southerly wwtc –getting the grease outdecember 2018 owea biosolids workshop grease unloading...

30
December 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881-6600 Jeff Ifft, PE– (216) 606-1316 Southerly WWTC –Getting the Grease Out 6055 Rockside Woods Blvd Independence, OH 44131

Upload: others

Post on 08-Oct-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Southerly WWTC –Getting the Grease OutDecember 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881 -6600 Jeff Ifft, PE – (216)

December 2018

OWEA Biosolids WorkshopGrease Unloading Station

Presented by:Harry Shaposka, PE – (216) 881-6600

Jeff Ifft, PE– (216) 606-1316

Southerly WWTC –Getting the Grease Out

6055 Rockside Woods BlvdIndependence, OH 44131

Page 2: Southerly WWTC –Getting the Grease OutDecember 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881 -6600 Jeff Ifft, PE – (216)

Summary• Project Overview and Objectives• Background• Design• Operations and Maintenance provisions• Performance and Feedback from Plant

Brown and Caldwell 2

Page 3: Southerly WWTC –Getting the Grease OutDecember 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881 -6600 Jeff Ifft, PE – (216)

Overview and Project Objectives• Grease delivered by privately owned trucking companies

• Grease was unloaded from the trucks into the septage receiving location upstream of the headworks

• Grease and septage were handled in the same manner

• Project Objectives: Do not dilute concentrated grease, preserve for reuse, reduce the downstream O&M issues of weir clogging

Brown and Caldwell

Note: The existing Septage Receiving Station will remain as a backup discharge location

3

Page 4: Southerly WWTC –Getting the Grease OutDecember 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881 -6600 Jeff Ifft, PE – (216)

Brown and Caldwell

Southerly WWTC Overview

Fluidized Bed

Incinerators

Existing DAFT and Skimmings Concentration

Historical accumulation at primary settling

tank weirs

4

Page 5: Southerly WWTC –Getting the Grease OutDecember 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881 -6600 Jeff Ifft, PE – (216)

Brown and Caldwell

Background - Existing Septage/Grease Unloading

5

Page 6: Southerly WWTC –Getting the Grease OutDecember 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881 -6600 Jeff Ifft, PE – (216)

Design Conditions

Parameter Value

Estimated Number of Trucks per Day• Average / Max Day 8 /17

Volume per Truck, gallons 3,000 to 4,000

Grease Total Solids, % 2 to 5

Grease Specific Weight, lbs/gal 8.3

Estimated Flow per Day• Average / Max Day, gpd 25,200 / 38,800

Two Tanks Provided 13,000 gal each

Brown and Caldwell 6

Page 7: Southerly WWTC –Getting the Grease OutDecember 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881 -6600 Jeff Ifft, PE – (216)

Design Process Schematic

Brown and Caldwell 7

Object Traps, Grinders and Unloading Pumps

Metering Pumps to DAF Tanks

Hopper to Concentrated Skimmings Tanks

Transfer Pump to Fluidized Bed Incinerators

Grease Storage Tanks

Existing Facility

Existing Unloading for Skimmings from NEORSD Westerly and Easterly Plants

Page 8: Southerly WWTC –Getting the Grease OutDecember 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881 -6600 Jeff Ifft, PE – (216)

Brown and Caldwell

Heating and Mechanical Room

Electrical Room

8

General Layout Challenge: Protect stormwater system during unloading process.

Garage Bay

Object Trap, Grinder and Unloading Pump

Metering Pumps to DAF Tanks and Concentration Tanks

Grease Storage Tanks Air Mixing

System

Spill containment berm and trench drain

Page 9: Southerly WWTC –Getting the Grease OutDecember 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881 -6600 Jeff Ifft, PE – (216)

Brown and Caldwell

New Grease Unloading FacilitySingle Story 2800 SF Facility, Prefab Metal BuildingStarted up Summer 2016$3.3M and 19 months to complete

9

• Keeps concentrated waste product separate from the liquid treatment process and avoids downstream removal and pumping

• Preserves the grease, a waste product with relatively high BTU content for use as a fuel in the fluidized bed incinerators

• Improves hydraulic distribution at weirs and within conduits

Page 10: Southerly WWTC –Getting the Grease OutDecember 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881 -6600 Jeff Ifft, PE – (216)

Safety Features - Combustible and Methane Gas Detectors

Combustible Gas Indicator (H2S)

Methane Gas Indicator(Sensor at Ceiling)

Floor Level Combustible Gas Sensing Head

Brown and Caldwell 10

Page 11: Southerly WWTC –Getting the Grease OutDecember 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881 -6600 Jeff Ifft, PE – (216)

