southern regional power committee - karnataka · corridor due to laying of transmission line and...
TRANSCRIPT
Agenda for the 28th TCC & 29thSRPC Meetings to be held on 4th and 5th March 2016
CONTENTS 1. INTRODUCTION....................................................................................................................................... 3
2. CONFIRMATION OF THE MINUTES OF 27th TCC & 28th SRPC MEETINGS ................................................ 3
3. GUIDELINES FOR PAYMENT OF COMPENSATION TOWARDS DAMAGES IN REGARD TORIGHT OF WAY
FOR TRANSMISSION LINES ...................................................................................................................... 3
4. PREPARATION FOR MEETING REVISED ENVIRONMENT NORMS AS PER ENVIRONMENT (PROTECTION)
AMEN DMENT RULES, 2015 .................................................................................................................... 4
5. ROADMAP TO OPERATIONALISE RESERVES IN THE COUNTRY ............................................................... 4
6. IMPLEMENTATION OF SPS FOR CONTINGENCY OF 400 kV NELLORE - NELLORE PS LINES AND
DIFFERENTIAL PROTECTION.................................................................................................................... 5
7. METERING AND ACCOUNTING OF NTPC KUDGI STPP STAGE-I .............................................................. 6
8. STATUS OF GENERATION IN GENERATING STATIONS ............................................................................ 8
9. TTC / ATC ................................................................................................................................................ 9
10. REVIEW OF ULDC / SCADA/COMMUNICATION .................................................................................... 10
11. UPCOMING TRANSMISSIONSYSTEM .................................................................................................... 12
12. UPCOMING RENEWABLE PROJECTS AND THEIR INTEGRATION WITH TRANSMISSION NETWORK ..... 27
13. FOLLOW UP ACTIONS ON THE RECOMMENDATIONS OF CENTRAL ADVISORY COMMITTEE (CAC) SUB -
COMMITTEE ON CONGESTION IN TRANSMISSION ............................................................................ 28
14. NEW PROJECTS OF NTPC, NLC, NPCIL, JOINT VENTURE & UMPP ........................................................ 29
15. NEW PROJECTS OF STATE SECTOR & IPP .............................................................................................. 30
16. EMERGENCY RESTORATION SYSTEM (ERS) .......................................................................................... 31
17. PROGRESS OF BUS/LINE REACTORS TO BE COMMISSIONED IN SR ...................................................... 32
18. ISSUES IN RESPECT OF CONGESTION CHARGES ................................................................................... 35
19. ADDITIONAL SUPPORT THROUGH 110 KV PARASALA – KUZHITURA FEEDER ...................................... 35
20. OUTSTANDING DUES BETWEEN SOUTHERN AND WESTERN REGIONS ............................................... 35
21. SRPC CERTIFICATION TO CLAIM ADDITIONAL RoE ............................................................................... 37
22. IEGC RELATED ISSUES REQUIRING ATTENTION/ACTION ...................................................................... 38
23. GRID STUDY COMMITTEE (GSC) (TASK-2) AUDIT PROGRESS DETAILS ................................................. 57
24. ISSUES RELATING TO PSDF FUNDING ................................................................................................... 58
25. AUGMENTATION OF TALCHER-II TRANSMISSION SYSTEM .................................................................. 58
26. APPROACH BEING TAKEN BY CTU FOR RESERVING THE TRANSMISSION CAPACITY FOR THE CUSTOMERS
WHO HAVE AVAILED LTA WITHOUT IDENTIFYING BENEFICIARIES ...................................................... 59
27. PENDING REACTIVE CHARGES .............................................................................................................. 60
28. TRANSMISSION CHARGES LIABILITY FOR THE LONG OUTAGE/ SUSTAINED INABILITY TO MAINTAIN THE
APPROVED INJECTION .......................................................................................................................... 60
Agenda for the 28th TCC & 29thSRPC Meetings to be held on 4th and 5th March 2016
29. REIMBURSEMENT OF SRPC EXPENDITURE ........................................................................................... 60
30. GRID OPERATION .................................................................................................................................. 61
31. PROTECTION SYSTEM ANALYSIS GROUP (PSAG-14) MEETING HELD AT MAPS, KALPAKKAM ON
18.12.2015 ............................................................................................................................................ 68
32. THOROUGH REVIEW OF ALL THE DRAWAL POINTS OF STATES FOR DRAWAL COMPUTATIONS ......... 68
33. INCLUSION OF DRAWAL OF MAHE IN REA ........................................................................................... 68
34. SHARING OF TRANSMISSION CHARGES OF TRANSMISSION ASSETS OF NATIONAL IMPORTANCE ..... 69
35. ACCOUNTING METHODOLOGY FOR LKPL STAGE II AND LKPL STAGE III ............................................. 70
36. TPCIL REQUEST TO EXEMPT DEVIATION CHARGES .............................................................................. 70
37. PROLONGED OUTAGE OF 765 KV RAICHUR-SHOLAPUR – 2ND CKT ...................................................... 70
38. AP & TELANGANA SCHEDULING ISSUES OF SHARED PROJECTS & OPERATIONAL ISSUES ................... 71
39. POWER SUPPLY ISSUES AFFECTING METRO SERVICES ......................................................................... 71
40. Outage Coordination through OCC....................................................................................................... 71
41. SCHEDULING OF NTPC RAMAGUNDAM SOLAR POWER PLANT (10 MW) ............................................ 72
42. Assessment of Metering Requirement ................................................................................................. 73
43. IMPLEMENTATION OF PROTECTION SUITE / PROTECTION MANAGEMENT SYSTEM FOR SOUTHERN
REGION ................................................................................................................................................. 73
44. STUDY PROGRAMME ON THE INTEGRATION OF RENEWABLE ENERGY RESOURCES INTO THE GRID . 74
45. FURNISHING THE WIND GENERATORS DATA FOR PLEXOS STUDY OF GREENING THE GRID PROJECT 74
46. UPDATE ON 230 KV BHAVINI-KANCHIPURAM ...................................................................................... 74
47. MEMBERSHIP OF NLDC ......................................................................................................................... 75
48. MEMBERSHIP OF COASTAL ENERGEN .................................................................................................. 75
49. ANY OTHER ISSUE WITH THE PERMISSION OF THE CHAIR ................................................................... 75
50. DATE & VENUE OF THE NEXT SRPC MEETING ...................................................................................... 75
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 3 of 75
SOUTHERN REGIONAL POWER COMMITTEE
BENGALURU
AGENDA FOR THE 28th
TCC & 29th
SRPC MEETINGS TO BE HELD ON 4th
AND 5th
MARCH 2016 AT VISHAKHAPATNAM
1. INTRODUCTION
The 28th
Meeting of Technical Co-ordination Committee and 29th
Meeting of Southern
Regional Power Committee (SRPC) would be held on 4th
& 5th
March 2016 respectively
at Vishakhapatnam.
2. CONFIRMATION OF THE MINUTES OF 27th
TCC & 28th
SRPC MEETINGS
Minutes of the 27th TCC Meeting held on 9th October 2015 in Goa were circulated vide
letter dated 18.11.2015. No comments have been received, Minutes may kindly be
confirmed
Minutes of the 28th
SRPC Meeting held on 10th
October 2015 in Goa were circulated
vide letter dated 09.12.2015. No comments have been received, Minutes may kindly be
confirmed.
For Deliberation in SRPC
3. GUIDELINES FOR PAYMENT OF COMPENSATION TOWARDS DAMAGES
IN REGARD TORIGHT OF WAY FOR TRANSMISSION LINES
3.1. Letter No.3/7/2015-Trans dated 15th
October 2015 of MoP (Annexure-I) contains
guidelines for payment of compensation towards damages with regard to right of way for
transmission lines. The following has been stated:
2. The Recommendations made by the Committee are hereby formulated in the form of
following guidelines for determining the compensation towards "damages" as
stipulated in section 67 and 68 of the Electricity Act, 2003 read with Section 10 and
16 of Indian Telegraph Act, 1885 which will be in addition to the compensation
towards normal crop and tree damages. This amount will be payable only for
transmission lines supported by a tower base of 66 KV and above, and not for sub-
transmission and distribution lines below 66 KV:-
(i) Compensation @ 85% of land value as determined by District Magistrate or any
other authority based on Circle rate/ Guideline value/ Stamp Act rates for tower
base area (between four legs) impacted severely due to installation of tower/pylon
structure;
(ii) Compensation towards diminution of land value in the width of Right of Way (RoW)
Corridor due to laying of transmission line and imposing certain restriction would
be decided by the States as per categorization/type of land in different places of
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 4 of 75
States, subject to a maximum of 15% of land value as determined based on Circle
rate / Guideline value / Stamp Act rates;
(iii) In areas where land owner/owners have been offered / accepted alternate mode of
compensation by concerned corporation / Municipality under Transfer Development
Rights (TDR) policy of State, the licensee /Utility shall deposit compensation amount
as per (i) & (ii) above with the concerned Corporation/ Municipality/ Local Body or
the State Government.
(iv) For this purpose, the width of RoW corridor shall not be more than that prescribed in
the table at Annex-2 and shall not be less than the width directly below the
conductors.
3. Necessary action may kindly be taken accordingly. These guidelines may not only
facilitate an early resolution of RoW issues and also facilitate completion of the vital
transmission lines through active support of State /UT administration.
4. All the States/UTs etc. are requested to take suitable decision regarding adoption of
the guidelines considering that acquisition of land is a State subject.
4. PREPARATION FOR MEETING REVISED ENVIRONMENT NORMS AS PER
ENVIRONMENT (PROTECTION) AMEN DMENT RULES, 2015
CEA vide letter dated 18.01.2016 had requested to furnish details of preparedness and
action plan in order to comply with revised water consumption and emission norms by
existing as well as new thermal units (to be installed from 01.01.2017 onwards) as per
Environment (Protection) Amendment Rules, 2015 notified by Ministry of Environment,
Forest & Climate Change (MOEF & CC) (Gazette Notification dated 07.12.2015). Vide
letter dated 20.01.2016 (Annexure- II) SRPC had communicated the same to the
concerned utilities. Information in this regard may kindly be arranged to be furnished to
CEA with a copy to SRPC. All thermal power plants are kindly requested to furnish
action plan to comply with Environment (Protection) Amendment Rules, 2015. SLDCs
are also requested to kindly take up the matter with thermal power plants in their state.
5. ROADMAP TO OPERATIONALISE RESERVES IN THE COUNTRY
Hon’ble CERC vide Order dated 13.10.2015 on Petition No. 11/SM/2015 in the matter of
Roadmap to operationalize Reserves in the country has directed as follows:
(b) The Commission reiterates the need for mandating Primary Reserves as well as
Automatic Generation Control (AGC) for enabling Secondary Reserves.
(i) All generating stations that are regional entities must plan to operationalise AGC
along with reliable telemetry and communication by 1st April, 2017. This would entail a
one-time expense for the generators to install requisite software and firmware, which
could be compensated for. Communication infrastructure must be planned by the CTU
and developed in parallel, in a cost-effective manner.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 5 of 75
(ii) On the other hand, National/Regional/State Load Dispatch Centres
(NLDC/RLDCs/SLDCs) would need technical upgrades as well as operational
procedures to be able to send automated signals to these generators. NLDC /RLDCs
and SLDCs should plan to be ready with requisite software and procedures by the same
date.
(iii) The Central Commission advises the State Commissions to issue orders for intra-
state generators in line with this timeline as AGC is essential for reliable operation of
India’s large inter-connected grid.
(c) To start with, a regulated framework in line with the Ancillary Services Regulations
would need be evolved for identification and utilising of spinning reserves and
implemented with effect from 1st April, 2016. This framework may continue till 31st
March, 2017.
……………
(d) In the long term, however, a market based framework is required for efficient
provision of secondary reserves from all generators across the country. For this,
NLDC/POSOCO is directed to commission a detailed study through a consultant and
suggest a proposal to the Commission for implementation by 1st April, 2017, giving
due consideration to the experience gained in the implementation of Spinning Reserves
w.e.f. 1st April, 2016.
For SRPC consideration through TCC
6. IMPLEMENTATION OF SPS FOR CONTINGENCY OF 400 kV NELLORE -
NELLORE PS LINES AND DIFFERENTIAL PROTECTION
6.1. SRLDC vide letter dated 08th
October 2015 had stated that considering the operational
security of grid and to be N-1 secure it was important to provide a SPS for contingency
of one 400 kV NPS-Nellore lines. There had been a few cases in the past where distance
relay at NPS-Nellore had over-reached and tripped for remote end faults. Since Nellore-
NPS lines were short lines and considering their importance in the grid it is important to
avoid unwanted tripping of these lines due to mis-operation of protection system and
hence it was necessary to provide differential protection at the earliest.
6.2. The following had been noted in the earlier Meeting:
CTU had informed that NPS-Nellore line was a short line with thermal limit of 2,100
MW for the PGCIL section. Other section was constructed by MEPL/SEL and CTU
was in the process to obtain feedback on thermal capability. As per SRLDC, line
loading had crossed 1,700 MW only during low generation at Krishnapatnam. As
per deliberations in Open Access Meeting, the inter-connector i.e. NPS-Nellore could
also be kept open.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 6 of 75
After deliberations, it had been agreed that during contingency, SRLDC would take
appropriate action in real time to contain line overloading.
6.3. The issue was further deliberated in the Special Meeting held on 20th
October 2015
(minutes available in SRPC website) wherein the following was noted:
SRLDC had stated that opening of NPS – Nellore (PG) is a sensitive issue as it would
require curtailment of STOA’s of the generators connected to NPS. As this has a
potential to trigger operational disputes between SRLDC and IPP’s on daily basis,
CTU has been requested to give basis for opening these lines by conducting proper
studies and reply/ advise SRLDC in a week’s time regarding the modalities of
opening NPS – Nellore (PG) lines including curtailment of STOA’s of generators.
It was also agreed that after receiving suitable inputs from CTU, a separate meeting
with all stake-holders would be convened to chalk-out the operational philosophy of
these lines.
6.4. Subsequently, SRLDC vide letter dated 20th
October 2015 (Annexure-III) and 02nd
November 2015 (Annexure-IV) addressed to CTU had sought clarity on the following
issues:
About the maximum power that can be evacuated from Nellore complex so that
curtailment of infirm power, STOA/MTOA transactions could be affected as per
Regulations.
If 400 kV Nellore PS- Nellore D/C line has to be opened to contain short circuit
level, the appropriate time frame for opening the line considering the availability of
generating units.
6.5. CTU vide letter dated 03.12.2015 (Annexure-V) had replied to SRLDC in this regard.
Subsequently SRLDC vide letter dated 07.12.2015 (Annexure-VI) had communicated
their views in this regard. In the 115th
Meeting of OCC, SRLDC had informed that they
were envisaging a Separate Control /Bid area for Nellore complex.
6.6. The issue regarding provision of differential protection for NPS complex was discussed
in the 50th
meeting of PCSC. After ascertaining opinion of PGCIL and Generators,
PCSC forum has agreed “in-principle” to provide line differential protection on all 400
kV lines of length less than 35 km emanating from Nellore PS.
7. METERING AND ACCOUNTING OF NTPC KUDGI STPP STAGE-I
7.1. This issue had been deliberated in the 29th
Meeting of Commercial Sub-Committee held
on 29th
September 2015 wherein the following had been agreed:
Metering and energy accounting of Kudgi STPP would be based on the SEMs on
400 kV outgoing feeders, HV side of 400/220 kV ICT and HV side of 220/11 kV
standby transformer.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 7 of 75
Drawal of KPTCL at Kudgi STPP would be computed based on SEMs at HV side of
400/220 kV ICT & 220/11 kV standby transformer.
Kudgi STPP Stage-I metering arrangement is given below :
7.2. The following had been noted in the earlier Meeting:
KPTCL had stated that methodology agreed in Commercial Committee Meeting
was not in accordance with CEA Regulations or as per provisions of PPA.
Metering was required to be done on the 220 kV outgoing feeders.
NTPC had observed that the issue had been deliberated in the Commercial
Committee Meeting wherein it had been agreed that SEMs on HV side of
400/220 kV ICT would be considered as main meters for accounting purposes.
Similar was the case for some of the other NTPC stations.
After deliberations, it had been agreed that this matter whether metering and
accounting was to be done on 220 KV outgoing feeders or on HV side of
400/220 KV ICT be referred to CEA.
7.3. SRPC Secretariat had taken up the issue with CEA vide letter dated 27.10.2015
(Annexure-VII). A Meeting was convened by CEA and Minutes of the meeting are at
Annexure-VIII. NTPC vide letter dated 01.02.2016 (Annexure-IX) has stated the
following:
“7. Although CEA has clarified the queries raised by SRPC, but two issues still remain
open and need to be discussed and finalized. These issues are:
a) Installation and ownership of meters on HV and LV side of ICTs
b) Who will bear the losses in ICTs?
……………………………….
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 8 of 75
8. The matter was deliberated and agreed in the 29th
Commercial Sub-Committee
meeting held on 29.09.2015 that the metering and accounting has to be at HV side of
ICTs since Kudgi STPP ex-bus for the purpose of sale energy is at 400 kV busbars of
the Station. This will solve both the issues as brought out at para 7 above.
9. Alternatively it is proposed that:
a) Meters at HV and LV side of ICTs may be owned and installed by CTU and STU
respectively.
b) Losses in the ICTs may be treated as system losses or these losses may be accounted
in the REA and billed to the beneficiaries of the station in proportion to their drawl.’
7.4. The issue was further deliberated in 30th
CCM wherein it was noted that CTU would
provide meters on all 400 kV outgoing feeders while STU would provide on all 220 kV
outgoing feeders as clarified by CEA. However, there was no consensus on NTPC’s
proposal for treating ICTs’s loss as system loss. It was agreed to refer this issue to
TCC/SRPC.
8. STATUS OF GENERATION IN GENERATING STATIONS
8.1. The issue regarding low generation in KKNPP, NLC TS-II Expansion, NTECL and
NTPL was deliberated in the 28th
SRPC / 27th
TCC meetings. The following had been
noted:
KKNPP Unit-I had been taken out for refueling during the month of June 2015 with
projected outage schedule of 60 days.
NTECL had informed that the main constraint was in transportation of coal. Vallur
STPS was receiving only 2 rakes/day via Paradeep Port against requirement of 4
rakes/day. Negotiations were in the final stages for getting coal through the Dhamra
Port. Second grab unloader was planned to be commissioned by middle of November
2015 and movement of coal via Dhamra Port was expected by end of November
2015. Issues regarding pipe conveyor were also likely to be resolved soon. Station
was expected to achieve 80 % generation level (1,200 MW) by middle of October
2015 & 100 % availability by end November 2015.
TANGEDCO and NTECL would hold a meeting shortly to identify measures to
improve availability at NTECL.
NLC had informed that the units at NLC TS-II Expansion would stabilize and
sustained full load generation could be anticipated in about 2 months’ time.
In respect of NTPL, NLC had informed that there were issues in blending of coal
relating to clinker formation in unit-I and choking of burner mouths. NLC had
assured that within 1 month, NTPL units would also maintain full load. Presently,
these units were running mostly on imported coal and since boiler was not designed
for the same, the station was facing clinkering problems. With assured domestic coal
supply, blending issues would get resolved.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 9 of 75
SRLDC had observed that increasing availability of power by scheduling NTPC
Kayamkulam to its full capacity also needed to be looked into. KSEBL had informed
that they had offered Kayamkulam power to Karnataka at an indicative cost of
Rs.6.50/unit, if requested for more than 2 months on RTC basis. PCKL had stated that
cost of Rs.6.50/unit appeared to be on a higher side. However, they would discuss
the matter with the Management/DISCOMs and revert back.
APGENCO had expressed concern that for supply of coal MCL was insisting for
inspection of Unit-II of Krishnapatnam JV after its CoD. All concerned agencies like
CEA, MCL etc had been duly invited to witness the full load test of Unit-II. However,
there had been no participation from MCL at that time. The coal supplied had already
been exhausted since supplied quantum was sufficient only for the full load test.
There was no coal available presently to demonstrate the capability to MCL. MCL
had clarified that as per recent policy, all new units commissioned could be supplied
coal only after due inspection by MCL. It was assured that they would depute a team
for inspection at the earliest
NTPC had informed that Simhadri TPS had received only 59% of the linkage in the
first two quarters. During September, the realization had been 73% which still
required improvement. NTPC was augmenting coal receipt through a new route from
Lingaraj. One NTPC loco from Kaniha had been diverted to Lingaraj. MCL had
informed that they had offered more than ACQ but on account of paucity of Railway
Wagons, realization had been less.
KPCL had stated that they would require about 2 Lakh T of coal for startup of Bellary
Unit-III. Coal synchronization was expected by end November 2015. MCL had been
requested to kindly expedite the sanction of coal for startup.
