight coat taken in the plane perpendicular to the longitudinal

    axis of the pipe and shall be not less than 0.08% of the circumferential axis of the

    pipe.

    5.2.3 A minimum overlap of 25 mm is required for the spirally wound reinforcement.

    5.2.4 A single wrap of reinforcement can be applied if the concrete coating thickness is

    50mm or less. This wrap shall be a minimum of 15mm from the outside surface of the

    anti-corrosion coating except at the start of the winding operation. A double wrap of

    reinforcement shall be applied if the concrete coating exceeds 50mm.

    5.2.5 Additional wraps of reinforcement may be required to be applied for thickness in

    excess of 102mm. The number of additional wraps shall be determined in agreement

    with ADMA-OPCO according to the minimum cross sectional areas required by this

    specification and would be as shown in the Data Sheet, see Appendix-B of this

    Specification.

    5.2.6 The external wire mesh wrap shall have a minimum of 15mm of concrete cover.

    5.2.7 The concrete coated pipe shall be tested with an ohm-meter to ensure that there is no

    contact between the wire reinforcement and the pipe or anode.

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    15

    SF / General / 002 Rev.0 sheet 1 of 1

    5.2.8 Should the Contractor propose alternative reinforcement, then it shall be

    demonstrated to the satisfaction of ADMA-OPCO that it provides similar benefits to

    the reinforcement specified above. The Contractor shall, specify the alternative type

    of reinforcement and the methods to be used to prove the adequacy of the alternative

    design, for acceptance by ADMA-OPCO.

    5.3 Placing of the Concrete Weight Coating

    5.3.1 General Method

    a. The concrete coating shall be placed by impingement. In all cases, each pipe joint shall be coated in a continuous operation and in such a manner that the concrete is

    applied uniformly throughout the total length and free from any abrupt

    irregularities or variations in thickness.

    b. If more than one application is required, the total time allowed for the completion of the operation shall not exceed 30 minutes.

    c. The application method in all cases, shall ensure that the concrete coating satisfies the minimum requirements of this Specification for:-

    c1. Concrete coating sizing and shaping.

    c2. Concrete coating specific gravity.

    c3. Concrete coating water absorption.

    c4. Concrete coating compression strength.

    c5. Emplacement of reinforcement.

    c6. Negative buoyancy.

    5.3.2 Pipe Length with Anodes or Mid-Section Supports

    a. The placing of concrete coating on those pipe lengths which have anodes attached or mid-section supports shall be performed in such a way so that the concrete

    coating is terminated 30mm from the anode or mid-section support.

    b. The procedure for handling this pipe before and after concrete application shall be submitted for ADMA-OPCO approval.

    c. The procedure for coating small diameter pipe with mid-section supports shall be submitted for ADMA-OPCO approval.

    5.3.3 Time Limitations

    In all cases, the time interval from adding water to the mix and final placing of the

    concrete shall not exceed 30 minutes.

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    16

    SF / General / 002 Rev.0 sheet 1 of 1

    Concrete placing shall be completed as quickly as possible and the surface of the

    concrete covered to prevent rapid evaporation.

    5.3.4 Curing of the Concrete

    a. The curing compound shall be applied to the exposed surfaces immediately after concrete application and shall be evenly applied over the complete surface of the

    concrete. The curing compound shall be prepared and applied in strict conformity

    with the manufacturers written instructions. Number of coats shall be determined and applied as per manufacturers recommendation to ensure complete coverage. Data sheets shall be submitted for ADMA-OPCOs approval.

    b. The use of curing membranes, polyethylene sheet wrapping membranes or coatings shall generally be permitted but the Contractor must provide means to

    satisfy the water absorption tests specified in Clause 6.1.2.

    c. The concrete coated pipe shall be stored in a single layer for a minimum period of 3 days and until a minimum compressive strength of 2100 psi is achieved.

    d. All concrete coated pipes shall be cured for a minimum of 10 days and until a minimum compressive strength of 3850 psi is achieved. No concrete coated pipe

    shall be skipped from the coating plant without satisfying both conditions unless

    otherwise specified by ADMA-OPCO.

    5.3.5 Reclaimed/Rebound Material

    The amount of reclaimed material used shall not exceed 5 percent of total mix by

    weight and shall not be added in an even flow during continuous coating operation.