Unloading Stations / Docks

2 Grease Unloading Stations

A sample is collected from every truck

Brown and Caldwell 11

Challenge: Assure contract haulers are only unloading grease

Page 12: Southerly WWTC –Getting the Grease OutDecember 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881 -6600 Jeff Ifft, PE – (216)

Unloading Station

Grease Tank Level Indicator in Gallons Remaining

Tank Level Light

Brown and Caldwell

Start Fill Sequence Pushbutton

Stop Fill Sequence Pushbutton

Test Strobes Pushbuttons

Gallons Remaining

12

Challenge: Make the unloading panels intuitive for non-NEORSD staff

Page 13: Southerly WWTC –Getting the Grease OutDecember 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881 -6600 Jeff Ifft, PE – (216)

Rock Traps and Grinders Manuf.: JWC Environmental

No. 2

Capacity per Trap: 600 gpm, 5 HP

Purpose:To collect heavy material before reaching the grinder, which then grinds remaining debris and protect the pumps

Brown and Caldwell

Basket

ScreensFlow

13

Page 14: Southerly WWTC –Getting the Grease OutDecember 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881 -6600 Jeff Ifft, PE – (216)

Brown and Caldwell

Rock Trap with Basket and GrinderSolids Collection Basket

Bar Screens

Seal Ring

Open/Close Grip Knob

Water Supply

Rock Trap

Flow In

14

Davit for Basket

Page 15: Southerly WWTC –Getting the Grease OutDecember 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881 -6600 Jeff Ifft, PE – (216)

In-line Grinder Control Panel

Grinder Disconnect Switch

PumpDisconnectSwitch

In Auto, Grinder Control Panel, controlled by “Fill Start” sequence

Brown and Caldwell

The Grease Storage Room is classified as an explosion proof area (Class 1, Div 1) and the Electrical Room is unclassified.

15

Page 16: Southerly WWTC –Getting the Grease OutDecember 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881 -6600 Jeff Ifft, PE – (216)

Qty: 1 per Tank

Manufacturer: Moyno (NOV)

Series: 2000

No. of Pumps: 2

Type: Positive displacement, progressive cavity

Capacity per Pump: 350 gpm

Discharge Head: 100 ft

Motor Hp: 20

Grease Unloading Pumps

Brown and Caldwell 16

Page 17: Southerly WWTC –Getting the Grease OutDecember 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881 -6600 Jeff Ifft, PE – (216)

Manufacturer: International Production Specialists (IPS)

No. of Tanks: 2

Unheated

Dimensions

• Diameter – 13.5 ft.

• Side Height – 12 ft.

• Max. Liquid Depth – 10 ft.

• Cone Depth – 6.75 ft.

Capacity per Tank: 13,000 gallons

Brown and Caldwell

Liquid Grease Storage and Mixing Tanks

Overflow Line

(4) Future Subcant Lines

17

Challenge: Future thickening/subcantingmay be desired

Page 18: Southerly WWTC –Getting the Grease OutDecember 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881 -6600 Jeff Ifft, PE – (216)

Liquid Grease Storage Tank Monitoring

High Level Alarm Sensor

Liquid Level Sensor

Brown and Caldwell

Level Indicator

18

Page 19: Southerly WWTC –Getting the Grease OutDecember 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881 -6600 Jeff Ifft, PE – (216)

Grease Storage Tank Air Mixing

Air In

Tank Floor

Leveling NutWeld

Brown and Caldwell

1. System parameters that control mixing efficiency:• Air Pressure• Pulse Duration• Pulse Frequency

2. Compressed air is injected to the diffuser plates at short pulses within the range of 40 to 80 psig.3. The number of times the air valve opens (Pulse Rate) can be adjusted by the operator to optimize mixing from 1 to 6 times

per minute. 4. Pulse duration can be adjusted by the operator between 0.2 to 0.8 seconds.

19

Challenge: Prevent stratification

Page 20: Southerly WWTC –Getting the Grease OutDecember 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881 -6600 Jeff Ifft, PE – (216)

Manufacturer: Moyno (NOV)

Series: 2000

No. of Pumps: 2

Type: Positive displacement, progressive cavity

Capacity per Pump: 50 gpm

Discharge Head: 230 ft

Motor Hp: 10

Brown and Caldwell

Grease Transfer Pumps

No Flow Sensor (There is a no flow sensor on each of the four grease pumps)

20

Page 21: Southerly WWTC –Getting the Grease OutDecember 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881 -6600 Jeff Ifft, PE – (216)

Where can the grease that is removed from the Grease Storage Tanks be pumped?