8.2. Subsequently, Unit-I of KKNPP was brought back on bars on 30th
January 2016. The
status of generation of some ISG stations is given below:
9. TTC / ATC
9.1. NRCE had issued operational guidelines for determination of Total Transfer Capability
(TTC), Available Transfer Capability (ATC) and Transmission Reliability Margin
Station Oct’15 Nov’15 Dec’15 Jan’16
KKNPP U1,
NPCIL
Generation
in MU
0 0 0 2.89
PLF 0 0 0 0.4%
NTECL,
Vallur
Generation
in MU
743.25 597.02 554.59 742.69
PLF 67% 55% 50% 67%
NTPL,
Tuticorin
Generation
in MU
301.76 374.86 410.55 501.93
PLF 41% 52% 55% 67%
NLC TS II
Exp
Generation
in MU
30.69 98.70 45.80 120.99
PLF 8% 27% 12% 33%
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 10 of 75
(TRM) for short term horizon (0-3 months) which is available on CEA website.
POSOCO had been advised to assess TTC considering temperature dependent thermal
ratings of lines / terminal equipment.
9.2. Temperature dependent thermal rating of lines / terminal equipment affecting TTC of SR
import was to be taken up.
9.3. NLDC vide letter dated 01.02.2016 (Annexure-X) had furnished list of transmission
elements affecting TTC/ATC to SR and had suggested that any planned outage on these
elements needs to be appropriately studied.
9.4. SRPC vide letter dated 04.02.2016 (Annexure-XI) had replied to NLDC letter. It was
also enquired whether dynamic line loadings had been considered. Further, when one
line of 400 kV Ramagundam- Bhadravathi was under shutdown, there had been 250
MW of curtailment in TTC.
9.5. During shutdown of 765 kV Raichur-Sholapur Ckt II and Bhadravathi Pole I, ATC of
500 MW was approved through WR-SR link, though there was one pole of Bhadravathi
(500 MW), one 765 kV Raichur-Sholapur circuit and two circuits of 765 kV Sholapur –
Kudgi (charged at 400 kV) available.
9.6. POSOCO is requested to kindly appraise the forum about ATC computations and
whether dynamic line loadings are being considered as per directions of Hon’ble CERC.
9.7. Transfer capability determination by States
In the 4th
meeting of NPC held on 10th
December 2015 (MoM dated 1.1.2016 enclosed
as Annexure-XII), it had been decided that to begin with, power system study for
assessment of operational limits / power transfer capability for each state would be done
by the concerned RLDC in association with concerned SLDC. Monthly TTC/ATC
would be uploaded by SLDCs in their respective websites and also communicated to
concerned RLDC & NLDC subsequently.
10. REVIEW OF ULDC / SCADA/COMMUNICATION
10.1. In previous Meetings, the following had been noted:
Review of SCADA and Communication availability was being carried out in the
OCC/Special meetings.
APTRANSCO had expressed concern over mismatch and wrong data in new SCADA
system. APTRANSCO vide letter dated 06.01.2016 (Annexure-XIII) had informed
that large variation was observed between real time SCADA data and SEM data
furnished for Deviation account for 09.11.2015 to 15.11.2015 which caused AP to
pay Rs. 2.26 Crores as deviation charge.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 11 of 75
SRLDC had expressed concern over interruption in real time data and requested
PGCIL to address this issue at the earliest. Dedicated Officers were required from
PGCIL side to improve availability of SCADA data to SRLDC.
NLDC had pointed out that this was a serious issue since it gave a misleading picture
to the system operators.
PGCIL had stated that they were seized about this issue. A core group was looking
into this issue and they would come out with a solution soon.
10.2. Matter regarding failure in providing data with redundant channel/path to SRLDC
(resulting in violation of Grid Code and system security) had been referred by SRLDC to
SRPC under Clause 1.5 of IEGC 2010. Subsequently, SRPC had taken up the issue with
the concerned. Utilities had been requested to examine the matter urgently and ensure
strict adherence to the provisions of IEGC/CEA Regulations. A Special Meeting to
deliberate on communication issues was also held on 19th
November 2015 in SRPC
Bengaluru (Minutes available at SRPC website).
10.3. In the 115th
OCC Meeting, it was again felt that there should be an active monitoring
system in place. Interruption in real time data was a matter of concern since commercial
and grid security issues were involved. Availability of SCADA was also being noted by
higher bodies.
10.4. Hon’ble Commission has issued Order dated 2nd
February 2016 in respect of Petition
No.7/SM/2014. The following direction merits attention please:
‘14. Under the Grid Code, it is the responsibility of all users, STUs and CTU to provide
systems to telemeter power system parameters in line with interface requirements and
other guideline made available by RLDC and associated communication system to
facilitate data flow up to appropriate data collection point on CTUs system.
Telemetry of on-line operational data is not only essential for effective monitoring of
grid but also forms key input for effective running of State estimation and other EMS
tools at RLDC and SLDCs, which are essential for reliable and secure operation of
the grid. In view of the critical importance of telemetry and associated
communication system for ensuring reliability in operation of the grid and optimum
utilization of the transmission system, there is an imperative need for all users to
establish the telemetry and associated communication system in time bound manner
so that the power system operation may be most reliable and optimum. Moreover, in
view of the requirement of communication system for a generating station and sub-
station, the planning should be done in advance by the generating company and
transmission licensee to ensure that necessary system are in place before
commissioning of generating station or sub-station to take care of the communication
requirements even at the time of injection of power infirm by a generating station and
sub-station during testing.
……………………………..
17. We further direct all the utilities/generating companies which have to still establish
telemeter power system parameters as per details given in para11 above to provide
data to RLDCs/SLDCs as per the provisions of the Grid Code and CEA Grid
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 12 of 75
Standards Regulations by 31.7.2016. If the utilities/generating companies do not
comply with our directions, it will be construed as non-compliance of the order of the
Commission and appropriate proceedings under Section 142 of the Electricity Act,
2003 shall be initiated against such utilities/generating companies. NLDC is directed
to submit user- wise latest status of telemetry, by 31.8.2016.
18. NLDC and respective RLDC are directed to up-date the status of telemetry every
month at their web-site and persistent non-availability of data from the generating
stations/sub-stations be taken up in RPC meetings for appropriate direction and
action.’
The matter needs to be deliberated as per the orders of Hon’ble Commission.
10.5. In the 116th
OCC Meeting (10.02.2016), it was agreed that PGCIL representative would
be present at SRLDC to sort out SCADA/Communication issues pertaining to Raichur,
Kurnool, Khammam, Warangal, Nagarjunasagar, Ramagundam, Bhadravathi and MEPL
on priority basis. Subsequently, other issues would be taken up. It was also agreed that
state wise reconciliation would be carried out. It was noted that it may take around one
month time for each state. Two officials from SRLDC and state (one each from SCADA
and Grid Operation) would sort out the issues. Drawal computation methodology would
also be reviewed. AP SCADA validation would be carried out from 15.02.2016
onwards.
11. UPCOMING TRANSMISSIONSYSTEM
11.1. Pending transmission elements in WR and SR for proper utilization of 765 kV
Raichur-Sholapur line (Out of planned 18 elements)
11.1.1. Updated status of pending transmission elements in WR and SR for proper utilization
of 765 kV Raichur - Sholapur lines (out of planned 18 elements) is furnished below
please:
Sl.
No
Name of
Transmission
Element
Exe.
Agency Sch. CoD Expected
date
Remarks
1 400 kV Gooty-
Tumkur D/C line
PGCIL June 2014 Commissio
ned on
01.12.2015
2 400/220 kV , 2 x
500 MVA, 63
MVAR Reactor
Tumkur S/S
PGCIL June 2014 Commissio
ned on
01.12.2015
Downstream network
not available
3 400 kV Tumkur-
Yelahanka D/C line
PGCIL June 2014 Severe RoW problem.
400 kV Yelahanka S/S
is ready.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 13 of 75
11.1.2. The following had been noted in earlier Meetings:
Downstream system by KPTCL was needed to be expedited to reap the benefit. LILO
of 400 kV Nelamangala – Hoody along with 400 kV Tumkur – Yelahanka together
could help in further evacuation.
SRLDC had stated that downstream system both at Tumkur and Yelahanka was
required for increasing the ATC.
Constituents had expressed that LILO of 400 KV Nelamangala - Hoody at Yelahanka
and Tumkur -Yelahanka line (even without downstream at Yelahanka) could help
increase ATC and hence PGCIL may prioritize commissioning.
KPTCL had informed that regarding Yelahanka PG- Yelahanka (KPTCL) link,
special cable (international source) was required and the same was being retendered.
Works could take about 6/7 months’ time (5 kM) once the award was in place.
KPTCL had informed that in respect of downstream system at Madhugiri, while
contract for two downstream lines was already in place, the other two lines may come
in a time frame of about one year. Out of four 220 kV lines planned for Tumkur
downstream system, two short lines (79 kM) were likely to be completed in 4 months
(3 months from the date of resolution of RoW issues). With these lines, about 350-
400 MW of evacuation from Tumkur would be possible. Other D/C line would come
in about one year.
Downstream system from Tumkur S/S was:
220 kV Tumkur – Antharasana Halli D/C
400 kV Tumkur S/S – 220 kV Tumkur S/S D/C
Tenders for the above line had been placed on 18.03.2015 and it would
take 18 months for completion.
Downstream network from Yelahanka S/S was:
400/220 kV Yelahanka S/S- 220 kV Yelahanka S/S D/C
400/220 kV Yelahanka S/S – 220 kV BIAL S/S D/C
11.2. Upcoming inter-regional transmission schemes
11.2.1. The updated status is furnished below please:
S.
No. Transmission Element Remarks
a) 765 kV Kudgi (PG) – Kolhapur D/C
line (charged at 400 kV)
Ckt I : COD on 19.11.2015
Ckt II : COD on 11.12.2015
b) 765 kV Wardha – Nizamabad D/C
line
Original Schedule by May 2018
PGCIL trying to complete the
system by May 2017
c) WR-SR 6000 MW HVDC Bipole
Link [Raigarh (Chhatisgarh) -
Pugalur-Trichur (TN/KER)]
2018-19
Tendering activity is continuing.
Land had been acquired at
Pugalur
Land identified at Trichur and
acquisition would start
Technical specifications are
being finalized with 10 %
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 14 of 75
overload capacity
d) 765 kV Angul - Srikakulam PS D/C
line
By August 2016, other associated
elements by December 2016
e) Additional inter-Regional AC link for
import to Southern Region, i.e.,
Warora-Warangal - Hyderabad-
Kurnool 765 kV link
TBCB, PFCCL- BPC– Bidding yet to
commence. RFQ inputs furnished by
CTU. Some scope of work/ reactive
compensation modified and RFQ
modified accordingly.
f) System strengthening within SR for
transmitting power beyond Vemagiri
TBCB- RECTPCL-BPC– SPV had
been incorporated on 06.04.2015 and
RFQ issued on 12.04.2015. Some
scope of work/ reactive compensation
modified.
11.2.2. Updated status of upcoming inter regional scheme is furnished at Annexure-XIV.
11.2.3. The following had been noted in earlier Meetings:
SRTS-I & II had informed that tendering activities in respect of Raigarh- Pugalur
-Madakathara HVDC were continuing. Land for the HVDC terminal at Pugalur
had been acquired. Land for HVDC terminal at Madakathara (Thrissur) had also
been identified and acquisition would commence shortly.
765 kV Wardha- Nizamabad D/C line was being advanced on the request of
Telangana Govt. and was now scheduled for May 2017. System beyond Vemagiri
was however coming under TBCB route and the benefits of increase in import
capacity could be achieved only after commissioning of the downstream system.
11.2.4. From 16th
December 2015, consequent to commissioning of 765 kV Kolhapur-Kudgi II
(charged at 400 kV) and 765 kV Raichur-Kurnool I, TTC on WR-SR corridor had been
enhanced by 800 MW. Entire ATC of 5,900 MW to SR had been allocated under
LTA/MTOA.
11.3. Status of various Associated Transmission Systems (ATS) of upcoming generators
11.3.1. Common System Associated with NTPL / Costal Energen Private Ltd / Ind-
Barath Power Ltd
11.3.1.1. Updated status of associated links is furnished below:
Transmission
Elements
Line
Length
(ckm)
Implem
enting
Agency
Sch
COD
Ant
COD/
Act
COD
Constraints/
Remarks
765 kV D/C Tuticorin
PS - Salem PS line
(Dharmapuri) (initially
charged at 400 kV)
735 PGCIL Dec'14 Jun’
2016
400 kV D/C Salem PS
– Salem line
120 PGCIL Line is ready.
765 kV S/C Salem PS
(Dharmapuri) -
Madhugiri P S line
244 PGCIL Dec'14 Mar’ 16 Severe ROW
problems in
Karnataka.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 15 of 75
(initially charged at
400 kV)
Critical.
765/400 kV Salem PS
(initially charged at
400 kV)
PGCIL PS is ready
400 kV D/C Coastal
Energen – Tuticorin
PS
Coastal
Energen
April 16 CEA in its
meeting held on
11.12.2015 has
advised Coastal
Energen to
complete the line
by April 16,
2016.
11.3.1.2. The following had been noted in earlier Meetings:
NLC had stated that both the units at NTPL had been commissioned and there
should not be any evacuation constraints for NTPL units.
Coastal Energen had enquired whether 2 units of NTPL and 1 unit of Coastal
Energen could be evacuated through the existing arrangement. D/C line from
Coastal Energen to Tuticorin Pooling Station would be completed in 6-8
months.
SRLDC had pointed out that 400 kV Madurai- Udumalpet was getting
overloaded under certain conditions. ATS for Coastal Energen also comprised
of upstream system from Tuticorin PS which was expected only by June 2016.
CTU had stated that as was known LTA would have more priority than MTOA.
11.3.1.3. Subsequently, a Meeting was held at CEA on 11th
December 2015 regarding “2x600
MW Mutiara Thermal Power Project-Permission for Synchronization and declaration
of COD of unit -2” (Minutes at Annexure-XV). It had been noted that total
evacuation from the two projects i.e. Coastal Energen & NTCL would be restricted to
1,350 MW up to 30.04.2016. Coastal Energen would firm up and submit their
schedule of completion of the dedicated transmission line up to Tuticorin pooling
station. They would give assurance that this line will be completed by 30th
April 2016
i.e. before onset of wind season in that area.
11.3.1.4. Coastal Energen vide letter dated 07.01.2016 (Annexure-XVI) had proposed an SPS
in Tuticorin PS-CEPL-NTPL Complex for running both units of CEPL till June, 2016
by which time both CEPL and PGCIL would complete their respective lines.
11.3.1.5. The issue was discussed in the 50th
PCSC meeting held on 27.01.2016, wherein
SRLDC had stated that SPS proposed could not be agreed to in its present form on
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 16 of 75
account of the following reasons:
Generation from second Unit of CEPL has not been tied up (for accommodating
which the present SPS is being proposed)
In the proposed SPS, details of loads to be held to balance LGBR in event of
tripping of one of the Units had not been spelt out;
In the event of non-operation of SPS, there is a real chance that end-equipment at
NTPL switchyard may get damaged due to limitation imposed by the bus-bar
rating.
TANTRANSCO opined that since loads are yet to be identified for the proposed
SPS, the issue be discussed in the forthcoming Meeting of OCC. A Meeting on
this issue has now been scheduled to be held on 23rd
February 2016.
11.3.2. Transmission system associated with IPPs (IL&FS) of Nagapattinam/Cuddalore
Area
11.3.2.1. Updated status of associated links is furnished below please:
(i) Transmission system associated with IPPs of Nagapattinam / Cuddalore Area –
Package A
Transmission
elements
Line
Length
(ckm)
Imp.Agenc
y
Sch
COD
Ant.
COD
Constraints/
Remarks
Nagapattinam PS-
Salem New
765 kV D/C line
211.73 Powergrid
Nagapattina
m-
Madhugiri
Transmissio
n Company
Limited
(PNMTCL)
(A
subsidiary
of PGCIL)
Mar’
15
Mar’16
Salem New –
Madhugiri 765
kV S/c line.
234.46 Jun’ 16 Severe RoW issues
being faced in
Karnataka section.
(ii) Transmission System Associated with Contingency plan for Evacuation of Power
from IL&FS (2x600MW)
Transmission
Elements
Line
Length
(ckm)
Imp.
Agency
Sch
COD
Ant
COD
Constraints/
Remarks
LILO of 2nd
Ckt of
Neyveli - Trichy 400
kV D/C line at
Nagapattinam PS
44 PGCIL Jul'15 Complete
d on
27.09.20
15
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 17 of 75
Strengthening of
Neyveli TS -II to
Neyveli TS-I
expansion link with
higher capacity
conductor
28 PGCIL Jul'15 Declared
on COD
from
09.11.20
15
11.3.3. Evacuation of Power from HNPCL (1,040 MW) Power Plant
11.3.3.1. Updated status of associated links under APTRANSCO’s scope is furnished
below:
Transmission
Elements
Line
Length
(ckm)/
MVA
cap.
Implemen
ting
Agency
Target
Date
Target
date
completi
on
Constraints/ Remarks
Startup Power
Line from M/s.
HNPCL TPP to
400/220 kV
Kalpakka SS
7 APTRANS
CO
Line Charged on
07.02.2014
400 kV TM D/C
Line from
HNPCL -
Kamavarapukota
S/S (Lot-I, II &
III)
Lot - III
200 ckm
(100 x 2)
APTRANS
CO
Jul ‘15 Oct’16
as
informed
in 27th
TCC
Works delayed due to
severe resistance from
farmers, water logging,
collapsible soil,
existing crops &
frequent rains.
However construction
activity is being
continued with the help
of Revenue and other
concerned authorities.
400 kV TM D/C
Line from
Kamavarapukota
S/S - Vemagiri
400 kV S/S
APTRANS
CO
Apr’17 LoI issued on
04.09.2015. Purchase
Order issued on
03.11.2015
400 kV TM D/C
Line from
Kamavarapukota
S/S - 400 kV
Chinna
Korukondi S/S
212 APTRANS
CO
Sept. ‘15 Oct’16
as
informed
in 27th
TCC
LoI issued on
15.07.2013. Delaying
due to standing crops
and compensation
issues.
Kamavarapukota
Substation
2x315
APTRANS
CO
Mar ‘16 Oct’16
as
informed
in 27th
TCC
Works awarded.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 18 of 75
2 Nos. of 400 KV
Bay Extensions at
existing 400/220
KV Kalpaka S/S
of HNPCL
APTRANS
CO
Oct’16
as
informed
in 27th
TCC
All works completed
for 1 No. of 400 KV
Bay on 07.02.2014
11.3.3.2. Updated status of associated links under TSTRANSCO’s scope is furnished below:
Transmission
Elements
Line
Length
(ckm)/
MVA
cap.
Implemen
ting
Agency
Target
Date
Target
date
completi
on
Constraints/ Remarks
400 kV TM D/C
Line from Chinna
Korukondi - 400
kV Suryapet S/S
212 TSTRANS
CO
2016-17 Works awarded in
March 2014. Tower
erection and stringing
under progress.
Suryapet S/S -
Nandiwanaparthi
S/S 400 kV Quad
D/C Line
240 TSTRANS
CO
Mar’15 2015-16 Works awarded in Sep-
13. Stringing
completed. OPGC
4.682 kM under
progress.
400 kV Quad D/C
Line from
Nandiwanaparthi
S/S -
Shankarapally
S/S
222 TSTRANS
CO
Mar’15 2015-16 Works awarded in Sep-
13.Under Progress.
Suryapet
Substation
400/230/132 & 2
Nos. of 400 KV
Bay Extensions at
400 KV
Shankarapalli S/S
2x315
TSTRANS
CO
Mar’15 2015-16 Work awarded in Sep’
2013 and under
progress
11.3.3.3. The following had been noted in earlier Meetings:
On an observation of SRLDC, APTRANSCO had agreed that maximum
evacuation from Vemagiri complex including HNPCL would be restricted to 600
MW.
APTRANSCO had stated that as per their studies on account of changes in system
configuration, around 750 MW of power injection could be possible from the
complex.
SRLDC had stated that generation at Vemagiri Complex had increased due to gas
pooling scheme. With HNPCL generation, injection limits at Vemagiri complex
needs to be ascertained through studies. APTRANSCO had stated they would
participate in the joint study and adhere to the limits finalized in the study.
11.3.3.4. A joint study comprising members from APTRANSCO, SRLDC and SRPC was
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 19 of 75
conducted to assess capability of evacuation of Gas Generation from Vemagiri
Complex and Hinduja TPS connected at 400 kV Kalpakka SS. Requirement for study
came on account of LILO of APTRANSCO owned 400kV Vemagiri- Nunna line-1 at
400kV Sattenapalli SS in the month of October, 2015.
From the study results (Annexure-XVII) the following was observed:
(i) Vemagiri Complex: With the present network, the entire generation of Vemagiri
Complex (1,450 MW) can be evacuated without any constraint. However, with nil
generation at VTS Stage 4 (Unit 7:500MW), the generation at Vemagiri has to be
reduced to 660 MW.