    The reclaimed material is used within less than 10 minutes from the time when it was

    originally mixed.

    5.3.6 Cutback

    The non-concrete coated section "cutback" at the ends of each pipe length shall

    typically be 300mm to 330mm, the cutback may extend to 400mm to satisfy the

    requirement of welding machine in case of automatic welding. The ends and inside of

    the pipe shall be free of concrete debris. The cutback should be square shoulder

    section unless otherwise specified by the project requirements.

    5.3.7 Tolerances

    The concrete coating shall be concentric with the pipe and have a thickness equal to

    the nominal thickness calculated from the specified pipe dimensions and required

    submerged weight taken from pipeline data sheet.

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    17

    SF / General / 002 Rev.0 sheet 1 of 1

    6. TESTING AND INSPECTION OF CONCRETE

    6.1 Testing

    6.1.1 Compressive Strength and Density of the Concrete

    a. The concrete coating compressive strength shall be checked by means of test cubes and core samples.

    b. Minimum dry densities measured after a minimum of 10 days shall be 3040 kg/m3

    (190 lb/cu.ft).

    c. The method of determining dry density must be provided for ADMA-OPCO approval.

    d. No change will be authorized without the written approval of ADMA-OPCO.

    e. The compressive strength shall be a minimum of 3600 psi at 7 days and a minimum of 5000 psi at 28 days. The strength shall be measured on test cubes and

    core samples as follows.

    e1. Cube Samples

    Cube samples shall be taken every 4 hours at every mix change and after every

    shutdown period with a minimum of 2 cubes samples taken per occurrence.

    e2. Core Samples

    e2.1 Where the coating is applied by the impingement or "Compression Coat"

    processes the concrete strength shall be determined by removing 1 core from

    the coating on one pipe to be selected from every ten pipes by ADMA-OPCO.

    The cores shall be extracted using a diamond core cutter modified to ensure

    that the core is cut perpendicular to the coating surface. Cores shall be

    removed in such positions that the main reinforcement will not be

    damaged. Should the main reinforcement be damaged then that section of

    weight coating shall be removed and recoated, or repaired by agreement with

    ADMA-OPCO. The core cutter shall have a positive depth of cut limit stop

    fitted to ensure that the core barrel cannot penetrate to within 8 mm of the

    pipe wrapping.

    e2.2 At least 2 core samples shall be drilled from the concrete weight coating on

    every 20th pipe length.

    e2.3 The diameter of core specimens shall be at least 50mm (preferably 75mm). A

    single core diameter shall be used throughout the job.

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    18

    SF / General / 002 Rev.0 sheet 1 of 1

    e2.4 The height to diameter (h/d) ratio shall be, as nearly as practicable, equal to

    2.0. A core having a height of less than its diameter (h/d 1.0) after capping

    shall not be tested.

    e2.5 Evaluation of test results shall be carried out in accordance with BS EN

    12504-1 or ASTM C42

    e2.6 For samples failing these tests, 2 more samples shall be cored and tested. If

    the test on these 2 samples fails, no more samples shall be taken, and the

    concrete shall be rejected.

    e2.7 All pipe lengths on which such tests indicate that the concrete does not reach

    the minimum specified values shall be rejected.

    e2.8 The coring procedure and method of evaluation shall be subject to the

    approval of ADMA-OPCO. The equipment used must include positive means

    to ensure that the depth of cut leaves at least 8mm of undamaged concrete

    between the coring tool and the anti-corrosion coating.

    e2.9 Core holes shall not be filled without prior inspection by ADMA-OPCO.

    e2.10 The method of refilling core holes is subject to the approval of ADMA-OPCO

    and shall be in line with the requirements of Clause 6.2.4 of this specification.

    6.1.2 Water Absorption Test

    a. The water absorption test procedure shall be submitted to ADMA-OPCO for approval.

    b. A water absorption test shall be carried out at the beginning of production and subsequently on one pipe in every 150 pipes.

    c. Further water absorption tests shall be carried out in the laboratory on cube and core samples.

    d. The water absorption shall not exceed 5%.

    e. Water absorption exceeding 5% shall result in rejecting all pipe lengths represented by the test.

