Southeast Louisiana Flood Protection Authority -East Operations Committee Meeting Thursday, January 9, 2014 1 Discussion of proposed floodwall servitudes on Port of New Orleans property 1) Almonaster to France Road Terminal (France Road Floodwall) 2) Jourdan Rd. eastward to Elaine St. (Citrus Back Levee)

Upload: others

Post on 17-Oct-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Southeast Louisiana Flood Protection Authority -East ...... · Almonaster to France Road Terminal “France Road Floodwall” Survey and Servitude document –both complete, pending

Southeast Louisiana Flood

Protection Authority - East

Operations Committee Meeting

Thursday, January 9, 2014

1

Discussion of proposed floodwall servitudes

on Port of New Orleans property

1) Almonaster to France Road Terminal (France Road

Floodwall)

2) Jourdan Rd. eastward to Elaine St. (Citrus Back Levee)

Page 2: Southeast Louisiana Flood Protection Authority -East ...... · Almonaster to France Road Terminal “France Road Floodwall” Survey and Servitude document –both complete, pending
Page 3: Southeast Louisiana Flood Protection Authority -East ...... · Almonaster to France Road Terminal “France Road Floodwall” Survey and Servitude document –both complete, pending
Page 4: Southeast Louisiana Flood Protection Authority -East ...... · Almonaster to France Road Terminal “France Road Floodwall” Survey and Servitude document –both complete, pending

� Port has enjoyed decades of great working relationships with Orleans Levee District, USACE, and recently Southeast Flood Protection Authority

� Port owns much of the property under and adjacent to floodwalls and levees in the New Orleans area

� Previous agreements between agencies were general, but worked well until Hurricane Katrina

� Post-Katrina, USACE requested emergency access to Port property to improve the levees in the France Road area� Result: Undocumented locations of floodwall and levee areas� Inconsistent servitude widths have been established over time ,

ranging from 30’ – 62’ from the toe of levee, encumbering Port of New Orleans property from potential development/use

� Becomes a challenge for maintenance responsiblity

Page 5: Southeast Louisiana Flood Protection Authority -East ...... · Almonaster to France Road Terminal “France Road Floodwall” Survey and Servitude document –both complete, pending

� In an effort to induce further maritime economic development, the Port’s Board has considered sales or transfers of its land.

� Lack of recorded, documented floodwall and levee servitudes is delaying some projects, as:o floodwalls and levees, and their servitude boundaries,

must be clarified for: � Surveys

� Appraisals

� Purchaser’s title insurance

� Uses allowed within servitude

� Maintenance responsibilities

� Access

� Previous/Existing improvements allowed/disallowed

Page 6: Southeast Louisiana Flood Protection Authority -East ...... · Almonaster to France Road Terminal “France Road Floodwall” Survey and Servitude document –both complete, pending

� Create servitude document to memorialize

and protect rights of: ▪ Orleans Levee District

▪ Southeast Flood Protection Authority East

▪ United States Army Corps of Engineers

▪ Port of New Orleans

▪ New Orleans Public Belt Railroad

Page 7: Southeast Louisiana Flood Protection Authority -East ...... · Almonaster to France Road Terminal “France Road Floodwall” Survey and Servitude document –both complete, pending

� Consistent 15’ floodwall servitude (from toe of levee)

throughout area

� Establishes rights for Port of New Orleans and New

Orleans Public Belt Railroad in the area

� Acknowledges existence of current site conditions and

improvements

� Access rights & Maintenance obligations

Page 8: Southeast Louisiana Flood Protection Authority -East ...... · Almonaster to France Road Terminal “France Road Floodwall” Survey and Servitude document –both complete, pending

Almonaster to France Road Terminal “France Road Floodwall”

� Survey and Servitude document – both complete, pending final legal signoff

� Board approval from SLFPAE may be necessary to memorialize the servitude agreement

� Once approved by SLFPAE, will be taken to Board of Commissioners of the Port of New Orleans for consideration and approval

� SLFPAE and Port sign servitude document

Page 9: Southeast Louisiana Flood Protection Authority -East ...... · Almonaster to France Road Terminal “France Road Floodwall” Survey and Servitude document –both complete, pending
Page 10: Southeast Louisiana Flood Protection Authority -East ...... · Almonaster to France Road Terminal “France Road Floodwall” Survey and Servitude document –both complete, pending
Page 11: Southeast Louisiana Flood Protection Authority -East ...... · Almonaster to France Road Terminal “France Road Floodwall” Survey and Servitude document –both complete, pending
Page 12: Southeast Louisiana Flood Protection Authority -East ...... · Almonaster to France Road Terminal “France Road Floodwall” Survey and Servitude document –both complete, pending

Citrus Back Levee (Jourdan Rd. to Elaine St.)� Current ROW line is inconsistent, varying

from around 30’ to 215’� High demand for additional developable land

in area for rail track, industrial improvements, etc.

� Would result in less maintenance responsibility for OLD

� Drawings showing existing vs. proposed levee ROW – 16.95 acres difference

Page 13: Southeast Louisiana Flood Protection Authority -East ...... · Almonaster to France Road Terminal “France Road Floodwall” Survey and Servitude document –both complete, pending

Citrus Back Levee (Jourdan Rd. to Elaine St.)

� Survey and Servitude document – need to be developed

� Board approval from SLFPAE may be necessary to memorialize the servitude agreement

� Once approved by SLFPAE, will be taken to Board of Commissioners of the Port of New Orleans for consideration and approval

� SLFPAE and PONO sign servitude document

Page 14: Southeast Louisiana Flood Protection Authority -East ...... · Almonaster to France Road Terminal “France Road Floodwall” Survey and Servitude document –both complete, pending

14