(ii) Hinduja TPS: With the present system, only 575 MW out of the total generation
can be evacuated without any constraint. However, with zero generation at VTS Stage
4 (Unit 7:500MW), the combined generation. (Vemagiri complex + Hinduja TPS)
needs to be restricted to 660 MW.
11.3.4. Transmission system of KPTCL for evacuation of power from Yermarus TPS
(2x800 MW)
11.3.4.1. Updated status of associated links is furnished below:
Transmission elements Imp.Age
ncy
Line
Length
(ckm)/
MVA
cap.
Sch. COD Constraints/ Remarks
Bellary 400 kV PS near
‘BTPS’
KPTCL Jul’16(As
informed
by JSWEL)
Gulbarga 400/220 kV
substation
KPTCL 2x500 New Scheme in place of
old one is approved in
56th TCCM meeting held
on30.11.2013.
Land is in possession of
KPTCL. Preliminary
survey work of 400 kV
line is completed.
Estimate to be prepared
Yeramarus TPS -
Gulbarga 400 kV D/C line
(QM)
KPTCL Estimate to be prepared.
400 kV switching station
at Chikkanayakanahalli
(C.N Halli) near “Loop in
Loop Out” (LILO) point
on the Nelamangala –
Talaguppa 400 kV lines to
Hassan.
KPTCL Land identified. Land
Acquisition is under
process.In 39th
SCPSPSR
KPTCL had suggested for
a step down station with 2
x 315 MVA, 400/220 kV
ICTs with 220 kV
connectivity.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 20 of 75
LILO of both the circuits
of Nelamangala –
Talaguppa 400 kV lines to
the proposed pooling
station near CN Halli.
KPTCL CN Halli land identified
near the intersection point
of all the proposed lines.
Termination of 400 kV
D/C line feeding 400/220
KV station at Hassan from
Nelamangala – Talaguppa
line at CN Halli 400 kV
pooling station.
KPTCL After CN Halli land
identification, survey
would be taken up.
Yermarus TPS - Bellary
Pooling Station 400 kV
D/C line with quad moose
conductor
KPTCL 300
(400 kV
MC Line
(5.138
Kms) and
400kV
DC line
(137.355
Km)
totally for
a route
length of
142.493
Kms)
DPR approved on
26.02.2015. Tendered on
09.03.2015. Techno
Commercial bids opened
on 21.05.2015. Price bids
opened on 01.07.2015.
The works have been
awarded.
Bellary Pooling Station -
C.N.Hally 400 kV D/C
line with quad moose
conductor
KPTCL 360 Survey using MST
conducted and reports
submitted to zonal office
vide ltr no:1682-83
Dt:30.06.15 and the same
is submitted for approval
to CEE(P&C) vide
ltr.no.2504-06 dt 7.7.2015
Bellary PS to Madhugiri
line (765/400kV V.N.pura
substation (PGCIL)
a) Madhugiri to Rampura
limits): 400kV DC line
with Quad Moose ACSR
(188.74 Kms)
b) Bellary pooling Stn 400
kV to Rampura limits
(Kelagina Kanavi):
(43.018 Kms)
KPTCL 380
22-Dec-16
Under Execution by KEC
International Ltd
DPR approved on
26.02.2015. Tendered on
09.03.2015. Award to be
issued.
Bellary TPS – Bellary
Pooling Station 400 kV
D/C line with quad moose
conductor
KPTCL 10 Survey work in
progress.In 39th
SCPSPSR
KPTCL had suggested to
drop the proposal.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 21 of 75
11.3.4.2. The following had been noted in earlier Meetings:
KPTCL had informed that 400 kV Tumkur-Bellary PS D/C line had been awarded
and was expected to come along with Bellary PS with schedule of one and half
years i.e March 2017. They were trying to compress construction to one year
against schedule of one and half year. Land identification was completed in C N
Hally but KPTCL was targeting this system in the second stage. CEA had been
requested to allow 500 MW of evacuation from Yermarus coupled with drawal at
Tumkur. It was assured that 500 MW of injection from Yermarus would not be at
the cost of regional ATC.
De-link 400 kV S/C line
running between RTPS-
BTPS-JSW-Guttur with
‘BTPS’ and JSW Bus so
as to retain direct
connectivity between
RTPS and Guttur
KPTCL
Only after all other
Transmission Elements
under Stage I are
commissioned. In 39th
SCPSPSR KPTCL had
suggested retaining the
LILO at BTPS only.
JSW TPS – Bellary
Pooling Station 400 kV
D/C line with quad moose
conductor
KPTCL Jul’16(As
informed
by JSWEL)
Only after all other
Transmission Elements
under Stage I are
commissioned.
KPTCL/JSW to discuss to
take up this work as
dedicated transmission
line by the generator.
400 kV CN Halli –Mysore
D/C (QM)
In 39th
SCPSPSR KPTCL
had proposed that the line
could be taken under
Southern Region system
strengthening.
400 kV Tumkur
(Madhugiri)–Mysore D/C
(QM)
In 39th
SCPSPSR KPTCL
had proposed that the line
could be taken under
Southern Region system
strengthening.
400/220 kV SS at Bellary
PS or JSWEL 2 x 315
MVA)
In 39th
SCPSPSR KPTCL
had proposed the SS.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 22 of 75
SRLDC had pointed out that 400 KV Hiriyur - Nelamangala lines were getting
overloaded and ATS was not ready for Bellary Unit-III and Yermarus TPS.
Generation from the Complex maybe required to be regulated by Karnataka
SLDC.
SRLDC had stated that only 2,090 MW of evacuation would be possible from
Raichur TPS, Yermarus TPS & Bellary TPS. KPTCL pointed out that with the
present network about 2,600 MW of power was already getting evacuated. SRLDC
confirmed that 400 kV N/W had only been considered in the studies.
11.3.5. Transmission System required for evacuation of power from Kudgi TPS (3x800
MW in Phase-I) of NTPC Limited
11.3.5.1. The updated status is furnished below:
11.3.5.2. The following had been noted in earlier Meetings:
KPTCL had informed that one 220 kV line was passing close to Kudgi
switchyard (3 kM). LILO of this line would be completed by October 2015 so
that NTPC could avail startup power. Three 220 kV D/C lines were planned
evacuation lines at 220 kV level to Vajramatti, Basavana Bagewadi and Bijapur.
The Vajramatti line had just been awarded and could take about 1 year. There
were some RoW issues in that area. Construction from B Bagewadi and Bijapur
ends had already commenced and about 50 % of the lines are completed
KPTCL had stated that they should be allowed dedicated ATC since radial loads
would be required to be provided by them besides temporary LILO arrangement
of 220 KV line. This would purely be a temporary arrangement till Kudgi unit
Transmission
Elements
Imp. Agency Scheduled
CoD
Revised
Target
Date
Constraints/ Remarks
400 kV Kudgi TPS
– Kudgi (PG)
2xD/C Line
M/s Kudgi
Transmission
Limited
(L&T
Infrastructure
Development
Projects Ltd.)
Feb-15 2015-16
One D/C line Kudgi TPS –
Kudgi (PG) declared on
deemed CoD from 04.08.15.
Kudgi (PG)-
Tumkur 765 kV
D/C Line
Dec - 15 2015-16 Under Progress
Tumkur -Bidadi
400 kV D/C
(quad) Line
Dec - 15 2015-16 Under Progress
400/220 kV ICT 1
& 2 at NTPC
Kudgi Switchyard
NTPC
400 kV Bus
Reactor -2
NTPC
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 23 of 75
commences generation. SRPC had noted that a Meeting would be held to
deliberate on the proposal of Karnataka for which TCC had agreed “ in
principle”.
11.3.5.3. Subsequently PCKL vide letter dated 17.12.2015 (Annexure-XVIII) had requested
to intimate status of corridor allocation under special ATC to Karnataka. SRPC vide
letter dated 23.12.2015 (Annexure-XIX) had communicated to PCKL that since
entire ATC had already been allocated under LTA/MTOA and complete system being
an inter-regional IST system, special ATC to Karnataka appears to be not feasible. It
was also indicated that this matter had already been discussed with POSOCO. NLDC
vide letter dated 21.01.2016 (Annexure-XX) had communicated similar aspects to
PCKL. It had been suggested that PCKL may apply for STOA in line with CERC
Regulations and in case of margins in the transmission system on day to day basis, the
same would be processed accordingly.
11.3.5.4. NTPC Kudgi had availed startup power as a HT consumer for the period from
29.10.2015 to 30.11.2015 through LILO of 220 kV Ballurthy - Kudgi line.
Subsequently, NTPC Kudgi was availing startup power through ISTS Grid.
11.3.6. Transmission System for evacuation of power from Singareni Collieries
Generating Project (2 x 600 MW)
11.3.6.1. The following is the status update:
Transmission
elements
Length
(ckm/MVA
capacity)
Imp. Agency
Sche
duled
CoD
Target
date of
Compl
etion
Constraints/
Remarks
1. 400 kV Singareni- Gajwel in two parts
a) 400 kV Jaipur
(Singareni) -
Rangampet D/C
(Quad)
149.636
TSTRANSCO
2015-16
Works awarded on
06.03.2013. Work
awarded to M/s Best
& Crompton
GVPR(JV), Hyd.
Under Progress.
b) 400 kV
Rangampet- Gajwel
D/C (Quad)
174.852
TSTRANSCO
Comp
leted
2. 400 kV Singareni-Nirmal in two parts
a) STPP, Jaipur -
Jagityal 142
TSTRANSCO Works Awarded on
Nov’15 and under
progress
b) Jagityal - Nirmal
156
TSTRANSCO Feb
17
Works Awarded on
Oct’15 and under
progress
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 24 of 75
11.3.7. Transmission System for Rayalaseema TPS (600 MW)
11.3.7.1. The following is the status update:
11.4. Status of upcoming links having impact on S1-S2
11.4.1. Following is the updated status:
Sl.
No. Transmission Element Schedule
Expected
Commissioning
Date
Remarks
1 400 kV Somanahalli-
Dharmapuri PS
June-15 Feb-16 The works under Tamil Nadu
portion had been completed
and severe RoW problems for
35 Kms. stretch of Karnataka
portion.
45 days shutdown for Hosur-
Salem line would be required
for stringing of this line.
PGCIL would coordinate with
Tamil Nadu.
2 400 kV Mysore- May 2015 COD on
Transmission
elements
Length
(ckm/M
VA
capacity)
Imp.
Agency
Schedul
ed CoD
Target
date of
Completi
on
Constraints/ Remarks
RTPP (Stage -
IV) - Chittoor
TM D/C Line
(a). RTPP -
Pedda Jamgam
Palli (P.J.Palli)
(b). P.J. Palli-
Chittoor
(c)
Muddanur(RTPP
)-
Chinakampally
432
120
APTRA
NSCO
Mar 16
Mar 16
Works Awarded on
02.04.2014 and under
progress. Tower erection
completed.
Works under progress.
400/220 kV,
Kalikiri S/S 2x315
MVA
APTRA
NSCO
LoI issued on 16.09.2015.
PO is placed in Nov-15.
LILO of both
circuits of
Rayalseema IV-
Chittoor 400 kV
D/C line| at
Kalikiri
APTRA
NSCO
Tenders under preparation
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 25 of 75
Kozhikode 16.10.2015
3 400/220 kV 2 x315
MVA SS at Kozhikode COD on
16.10.2015
4
400 kV Mangalore
(UPCL ) -Kasargode-
Kozhikode
In the Meeting taken by
Secretary(Power), MoP on 18th
August 2015 it was noted that
this line was considered in the
transmission plan.
11.4.2. In earlier Meetings the following had been noted:
PGCIL had informed that regarding 400 kV Dharmapuri - Somanahalli line, DC
(Urban) had ordered compensation of 100 % of fair value for tower footing and 55
% for line corridor. With this, cost of 30 kM line was working out to as high as Rs
90 crore. Hon’ble Power Minister of Karnataka was scheduled to make a site visit
shortly to look into compensation issues etc.
KSEBL had suggested that ICTs at Areakode substation be enhanced to 3x315
MVA or 2x500 MVA from the existing 2x315 MVA in view of the increased
power flow towards North Malabar region. CTU had agreed in principle for the
additional ICT and stated that the requirement and capacity (315 or 500 MVA)
could be finalized in the Standing Committee. Space actually available in the
substation was also required to be kept in mind
KPTCL had stated that they had already referred issue of 400 kV UPCL-
Kasargode- Kozhikode line to the Standing Committee.
11.5. Critical Intra-regional transmission elements
11.5.1. The following is the status update:
Sl.
No. Transmission Element Expected CoD Remarks
1 765 kV Salem- Tumkur
By PGCIL
Through TBCB
March 2016
June 2016
Severe RoW problem near Tumkur.
2 400 kV Edamon-Kochi Dec’2016 Govt. of Kerala issued revised G.O
in Jan’2015 with enhanced
compensation. Being monitored
under PRAGATI
3 765 kV Raichur-Kurnool COD on
15.12.2015
4 400 kV Khammam– N’Sagar
D/C
COD on
03.01.2016
TBCB
11.5.2. The following was noted in earlier Meetings:
KSEBL had informed that associated works regarding 400 kV Edamon-Kochi may
commence after two weeks. KSEBL had assured of full assistance and cooperation
in this regard.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 26 of 75
PGCIL had informed that 400 kV Edamon-Kochi was being monitored under
‘PRAGATI’ (Pro Active Governance And Timely Implementation). Chief
Secretary, Govt. of Kerala had conducted a meeting with DCs, SPs and senior
police officials to sort out the survey/sorting of RoW issues. Detailed survey was
still pending in about 20 kM stretch which was required to finalize tower schedule
etc. With considerable efforts, the contract which was originally entered in 2007
had been revived. Immediately, a Task Force had also been formed to expedite
addressing of various issues. With the support of Kerala Govt. and MoP, this line
was likely to move ahead.
Regarding 765 kV Tumkur - Dharmapuri, PGCIL had informed that the line was
crossing four districts in Karnataka (Tumkur, Kolar, Chikkaballapur & Bengaluru
Rural) and RoW issues were being addressed in a stepwise manner.
11.6. 400 kV Trichur-Kozhikode line (Madakkathara-Areakode)
In the 27th
Meeting of SRPC it had been agreed that KSEBL could execute Madakkathara-
Areakode and Kozhikode-Mylatti lines after due ratification by Standing
Committee/CEA. In the 28th
SRPC Meeting, KSEBL had informed that KSEBL would
get the modifications ratified by the Standing Committee of PSPSR. Works would only
be taken up subsequently.
11.7. Closing of Upper Sileru-Balimela Line
In the 27th
TCC Meeting, APTRANSCO had stated that downstream lines such as Lower
Sileru - Bommur were getting overloaded and hence it may not be feasible to close the
lines on sustained basis.
11.8. Utilization of Jeypore - Gazuwaka link to its full capacity i.e 1,000 MW
11.8.1. The following had been noted in .earlier Meetings:
TSTRANSCO had expressed concern that the link capacity needed to be utilized
fully and some short term measures need to be identified. This could also involve
shifting of any STATCOM from other parts of the country to Gazuwaka.
SRLDC had stated that in the present Grid scenario due to low short circuit level of
Gazuwaka and upstream line loadings in GRIDCO system power up to 750 MW
only could be imported. NLDC had observed that Jeypore had a low fault level of
2,400 MVA while other adjoining nodes were having fault level of about 4,000
MVA. In case of any line tripping, the fault levels are reducing. Severe voltage
oscillations were being observed even for 100 MW upstream change in
load/generation
CTU had intimated that STATCOM along with mechanically switched
reactors/capacitors were planned to be commissioned in 2 to 3 years’ time frame
(tendering stage) which would then stabilize voltage variation at Jeypore. Around
650 MW was being permitted on this link. Few issues such as Pole-I being an old
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 27 of 75
installation, non-commissioning of Talcher- Behrampur- Gazuwaka backup system
were constraints in utilizing the link to full capacity.
After deliberations, it was agreed that the issue would be discussed in a Special
Meeting to be held with participation from CTU to assess possibility of short term
measures to improve import capability. Subsequently, a Meeting with
ERLDC/ERPC could be held.
11.8.2. In the Special Meeting held on 30.10.2015 (minutes available in SRPC website) the
following had been noted:
CTU representative informed that to overcome above stated issues, one
STATCOM has been approved at Jeypore along with other proposed STATCOMs
in the Eastern Region in SCPSPSR-36. However, as all STATCOMs proposed in
the Eastern region are planned to be implemented through PSDF funding, there is a
delay in clearing procedural formalities, and steps are being taken to expedite the
same. .
11.9. NLDC vide letter dated 8th
January 2016 (available in NLDC website) had highlighted
prioritization of transmission system under implementation to relieve congestion.
ISTS system already approved and commissioning of which was expected to relieve
congestion in respect of SR as given below:
Talcher backup system being executed by TTCL and approved timeline was
Sep’2013
HVDC Raigarh-Pugalur Bi-pole
765 kV Wardha-Hyderabad D/C
765 kV Angul-Srikakulam –Vemagiri
System beyond Vemagiri
765 kV Kudgi- Madhugiri D/C (to be charged at 400 kV)
400 kV Madhugiri-Bidadi
400 kV Madhugiri-Yelahanka
400 kV UPCL-Mylatti-Kozhikode
765 kV Tumkur PS- Dharmapuri S/C
765 kV Tuticorin PS – Dharmapuri PS D/C
400 kV New Somanahalli- Salem D/C
400 kV Tirunelveli-Edamon- Muvaptuzha(Kochi) D/C
400 kV Tirunelveli-Kanarpatty D/C
400 kV Kanarpatty-Kayathar
400 kV Trichur – Kozhikode D/C
It had also been highlighted that most of the transmission was required on priority.
12. UPCOMING RENEWABLE PROJECTS AND THEIR INTEGRATION WITH
TRANSMISSION NETWORK
Status update of the upcoming schemes in Southern Region for renewables as given
below is given at Annexure-XXI.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 28 of 75
Uravakonda Wind – AP
Solar Power Park at Ghani/Panyam (1000 MW )Phase-I Works – AP
1000 MW Wind Power at Aspiri- AP
1500 MW NP Kunta Solar Project- AP
Kamuthi Solar (Max 100 MW injection)- TN
Samugarengapuram Wind (1800 MW existing + 300 MW) - TN
Green Energy Corridors:- Inter State Transmission Scheme (ISTS) - Part - A
LTA to Wind Generators in Tirunelveli Area - Tamil Nadu
Connectivity to Wind Generators in Coimbatore Area -Tamil Nadu
Connectivity to Wind Generators in Anantpur Area – AP
Renewables (KfW) Hindupur - AP
Renewables (KfW) Jammalamadugu - AP
Renewables (KfW) Uravakonda - AP
Renewables (KfW) 220 kV Interconnectivities - AP
Renewables (KfW) 132 kV Interconnectivities – AP
Renewables (KfW) Intra-state - Karnataka
Renewables (KfW) Phase I – Tamil Nadu
Tumkur Ultra Mega Solar Park (2000 MW) – Karnataka
13. FOLLOW UP ACTIONS ON THE RECOMMENDATIONS OF CENTRAL
ADVISORY COMMITTEE (CAC) SUB - COMMITTEE ON CONGESTION IN
TRANSMISSION
13.1. Hon’ble CERC had passed order (date of order: 5.8.2015) in Petition No.009/SM/2015,
in the matter of follow up actions with regard to recommendations of Central Advisory
Committee (CAC) Sub-Committee on Congestion in Transmission. Sub-Committee had
recommended measures to reduce congestion in transmission for which necessary
actions is to be taken by CEA, NRCE, CTU, POSOCO, POWERGRID, RPCs as well as
CERC. Commission had considered the report and accepted its recommendations
.Recommendations of the Committee with regard to the actions to be taken by various
agencies along with timelines was decided by the Commission.
13.2. In ROP dated 19.1.2016 in respect of Petition No.009/SM/2015, the following had been
stated:
‘The Commission observed that there is a need to institute a mechanism for monitoring of
the implementation of the recommendation of the CAC Sub-Committee on Congestion in
Transmission in accordance with the time line specified in the Commission`s order dated
5.8.2015. The Commission further observed that National Reliability Council (NRC) be
entrusted with the task of monitoring the implementation of the direction given in order
dated 5.8.2015 and submit periodical report to the Commission for information/further
direction. The Commission directed that an officer associated with NRC may be present
during the next date of hearing.’
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 29 of 75
14. NEW PROJECTS OF NTPC, NLC, NPCIL, JOINT VENTURE & UMPP
14.1. Krishnapatnam UMPP (6x660 MW)
The following had been noted in Meetings of TCC/SRPC:
Hon’ble CERC had passed Orders on 04.08.2015 in respect of Petition No.