Brown and Caldwell 21

Challenge: Integrate into existing skimmings handling facility which is not continuously staffed

Page 22: Southerly WWTC –Getting the Grease OutDecember 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881 -6600 Jeff Ifft, PE – (216)

Brown and Caldwell

Existing DAF Tanks and Concentrated Skimmings Tanks

22

Heated CSKIM Tank

DAF Tank contents transferred to CSKIM Tanks

Page 23: Southerly WWTC –Getting the Grease OutDecember 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881 -6600 Jeff Ifft, PE – (216)

SCADA Operational Overview Provisions

Brown and Caldwell 23

Three screens developed with Operations Staff• Unloading• Transferring• Mixing

Page 24: Southerly WWTC –Getting the Grease OutDecember 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881 -6600 Jeff Ifft, PE – (216)

Brown and Caldwell

Operations Remote Monitoring Provisions

Grease Tanks

DAF Tanks

24

Challenge: remotely monitor DAF tanks to prevent overfilling from other skimmings pumps

Five video cameras for security and to monitor the process

Page 25: Southerly WWTC –Getting the Grease OutDecember 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881 -6600 Jeff Ifft, PE – (216)

Brown and Caldwell

Garage bay allows truck to partially back into the GUS, if a heavy object were trapped or for tank cleaning

4 hot water hose reel stations

Grease Tanks

Mechanical Room

Electrical Room

25

Maintenance Provisions Spill containment berm and trench drain

Page 26: Southerly WWTC –Getting the Grease OutDecember 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881 -6600 Jeff Ifft, PE – (216)

Early Performance in Year 2016

Brown and Caldwell

June July Aug Sep Oct Nov Dec

# Loads 10 34 103 126 62 138 108

Gallons 40,000 133,000 380,000 440,000 152,000 470,000 405,000

# of Vendors 2 3 5 11 14 14 10

Loads/day

No data 2.3 4.7 6.0 6.2 6.0 4.1

Avg gal /load 4,000 3,900 3,700 3,500 2,500 3,400 3,800

26

Initial challenge: Building confidence that contract haulers are only unloading grease

Page 27: Southerly WWTC –Getting the Grease OutDecember 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881 -6600 Jeff Ifft, PE – (216)

Beneficial Plant Impact

Brown and Caldwell 27

-

100,000

200,000

300,000

400,000

500,000

600,000

700,000

May

-16

Jun-

16

Jul-1

6

Aug-

16

Sep-

16

Oct

-16

Nov

-16

Dec

-16

Jan-

17

Feb-

17

Mar

-17

Apr-1

7

May

-17

Jun-

17

Jul-1

7

Aug-

17

Sep-

17

Oct

-17

Nov

-17

Dec

-17

Jan-

18

Feb-

18

Mar

-18

Apr-1

8

May

-18

Jun-

18

Jul-1

8

Aug-

18

Sep-

18

Performance and Discharge Since 2016

NEORSD Easterly and Westerly Plants direct to DAFT (gal)Septage Station Bays 1-4 (gal)GUS (gal)

~15,000 BTU/lb volatile solids11 million gallons and 73% reduction in

hauling discharge volume to headworks

Page 28: Southerly WWTC –Getting the Grease OutDecember 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881 -6600 Jeff Ifft, PE – (216)

Lessons Learned / Operations Feedback

• Two shift operation, 24 hours a day, 28 staff trained• 5 days a week, operating at 50% capacity• Loads received during day shift• Night shift cleans and flushes• <15 minutes to unload, not every truck is full• Storage tanks operated in tandem• Rock trap is efficient but heavy, so davits added• Tanker weighed, converted to gallons for billing• SOPs incorporated for winter draining of traps• Staffing resulted in addition of small operations

office

Brown and Caldwell 28

NEORSD currently charges a flat charge of $40.00 per grease truck up to 1000 gallons. Over 1000 gallons, the fee charged is $0.04/gallon.

Page 29: Southerly WWTC –Getting the Grease OutDecember 2018 OWEA Biosolids Workshop Grease Unloading Station Presented by: Harry Shaposka, PE – (216) 881 -6600 Jeff Ifft, PE – (216)

Lessons Learned / Operations Feedback

• Trucks with “heavy grease” are routed directly to DAFT; some haulers concentrate before delivery

• Grease transferred to DAFT, subcanted and mixed in two skimmings concentration tanks, then discharged to 3rd tank

• Fed to Fluidized Bed Incinerators 1-2 gpm• Thickened ~54% total solids, 98.5% volatile,

heated to 140°F

Brown and Caldwell 29

Existing DAFT and Skimmings Facility