    6.1.3 Location of Reinforcement

    a. At the centre of the first pipe of each production shift a water jet shall be used to clear away the freshly placed concrete down to the anti- corrosion coating for an

    area approximately 50mm wide and 200mm long in the longitudinal direction.

    This exposed area (slot) shall be used to confirm that the reinforcement is

    positioned and covered with the concrete as specified.

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    19

    SF / General / 002 Rev.0 sheet 1 of 1

    b. If the reinforcement is not positioned correctly, the pipe shall be rejected and recoated. Each pipe in succession shall be inspected in this manner until the

    position of the reinforcement is acceptable. The repair of the inspection slot shall

    be as specified in Sub-section 7.1 of this Specification.

    6.1.4 Weight Control

    a. Pipe lengths shall be weighed using calibrated load cells. Calibration certificates for weighing equipment shall be provided for approval by ADMA-OPCO.

    b. At least once every shift, all weighing equipment used during the concrete coating operations shall be calibrated against a standard test weight of the same order of

    magnitude as a concrete coated pipe length.

    c. The weighing procedure shall be subject to approval by ADMA-OPCO.

    6.1.5 Negative Buoyancy

    a. Each pipe length shall be weighed immediately before and after concrete coating. Girth measurements at approximately 5 equidistant locations shall be taken, in

    order to calculate the average girth.

    b. The maximum permitted tolerances on negative buoyancy are for each pipe length, with or without an anode shall be as follows: -

    b1. Single pipe -2 % +10 %.

    b2. Shift Production -0 % +5 % calculated on the specified negative buoyancy.

    c. The negative buoyancy requirements are based on concrete in the as-applied condition, and not on concrete in a fully saturated condition.

    d. The formulae to be used in calculating the "as applied" negative buoyancy is as given in Appendix- A of this Specification.

    N.B:

    a. If the pipe requires additional concrete to increase the weight or thickness, the

    additional concrete shall be added within 30 minutes after the first concrete was

    applied.

    b. If the tolerances and conditions cannot be obtained, the pipe over its full length

    shall be stripped and recoated.

    c. For each pipe size and concrete thickness negative buoyancy limits based or

    pipeline data sheet shall be calculated and submitted for ADMA-OPCO approval.

    d. Separate procedure for weighing concrete coated and anode fitted pipes, and

    determination of negative buoyancy and density of weight coating shall be

    submitted for ADMA-OPCO approval.

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    20

    SF / General / 002 Rev.0 sheet 1 of 1

    6.1.6 Cleanliness

    Testing and inspection shall include regular check of cleanliness and grading of

    aggregates e.g. every third day during production.

    6.2 Inspection

    6.2.1 Every length of coated pipe shall be non-destructively tested, not less than 3 days

    after coating, by such means as "ringing" to determine whether any defects are

    present.

    6.2.2 Where this procedure indicates faulty coating, the Contractor shall remove cores from

    the suspected pipe. If these cores indicate defective concrete coating the, Contractor

    shall remove the coating by a method agreed with ADMA-OPCO. The coating shall

    not be replaced without the agreement in writing of ADMA-OPCO.

    6.2.3 Areas where coating has not adhered during placement or has been damaged

    subsequently (in particular the ends of the concrete coating), may be patch repaired

    by hand where the area of defective coating is not in excess of 0.1 sq. metre in any 1

    metre length of coated pipe. Any more extensive damage shall cause that section of

    pipe coating to be rejected.

    6.2.4 Patching shall be carried out only by removing the affected coating down to at least

    the reinforcement level, taking care not to damage the reinforcement, and making

    good the cavity using a similar mix to that used in the coating process with the

    addition of just sufficient water to allow hand application. A bonding agent or

    additive agreed by ADMA-OPCO shall be used, in strict accordance with the

    manufacturer's instructions. A similar mix shall be used to fill core holes after

    inspection of the holes by ADMA-OPCO.

    6.3 Qualification Tests

    Qualifications tests shall be performed in accordance with a procedure agreed

    between ADMA OPCO and the concrete coating Contractor and witnessed by the

    Third Party Agency.

    6.4 Inspection and Test Plan

    The Inspection and Test Plan shall be developed by the coating Contractor and

    approved by the Third Party Agency.