283/MP/2012. Relevant extracts reproduced below please:
“Therefore, the issue before the Hon`ble High Court and this Commission is the same
i.e. whether the change in the coal prices on account of promulgation of Indonesian
Regulations is an event of Force Majeure and Change in Law. Moreover, while the
petitioner is challenging the jurisdiction of the Commission to deal with the said
Force Majeure event before the Hon`ble High Court of Delhi, the petitioner is
invoking the jurisdiction of this Commission for a declaration that increase in coal
price on account of Indonesian Regulations is covered under Force Majeure or
Change in Law. In our view, the petitioner should either pursue the appeal before
the Hon`ble High Court or pursue the petition before this Commission. It is pertinent
to mention that despite committing before this Commission, the petitioner did not
take any effective steps to expedite the hearing before the Hon`ble High Court of
Delhi. Since the petitioner is pursuing the appeal before the High Court, we are of
the view that no useful purpose will be served by keeping the petition pending in the
Commission. Accordingly, we dispose of the petition, with liberty to the petitioner to
approach the Commission at the appropriate stage in accordance with law, if so
advised”
In the 27th TCC Meeting, PCKL had informed that the lead procurer and PCKL had
taken appropriate steps with their legal counsel to expedite hearing before Hon’ble
High Court of Delhi.
14.2. Cheyyur UMPP (4,000MW)
In the 27th
TCC Meeting, CTU had informed that this project had been identified
under ‘Plug and Play Mode’ and new bids would be invited during 2015-16.
14.3. Schedule of synchronizing/commissioning of the new projects of NTPC, NLC,
NPCIL, BHAVINI, Joint Venture & UMPP is furnished below:
Station Unit
Installed
Capacity
MW
Scheduled date of
synchronizing /
commissioning
Remarks
NTPC
Kayamkulam I, II,
III
1050/
1950
12th
Plan
Kudgi TPS
Stage-I
I,I,
III
3x800=
2400
Unit-I Synchronization
by March 2016.
CoD by January
2017.
Unit-II
synchronization by
October 2016. CoD
by March 2017.
One Narendra-Kudgi D/C line
declared deemed COD on
04.08.2015 by KTL (L&T infra
projects).
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 30 of 75
Unit–III synchronization by
March 2017. CoD
by July 2017.
Telangana STPP
Phase I
2x800
Pudimadaka -
AP
5x800 85% share to AP
NLC
New Thermal
Power Project
I 500 October 2017
II 500 April 2018
Sirkali TPP I, II,
III
3x660 From GoI approval
Unit I – 52 months
Unit II – 58 months
Unit-III – 64 months
PPA has been signed. Fuel
imported coal. Approval of
Feasibility Report was awaited
from NLC Board.
NPCIL
Kudankulam St-I II 1000 Unit-II:
Synchronization by
April’ 2016.
BHAVINI
Kalpakkam
(PFBR)
I 500 September 2016
UMPP
Krishnapatnam 3960
(6x660)
APEPDCL and PCKL had taken
steps with their legal counsel to
expedite the hearing before
Honorable High Court of Delhi
Cheyyur 4000 MoP had identified the
UMPP under ‘Plug and Play
Mode’ and new bids would
be called in year 2015-16.
In the 116th OCC Meeting NTPC had informed that Kudgi Unit I was planned to be
synchronized during March 2016. Kudgi 400/220 kV ICT was scheduled to be
commissioned by March 2016
15. NEW PROJECTS OF STATE SECTOR & IPP
15.1. Updated status of new projects of State sector furnished below:
Sl
No.
Name of project Located
in
Capacity in
MW
Commissioning Schedule
/Remarks
1 Rayalaseema TPS ST-
IV
AP 1x600 CoD by Dec’ 2016
2 Dr. NTTPS,
Vijayawada
AP 1x800
3 Polaki AP 4000
4 Bellary TPS U-3 KAR 1x700 Synchronized to grid on
25.12.2015. CoD expected by
Feb’2016
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 31 of 75
Coal sync. By Dec.2015
5 Yermarus TPS KAR 2x800 Unit-I: Synchronization by Jan’
2016 and CoD by Feb’2016.
Unit II: CoD by May’ 2016.
6 Kakatiya TPP St.-II Telangan
a
1x600 Light up with Oil started on
07.12.2015 and first
synchronization on 15.12.2015.
7 Singareni Telangana 2x600 Unit I: CoD by April 2016
Unit II: CoD by June 2016
8 Manuguru PPP Telangana 4x270
9 Kothagudam TPS Phase
VII
Telangana 1x800
10 Damaracherla Telangana 2x600 +
4x800
15.2. Updated status of new projects of IPPs is furnished below:
Sl
No.
Name of project Located
in
Capacity
in MW
Commissioning Schedule /Remarks
1 Meenakshi PH-II AP 1x700 2016-17
Untied: 640 MW
2 East Coast Energy
Thermal
AP 2x660
2015-16
AP : 300 MW
3 Thermal Powertech.
(TPCIL) Unit-III
AP 1x660
CoD : 2016-17
4 NCC Krishnapattnam AP 2x660
Unit I : CoD by 2015-16
Unit II: Syn. by September 2016
AP : 500 MW (firmed up PPA to
be signed).
5 Hinduja NPCL, Vizag AP 2x520 Synchronized to grid& Full load
achieved on 27.12.2015
6 Coastal Energen Unit-II TN 1x600 First synchronized to grid on
28.12.2015
7 IL&FS
(ITPCL) Unit-II
TN 1x600
16. EMERGENCY RESTORATION SYSTEM (ERS)
16.1. Availability and proposed plan for development of ERS in Southern Region had been
noted in the 27th
Meeting of SRPC. As per requirement of ERS outlined in MoP letter
dated 05.12.2014, status update is given below please:
Transmission Utility
Requirement as per MoP
Existing Status/Remarks
APTRANSCO 3 Nos. ERS I – Inspection completed on
18.08.2015 (for Nellore). ERS II –
Inspection completed on 22.11.2015 and
expected by February 2016 (for Vizag.)
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 32 of 75
For 3rd
ERS, tendering process had been
initiated.
TSTRANSCO 1 No. Procuring 1 No. of ERS and it would take
10-12 months.
KPTCL 2 No. 2 Nos.
KSEBL 1 No. 1 No. was being taken up by their
transmission wing and was put up for
Budgetary approval.
TANTRANSCO 2 Nos Demo had been given by Vendor.
Estimate to be prepared and would be
submitted to Board.
PED Nil
PGCIL 4 Nos. ( 2 Nos
additional)
2 Nos (SR I
& SR II was
having 1 No.
each)
SR I & II, PGCIL informed that work has
been awarded to procure ERS at 400 kV
level. One of ERS was planned at
Somanahalli and Vijayawada each.
In the 116th OCC Meeting, APTRANSCO had informed that one ERS has been
received on 22nd
December 2015 and has been located at Nellore. Training was being
imparted. The second ERS would be delivered by end February 2016.
17. PROGRESS OF BUS/LINE REACTORS TO BE COMMISSIONED IN SR
17.1. Status of implementation of Bus / Line Reactors / Dynamic Compensation approved in
the Standing Committee / SRPC pending for commissioning by the SR constituents is
furnished below please:
Entity Bus Name Status REMARKS
KPCL Raichur TPS Commissioned on
01.12.2015
As identified in the 22nd
Standing Committee Meeting
on Power System Planning of
SR and as approved in the 4th
SRPC Meeting held on 7th
June
2007 KPTCL
Hoody By December 2015
Nelamangala By December 2015
Talaguppa Commissioned on
26.11.2015
Entity Bus Name
Capacity
in
MVAR
Approved
in Type Remarks
PGCIL Vijayawada 2x125
20th
SRPC/
34th
SC
Bus LOA placed
Would be
Commission
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 33 of 75
17.2. Dynamic Compensation (Approved in 36th
SC)
Entity Bus Name
SC
MVA
GVA /
KA
Dynamic
Compensation
(STATCOM)
Mechanically
Switched
Compensation
(MVAR)
Remarks
Nagarjuna Sagar 125
21st
SRPC/
34th
SC
Bus
ed
progressivel
y by
September
2016 Narendra 125
21st
SRPC/
34th
SC
Bus
Hyderabad 125 21st SRPC
Gooty 125
22nd
SRPC /
36th
SC
Bus
Hassan 125
36th
SC
Bus
Khammam 125 Bus
Kudgi PG 125 Bus
Trivandrum 125 Bus
Nellore (Existing) 125 Bus
Yelahanka 2x63 Bus
Nellore PS on NPS-
Gooty Line
2x63
(37th
SC) Line
Kudgi PG–Tumkur
D/C at each end 4x63 Line
APTRANSCO
Vemagiri 80
21st
SRPC/
34th
SC
Bus By June
2015
Vemagiri 125
36th
SC
Bus By March
2016
Kurnool 125 Bus Tender to
be called
Kalpakka 125 Bus By April
2016
TSTRANSCO
Mamidipalli 125
36th
SC
Bus
By June
2016
Gajwel 125 Bus
Sankarapalli 125 Bus
Mehboob Nagar 125 Bus
NPCIL Kaiga 2 x125
Bus
Process
started
Expected
in one and
half year
after
award.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 34 of 75
Reactor Capacitor
PGCIL
Hyderabad 18.4/
26.5
+ 200 MVAR 2x125 1x125
Under
Tendering
Udumalpet 19.4/
28.0
+ 200 MVAR 2x125 1x125
Trichy 12.5/
18.0
+ 200 MVAR 2x125 1x125
17.3. Possibility of Reactor at Srisailam
17.3.1. A Joint Meeting with CEA, TSGENCO & TSTRANSCO had been held on
16.04.2015. It was noted that reactor at Sattenapalli or Kurnool had been proposed
instead of Srisailam due to space constraint.
17.3.2. In the 114th
OCC Meeting, TSTRANSCO had informed that vide letter dated
06.10.2015 it had taken up the issue with CEA. TSTRANSCO had requested that CEA
may kindly arrange to conduct a comprehensive feasibility study including load flow
studies, reactive power compensation etc. on installation of reactors at Srisailam and at
other ends of connected lines. Necessary information, if any, required from TSGENCO
would be furnished for carrying out the above study.
17.4. Reactive Power Planning
In the 4th
NPC meeting held on 10.12.2015 (MoM dated 01.01.2016), the following had
been noted:
All States to carry out reactive power planning not only at transmission level
but also at distribution level and prepare schemes to maintain voltage profile
as per relevant Regulations / Standards.
NPC agreed that states should adopt a proactive approach in the matter of
reactive power planning, and that the provisions regarding reactive power
planning similar to those mandated in the IEGC for the CTU should be
included in the respective State Grid codes. It was decided that RPCs would
follow up the matter further with the states.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 35 of 75
18. ISSUES IN RESPECT OF CONGESTION CHARGES
18.1. In the 28th
SRPC Meeting it had been agreed as a special case for waiving off of
congestion charges for the first week of June 2015 in view of the fact that notice
/messages had not been timely received by a number of entities. SRLDC had stated that
balance amount had already been transferred to PSDF. It was hence agreed that if
charges are refunded by the receivable entity, it could be given back to the entities (who
had made payment for that week).Else, payments could only be adjusted in the future
congestion accounts.
18.2. Subsequently SRPC vide letter dated 01.01.2016 (Annexure-XXII) had withdrawn the
account issued on 16.06.2015.
19. ADDITIONAL SUPPORT THROUGH 110 KV PARASALA – KUZHITURA
FEEDER
19.1. KSEBL vide letter dated 09.12.2015 (Annexure-XXIII) had requested TANTRANSCO
for drawing up to 250 A on 110 kV level from Kuzhiturai Substation as interim measure
till the 220 kV Substation at Kattakkada is commissioned. It was mentioned that for
drawing about 250A, reconductoring in some stretches and replacement/renovation of
some of the towers are necessary which would take a period of about 2 months to
complete. It was also requested by KSEBL that an early confirmation on facilitating
drawing up to 250A from Kuzhithurai may kindly be communicated so as to commence
line strengthening works as early as possible. It was noted that line strengthening work
carried out by KSEBL would be mutually beneficial in the long run.
19.2. The issue had been deliberated in 115th
OCCM held on 08.01.2016 in which
TANTRANSCO had stated that the line was already loaded up to .maximum and even
for 20 MW flow, the same was getting tripped on overload. Increasing drawal at
Parasala end would overload the feeder feeding from SR Pudur to Kuzhithurai S/S.
19.3. Vide letter dated 07.01.2016, Chief Engineer (GO), TANTRANSCO had communicated
to KSEBL in this regard (Annexure-XXIV).
20. OUTSTANDING DUES BETWEEN SOUTHERN AND WESTERN REGIONS
20.1. TANTRANSCO vide letter dated 09.12.2015 had informed that they had received Rs
98,64,551/- from Maharashtra State Electricity Distribution Co. Ltd
(MAHAVITARAN/MSEDCL) towards, energy transaction for the period from August
1999 to December 2002 (Annexure-XXV).
20.2. MAHAVITRAN vide letter dated 20.11.2015 (Annexure-XXVI).had informed that
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 36 of 75
following payments had been made to SR constituents.
S.NO Constituent Bill amt in (`) Pmt. Details Payment amt in
(`)
1 KSEB 1,19,61,444/- 111 – 12.10.15 1,19,61,444/-
2 Puducherry 27,39,427/- 112 – 12.10.15 27,39,427/-
3 Tamilnadu 98,64,551/- 109 – 12.10.15 98,64,551/-
4 KPTCL 12,09,650/- 110 – 12.10.15 12,09,650/-
Total 2,57,75,072/- 2,57,75,072/-
20.3. Pending payments between WR & SR Constituents as on 09.12.2015 are as follows:
ANDHRAPRADESH / TELANGANA
RECEIVABLE FROM (Rs) PAYABLE TO (Rs)
MPPMCL 1,21,76,270 NIL
KARNATAKA
RECEIVABLE FROM (Rs) PAYABLE TO (Rs)
MPPMCL 13,27,208 CSPDCL 73,72,176
GUVNL 9,40,320
KERALA
RECEIVABLE FROM (Rs) PAYABLE TO (Rs)
MSEDCL 1,19,61,444*
NIL MPPMCL 1,21,47,260
CSPDCL 7,05,279
GUVNL 4,98,019
TAMIL NADU
RECEIVABLE FROM (Rs) PAYABLE TO (Rs)
MPPMCL 1,17,17,268 CSPDCL 92,77,878
PUDUCHERRY
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 37 of 75
RECEIVABLE FROM (Rs) PAYABLE TO (Rs)
MSEDCL 27,39,427* NIL
GUVNL 1,02, 721
Payable by PGCIL (WRTS / SRTS)
State/UT Amount (Rs.) Received Balance to
receive (Rs.)
Andhra Pradesh/
Telangana
47,05,447 3,69,848 4,335,599
Karnataka 49,79,733 3,91,407 45,88,326
Kerala 27,58,402 2,16,811 25,41,591
Tamil Nadu 47,21,994 3,71.149 43,50,845
Puducherry 9,24,035 72,629 8,51,406
Total 1,80,89,611 14,21,844 1,66,67,767
* confirmation is pending from the concerned utility that payment has been
received from MAHAVITRAN (MSEDCL).
20.4. KSEBL had confirmed receipt of payment while Puducherry and KPTCL had yet to
confirm receipt of payment from MAHAVITRAN (MSEDCL).
21. SRPC CERTIFICATION TO CLAIM ADDITIONAL RoE
21.1. PGCIL vide letters dated 19.01.2016 & 02.02.2016 (Annexure-XXVII) have requested
SRPC certification to claim additional RoE in respect of the following assets:
Kurnool – Raichur 2nd
765KV S/C Line along with associated bays and equipment at
Kurnool and Raichur Substations under ISGS Krishnapatnam :It was stated that the
line has been put into commercial operation w.e.f. 21.06.2014 i.e. commissioned
1.35 months ahead of CERC completion schedule.
Kurnool(New) – Raichur 765KV S/C Line along with associated bays and
equipment at Kurnool and Raichur Substations under SRSS - XXII: It was stated that
the line has been put into commercial operation w.e.f 15.12.2015 i.e. commissioned
13.71 months ahead of CERC completion schedule.
Kurnool – Thiruvalam 765KV S/C Line along with associated bays and equipment at
Kurnool and Thiruvalam Substations under SRSS - XIX: It was stated that the line
has been put into commercial operation w.e.f 29.11.2014 i.e. commissioned 13.04
months ahead of CERC completion schedule.
Nellore – Kurnool 765KV D/C Line along with associated bays and equipment at
Nellore and Kurnool Substations under ISGS Krishnapatnam: It was stated that the
line has been put into commercial operation w.e.f 01.11.2014 i.e. commissioned 1
month ahead of CERC completion schedule.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 38 of 75
21.2. In the 116th
OCC Meeting held on 10.02.2016, the forum had recommended for
Additional RoE.
22. IEGC RELATED ISSUES REQUIRING ATTENTION/ACTION
22.1. Automatic Demand Management Schemes
22.1.1. In line with clause 5.4.2 (d) of IEGC, Automatic Demand Management Scheme was to
have been provided by all constituents by 1stJanuary 2011.SRLDC & SRPC Secretariat
had repeatedly pointed out that automated scheme was to be in place to meet
Regulatory requirements.
22.1.2. In 28th
SRPC Meeting, the following had been noted:
The AMDS logic was finalized as OD >250 MW or 20 % of Schedule, whichever
lower, for 15 minutes when frequency < 49.8 Hz. This setting (49.8 Hz) would be
reviewed for subsequent enhancement to 49.9 Hz. All states would implement this
revised logic by 1st November 2015 without linking to SCADA activities.
However, SRLDC maintained that frequency setting for ADMS scheme should be
49.9 Hz in accordance with IEGC Regulations.
22.1.3. In the OCC Meetings it had been noted that all entities except TN had implemented the
ADMS. Issues like enhancement of quantum and logic were being discussed in the
OCCM. KPTCL was yet to implement the revised logic.
22.1.4. It is now recommended to change the set points to 49.9 Hz in line with IEGC
provisions.
22.1.5. In the 116th OCC Meeting (10.02.2016) the following was noted:
AP: 100 MW additional loads (total 250 MW) had been identified for ADMS and
would be implemented
TN: Mock test had been conducted on 07.02.2016 and ADMS (650 MW) would be
commissioned by 15.02.2016.
22.2. UFR and df/dt reliefs
22.2.1. All States have implemented AUFR and df/dt schemes fully. Details of recommended
and implemented quantum wrt AUFR & df/dt schemes by constituents are shown in
the Table below:
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 39 of 75
Sl.
No
AUFR and df/dt stages
AP TS KAR KER T N Pudu
Reco
mm
end
ed
Imp
lemen
ted
Reco
mm
end
ed
Imp
lemen
ted
Reco
mm
end
ed
Imp
lemen
ted
Reco
mm
end
ed
Imp
lemen
ted
Reco
mm
end
ed
Imp
lemen
ted
Reco
mm
end
ed
Implem
ented
AUFR Average MW
1 Stage-I (49.2 Hz) 392 392 417 419 576 578 204 214 740 804 21 21
2 Stage-I (49.0 Hz) 393 393 419 420 578 578 205 217 744 808 21 22
3 Stage-I (48.8 Hz) 398 398 424 426 586 593 208 212 753 867 21 25
4 Stage-I (48.6 Hz) 399 399 426 431 588 593 209 211 756 867 22 24
AUFR Total 1582 1582 1686 1696 2328 2342 826 854 2993 3346 85 92
1 df/dt stage-I (at 49.5 Hz
& 0.2 Hz/sec fall of
frequency) 345 345 367 368 474 483 172 178 624 626 18 12
2 df/dt stage-II (at 49.3
Hz & 0.3 Hz/sec fall of
frequency) 855 855 912 914 737 734 175 175 559 572 0 6
df/dt Total 1200 1200 1279 1282 1211 1217 347 353 1183 1198 18 18
22.2.2. Hon/ble CERC vide Order dated 27.11.2015 in respect of Petition No. 60/MP/2014 had
directed KSEBL to file a confirmation report regarding completion of AUFR & df/dt
relays mapped to SCADA system of KSEBL to SRPC by 31.12.2015 . In the Order
SRPC Secretariat had also been directed to submit status of Implementation of
mapping of AUFR & df/dt relays with SCADA system in respect of all constituents of
SR by 31.01.2016.
22.2.3. SRPC vide letter dated 29.01.2016 (Annexure-XXVIII) had submitted status report
duly certified by SRLDC and SRPC wrt implementation of SCADA mapping of all
constituents to Hon’ble CERC. SCADA mapping confirmation report of KSEBL had
also been submitted to Hon’ble CERC. Status of SCADA mapping details as submitted
to Hon’ble CERC is given below please:
Figures in MW
Recommend
ed quantum
(AUFR+df/dt)
Implemented
quantum
(AUFR+df/dt)
SCADA
monitorable at
SRLDC
% Monitorable
wrt
Recommended
quantum
AP 2782 2782 1169 42%
TS 2965 2978 1898 64%
KAR 3539 3559 3557 101%
KER 1173 1207 1184 101%
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 40 of 75
TN 4176 4544 3849 92%
Pudu 103 116 116 113%
SR 14738 15186 11773 80%
22.2.4. In the 4th
NPC meeting held on 10.12.2015 (MoM dated 01.01.2016), the following
had been noted:
Ensuring proper functioning of Under Frequency Relay (UFRs) and df/dt
relays
…………. at least 20% of the under frequency relays installed in the respective
regions should be physically inspected by respective RPCs in each year besides
self-certification by the STUs. Regarding self-certification by the STUs
regarding healthiness of the UFRs as per checklist proposed by NRPC, Other
RPCs were requested to forward their comments / suggestions to NPC for
evolving a uniform procedure across the states at the next meeting.