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    21

    SF / General / 002 Rev.0 sheet 1 of 1

    7. REPAIRS AND CAUSES OF REJECTION

    7.1 Repair of Spalling

    7.1.1 If spalling, due to impact or from improper application of the concrete is found to be

    not more than 25% of the depth of the coated surface. The following repairs shall be

    undertaken for each pipe length:

    a. If the damage zone is less than 1000 cm 2

    no repairs shall be undertaken.

    b. If the damage 2 surface is between 1000cm2 and 3000cm

    2, the concrete coating

    shall be repaired as follows:-

    b.l The concrete coating on the damaged area shall be removed until the

    reinforcement is visible and shall be undercut to ensure that a key lock is formed.

    Sufficient cover to the corrosion protection layer (min. 10mm) shall be

    maintained.

    b.2 The edges of the damaged zone shall be trimmed square.

    b.3 Fresh concrete shall be gunnited into the hole until the surface is at the same level

    with the surrounding coating around the repair.

    b.4 The repaired area shall be protected and properly cured to prevent rapid

    evaporation.

    b.5 The pipe shall be allowed to cure for a minimum of 48 hours.

    c. If the damage exceeds 3000 cm2, the coating shall be removed down to the

    corrosion coating on the entire periphery of the pipe at the damaged area. If

    damaged wire reinforcement shall be replaced. The cavity shall be refilled with

    fresh concrete of the required density as per the requirements of Sub-section 5.3

    of this Specification.

    7.1.2 If the depth of the spalled area exceeds 25% of the coating depth and the damage is

    less than 500cm2 and does not expose the anti-corrosive coating, then the procedure

    in Clause 7.1.b shall be followed. For damaged zones of 500cm2 or more, the

    procedure specified in point (c) above shall be followed.

    7.2 Cracking

    7.2.1 Every effort shall be made to avoid concrete cracking during handling or stockpiling

    operations.

    7.2.2 The following cracks shall be repaired:

    a. Deep cracks exceeding 1.6mm in width and extending for 180 or more

    circumferentially around the pipe.

    b. Cracks over 30 cm in length longitudinally along the pipe, irrespective of width.

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    22

    SF / General / 002 Rev.0 sheet 1 of 1

    7.2.3 Repairs shall be made by chiselling out the crack to a width of at least 2.5cm

    throughout the length of the crack. The crack shall then be refilled with fresh concrete

    having a density equal to that originally applied. A suitable additive to render the

    concrete shrinkage free shall be used. However, the additive type shall be approved

    by ADMA-OPCO prior to its use.

    The pipe shall then be allowed to cure for a minimum of 48 hours.

    7.3 Causes for Rejection

    Causes for rejection of the concrete coating shall include, but not be limited to, the

    following:-

    7.3.1 Negative Buoyancy

    Negative buoyancy less than or greater than the tolerances allowed in Clause 6.1.5 of

    this Specification.

    7.3.2 Concrete

    Concrete which does not meet the specified requirements.

    7.3.3 Reinforcement

    Improper placement of the reinforcement.

    7.3.4 Spalling

    a. If the damage of the surface extends to the anti-corrosive coating. A holiday

    detection shall be made of the anti-corrosion coating before the concrete is re-

    applied.

    b. If the damaged zone is more than 3000cm2.

    7.3.5 Handling

    Pipe coating damaged during handling operations shall be treated as per Sub-section

    7.1 of this Specification.

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    23

    SF / General / 002 Rev.0 sheet 1 of 1

    8. DOCUMENTATION AND REPORTING

    8.1 Production and Test Reports

    The Contractor shall submit to ADMA-OPCO for approval example of all reports

    required to document accurately the production, testing and reporting.

    As a minimum, the following shall be recorded for each and every pipe length:

    a. Serial number.

    b. Length meters.

    c. Condition of end bevels and surface receipt.

    d. Weight (bare) (kg).

    e. Weight after concrete coating (kg).

    f. Fitted with anode if applicable.

    g. Date and time of placement of coating.

    h. Calculated fully saturated negative buoyancy.

    i. Details of water absorption test.

    j. Concrete details including;

    j.l Quantity and type of cement, sand & aggregate,

    j.2 Quantity of water and density of mix,

    j.3 Crushing strength,

    j.4 Thickness of coating.

    k. Conditions of end bevels on shipping.

    l. Colour Code.

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    24

    SF / General / 002 Rev.0 sheet 1 of 1

    9. MARKING OF CONCRETE WEIGHT COATED PIPE

    9.1 Colour Identification

    Contractor shall propose the colour coding requirements.

    It shall be necessary to ensure that every concrete coated pipe has at one end indelibly

    marked circumferential band to show the specific gravity.

    10. STORING AND HANDLING CONCRETE WEIGHT COATED PIPE

    10.1 Handling of Pipe after Coating

    10.1.1 After completion of the concrete weight coating the pipe shall be carefully handled

    during removal from the coating machine to the curing yard.

    10.1.2 The pipe shall remain in a single layer for a minimum of 3 days before being removed

    from the curing yard and until a minimum compressive strength of 2100 psi is

    achieved.

    10.1.3 The maximum allowable stacking heights of concrete weight coated pipe shall be

    determined so that no pipe is overstressed and coatings are not damaged.

    10.1.4 Pipe with anodes fitted shall always be stacked on the top of the stockpile, without

    exception.

    10.2 Handling of Pipe for Load-out

    The procedure for handling concrete weight coated pipe to an appointed load-out

    location and loading onto trucks, barges or supply boats shall be subject to prior

    approval by ADMA-OPCO.

    10.3 Pipe Handing Over Certification

    It shall be necessary on completion of all load-outs, to issue, in respect to each and

    every pipe, a "Pipe Handing Over" certificate.

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    25

    SF / General / 002 Rev.0 sheet 1 of 1

    11. CATHODIC PROTECTION (SACRIFICIAL ANODES)

    Cathodic Protection shall be in accordance with ADMA-OPCO Specification SP-1053 and

    the following:-

    11.1 Anodes

    11.1.1 Number and Location

    When a single anode is to be installed, it shall be placed approximately at the mid

    point of the pipe.

    Where two anodes are to be installed on a pipe they shall be placed at approximately

    1/3 of the pipe length from each pipe end.

    11.1.2 Installation

    Each anode must be securely attached so that it cannot be rotated and no damage

    should be inflicted to the corrosion coating. After bolting the straps must be

    tackwelded to insure continuity. The anode external diameter should be the same as

    the concrete coating and must not protrude beyond the weight coating thickness.

    11.2 Method of Attachment

    11.2.1 Electrical Connections

    Connections shall be made by connecting strips, which are to be bolted or welded

    between the 2 halves of the anode bracelet.

    Each half bracelet shall be attached to the pipe by two 16mm2 diameter double layer

    PVC insulated copper cables.

    Connections shall be made to the ADMA-OPCO approved thermo weld method.

    11.2.2 Coating of Anodes and Connections

    After completion of the connections and testing of the electrical continuity, two pack

    patching compound / paint shall be applied, to the connecting strips.

    11.2.3 Concrete Weight Coating Application

    Concrete weight coating shall be applied in the same manner as for the pipe without

    bracelets, except that the concrete coating is terminated 30mm from each side of the

    anode. The gap shall be filled with HDPUF infill material to same diameter of

    Concrete Coating. Same concrete mix may be used as a filler material between the

    anode and the concrete coating after ADMA OPCOs approval.

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    26

    SF / General / 002 Rev.0 sheet 1 of 1

    11.3 Testing and Inspection

    11.3.1 An electrical continuity test shall be performed prior to the coating of the connection

    strips.

    11.3.2 On completion of concrete weight coating, a further electrical continuity test shall be

    performed to confirm that there is no contact between the reinforcement wire and the

    anodes.

    11.4 Storing, Stacking and Handling of Pipe with Anodes Fitted

    11.4.1 Storing & Stacking

    a. Stacking calculations shall be provided for ADMA-OPCOs approval.

    b. Concrete coated pipe shall be stacked only after the concrete has attained the minimum required design strength.

    c. The pipe shall be stacked on a minimum of two loose graded sand windrows at least 15 cm deep and not less than 2 m wide (each), approximately 7 m apart, and

    shall not be separated by bearers.

    d. The pipe shall be carefully lowered to limit impact effects and stacked in such a way that water, mud and sand cannot accumulate within the pipe.

    e. Pipe with anodes fitted shall be carefully removed from the curing yard and stacked on top of the stockpipe.