Automatic Under Frequency Load Shedding (AUFLS) scheme:
NPC expressed satisfaction that barring a few states, the revised AUFLS scheme
had been implemented by the states in the country. It was decided that the RPCs
would take up the matter of implementation of the scheme with the states which
had not so far implemented the same and inform the progress at the next
meeting.
Review settings of df/dt relays and UFR based automatic load shedding
schemes
Review of df/dt relays:
NPC opined that in the event of a sudden loss of generation or any grid
disturbance, the rate of fall of frequency would vary from one location to another,
and it would also vary from one point of time to another at a particular location
depending upon the distance from the location of the fault. Therefore, there could
be no uniform setting of df/dt relays in different regions. In view of this, NPC
decided that settings would be determined by each RPC separately after detailed
study of load and generation balance in different areas of the region and
communicate the same to the Committee for ratification.
Review of Automatic Under-Frequency relay based Load-shedding Scheme
(AUFLS)
NPC decided to maintain status quo in respect of AUFLS. It was also agreed by
the RPCs to initiate the process of mapping of feeders covered under AUFLS
scheme like SRPC with a view to ensuring proper implementation of the scheme
and also have a real time assessment of load-relief likely to be available under the
scheme if it operated.
22.3. UV Relay Installation at Low Voltage Nodes
22.3.1. The following had been noted in various Meetings:
KPTCL: Automated UV relay scheme was under review.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 41 of 75
SRLDC had stated that Bangalore voltage was very less for around 20 % of time
during December 2015 and touched 380 kV also. KPTCL was requested to expedite
the automated UV relay implementation.
KSEBL: Revised set points had been implemented both at Palakkad and Thrissur.
TANTRANSCO: TN to provide relays and cable terminations to PGCIL to extend
under voltage conditions (dv/dt or V+t to Myvadi 230 kV RTU) of Myvadi 400 kV
Bus for the implementation of UV relay scheme at Udumalpet. This was expected to
be completed by June 2016. PGCIL informed that they had extended the signal to
Myvadi substation as desired by TN and relay procurement and other works were
under TANTRANSCO’s scope.
It was noted that in the 27th
TCC Meeting held on 9th
October 2015, TANTRANSCO
had committed that they would implement UV relays by December 2015. No action
plan had been given by TANTRANSCO. Need for implementation of the same on
urgent basis was emphasized. TANTRANSCO had been requested that this issue may
kindly be taken up with their Higher Management.
22.3.2. In the 116th
OCC Meeting (10.02.2016) the following was noted:
KAR: It was noted that UV Relay had operated on 12.01.2016. KPTCL stated that
Automated UV Scheme was in place.
TN: Would be commissioned by end of February 2016
22.4. Restricted Governor Mode of Operation (RGMO)/FGMO of Generating Units
22.4.1. RGMO response was being analyzed in the OCC meetings and inadequate response
was an area of concern and there was no noticeable improvement. SLDCs were to
analyze RGMO instances posted by SRLDC for the generators in their control area and
initiate suitable action as per orders in respect of 84/MP/2015. Inadequate Response
was to be taken up with SERC (Petition No.302/MP/2013).
22.4.2. It was noted that Hinduja NPCL (IPP) was yet to confirm that RGMO was meeting
IEGC requirements. In Bellary Unit-III (KPCL), & Kakatiya Stage-II Unit
(TSGENCO), RGMO was implemented and enabled. RGMO was not implemented in
Mettur Stage-III which was in violation with IEGC provisions.
22.4.3. Regarding extension of RGMO status point to SRLDC/SLDC, the following had been
noted in the Meetings of OCC:
APTRANSCO: Upper Sileru (Cable problems) & Machkund (RTU problem)
stations. Krishnapatanam Unit -1 have implemented RGMO and extended the
status point to SLDC. It was informed that RGMO implementation and extending
the status point of Unit-2 will be completed by 25th
Dec 2015.
TSTRANSCO: Status points were done for Thermal units. Status on Hydro units
was to be furnished.
TANTRANSCO: MTPS- I & II, MTPS St-III & Hydro stations were pending
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 42 of 75
KPCL: Taking up with the Management and they would extend the status point of
all thermal units except Unit 4 of RTPS as it was under Japanese OEM. Status
points of all hydro units like Almathy, Kadra & Gerusoppa HEPs to SLDC had
been made available but yet to be configured to SLDC.
22.4.4. Hon’ble CERC had issued Order on 23.10.2015 in respect of Petition No.
302/MP/2013 and the following are the highlights:
Oil support, if required, for grid security needs to be resorted.
Taking out of RGMO/FGMO with MI during technical minimum condition or for
any other reason is not desirable, as it would jeopardize grid security.
RLDCs/SLDCs have inherent powers to restrict the schedule corresponding to 100
% if installed capacity without vide valve open condition even at part loads
ensuring primary governor response at all stages. It was reiterated that unit should
not be scheduled beyond 100 % of MCR rating.
SLDCs through their respective SERCs may initiate action against Generators
which are not adhering to Regulation.
It was mentioned in the Order that irrigation based project would be exempted
from implementation of RGMO/FGMO.
22.4.5. SRLDC had pointed out that in view of CERC Order w.r.t Petition No.302/MP/2013,
SLDCs need to restrict the state generators schedule suitably. They would take
normative auxiliary consumption from REA of SRPC and would apply it to on bar
installed capacity. In case DC being declared was less due to some coal/technical
constraints it was generators responsibility to accommodate 5% margin for RGMO
response. It was emphasized that wide valve operation should not be envisaged during
DC declaration.
22.4.6. In the 116th
OCC meeting, Mettur TPS St- III confirmed that FGMO with MI was in
place and RGMO was under consideration.
22.4.7. KSEBL vide letter dated 06.02.2016 had raised certain issues regarding curtailment
of schedule without change in DC. In 116th
OCC Meeting, the following
methodology was agreed regarding curtailment of schedule to ensure suitable margins
for RGMO/FGMO:
ISGS generators would also furnish the ex- bus capability to ensure margins
for RGMO/FGMO.
Schedules would be restricted to the above ex-bus capability.
Revisions in schedules and URS surrenders/allocation methodology would be
furnished by SRLDC
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 43 of 75
22.5. Low Voltage Ride Through (LVRT)/Provisions of CEA Regulations in respect of
Renewables
Hon’ble Commission had issued Order dated 05.01.2016 in respect of Petition
420/MP/2014 and number of actionable points had been directed for different Utilities.
A Meeting in this regard was held at SRPC, Bangalore on 05.02.2016 (record notes
available in SRPC website). All concerned utilities are kindly requested to take
necessary action as enumerated in the record notes to ensure compliance of CERC Order
as well as CEA Regulations.
22.6. Demand Estimation for Operational Purpose (Clause 5.3 of IEGC)
Each SLDC was to create a mechanism and facilities to facilitate on-line demand
estimation of demand for daily operational purpose for each 15 minutes block by
01.01.2011. In this regard, following may kindly be noted as contained in Order dated
19th
December 2013 of Hon’ble CERC in Petition No. 249/250/251/MP/2012:
“We direct all STUs/SLDCs of the Northern Region, Southern Region and
Eastern Region to forecast their demand and make adequate arrangements to
avoid dependence on Unscheduled Interchange for meeting their demand or for
injecting short term surplus power, irrespective of the frequency.”
Load Forecasting tool meeting the regulatory requirement yet to be developed by all the
utilities.SRLDC/SRPC Secretariat had expressed concern that Regulatory requirements
had not been met since the scheme was to have been in place by 01.01.2011.
22.7. Sudden Change in Demand/Frequency Excursion
22.7.1. In the earlier Meetings, violation of Clause 5.2 (j) of the IEGC Regulations has been
highlighted. No user is to cause sudden variation in its load by more than 100 MW
without prior intimation to and consent of the RLDC. Similarly no user should reduce
the generating unit output by more than 100 MW without prior intimation to and
consent of the RLDC. Necessary action was sought in respect of demand and
generation management as well as power purchases, so that clause 5.2 (j) of IEGC
Regulations is not violated.
22.7.2. SRLDC/SRPC Secretariat had expressed concern that Regulatory provisions were not
being fully met and requested for necessary compliance.
22.8. Arranging of interruptible loads in four groups
22.8.1. As per IEGC, to maintain the frequency within stipulated band and also to ensure
network security, interruptible loads are to be arranged in four groups of loads. This
was for the purpose of scheduled power cuts/load shedding, loads for unscheduled load
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 44 of 75
shedding, loads to be shed through UF relays, df/dt relays and loads to be shed under
any SPS Scheme. These loads are to be grouped in such a manner that there was no
overlapping between different groups of loads.
22.8.2. Existing schemes were not meeting the Regulatory requirement fully and further action
was required in this regard please.
22.9. PSS Tuning
22.9.1. 2nd
Meeting of PSS tuning was held on 30.10.2015 and many actionable points were to
be carried out by Generators of SR. Many generators had not furnished information in
this regard as requested. SRPC vide letter 22.01.2016 (Annexure-XXIX) had
communicated that all generators/utilities may kindly furnish PSS details and Step
Response Test Reports in the specified format at the earliest.
22.9.2. It is kindly requested that necessary action may kindly be taken as finalized in the 2nd
meeting of PSS.
22.9.3. In 4th
NPC meeting held on 10.12.2015 (MoM dated 1.1.2016), it was noted that the
Enquiry Committee constituted by GOI to enquire into grid disturbances of July 2012
had recommended proper tuning of electronic devices and PSS of generators.
Accordingly, NRPC submitted their recommended procedure to NPC for comments
/adoption by other RPCs so as to bring uniformity across all regions. It was agreed that
other RPCs would examine the proposal of NRPC and revert back in the next NPC
Meeting.
22.10. Scheduling of Simhadri STPS Stage-I by SRLDC
APTRANSCO had filed a Petition in CERC in this regard and the petition was admitted
on 7th
January 2016. A hearing in this regard is also scheduled on 16th
February 2016.
22.11. SPS related Issues
22.11.1. Implementation of additional loads for SPSs
22.11.1.1. The following was deliberated in earlier Meetings:
Mock Testing of signal extension w.r.t TANTRANSCO, KSEBL & KPTCL had
been carried out on 13.10.2015 for additional requirement of SPS loads of 1,500
MW as per NLDC and found successful.
TSTRANSCO had identified loads of 875 MW under Veltoor, 400/220 kV Gajwel
S/S, 220 kV Budidampadu S/S and 220 kV RSS S/S. All DTPCs had been
installed in TSTRANSCO identified substations. PGCIL needed to extend signal
from Kolar to TS DTPCs.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 45 of 75
22.11.1.2. Unit II of Kudankulam was expected by April 2016 and all constituents thus need to
identify feeders for the quantum envisaged as given below:
22.11.2. Modification in SPS of Raichur-Sholapur
22.11.2.1. It was noted that NLDC vide letter dated 23.12.2015 (Annexure-XXX) had
furnished revision in SPS settings subsequent to the commissioning of 765 kV
Kolhapur-Kudgi D/C line of Powergrid. KSEBL vide letter dated 07.01.2016 had
raised certain observations on SPS settings and stated that being an important issue
implementation could be considered only after detailed discussion. SRPC vide letter
dated 07.01.2016 had brought to attention of NLDC the views of Kerala.
22.11.2.2. A Meeting in this regard is scheduled to be held on 19th
February 2016.
22.11.3. Non Operation of Raichur-Sholapur SPS
22.11.3.1. NLDC vide letter dated 5th
January 2016 (Annexure-XXXI) had expressed concern
on the following issues regarding SPS scheme for Raichur-Sholapur D/C lines which
required urgent attention in terms of root cause analysis and taking necessary
actions:
I. Non – Operation of SPS on 2nd
January 2016
II. Revision in SPS settings subsequent to the increased TTC/ATC and
operationalized LTA/MTOA.
Trip
Signal AP KAR KER TN TS PUDU SR SPS
KKNPP 116 174 91 315 132 20 848
Loads to be identified & implemented by March 2016
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 46 of 75
22.11.3.2. SRPC vide letter dated 07.01.2016 (Annexure-XXXII) had requested Powergrid
SRTS I & SRTS II that reasons for non-operation of SPS may be kindly examined
and needful corrective action taken to ensure healthiness of SPS at all times.
22.11.4. Udumalpet - Palakkad SPS
22.11.4.1. SPS for Udumalpet-Palakkad lines was discussed in a Special Meeting held on
03.02.2016 (Minutes enclosed as Annexure-XXXIII). The SPS would be reviewed
after commissioning of Tirunelveli-Kochi Line.
22.11.4.2. KSEBL/PGCIL are requested to kindly initiate necessary action.
22.11.5. SPS Maintenance Protocol
22.11.5.1. In the 28th
SRPC meeting, SPS Maintenance Protocol to be implemented by PGCIL
was agreed. In the OCC Meetings, PGCIL had informed that Management approval
had been taken and work would be awarded soon.
22.12. Instantaneous Scheme for Sudden Withdrawal of Wind
22.12.1. In the Special Meeting held at Chennai on 20th
July 2015. TANTRANSCO had
informed that their P & C wing was taking up the above scheme and it would be in
place by 31st August 2015. In 27
th TCC meeting, TANTRANSCO had informed that
the scheme would be implemented by December 2015. In 115th
OCC meeting,
TANTRANSCO had stated that the scheme would be implemented by June 2016.
22.12.2. Hon’ble CERC in its Order dated 05.01.2016 on Petition No. 420/MP/2014 had stated
“In our view TANTRANSCO has failed to comply with the Commission's direction
given in order dated 22.2.2014 in Petition No. 120/MP/2011. Accordingly, we direct
SLDC, Tamil Nadu to explain the reasons, on affidavit, by 29.1.2016 as to why action
under Section 142 of the Act should not be initiated against it for non-compliance with
the provisions of the Grid Code and order of the Commission.”
22.13. Energy Generation data Management from Renewable Energy Sources
The following had been noted in earlier Meetings:
TANGEDCO had informed that a comprehensive scheme from the Energy Meters
along with AMR was under implementation. Scheme covered 4,500 existing
Energy Meters along with 8,500 new Energy Meters.
On a query it had been confirmed that Real Time Data (2-4 seconds) would also
be available at SLDCs. The scheme was being planned through GPRS and a
number of service providers were covered. This would improve the visibility of
wind generation significantly and assist in judicious decision making by the
operators at SLDC.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 47 of 75
In the 27th
TCC meeting, TANGEDCO had informed that the comprehensive
scheme of Energy Meters along with AMRs would be in place by February 2016.
22.14. Pending issues of KKNPP
22.14.1. Need for additional reactor at KKNPP switch yard
NPCIL had informed that KKNPP unit would absorb 150 MVAR against 100
MVAR presently.
NPCIL had approached CTU regarding study for need for additional reactor.
As agreed in the 28th
SRPC Meeting, a Special Meeting was conducted at Bengaluru
on 20th
October 2015 (Minutes available on SRPC website) .The following was noted:
CTU representative stated that it was desirable that any additionally required
reactor come at a location that is close to source of VAR generation.
It was decided that KKNPP would take suitable measures to ensure that no VAR
injection takes place (from LV side) at voltages greater than 400 kV.
22.14.2. Implementation of auto reclose with 1½ breaker scheme
In the Special Meeting held on 20.10.2015, it was decided that KKNPP would come
up with suitable action plan to provide A/R on 400 kV KKNPP – Madurai line.
In the 115th
OCC Meeting, KKNPP informed that the response from Corporate was
awaited.
22.14.3. Pending SCADA inputs to SRLDC
KKNPP had informed that tenders had been opened and SCADA inputs would be
provided by February 2016.
In the 115th
OCC Meeting, KKNPP had informed that out of 13 pending SCADA
points, 11 points had been extended up to RTU.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 48 of 75
22.15. UN-REQUISITIONED POWER
22.15.1. In the 113th
OCC Meeting SRLDC had informed that as per CERC Order dated
05.10.2015 on Petition No. 310/MP/2014 they would implement a new methodology
for URS allocation from 1st December 2015 onwards. A Special Meeting was held on
20.11.2015 (MoM available at SRPC website) for further deliberations on this issue.
22.15.2. SRPC vide letter dated 03.12.2015 (Annexure-XXXIV) had submitted
implementation difficulties in respect of Hon’ble CERC Order dated 05.10.2015 on
Petition No. 310/MP/2014. It had been requested that issues may kindly be arranged to
be examined and scheduling of URS Power may kindly be continued by
RLDC/POSOCO for improved utilization. Subsequently Hon’ble CERC had brought
out Order dated 18.12.2015 on Petition No. 16/SM/2015.
22.15.3. Extracts of CERC Order dated 18.12.2015 on Petition No. 16/SM/2015
Quote
3 Considering importance of the issues highlighted by the Member Secretary, SRPC,
the Commission is of the view that the matter needs to be heard at length with the
involvement of NLDC, SRLDC, SRPCs, ISGSs in Southern Region and the
Beneficiaries of the Southern Region.
4 Accordingly, it is directed that all concerned may file their views on affidavit on
the issues highlighted by Member Secretary, SRPC by 30th
December 2015.The
matter will be heard by the Commission on 05.01.2016. It is also directed that
RPCs / RLDCs/ISGs/ Beneficiaries of ISGSs of the other regions are also at
liberty to participate in the process dings of the Commission.
5. It is further directed that pending issue of clarification by the Commission as may
be considered necessary; RLDCs shall continue to schedule the URS Power in
accordance with our directions in order dated 05.10.2015.
Unquote
22.15.4. Hearing on the Petition was held on 05.01.2016. ROP dated 11.01.2016 is enclosed at
Annexure-XXXV and the extracts are reproduced here:
Quote
7. After hearing the learned counsel and the representatives of the parties, the
Commission observed that while SPL and CGPL do not have any difficulty in
scheduling of URS power in accordance with the direction of the Commission dated
5.10.2015, the Central Generating Stations and their beneficiaries have expressed
their difficulties in arranging consents of the surrendering beneficiary (ies) and the
requesting beneficiary (ies) for scheduling of URS power for each revision of
schedule. The Commission further observed that the Central Generating Stations and
their beneficiaries do not appear to have any difficulty in giving standing
unconditional consents with regard to scheduling of URS power. The Commission
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 49 of 75
directed that in modification of the direction in para 5 of the order dated 5.10.2015
and pending final decision on the issue, the following procedure shall be followed:
Where both the generating station and its beneficiaries (surrendering and requesting
beneficiaries) give their standing consents in writing to RLDC that the decision of the
concerned RLDC will be binding on them with regard to scheduling and dispatch of
URS power, the concerned RLDC shall schedule such URS power to the requesting
beneficiaries in relative proportion to the quantum requested by them. In other cases,
RLDCs shall schedule URS power on the basis of the consents submitted by the
generating stations in terms of the order dated 5.10.2015.
8. The Commission directed the respondents to file their replies by 22.1.2016, if already
not filed. The Commission directed that due date for filing the replies should be
strictly complied with. No extension shall be granted on that account.
9. The petition shall be listed for hearing on 23.02.2016.
Unquote
22.16. PROLONGED OUTAGES
22.16.1. In the 115th
OCCM Meeting held on 08.01.2016, the criteria for putting generating
units/Transmission elements under prolonged outage criteria was finalized:
In case of Annual Maintenance:
i. Generating units - Revival beyond five days of scheduled period.
ii. Transmission elements - Revival beyond two days of scheduled period
In case of forced outages:
i. Generating units - Revival beyond five days of tripping.
ii. Transmission elements - Revival beyond two days of tripping
22.17. Treatment of Bilateral short term and collective transaction in case of grid
disturbances
22.17.1. In the 4th
NPC meeting held on 10.12.2015(MoM dated 1.1.2016), the following was
noted:
Committee felt that the matter be first deliberated threadbare among the officers
of RPCs, who deal with the work of regional energy accounting, and a report /
recommendations thereon be put up by them during next meeting for
deliberations by the NPC.
Committee constituted a Working Group with following composition:
1. Director level representative from GM Division, CEA
2. SE/EE (Commercial) level representative from each RPC
3. AGM level representative from NLDC
4. Director (NPC) -Member Secretary/Convener
Working Group would examine & discuss possible options for Treatment of
Bilateral short term and collective transactions in case of grid disturbances and
submit its recommendations within two months for consideration of NPC at its
next meeting.
NPC requested CEA, RPCs and NLDC to nominate their representative for the
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 50 of 75
above Working Group.