    11.4.2 Handling

    In the case of small diameter pipe, it shall be necessary to utilize a three point lifting

    system. Contractor shall submit to ADMA-OPCO all calculations related to the

    number of lifting points to utilize.

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    27

    SF / General / 002 Rev.0 sheet 1 of 1

    APPENDIX-A: CALCULATION OF NEGATIVE BUOYANCY

    A1 Formula for Computing "As Applied" Negative Buoyancy for Concrete Fitted

    Pipe

    Definitions

    L = Length of the Pipe Joint, m.

    Ll = Length of the cutback, mm (assumed same for anti-corrosion

    coating and weight coating).

    D = Outside pipe diameter, mm

    Dl = Outside pipe diameter, including anti-corrosion coating, mm.

    D2 = Outside pipe diameter, including weight coating, mm.

    W = Weight of the pipe joint, including anti-corrosion coating, kg.

    Wl = Weight of the pipe joint, including weight coating, kg.

    B = Buoyancy of the pipe joint in sea water, kg.

    Sea = Density of seawater, (1031 kg/m 3).

    Conc = Density of weight coating, kg/m 3

    NB: Refer to Fig. 6.1.

    Computations

    1. Dry weight of the pipe joint = Wl.

    2. Buoyancy of the pipe joint:

    B = Sea D22 (L - 2Ll )+ D2 x 2L1 4 1000 1000 1000 1000

    3. "As applied" negative buoyancy:

    WSUB = Submerged weight.

    = Negative buoyancy.

    = (W1 - B)/L. kg/m.

    If required, the density of "as applied" weight coating and the specific gravity of the

    pipe joint can be checked as follows:-

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    28

    SF / General / 002 Rev.0 sheet 1 of 1

    Density of weight coating

    conc = density of weight coating.

    = Wl - W x 4 X 106 x 1 kg/m

    3

    D22

    -Dl2

    (L - 2L1)

    1000

    Specific Gravity of the Pipe

    SG = Wl

    B

    Figure 6.1

    Concrete Fitted Pipe

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    29

    SF / General / 002 Rev.0 sheet 1 of 1

    A2 Formula for Computing "As Applied" Negative Buoyancy for Anode Fitted &

    Concreted Pipes

    Definitions

    L = Length of the Pipe Joint, m.

    Ll = Length of the cutback, mm (assumed same for anti-corrosion coating

    and weight coating).

    LA = Length of Anode mm.

    D = Outside pipe diameter, mm

    Dl = Outside pipe diameter, including anti-corrosion coating, mm.

    D2 = Outside pipe diameter, including weight coating, mm.

    DA = Outside diameter of Anode.

    W = Weight of the pipe joint, including anti-corrosion coating, kg.

    Wl = Weight of the pipe joint, including weight coating, kg.

    B = Buoyancy of the pipe joint in sea water, kg.

    sea = Density of seawater, (1031 kg/m3).

    Conc = Density of weight coating, kg/m3

    NB:

    Refer to Fig. 6.2.

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    30

    SF / General / 002 Rev.0 sheet 1 of 1

    Computations

    1. Dry weight of the pipe joint = Wl.

    2. Buoyancy of the pipe joint:

    B = Sea D22 (L - 2Ll-LA )+ D2 x 2L1 + DA2 x LA 4 1000 1000 1000 1000 1000 1000

    3. "As applied" negative buoyancy:

    WSUB = Submerged weight.

    = Negative buoyancy.

    = (Wl - B)/L. kg/m.

    If required, the density of "as applied" weight coating and the specific gravity of the pipe

    joint can be checked as follows:-

    Density of weight coating

    conc = density of weight coating.