22.18. Common Commercial Input data formats for all RPCs
22.18.1. In 4th
NPC meeting held on 10.12.2015 (MoM dated 1.1.2016),it was decided that the
committee formed for finalization of methodology for treatment of collective
transactions may also look into this issue and formulate uniform accounting
philosophy in Regional Energy Accounts being prepared by the RPCs.
22.19. Power swing blocking (PSB) setting in Distance relays:
22.19.1. In the 4th
NPC meeting held on 10.12.2015 (MoM dated 1.1.2016), NPC while
agreeing to NRPC's opinion to have a uniform PSB setting across all regions, decided
to maintain status quo in different regions and await the report of the Consultant
appointed for implementation of the recommendations of the 'Task Force for Power
System Analysis under contingencies' before further deliberations in the matter.
22.20. Other Issues requiring kind attention of TCC / SRPC
The following issues which are being followed up in the Meetings of Sub-Committees
of SRPC merit kind attention:
a) Nominations for Study Group of SLDCs from APSLDC and TSSLDC are awaited.
In the 27th
TCC Meeting, APTRANSCO had informed that nominations would be
communicated after final bifurcation of staff. TSTRANSCO had informed that new
engineers would be recruited by Dec’2015 and subsequently, nominations would be
communicated.
b) URTDSM (PMU) project in SR was to be implemented in 24 months from date of
award. In 115th
OCC Meeting, PGCIL had informed that Ist Stage PMUs have been
already supplied. PDCs are also supplied to AP and Telangana and installation was
being coordinated. 2nd Stage preparations were also underway. It was mentioned that
regular meetings had been conducted on monthly basis and a complete report would
be given to SRPC/RLDC. In the first stage, out of 76 PMUs to be installed, 62 had
been received and 52 had been installed.
c) Phase- I & Phase-II activities identified in Protection Audit need to be completed in
a time bound manner. Timelines given to Constituents vide various Orders of
Hon’ble CERC are given below please:
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 51 of 75
S.
N
o
Constituent CERC
Petition No.
/Date of
Order
Date for
completio
n of
Phase-I
activities
Date for
completio
n Phase-II
activities
Remarks
1 APTRANS
CO
95/MP/2015
Date of
Order :
27.4.2015
31.12.2015 31.12.2015 As the timelines given for
Phase-I and Phase-II works
have been completed,
APTRANSCO informed that
their management is in the
process of filing an
application before CERC for
obtaining further time
extension.
2 TSTRANS
CO
83/MP/2015
Date of
Order :
14.5.2015
31.10.2015 31.08.2016
3 KSEB 86/MP/2014
Date of
Order :
18.8.2015
31.12.2015
31.12.2015
31.3.2016
for R&M
works at
Idukki
HEP
As the timelines given for
Phase-I and Phase-II works
have been completed, KSEB
informed that their
management is in the process
of filing an application before
CERC for obtaining further
time extension.
4 TANTRAN
SCO
374/MP/201
4
Date of
Order :
18.8.2015
30.6.2016 30.11.2016
5 NLC Date of
Order :
18.8.2015
NLC has sought time up to
31-12-2014 and 31-03-
2015 for completion of
Phase-I and Phase-II works
respectively. As the
completion dates for Phase-
I and Phase-II of protection
audit remarks had already
been over, NLC was
directed to file a
confirmation report
regarding completion of
protection audit works for
Phase-I and Phase-II.
NLC informed that their
pending Phase-II works (2
no.) would be completed by
the second week of February,
2016.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 52 of 75
APGECO and TSGENCO had informed that their managements are in the process
of obtaining further time extension.
From the above, it can be kindly seen that time extensions given to various
Constituents have been completed As such, following SR-Constituents, viz.,
APGENCO, APTRANSCO, TSGENCO, TSTRANSCO, KPCL, KPTCL, KSEB,
NPCIL (MAPS), NTPC (Ramagundam), PGCIL (SR-I & II), Spectrum PGL,
GMR-Vemagiri, GMR-Kakinada, APGPCL (Vijjeswaram Stage-I & Stage-II),
Konaseema GPL & LANCO-Kondapalli PL, have been requested to approach
Hon’ble CERC for obtaining further time extensions for the completion of their
pending protection audit works.
d) Reactive Power Planning including at distribution level needs to be submitted to
CEA with a copy to SRPC Secretariat. In earlier Meetings the following details
had been furnished by utilities:
Utility Reactive power Planning Voltage Level Remarks
APTRANSCO 32 x 7.5 MVAR
4 x 14.4 MVAR
33kV level
of 132/33 kV
SS
i.
APEPDCL Srikakulam : 5 x 2 MVAR
Vizianagaram : 5 x 2 MVAR
33/11 kV ii.
6 KPTCL Date of
Order :
18.8.2015
15.1.
2016
15.1.2016 As the timelines given for
Phase-I and Phase-II works
have been completed,
KPTCL filed a separate
application before CERC on
07.01.2016 seeking time
extension up to 31.05.2017,
and the same is under
consideration by CERC.
7 KPCL Date of
Order :
18.8.2015
31.10
.2015
31.12.2015 KPCL informed that they
filed a Petition (No.
265/MP/2015) dated
29.10.2015 before Hon’ble
CERC praying to grant an
extension of time up to
30.12.2016 for completing
the Phases I and II activities.
The Commission in its ROP
dated26.11.2015 for the
Petition No.265/MP/2015 has
directed the KPCL to file
additional submission, if any,
by22.12.2015.
However, as no additional
submission is made by
KPCL, order of Hon’ble
CERC for the petition is
awaited.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 53 of 75
Visakhapatnam : 5 x 2 MVAR
Rajahmundry : 10 x 2 MVAR
Eluru : 4 x 2 MVAR
:
level
APSPDCL April 2015 : 11x2MVAR
May 2015 : 16 x2 MVAR
June 2015 : 16 x2 MVAR
July 2015 : 1 x 2 MVAR
August 2015 : 2 x 2 MVAR
September 2015 : 2 X 2 MVAR
October 2015 : 0
November : 0
11 kV level
TSNPDCL 248*2 MVAR 81x1 MVAR and 80x2 MVAR
capacitor banks commissioned at
11 kV level. Orders had been
placed for 248x2 MVAR capacitor
banks and planned to be
commissioned by March 2016.
TSSPDCL 249 x2 MVAR 11 kV level LoA issued on 29.04.2015 for 221
x 2 MVAR capacitors at 11 kV
level with supply schedule of 4
month.
179 x5 MVAR 33 kV level Tendering under way.
Karnataka Bengaluru Tr. Zone:708.8 MVAR
Bagalkot Tr. Zone :258.1 MVAR
Hassan Tr. Zone :136.3 MVAR
Mysore Tr. Zone :60.9 MVAR
Gulbarga Tr. Zone :98.60 MVAR
Tumkur Tr. Zone :281.3 MVAR
Total of 1544 MVAR which were
planned to be implemented new
PO is placed. Bangalore zone
had ben retendered.
Kerala 15 MVAR 66kV level PO under Progress
TANGEDCO 34 x 2.4 MVAR 11 kV level Material had been received by
December 2015. Work will be
started from January 2015 and
may be commissioned by March
2016.
16 x 2.4 MVAR 22 kV level
7 x 24 MAVR 110 kV level
780 MVAR of capacitors at distribution level had been commissioned out of 1,005
MVAR capacitors planned. 2.4 MVAR capacitors at Somalapauram had been
commissioned on 30.06.2015.
e) Information regarding tripping details with relay indications needs to be furnished in
a timely manner.
f) Information regarding Cyber Security to be furnished to Chief Engineer, DPD, CEA,
New Delhi. Report on Physical Security, other Mock Drills for CMP, Mock Drill for
Black Start Restoration to be furnished to Chief Engineer, DMLF, CEA, New Delhi.
Copy of the report is to be sent to SRPC Secretariat by e-mail.
g) Procedure for restoration of remotely controlled sub stations of PGCIL along with the
contact no. of the person who would take care during emergency conditions needs to
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 54 of 75
be developed and furnished to SRLDC. The procedure was yet to be developed
despite follow-up.
h) Tap changing to recommended voltage level to be carried out at Kaiga GS, Upper
Sileru, Kothagudem TPS (Unit-2,3,4,5,6,7&8), Kadra, Kodasalli, Sharavathi Unit-9,
UPCL, JSWEL, Idukki, Lower Periyar Unit-1, Sabarigiri Unit-1,2&5, Tuticorin TPS,
Mettur Stage-III etc.
Issue regarding high voltages & additional reactor at KGS was discussed in the
Special Meeting held on 20.10.2015 and it was decided that NPCIL would
expedite the commissioning of 125 MVAR Bus Reactors. Further suitable
measures would be taken by Kaiga (U1 & U2) and Kaiga (U3 & U4) to ensure
that no VAR injection takes place (from LV side) at voltages greater than 220 kV
and 400 kV respectively. It was assured by Kaiga U3 & U4 for absorption up to
60 MVAR each from their Units. Kaiga Unit 1 & 2 also assured that absorption
form their units would be as per the corresponding capability curve.
In the OCC meetings, SRLDC/SRPC had expressed serious concern that GT taps
of KGS units were not being changed to recommended levels since long time
which was desirable from grid point of view. SRLDC stated that they would be
constrained to approach CERC if GT taps are not changed as recommended.
SRPC pointed out that it was to be noted that except Kaiga GS, all ISGS/CGS
stations had been changed as per recommendations.
i) Auto Reclose feature enabling for 400 kV Ramagundam – Chandrapur lines, 400 kV
lines at Kaiga (Kaiga –Narendra –II already enabled), 230 kV Neyveli – Villianur
lines , 230 kV Neyveli – Bahoor line, 230 kV BHAVINI – Siruseri, Chikkodi-
Mudshingi/Talangde & Ambewadi-Ponda lines Auto Reclose to be enabled for all
Inter Regional, Inter State and 220 kV& above lines
It was noted that the scheme of both the lines at Bhadrawati had been checked
for its correctness and functionality.SR I PGCIL had requested HVDC
Bhadravathi to confirm on the action plan for implementation of the A/R
scheme on Ramagundam- Chandrapur-D/C lines at Bhadrawati end.
SR-II, PGCIL had informed they were agreeable for PLCC up gradation at their
own cost and proposal had already been initiated and it would take 5-6 months
from completion. PLCC panels were ready and procurement of protection
couplers was going on. One spare protection coupler at Sriperumbudur could be
used and the works would be completed by end of January 2016
KGS had informed that A/R scheme was enabled for Kaiga-Narendra I & II line
and they would implement A/R feature for Kaiga-Guttur lines after stabilization
of lines.
TANTRANSCO had confirmed that A/R feature was available at Siruseri end. It
was noted that in the Meeting held at MAPS, Kalpakkam on 16th
December 2015
it was informed by BHAVINI that they will revert back in this regard.
Regarding Chikkodi- Mudshingi/Talangde lines KPTCL confirmed that at load
end (Chikkodi) A/R was not in service because of some relay replacement issues
which would be completed by month end. As soon as the relays were replaced
A/R would be energized at Chikkodi end by January 2016. It was noted that at
Mudshingi A/R was in service.
Regarding Ambewadi-Ponda KPTCL had informed that the R&M works were
going out for this line and the A/R would be covered in R&M works.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 55 of 75
j) Operation of Nagarjuna Sagar in pump mode.
k) Restoration of 200MVA, 400/132 kV ICT-II at NTPC Ramagundam. TSTRANSCO
had offered 315MVA, 400/220 kV ICT for interim replacement as it was essential to
cater loads around RSS (Malyalapalli), Jagityal and Karimnagar areas.
l) TANTRANSCO had requested PGCIL to prioritize and expedite commissioning of
3rd
ICT at Kalvinthapattu. In the TCC Meeting, PGCIL had informed that they were
expediting 3rd
ICT at Kalvinthapattu and the same would be commissioned by January
2016. Associated bays would also get commissioned.
m) UPCL vide E-mail dated 05.01.2016 (Annexure-XXXVI) had expressed concern
regarding the increased tripping of 400 kV UPCL – Hassan and 220 kV UPCL –
Kemar lines severely hampering UPCL generation. The issue was deliberated in the
115th
OCC Meeting held on 08.01.2016 in which PGCIL had assured of improved
availability since they had taken over the maintenance from KPTCL.
n) 400 kV Kaiga-Guttur lines were out due to tower collapse in KPTCL portion of the
line. The lines were out from 29.11.2015. Ckt I was revived on 20.12.2015 while ckt
II was revived on 13.01.2016. It is a critical evacuation line for Kaiga. Important lines
need to be restored on priority.
o) SRLDC has taken up the task of Tap optimization of all ICTs in SR. As of now
SRLDC has done the tap optimization of 765/400kV, 400/200kV ICTs. To optimize
tap position of all 220/132kV and 230/110kV transformers, tap information (number
of taps, nominal tap position and present tap position) of all 220/132kV and
230/110kV transformers is required. It was requested by SRLDC that tap information
of all 220/110kV and 230/110kV transformers in the respective control areas may
kindly be provided as early as possible’
p) In the OCCM it was noted that NPCIL units would ensure DC close to actual and also
revise DC at the earliest during tripping of the units (within next block).
q) SRLDC had expressed concern on high loadings and N-1 violation of Nellore,
Arasur, Vemagiri, Somanahalli & Ramagundam ICTs. It was pointed out that there
was insufficient action in controlling the loading of ICTs leading to N-1 criteria
violation in compliance of Regulation 3.1f (8) of CEA (Grid Standards) Regulations
2010 and Regulation 3.5 a(i) of CERC Indian Electricity Grid Code Regulations
2010. High loading of Arasur and Nellore ICTs were referred to the Member
Secretary, SRPC under Clause 1.5 of IEGC 2010 vide SRLDC letters dated
30.12.2015.
r) SRLDC had informed that request for SCADA integration of new elements in ISTS
& Intra-STS network should be communicated at least one week in advance of COD
and last minute request would not be entertained. In GE system it could be integrated
online while in Alstom system shutdown was required (main and standby one at a
time). SRLDC had also emphasized that permission for synchronization of new units
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 56 of 75
would be given only after ensuring that their GT Tap positions were kept at a position
corresponding to 400 kV.
s) In the 114th
OCC Meeting it was noted that Puducherry vide letter dated 12.11.2015
had informed that they would explore the possibilities of diverting 23 MW quantum
of load relief from ADMS in operation at Puducherry to the newly proposed SPS
scheme at the first instance and accordingly co-ordinate with PGCIL for further
action. SR II, PGCIL had agreed that they would extend the signal up to Puducherry
SLDC.
t) Preparation of National Electricity Plan (NEP) is the responsibility entrusted to CEA
under Electricity Act, 2003. Under Section 3(4) of the Electricity Act, 2003, the
Authority shall prepare the NEP in accordance with the NEP and notify such plan in
five years after obtaining the approval of the Central Government. SRPC had
communicated to SR constituent/ states requesting information in the specified
formats vide letters dated 12.01.2016 and 25.01.2016.
u) In the 116th OCC Meeting the following was noted:
KGS: SRPC/SRLDC had expressed concern and stated that the taps were
required to be changed to the recommended value.
JSWEL: Agreed to change to 400 kV level. Unit 2 & 3 shut down was planned
shortly and after verifying the healthiness of OLTC the taps would be changed.
KAR SLDC was requested to ensure that the units come back with recommended
taps.
TTPS: TANTRANSCO informed that they would change the taps to
recommended, as and when opportunity arises.
Mettur Stage III : Agreed to change the Taps to 400 kV level. It was informed
that Bus reactor at Mettur Stage III switch yard was planned to be commissioned
by 31st March 2016.
In the 116th OCC meeting, it was agreed that constituents would take action to
ensure loading below 210 MVA (240 MVA emergency loading for short
duration) for 315 MVA ICTs. Loading up to 340 MVA only would be ensured
for 500 MVA ICTs. States would come up within 10 days about their short term
and long term plan to curtail the loadings.
TANTRANSCO and TSTRANSCO had informed that SPS for Arasur and
Ramagundam ICTs were being planned.
APTRANSCO had informed that 3rd ICT at Nellore was charged on 2nd
February 2016.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 57 of 75
23. GRID STUDY COMMITTEE (GSC) (TASK-2) AUDIT PROGRESS DETAILS
23.1. As per the MoP order dated 16.07.2014, M/s Tractebel Engineering (TE) has been
appointed as Consultant to conduct the study/ analysis of National Grid. The terms of
reference of the Consultant are as follows:
a) To Review the status of implementation of the recommendations of the Enquiry
Committee (Task-1).
b) Carrying out actual protection audit check for 10% (76 nos.) of 762 substations across
the country to address the gaps, in consultation and collaboration with states and all
stakeholders as per present and future requirements (Task-2).
23.2. Task-1 for SR-Constituents was already completed by the first week of September,
2015. The draft report on Task-1 prepared by the Consultant was discussed in the third
Grid Study Committee (GSC) meeting held on 18th
November, 2015. Subsequently, the
feedback of the SR-Constituents was furnished to the Consultant by the last week of
November, 2015. The final report on TASK-1 by the Consultant is awaited.
23.3. Under Task-2, 15 Stations have been identified from SR for protection audit-check by
the Consultant. Various inputs (relating to relay settings, protection parameters, etc.)
sought by the Consultant in this regard have been collected from respective SR-
Constituents, and furnished to the Consultant. Based on the data furnished, Consultant is
to provide a set of recommended settings covering various relays for each of the 15
Stations, and to carry out physical protection audit of the same.
23.4. In this regard, 5 stations have already been audited during Dec 2015 – Jan 2016 as given
below:
Sl.No Name of the Station Period of Audit
1 Hosur SS of PGCIL (SR-II) 9th
-11th
December, 2015
2 Gazuwaka SS of PGCIL (SR-I) 28th
-30th
December, 2015
3 Alamathy SS of TANTRANSCO 4th
- 6th
January, 2016
4 Tirunelveli SS pf PGCIL (SR-II) 8th,
,9th
and 11th
January, 2016
5 Edamon SS of KSEB 18th
-20th
January, 2016
23.5. Out of the remaining 10 stations, 5 stations would be audited in Feb 2016 as given
below:
Sl.No Name of the Station Period of Audit
1 NLC TPS-II Station 8th
– 10th
February, 2016
2 Nelamangala SS of KPTCL 8th
– 10th
February, 2016
3 Gooty SS of PGCIL (SR-I) 12th
,13th
and 15th
February,
2016
4 Kurnool SS of APTRANSCO 16th
– 18th
February, 2016
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 58 of 75
5 Ramagundam Station of NTPC 18th
- 20th
February, 2016
23.6. The last set of 5 stations, namely Guttur, Kaiga, Raichur, Sharavathy and Kothagudem
would also be audited.
24. ISSUES RELATING TO PSDF FUNDING
24.1. Constituents had raised issue regarding LOAs placed before date of approval of scheme
by the Monitoring Committee for funding by PSDF. It had been stated that the subject
of sanction of funds from PSDF the works already taken up by the entities.
24.2. In this regard, Chairperson, SRPC had taken up this matter with Secretary (Power) vide
letter dated 21st May 2015.
24.3. In the 28th
SRPC meeting, CMD, APTRANSCO & APGENCO had stated that the issue
could be taken up with MoP for relaxation of the criteria for the compliance of
observations of Protection Audit.
24.4. Subsequently Chairperson, SRPC had taken again up this matter with Secretary (Power)
vide letter dated 19th
December 2015.
25. AUGMENTATION OF TALCHER-II TRANSMISSION SYSTEM
25.1. KSEBL vide letter dated 25th
September 2015 had stated that since all Southern states
would get benefitted with the early commissioning of Talcher-II transmission system, all
SR Constituents may jointly implead as a party in the Civil Appeal filed by TNEB
before Hon’ble Supreme Court. In the 27th
TCC meeting it was suggested that SR
constituents may jointly implead as a party in the Civil Appeal filed by TNEB in
Honorable Supreme Court.
25.2. Hon’ble Commission in its Order dated 05.11.2015 in respect of Petition No.
14/SM/2015, in the matter of ‘Notice under Section 19 of the Electricity Act, 2003 for
revocation of the inter-State transmission licence granted to Talcher II Transmission
Company Ltd.’ had passed the Order :
‘13. In exercise of our power conferred under Section 19 (3) of the Act and Regulation 20 of
the Transmission Licence Regulations notice is given to the licensee to show cause within
three months from the date of this order as to why the transmission licence granted for the
transmission project should not be revoked in terms of the provisions of Section 19 of the
Electricity Act and Transmission Service Regulation as quoted above. If no response is
received within three months from the date of issue of the order, the licence shall be deemed
to have been revoked.’
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 59 of 75
26. APPROACH BEING TAKEN BY CTU FOR RESERVING THE
TRANSMISSION CAPACITY FOR THE CUSTOMERS WHO HAVE AVAILED
LTA WITHOUT IDENTIFYING BENEFICIARIES
26.1. KSEBL vide letter dated 25th
September 2015 had suggested that CTU be requested to
take an approach that though LTA could be applied based on target region, availing or
booking of corridor for such LTA applicants could be made only after signing PPA with
firm beneficiaries. Further, LTA applicants earlier applied based on target region may be
given preference over new LTA applicants with firm PPA when the target region LTA
customer approaches CTU with firm PPA and when there are transmission corridor
constraints.
26.2. The following was noted in the SRPC Meeting:
KSEBL had pointed out that the generators had been granted LTA with target region
about 5-6 years ago. The prospect of entering PPAs by these generators was quite
remote. Most of the generators were selling power under STOA/MTOA. Many
generators were not paying transmission charges since LTA had not been
operationalized. Basic issue was the time limit for the LTA to get operationalized
and also applicability of the transmission charges. KSEB felt that this arrangement
was blocking eligibility of other states.
CTU had stated that most of the referred generators had been granted LTA in 2009-
10. Transmission corridors were planned for them which was getting commissioned
in phases. LTA would get operationalized once the identified system is commissioned
and they would be liable to pay transmission charges. System takes around 3 -4 years
to develop. It was also pointed out that the Regulation allowed application with only
target region.
26.3. KSEBL issue was heard on Petition No. 249/MP/2015 on the following subject :
Petition under Section 79(1) (c) and 79(1)(f) of the Electricity Act, 2003 and Regulation
32 of the Central Electricity Regulatory Commission (Grant of Connectivity, Long-Term
Access and Medium-Term open access in Inter-State transmission and related matters)
Regulations, 2009, seeking intervention of Hon'ble Commission 'in the matter of non-
grant of LTA from the start date sought for in the LTA applications made in December
2014 with firm PPAs executed under DBFOO bidding framework between Generators
and KSEB Ltd., despite availability of ATC during the time frame sought for in the LTA
application, by reserving ATC in favour of very old target region LTA customers who
failed to submit firm PPAs to the intended regions within a reasonable period, causing
irreparable financial loss to KSEB Ltd. and other related matters.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 60 of 75
27. PENDING REACTIVE CHARGES
27.1. PED vide letter dated 28.12.2015 had informed that payment of Rs. 6,12,755 was
pending from APTRANSCO towards reactive energy charges for the period 04.02.2013
to 30.08.2015. The issue was discussed in the 30th
CCM meeting wherein APTRANSCO
informed that LoA has been raised and dues would be cleared in a few days.
27.2. TSPCC vide letter dated 18.12.2015 had informed that payment of Rs. 1,23,25,064 ( for
the period 23.02.2015- 29.11.2015) & Rs. 1,42,99,492 (for the period 09.06.2014-
11.01.2015 ) was pending from APTRANSCO towards reactive energy charges and
interest. The issue was discussed in the 30th
CCM meeting wherein APTRANSCO
informed that an amount of Rs. 138 Crores was due from TSTRANSCO towards
transmission and wheeling charges. It was agreed that a reconciliation meeting would be
held between AP & TS.
28. TRANSMISSION CHARGES LIABILITY FOR THE LONG OUTAGE/
SUSTAINED INABILITY TO MAINTAIN THE APPROVED INJECTION
28.1. TANTRANCO vide letter dated 30.12.2015 had expressed concern over long outage of
generators and also inability of some generators to sustain approved injection. As per
POC regulations, TN has paid withdrawal charges for withdrawal quantum. TN had
requested that the whenever a Generating unit is under long shutdown or not maintaining
the approved injection quantum for long time, then transmission charges for that period
be paid by Generators alone and it should not be passed on to the DIC/Beneficiaries
bills.
28.2. The issue was deliberated in the 30th
CCM, wherein it was noted that in absence of
specific Regulation, TANTRANSCO/ other constituents may consider approaching
Hon’ble CERC through a Petition.
29. REIMBURSEMENT OF SRPC EXPENDITURE
29.1. Statement showing net amount payable by Member Utilities of SRPC for the year 2015 -
16, after adjustment of surplus/deficit for the previous period is furnished in Annexure-
XXXVII.
29.2. Fund Requirement for NPC:
In the 4th
NPC meeting held on 10.12.2015 (MOM dated 1.1.2016), it was agreed
that for the time being, expenditure towards hosting the various meetings of NPC
meetings be met by RPCs on rotational basis.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 61 of 75
30. GRID OPERATION
Tamil Nadu had placed on record appreciation for the efforts of PGCIL for the
active support extended during the recent crisis due to heavy rains/floods.
Active support extended by SRLDC constituents, Generators and PGCIL in the
Crisis management in TN necessitated by heavy rain/flooding.
Black Start Workshop for Telangana System was conducted on 20th
November
2015 at Vidyut Soudha, Telangana by SRLDC
MVAR testing at Sharavathi HEP and Black Start workshop in Karnataka System
had been conducted successfully on 27.10.2015 and 03.11.2015 respectively and
the efforts made by KPTCL/KPCL/SRLDC officers in this regard were placed on
record
Black Start Workshop for Karnataka system was conducted on 3rd
November 2015
at Bangalore.
Unit - 7 of Ramagundam Thermal Power Station completed 458 days of continuous
operation . This unit had overtaken the record of Simhadri Stage I Unit I which had
made uninterrupted operation for 441 days. Earlier Unit-6 of Ramagundam had
been completed 406 days of continuous operation which was interrupted during
Grid disturbance
30.1. Grid events/highlights during October 2015
Frequency profile was better compared to last year and last month. Frequency
histogram shows same pattern as last year and last month.
As per load duration curve of October 2015, the loads had considerably increased
when compared to previous month & year.
Reservoir position as on 31.10.2015 was lesser than 41 % of last year same date.
Hydro Storage was less by around 4950 MU compared to last year.
Hydro generation was 2000 MU less in the month of October 2015 when compared to
October 2014.
Some wind generation was observed in first week of October 2015 and after that
completely stopped.
220 kV Appayyadorapalem (ADR Palem) in Viziznagaram district was
commissioned on 15.10.2015 by APTRANSCO
220/132 kV Miyapur S/s of 1x160 MVA Transformer Capacity was augmented to
2x160 MVA Transformer Capacity on 07.09.2015 by TSTRANSCO.
220 KV D/C XLPE UG Cable from 220 kV Moulali SS to 220 KV GIS at Osmania
University in Hyderabad of cKm 17.926 was commissioned on 14.10.2015 by
TSTRANSCO.
220 KV line on Narrow Based Multi Circuit Towers with 4 Circuits for LILO of both
Circuits of Dindi - Chandrayangutta 220 KV D/C Line to the proposed 220 kV SS,
Bonguloor of ckm 2 was Commissioned on 31.10.2015 by TSTRANSCO.
LILO of 220kV Ramagundam- Mandamarry circuit-I to 220/6.6kV LI SS Murmur in
Karimnagar district of 3.9 ckm was commissioned on 21.10.2015 by TSTRANSCO.
220 KV 2nd
ckt stringing from 220 KV RSS 220 KV Mandamarry (34 KM) in
Karimnagar of 34 ckm was commissioned by 20.10.2015 by TSTRANSCO.
LILO of 220kV Ogulapur- Durshed to 220/6.6kV LI SS Bommakal in Karimnagar
district of 0.108 ckm was commissioned on 27.10.2015 by TSTRANSCO.
220/132 KV GIS Osmania University in Chilakalaguda, Hyderabad was
commissioned on 14.10.2015 by TSTRANSCO.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 62 of 75
220/6.6KV Murmur LI substation in Karimnagar district was commissioned on
21.10.2015 by TSTRANSCO.
220/6.6KV Bommakal LI substation in Karimnagar district was commissioned on
27.10.2015 by TSTRANSCO.
220/6.6KV Mallaram LI substation in Medak district was commissioned on
31.10.2015 by TSTRANSCO.
220/132 KVSS Bonguluru in Ranga Reddy Dist. (originally charged with
1x100MVA) was commissioned on 31.10.2015 by TSTRANSCO.
MoP had allocated 200 MW of Power Round the Clock(RTC) to Karnataka from
Unallocated Power of ISG Stations of SR by reducing the share from the shares of
Andhra Pradesh and Telangana by 50 MW, Kerala by 20 MW and Tamil Nadu by
80 MW w.e.f 06.11.2015.
Peak Demand of AP touched all time maximum of 6913 MW on 29th
October 2015.
Peak Demand of TS touched all time maximum of 6849 MW on 16th
October 2015.
PGCIL vide letter dated 16.10.2015 had informed that consequent to the successful
completion of Trial Operation, Transmission system associated with Kaiga 3 & 4
(2x235 MW) Project (Mysore-Kozhikode 400 D/C line along with new 400/220 kV
S/S with 2x315 MVA ICTs and 2x50 MVAR switchable line reactors at Kozhikode
and associated bay equipment at Mysore Substation) had been put under COD w.e.f
00:00 hours of 16th
October 2015 in terms of Clause 4 of CERC(Terms and
Conditions of Tariff) Regulations 2014.
30.2. Grid events/highlights during November 2015
As per load duration curve of November 2015, the loads had considerably reduced
when compared to previous month.
Reservoir position as on 30.11.2015 was lesser by 34 % w.r.t. last year. Hydro
Storage was less by around 3790 MU compared to last year.
Hydro generation was 1536 MU less in the month of November 2015 when compared
to November 2014.
Wind generation was observed very less during November 2015.
7.5 WM Installed Capacity was added in Tamil Nadu in Private Sector during the
month of November 2015.
Unit – VI at Nagjhari Power House up rated from 135MW to 150MW.
220kV D/C Line from Pallantla substation to 220/11kV LIS substation at Pattiseema
in East Godavari district of 60 CkM was commissioned (feeder I on 06.11.2015 &
feeder II on 07.11.2015) by APTRANSCO.
220kV Appayyadorapalem - Bobbili SC line in Vizianagaram District of 84 CkM was
commissioned on 12.11.2015 by APTRANSCO.
220/11 kV LIS substation at Pattiseema in East Godavari district of 60 MVA
Capacity was commissioned on 08.11.2015 by APTRANSCO.
Bobbili Growth Center 220kV SS in Vizianagaram District of 100 MVA Capacity
was commissioned on 13.11.2015 by APTRANSCO.
2nd PTR at 220kV SS Rachagunneri in Chittoor district of 100 MVA Capacity (2
nd
PTR) was commissioned on 25.112015 by APTRANSCO.
220kV SS Kalyandurg in Ananthapur District(220 kV, 2x100 MVA) was
Augumented to a capacity of 3x100 MVA and commissioned on 02.11.2015 by
APTRANSCO.
220kV SS Kamavarapukota in East Godavari District (220 kV, 2x100 MVA) was
Augumented to 3x100 MVA capacity of and was commissioned on 21.11.2015 by
APTRANSCO.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 63 of 75
220 kV D/C Line from Pallantla substation to 220/11kV LIS substation at
Pattiseema in East Godavari district of 60 CkM was commissioned. (feeder I
on 06.11.2015 & feeder II on 07.11.2015) by APTRANSCO.
220 kV LILO to 220 kV existing Gajwel-Kamareddy line to 220/6.6 kV water
pumping SS to Kondapaka of 19.5 CkM was commissioned on 10.11.2015 by
TSTRANSCO.
220/6./6 kV Kondapaka water pumping substation in Medak District of 63 MVA
Capacity was commissioned on 10.112015 by TSTRANSCO.
220/132/33 kV SS Waddekothapally in Warangal District (3x100 MVA) capacity
was Augumented to a Capacity of (1x160 +2x100) MVA and was commissioned on
24.11.2015 by TSTRANSCO.
220/132/33 kV Boothpur SS in Mahaboobnagar District (2x100+1x160+1x16) was
Augumented to a capacity (2x100+1x160+1x16+1x50) and was commissioned on
18.11.2015 by TSTRANSCO.
220/132/33 kV SS Narketpally in Nalgonda District of (1x31.5+1x15) MVA capacity
was Augumented to a capacity of (1x50+2x31.5) MVA and was commissioned on
13.11.2015 by TSTRANSCO.
220/132/33 kV SS Kalwakurthy in Mahaboobnagar Dist.of (1x50+2x31.5)MVA
Capacity was Augumented to a Capacity of 2x50+1x31.5 MVA and was
Commissioned on 16.112015 by TSTRANSCO.
765kV Kudgi – Kolhapur I charged at 400kV level on 14th
November 2015 by
PGCIL
400kV Narendra – Kudigi I charged on 17th
November 2015 by PGCIL
400kV Gooty – Madhugiri (Tumkur) D/C charged on 29th
November 2015 by PGCIL
400kV Kudgi –Kudgi NTPC charged on 17th
November 2015 by PGCIL
400/220kV ICT- 3 & 63 MVAR Bus Reactor at Raichur was charged for first time on
24th
November 2015 by KPTCL.
63 MVAR Bus Reactor charged at 400kV Talaguppa S/S on 26th
November 2015 by
KPTCL..
125 MVAR Bus Reactor charged at NCC for first time on 04th
December 2015
PGCIL vide letter dated 09.11.2015 had informed that consequent to the successful
completion of Trial Operation, the following assets under Transmission System
Associated with “Contingency Plan for evacuation of Power from IL & FS (2x600)
MW have been put under Commercial Operation with effect from 00:00 hrs of
November, 2015 in terms of Clause 4 CERC (Terms and conditions of Tariff)
Regulations, 2014.
Strengthening of Neyveli TS II – TS- I expansion Link with higher Capacity
Conductor).
PGCIL vide letter dated 01.12.2015had informed that consequent to Successful
completion of Trial Operation, the following assets under “Transmission System
associated with System Strengthening –XIII in Southern Regional Grid” have been
put under Commercial Operation w.e.f 00:00 Hrs of 1st December 2015 in terms of
clause 4 of CERC (Terms & Conditions of Tariff) Regulations 2014 and 27th SRPC
minutes of meeting point No 3.2.3.
Gooty – Madhugiri 400KV D/C line
Extension of 400/220KV substation at Gooty – Madhugiri 400KV D/C Line.
400/200KV Substation at Madhugiri (Tumkur) with 2x500MVA
Transformers and 1x63MVAR Bus Reactor along with associated bay &
Equipments for Gooty – Madhugiri 400KV D/C Line.
Transmission charges of the above assets are payable with effect from 1st
December 2015.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 64 of 75
PGCIL SR II vide letter dated 11.12.2015 had informed that consequent to the
successful completion of Trial Operation the following assets under Transmission
System associated with “System Sregthening-XVII in Southern Grid” have been put
under Commercial Operation with effect from 00:00 hrs of 11th
December 2015 in
terms of Clause 4 of CERC(Terms and Conditions of Tariff) Regulations, 2014.
Second Circuit of Narendra(New Kudgi) – Kolhapur(New) 765 D/C
Transmission line(initially charged at 400 KV) along with bays & equipments
at Narendra(New Kudgi) substation and Kolhapur(New) substation.
Transmission charges for the above assets are payable with effect from 11th
December 2015.
PGCIL SR II vide letter dated 11.12.2015 had informed that consequent to the
successful completion of Trial Operation the following assets under “Sub Station
Extension works associated with transmission system required for evacuation of
power from Kudgi TPS(3x800 MW in Phase I) of NTPC Limited in Southern
Regional Grid” have been put under Commercial Operation with effect from 00:00
hrs of 11th
December 2015 in terms of Clause 4 of CERC(Terms and Conditions of
Tariff) Regulations, 2014.
4 Nos. 400 kV Line bays at Narendra(New, Kudgi) for Kudgi TPS-Narendra
(New, Kudgi) 400 kV 2xD/C Quad Lines.
Transmission charges for the above assets are payable with effect from 11th
December 2015.
PGCIL SR II vide letter dated 11.12.2015 had informed that consequent to the
successful completion of Trial Operation the following assets under Transmission
System associated with “System Sregthening-XVII in Southern Grid” have been put
under Commercial Operation with effect from 00:00 hrs of 11th
December 2015 in
terms of Clause 4 of CERC(Terms and Conditions of Tariff) Regulations, 2014.
Narendra(New Kudgi) – Narendra(Existing) 400 kV D/C Quad Transmission
line along with associated bays & equipment at Narendra(New Kudgi)
substation and Narendra(Existing) substation.
Transmission charges for the above assets are payable with effect from 11th
December 2015.
PGCIL SR II vide letter dated 15.12.2015 had informed that consequent to the
successful completion of Trial Operation the following assets under Transmission
System associated with “System Strengthening-XXII in Southern Grid” have been
put under Commercial Operation with effect from 00:00 hrs of 15th
December 2015
in terms of Clause 4 of CERC(Terms and Conditions of Tariff) Regulations, 2014 and
27 SRPC Minutes of Meeting point No. 3.7.
Kurnool(New) – Raichur 765 kV S/C line.
Extension of 765/400 kV S/S at Kurnool(New)- 1 No. 765 kV line bay for
Kurnool(New) – Raichur 765 kV S/C line
Extension of 765/400 kV S/S at Raichur - 1 No. 765 kV line bay for
Kurnool(New) – Raichur 765 kV S/C line
Transmission charges for the above assets are payable with effect from 15th
December 2015.
Andhra Pradesh, Telangana, Kerala & Tamil Nadu imported 363 MU, 1236 MU, 10
MU & 74 MU respectively intra-regionally through bilateral exchanges.
Andhra Pradesh, Telangana, Karnataka, Kerala& Tamil Nadu imported 284 MU, 285
MU, 9 MU, 113 MU & 906 MU respectively inter-regionally through bilateral
exchanges.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 65 of 75
Utilities located in Andhra Pradesh, Telangana, Karnataka, Kerala & Tamil Nadu
imported 105 MU, 115 MU, 53 MU, 102 MU & 13 MU respectively through Power
Exchange.
Utilities located in Andhra Pradesh, Telangana, Karnataka, Kerala, SEPL, MEPL &
TPCIL exported 9 MU, 40 MU, 125 MU, 2.51 MU, 10 MU, 28 & 25 MU
respectively through Power Exchange.
Utilities located in Andhra Pradesh, Telangana, Karnataka & Tamil Nadu exported
1026 MU, 11 MU, 573 MU & 74 MU intra-regionally.
CoD of LANCO St 3 Unit 3A was declared on 11.08.2015.
CoD of Unit-II (800 MW) of SDSPP (Krishnapatnam JV) of APGENCO was
declared on 00:00 hrs of 24.08.2015
Unit-I (600 MW) of IL &FS was synchronized to grid on 05.08.2015.
Unit-II (500 MW) of NTPL was declared CoD on 00:00 hrs of 29.08.2015.
0.75 MW Wind Generation Capacity was added in Tamil Nadu.
The following assets under “ Transmission System associated with System
Strengthening –XVIII in SR grid “ along with Communication Signal from sending
end to receiving end, metering, telemetry and protection system had been put under
CoD 08.08.2015:
400 kV Vijayawada (Nunna PG)- Nellore (APTRANSCO) Ckt-III along with
1 x 63 MVAR line reactor.
400 kV Vijayawada (VTPS)-Nellore (APTRANSCO) along with 1 x 63
MVAR line reactor.
30.3. Grid events/highlights during December 2015
As per load duration curve of December 2015, the loads had marginally increased
when compared to previous month. Around 60 % of time the loads remained more
compared to last year same month.
Reservoir position as on 31.12.2015 was lesser by 28 % w.r.t. last year. Hydro
Storage was less by around 2876 MU compared to last year.
Hydro generation was 1300 MU less in the month of December 2015 when compared
to December 2014.
Kakatiya TPP Unit-2 (600 MW) was first time synchronized on 15th December 2015
by TSGENCO.
Hinduja NPCL Unit-1 (520 MW) in AP was first time synchronized on 25th
December 2015.
Bellary TPS Unit -3 (700 MW) was first time synchronized on 25th December 2015
by KPCL.
Coastal Energen Unit -2 (600 MW) in TN was first time synchronized on 28th
December 2015. CEA vide letter dated 06.01.2016 had communicated that M/s
Coastal Energen Private Limited vide their letter dated 04.01.2016 had informed that
Mutiara TPP Unit II(600 MW) had been achieved Full Load on 02.01.2016
765 kV Raichur – Kurnool Line I was charged on 13th December 2015 by PGCIL.
400 kV Nagarjunasagar – Khammam II & III were charged on 31st December 2015
by PGCIL
PGCIL vide letter dated 04.01.2016 had informed that consequent to the successful
completion of Trial Operation, the following assets under “Substation works
associated with System Strengthening in Southern Region for import of Power from
Eastern Region” have been put under Commercial Operation with effect from 00:00
hrs of 4th January 2016 in terms of Clause 4 CERC (Terms and conditions of Tariff)
Regulations, 2014.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 66 of 75
400 kV Bays each at Khammam(Existing) and Nagarjunasagar for
terminating Khammam - Nagarjun Sagar 400 kV D/C line has been
implemented under Tariff Based Competitive Bidding.
Transmission charges of the above assets are payable with effect from 4th
January 2016.
PGCIL vide letter dated 03.01.2016 had informed that on successful completion of
seventy two (72) hours of connection with the interconnection facilities the following
element is put under Commercial operation w.e.f. 1600 Hrs on 03.01.2016 in terms of
article 6.2.1, Transmission service Agreement (TSA) dated 14.05.2013 and
accordingly POWERGRID Vizag Transmission Limited is entitled for all benefits
envisaged in the aforesaid TSA.