    = Wl - W x 4 X 106 x 1 kg/m

    3

    D22

    - D12 (L - 2L1-LA)

    1000

    Specific Gravity of the Pipe

    SG = Wl

    B

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    31

    SF / General / 002 Rev.0 sheet 1 of 1

    Figure 6.2

    Concrete /Anode Fitted Pipe

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    32

    SF / General / 002 Rev.0 sheet 1 of 1

    APPENDIX-B: CONCRETE COATING DATA SHEET

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    33

    SF / General / 002 Rev.0 sheet 1 of 1

    APPENDIX-C: ABBREVIATIONS

    Abbreviation Description

    ADMA-OPCO Abu Dhabi Marine Operating Company

    HDPUF High Density Polyurethane Foam

    QA Quality Assurance

    QAS Quality Assurance System

    QC Quality Control

    QMS Quality Management Systems

    SI Systeme International dUnites

    TPA Third Party Agency

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    34

    SF / General / 002 Rev.0 sheet 1 of 1

    APPENDIX-D: DEFINITIONS

    D.1 General Definition

    Term Definition

    Contractor Is the Company contracted to undertake the works of a Project and is

    accountable to ADMA-OPCO's or its nominated representative.

    Quality Assurance

    All those planned and systematic actions (QA) necessary to ensure quality

    i.e. to provide adequate confidence that a product or service will be fit for

    its intended purpose.

    Quality Manual A Document setting out the general quality policies, procedures and

    practices of an organization.

    Quality Plan A document prepared by the Contractor/Vendor setting out the specific

    quality practices, resources and activities relevant to a particular project.

    Quality

    Management

    System

    The structure organization, responsibilities, activities, resources and events

    that together provide organized procedures and methods of implementation

    to ensure the capability of the organization to meet quality requirements.

    TPA Is the Company contracted to undertake the Third Party Inspection &

    Verification Tasks (TPA) on behalf of ADMA-OPCO.

    Vendor

    Is the named Manufacturer or Supplier in the ADMA-OPCO Purchase

    Order. The term Vendor as used herein includes all Manufacturers and sub-suppliers of equipment covered by this Document.

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    35

    SF / General / 002 Rev.0 sheet 1 of 1

    APPENDIX-E: REFERENCED DOCUMENTS

    Unless otherwise specified, the latest edition of the Standard Engineering Documents listed below

    shall to the extent specified herein, represent part of this document.

    Designation Title

    ADMA-OPCO

    CP-102 Third Party Inspection and Certification Requirements for New Equipment

    and Materials in Manufacture.

    MNL-01 Painting Manual

    SL-001 Status List for ADMA-OPCO Standard Engineering Documents.

    SP-1009 Requirements for Contractors Quality Systems on Major Projects

    SP-1053 Cathodic Protection of Submarine Pipelines

    STD-00 Part-1: Measurements Units

    Part-2: Site Condition & Data

    British Standards Institution (BSI)

    BS EN 10204 Metallic Products Types of Inspection Documents.

    BS 410 Specification for test sieves.

    BS 812 Testing Aggregates

    BS EN 1008

    Mixing Water for Concrete - Specification for Sampling, Testing and

    Assessing the Suitability of Water, Including Water Recovered from

    Processes in the Concrete Industry, as Mixing Water for Concrete

    Supersedes BS 3148:1980

    BS EN 12390 Testing Hardened Concrete

    BS EN 12504-1 Testing concrete in structures Part 1: Cored specimens Taking, examining

    and testing in compression

    BS EN 197-1 CEMENT Composition, Specifications and Conformity Criteria for Common Cements

    BS EN 12620 Aggregates for concrete

    International Organization for Standardization (ISO)

    ISO 9001 Quality Management Systems - Requirements.

    ISO 21809-5 External Concrete Coating

  • 1.0 07-11 Issued for Implementation

    Rev. Date Description / Text Affected

    Specification For Concrete Weight Coating of Subsea Pipeline

    ADMA-OPCO SP-1024 PAGE

    36

    SF / General / 002 Rev.0 sheet 1 of 1

    APPENDIX-E: REFERENCED DOCUMENTS (CONTD)

    Designation Title

    ASTM

    ASTM A 810 Standard Specification for Zinc-Coated (Galvanized) Steel Pipe Winding

    Mesh

    ASTM C 33 Specification for Concrete Aggregates.

    ASTM C 150 Specification for Portland Cement.

    ASTM C 171 Standard Specification for Sheet Materials for Curing Concrete

    ASTM C 309 Specification for Liquid Membrane-Forming Compounds for curing

    concrete.

    Det Norske Veritas (DNV)

    DNV-OS-F101 Offshore Standard: Submarine Pipeline Systems