400 kV Khammam(existing) – Nagarjunasagar Transmission D/C line under
Transmission system for System Strengthening in Southern Region for import
of power from Eastern Region.
In the 116th OCC Meeting KPCL had informed that Yeramarus Unit I had been
synchronized for the first time on 09th
February 2016.
30.4. Installation of Shunt Capacitors
Progress of installation of capacitors by the constituents during the year
2015-16 is furnished in the Table below:
(Figures in MVAR)
State Requirement
for 2015-16
Installed during the year 2015-
16 (till 31.01.2016)
Andhra Pradesh 26.20 0
Karnataka 56.31 0
Kerala 10.00 0
Tamil Nadu 122.40 2.4
30.5. DEMAND VARIATION (Peak Vs Off-peak)
Issue regarding large variation between minimum and maximum demands has been
under the consideration of TCC/SRPC. The issue is also being discussed in the
monthly Meetings of OCC. Following was observed with regard to the period from
October 2015 to January 2016:
Description
Minimum to Maximum Demand Variation %
Andhra
Pradesh Telangana Karnataka Kerala Tamil Nadu Puducherry
Southern
Region
October 2015
Highest 6913 6849 7460 3479 13307 332 35808
Date (Day) 29.10.2015
(Thursday)
16.10.2015
(Friday)
26.10.2015
(Monday)
26.10.2015
(Monday)
16.10.2015
(Friday)
17.10.2015
(Saturday)
29.10.2015
(Thursday)
Lowest 4312 4625 4232 1733 8128 190 24487
Date (Day) 11.10.2015
(Sunday)
22.10.2015
(Thursday)
05.10.2015
(Monday)
05.10.2015
(Monday)
05.10.2015
(Monday)
31.10.2015
(Saturday)
05.10.2015
(Monday)
Average 16.36 17.49 17.02 38.64 21.66 30.32 14.25
November 2015
Highest 6755 6479 7623 3426 12481 319 35383
Date (Day) 06.11.2015 05.11.2015 19.11.2015 27.11.2015 03.11.2015( 03.11.2015 04.11.2015
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 67 of 75
(Friday) (Thursday) (Thursday) (Friday) Tuesday) (Tuesday) (Wednesday
)
Lowest 3256 4514 5107 1835 4723 27 21980
Date (Day) 17.11.2015
(Tuesday
20.11.2015
(Friday)
22.11.2015
(Sunday)
15.11.2015
(Sunday)
10.11.2015(
Tuesday)
09.11.2015
(Monday)
10.11.2015
(Tuesday)
Average 22.15 16.40 22.71 38.59 29.98 39.74 21.03
December 2015
Highest 6540 6138 8396 3471 12680 309 35758
Date (Day) 31.12.2015
(Thursday)
24.12.2015
(Thursday)
30.12.2015
(Wednesda
y)
16.12.2015
(Wednesday)
31.12.2015(
Thursday)
24.12.2015
(Thursday)
31.12.2015
(Thursday)
Lowest 4031 3657 5415 1841 6141 128 23362
Date (Day) 07.12.2015
(Monday)
24.12.2015
(Thursday)
01.12.2015
(Tuesday)
26.12.2015
(Saturday)
04.12.2015(
Friday)
03.12.2015
(Thursday)
03.12.2015
(Thursday)
Average 23.12 21.41 19.33 37.99 29.17 37.24 20.81
Note: Highest &lowest figures for the month have been computed based on the daily values.
30.6. FREQUENCY OF OPERATION OF SOUTHERN GRID
Frequency of operation of the Southern Grid for the period under review is
furnished below please:
Month
Percentage of time when frequency (Hz) was
Month
Avg. freq. Less
than
49.5
49.5
to
49.7
49.7
to
49.9
49.9
to
50.0
50.0
to
50.05
50.05
to
50.20
More
than
50.20
Within
IEGC
range
49.9 to
50.05
October 2015 0.00 0.04 15.28 44.66 23.67 16.16 0.19 68.33 49.98
November 2015 0.00 0.04 12.53 41.44 24.78 21.00 0.20 66.22 49.99
December 2015 0.00 0.08 17.33 42.94 21.93 17.42 0.29 64.87 49.98
January 2016 0.00 0.00 11.45 42.75 25.88 19.60 0.32 68.63 50.00
During the period under review, caution / violation messages (Annexure-
XXXVIII) were issued to the constituents by SRLDC. Matter regarding
overdrawal at low frequency by some constituents is being regularly deliberated in
the OCC forum. Utilities are requested to kindly adhere to Regulations in this
regard.
30.7. Reasons for demand -supply gap and its variation:
In 4th
NPC meeting held on 10.12.2015 (MoM dated 1.1.2016) the following was noted:
Reason for demand-supply gap needed to be clearly mentioned to reflect true
picture of power supply position in different states and also to invite attention
of various agencies including policy makers to the specific problem areas in
the power sector for suitable solution. It was requested to RPCs to advise the
states in their respective regions to intimate broad break-up of demand-supply
gap due to various reasons, or at least, the main reason(s) for demand-supply
gap in each month. It was suggested that this matter could be discussed in the
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 68 of 75
OCC forum of RPCs on regular basis and the reasons for demand-supply gap
ascertained from the States therein and communicated to CEA.
RPCs agreed to take action accordingly and furnish above information to
CEA along with the power supply position related data every month.
For Information of SRPC/TCC
31. PROTECTION SYSTEM ANALYSIS GROUP (PSAG-14) MEETING HELD AT
MAPS, KALPAKKAM ON 18.12.2015
31.1 In pursuance with the decision taken in the 49th
meeting PCSC, a meeting of Protection
System Analysis Group comprising officials from SRPC, SRLDC, PGCIL,
TANTRANSCO & MAPS was held on 16th
December, 2015 at MAPS, Kalpakkam to
discuss protection & operational issues concerning MAPS, in the context of Grid
Disturbance that occurred at S.P. Koil SS of TANTRANSCO & MAPS of NPCIL on 9th
November, 2015.
31.2 In the Meeting, apart from analyzing the events that led to the Grid Disturbance at S.P.
Koil & MAPS on 09.11.2015, the general operational & protection issues pertaining to
MAPS were also discussed. Specific recommendations have been given with regard to
the following issues:
Replacement of Disc Insulators on the 230kV lines emanating from MAPS.
Improving the flow/ exchange of information between MAPS and TANTRANSCO
substations for the faults occurring on the connecting lines.
Providing dual AC supply to Compressor Motor and redundant Compressor Unit.
Carrier communication/ PLCC related issues on 230kV MAPS-Arani line.
Status of providing Line CVT in the Y phase of all feeders excepting SP Koil-2.
Provision of Auto-reclosure on all 230kV lines emanating from MAPS.
Ensuring Grid Connectivity of MAPS
31.3 TANTRANSCO and MAPS have been requested to comply with the above set of
recommendations to prevent recurrence of Grid Disturbance such as that occurred on
09.11.2015.
32. THOROUGH REVIEW OF ALL THE DRAWAL POINTS OF STATES FOR
DRAWAL COMPUTATIONS
SRPC vide letter dated 30.10.2015 (Annexure-XXXIX) had suggested a methodology
for reviewing the Touch Points for drawl computations. The issue was discussed in the
30th CCM wherein the methodology was agreed in principle. It was agreed that SRLDC,
SRPC and respective states would review the drawl points.
33. INCLUSION OF DRAWAL OF MAHE IN REA
33.1 PED vide letter dated 11.01.2016 (Annexure-XL) had informed that including the drawl
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 69 of 75
of Mahe region into REA was approved in 21st SRPC Meeting. Metering equipment at
Panoor (KSEB) and Mahe would be commissioned by January 2016 end.
Communication facilities had also been established. It had been requested to arrange for
ABT compliant SEMs at both the ends. The issue was deliberated in 30th
CCM wherein
it was agreed that in line with CEA Metering Regulations KSEBL & PED would provide
ABT compliant SEMs respectively at their ends.
34. SHARING OF TRANSMISSION CHARGES OF TRANSMISSION ASSETS OF
NATIONAL IMPORTANCE
34.1 Hon’ble Commission in its Order in Petition No. 67/TT/2015 [ in the matter of approval
of transmission tariff ( PGCIL) of (i) Asset-I (HVDC Portion) and ( ii) Combined
Asset-II (AC portion) from anticipated COD to 31.03.2019 under the transmission
system associated with “North East-Northern / Western Interconnector-I Project” in
North Eastern, Northern & Western Region ] has decided to grant tariff of the assets
covered in the petition in terms of proviso (i) of regulation 7(7) of the 2014 tariff
regulations. SRPC vide letter dated 13.01.2016 (Annexure-XLI) had brought to
attention of SR entities, the highlights of the Order.
Hon’ble Commission in the Order (Sharing of Transmission charges) had stated
the following in item Para 30:
“Since, these assets are proposed to be considered as assets of national importance
and all the regions are proposed to bear the transmission charges, we consider it
necessary to hear the DICs of all the regions”.
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 70 of 75
34.2 The issue was deliberated in the 30th
CCM and it was noted that SR entities could furnish
their comments to Hon’ble CERC.
35. ACCOUNTING METHODOLOGY FOR LKPL STAGE II AND LKPL STAGE
III
35.1 In case of LKPL Stg II and LKPL Stg III as both the units are connected to the same
outgoing feeders the bifurcation of LKPL Stg II and LKPL Stg III cannot be as carried
out using main meters since both lines are connected to same bus. For accounting of
LKPL Stg II and LKPL Stg III bus coupler was opened and accounting was carried out
using Main Meters. Keeping in view reliability of generation from Stage II & III, iIt is
proposed to close the bus coupler and use standby meters to apportion the generation
between LKPL Stg II and LKPL Stg III. The Energy accounting and audit meter (ABT
meter) in the Generating stations (LKPL Stg II and LKPL stg III) could be used as a
backup meter for standby meters.
35.2 The issue was deliberated in the 30th
CCM meeting and it was agreed to close the bus
coupler for reliability purpose. It was noted that accounting methodology would not be
changed during failure/spurious readings of Main and Standby SEMs and all the
commercial implications, if any, would be borne by LKPPL. It was in the interest of
LKPPL to provide backup SEMs for standby meters which would ensure correct
accounting during failure/spurious readings of Main/Standby SEMs
36. TPCIL REQUEST TO EXEMPT DEVIATION CHARGES
36.1 TPCIL vide letter dated 07.01.2016 (Annexure-XLII) had requested for to consider the
event of 30.12.215 as “force majeure” during CTU system outage (ISTS) and revise the
deviation account for the week 28-Dec-15 to 03-Jan-16.
36.2 The issue was deliberated in the 30th CCM wherein it was noted a Working Group of
NPC was meeting shortly to recommend the methodology for ‘Treatment of Bilateral
short term and collective transaction in case of grid disturbances’. The methodology
would be put up to NPC and finalized methodology would be communicated up to
Hon’ble Commission for further directions.
37. PROLONGED OUTAGE OF 765 KV RAICHUR-SHOLAPUR – 2ND
CKT
765 kV Raichur – Sholapur Circuit II owned by RSTCPL had tripped at 10:46 hrs on
02.01.2016 and was revived only at 13:03 hrs on 07.01.2015. The line was revived after
rigorous follow up by SRLDC/SRPC. Outage of this critical inter regional link affects
the security of the grid significantly and lead to huge reduction of TTC/ATC (around
2500 MW) resulting in curtailment of approved transactions. A Special Meeting was
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 71 of 75
held on 11.01.2016 with RSTCPL (minutes available in SRPC website) to deliberate in
detail about the delayed restoration of this line and number of actionable points were
finalized.
38. AP & TELANGANA SCHEDULING ISSUES OF SHARED PROJECTS &
OPERATIONAL ISSUES
A meeting on Scheduling issues of shared projects of AP & Telangana & Operational
issues was held at Hyderabad on 18th December 2015 (Minutes available on SRPC
website). Scheduling issues during backing down/reserve shutdown for load generation
balancing and integration of renewable was discussed. Since this issue had technical,
operational, commercial and regulatory implications it was recommended to flag for
discussion in higher forum to arrive at a long term solution. These issues had been
referred to CEA vide letter dated 4th
January 2016 (Annexure-XLIII) emphasizing that
the issue was required to be deliberated in threadbare.
39. POWER SUPPLY ISSUES AFFECTING METRO SERVICES
BMRCL services were affected on 21st December 2015 and on 17
th December 2015 due
to power supply issues which affected Metro operations. A Meeting to discuss
disruption of power supply affecting BMRCL services was held on 31st December 2015
(Minutes available in SRPC website). It needs to be ensured that the services of
BMRCL/Metros are not affected either due to grid side problem or due to electrical side
problems in the Metro network.
40. Outage Coordination through OCC
40.1 CERC Order dated 14.12.2015 on Petition No. 008/SM/2014 on Grid Disturbance
envisaged that only OCC approved transmission shut downs be availed. The Order states
that no unplanned outage can be approved and even construction activities need to be
planned.
40.2 The issue was deliberated in 115th OCC meeting held on 08.01.2016. After deliberations
it was agreed that in order to facilitate changes in the dates of construction outages,
critical shut downs etc. one more set of transmission proposals would be considered
through OCC Outage web group. Modifications in the dates of the constructions/critical
shut downs would only be considered (not normal AMP works) provided it is supported
by valid reasons.
40.3 The procedure to be followed is below:
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 72 of 75
Construction/critical shutdown proposals would be submitted to Outage Web
Group/SRPC/SRLDC in the requisite format by 20th
of the month for the outages
planned for next month.
SRPC/SRLDC would jointly review the proposal and furnish the details along
with observation/ATC curtailment etc. between 21st and 25
th of the month.
SRLDC would coordinate with NLDC /other RLDCs for the Inter – Regional /
critical elements shutdown proposals. It would be posted in the OCC Outage Web
Group.
Constituents/entities could revert back with observations between 26th
and 28th
of
the month in the OCC Outage Web Group. In case no comments received, shut
down would be treated as approved.
Approved outages would be posted on SRPC website before end of the month.
It needs to be noted that the new list of shutdown proposals would consists only
the modified/additional construction/critical shutdowns. Approval would be at the
discretion of SRLDC/SRPC/Constituents.
40.4 In the 4th
NPC meeting held on 10.12.2015 (MOM dated 1.1.2016), NLDC stated that
they were experiencing difficulty in coordinating planned shutdown of inter-regional lines
with the concerned RPCs since some RPCs were approving shutdowns early in the
month, while other RPCs were doing so somewhat later in the month. Keeping in view
the specific issue raised by NLDC, it was agreed that all RPCs would conduct OCC
meetings in a distributed manner by 15th of every month for finalizing the planned
shutdown of different transmission lines including inter-regional ones for the following
month, and 10 days’ time would be allowed to NLDC to finalize TTC/ATC etc. of
various inter-regional corridors taking approved shutdowns into consideration.
40.5 In the 116th
OCC Meeting SRLDC presented the details of outages availed vis-a -vis
outages approved in OCC. 49 % of outages were not availed as per the schedule in the
month of January 2016 which was a matter of concern. It was agreed that all the entities
would furnish the details of outages availed vis-a -vis outages approved along with
reasons
41. SCHEDULING OF NTPC RAMAGUNDAM SOLAR POWER PLANT (10 MW)
41.1 A Special Meeting was held on 17th November 2015 to discuss scheduling of NTPC
Ramagundam Solar Plant (10 MW) by SRLDC (Minutes available in SRPC website).
To facilitate scheduling by SRLDC, the following prerequisite criteria are to be met by
NTPC:
Forecasting of generation.
MW-MVAR data of the station.
Voltage at inter connecting point.
Inverter status
SEM as per CEA, Metering Regulations, 2006
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 73 of 75
Data compatibility with SRLDC format etc.
41.2 NTPC to kindly expedite the implementation.
42. Assessment of Metering Requirement
42.1 In the 25th
Meeting of Commercial Sub-Committee held on 22.08.2014, CTU had agreed
to furnish SEM requirement projections for next one year which would be installed by
CTU in line with provisions of CEA Regulations. STU and Generators were also
similarly requested to furnish the SEM requirement assessment for the next one year. In
the 28th Meeting of Commercial Sub-Committee held on 20th June 2015 CTU, STU and
generators had been requested to furnish the assessment of SEM requirement for the next
one year.
42.2 NTPC had furnished information regarding number of SEMs required by NTPC for next
one year. The requirement of SEMS for Kudgi STPP is as given below:
220 kV side – 15 Nos.
400 kV Side – 18 Nos.
42.3 APTRANSCO informed that 04 Nos. of SEMs were required by them for next one year.
It was observed that while the assessment of SEM requirement would facilitate the
utilities in timely procurement, it is the prime responsibility of the utilities to procure the
SEMs themselves.
42.4 CTU, STU and generators had been requested to furnish the assessment of SEM
requirement for the next one year.
43. IMPLEMENTATION OF PROTECTION SUITE / PROTECTION
MANAGEMENT SYSTEM FOR SOUTHERN REGION
43.1 In the 26th
SRPC meeting held on 20th December, 2014 at Visakhapatnam, SRPC had
approved the proposal to procure Protection Suite (Protection Management System) that
comprises Web based management software and protection setting calculation tool
through PSDF funding. The detailed scope of the work is enclosed at Annexure-XLIV.
In this regard, steps have been initiated to procure Protection Suite through PSDF
funding. The number of suites per utility required for Southern Region is listed below:
S.No Utility Quantity
1 Karnataka 6
2 Tamil Nadu 8
3 Andhra Pradesh 4
4 Telangana 4
5 Kerala 4
6 Puducherry 1
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 74 of 75
7 Power Grid 2
8 NPCIL 1
9 NTPC 1
10 NLC 1
11 SRLDC 1
12 SRPC 2
Total 35
43.2 After obtaining approval for PSDF funding, tendering process for executing Protection
Suite would be initiated. For evaluating the technical and financial bids that would be
received, a Committee comprising members from SR- Constituents would later be
constituted with approval of Chairperson, SRPC.
44. STUDY PROGRAMME ON THE INTEGRATION OF RENEWABLE ENERGY
RESOURCES INTO THE GRID
Chairperson SRPC has approved the proposal for study programme on Integration of
Renewable Energy Resources (RES) into the Grid for SRPC constituents in line with the
proposal already approved for NRPC. Proposal has been submitted to the Appraisal
Committee of PSDF.
The countries where the Programme is to be organized are Germany and Spain. The
Programme content is for the higher management and middle level Management. The
Programme will be implemented in 3-4 batches. The total participants in the study
Programme are around 75. Byelaws and other procedures will be carried out with the due
approval of Chairperson, SRPC.
45. FURNISHING THE WIND GENERATORS DATA FOR PLEXOS STUDY OF
GREENING THE GRID PROJECT
As part of Greening the Grid Project, studies for integration of renewable in to the Grid
were being conducted in PLEXOS software. The network data for the PLEXOS study
case was imported from All India PSSE Base case which had been used in calculation of
ATC/TTC. The details of connectivity of renewable energy generators had not been
modeled in the base case since these generators were connected at voltage level below
132/110 kV. SRLDC vide letter dated 26.11.2015 (Annexure-XLV). had requested that
the information like Name of the generating station, Installed Capacity and details of the
nearest 132/110/220 kV stations where it was connected etc may be furnished in the
format given at the earliest preferably in EXCEL format
46. UPDATE ON 230 KV BHAVINI-KANCHIPURAM
TANTRANSCO vide letter dated 14.09.2015 (Annexure-XLVI) had informed
regarding commissioning of Kanchipuram S/S that tender had been floated and tender
Agenda for 28th TCC & 29th SRPC Meeting to be held on 04th and 05th March 2016 Page 75 of 75
opening date was on 11.09.2015. Substation works would be completed in one year from
the date of award of contract and 230 kV & 110 kV line works were already under
progress. It was also informed that meanwhile the feasibility of connecting 230 kV
BHAVINI-Kanchipuram line to the existing nearby substations was also under study.
However, since the commercial operation of BHAVINI unit was not yet decided and 4
nos. of 230 kV lines emanating from BHAVINI were already in service, there would not
be any constraint in power evacuation from the BHAVINI.
47. MEMBERSHIP OF NLDC
In the 4th
NPC meeting held on 10.12.2015 (MoM dated 1.1.2016), all RPCs informed
that the proposal of Membership of NLDC in the NPC was agreeable to them.
Accordingly, the Committee requested Member Secretary (NPC) to take up with MoP
the necessary amendment in the resolution of constitution of NPC.
48. MEMBERSHIP OF COASTAL ENERGEN
It is proposed to include Coastal Energen as a Member of SRPC since it meets the
criterion in the MoP resolution on RPC Membership.
49. ANY OTHER ISSUE WITH THE PERMISSION OF THE CHAIR
50. DATE & VENUE OF THE NEXT SRPC MEETING