Page 1: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

South Massachusetts Avenue Corridor Safety Improvements

SMA Advisory Committee Meeting #4| Sept. 12, 2018

Page 2: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

• Welcome• Review of Project

Background & Goals• Recent Process• Review of Current Issues• Discussion of Evaluation

Questions and Metrics• Schedule Update• Discussion/

Questions

AgendaMassachusetts Avenue – Sidney Street to Memorial Drive

Page 3: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

PROJECT BACKGROUND

Municipal Policies

Complete Streets are designed and operated to enable safe access for all users –regardless of age, ability, or mode of transportation (2016).

Vision Zero calls for the elimination of fatalities and serious injuries resulting from traffic crashes, and emphasizes that they can, and should be prevented (2016).

Vehicle Trip Reduction Ordinance established programs to encourage alternatives to single-occupancy vehicle travel (1992).

Cambridge Growth Policy emphasizes sustainable modes of transportation such as walking, biking and using transit and low-emission vehicles, which promote livability and help to improve air quality and reduce greenhouse gas emissions (1993/2007).

Page 4: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

PROJECT BACKGROUND

Flexible Implementation

Based on Policies and Plans and direction of City leadership:

• Evaluate and implement “quick build” solutions to enhance the comfort and promote sustainable transportation for people walking, biking, driving and using transit

Designs that are flexible after implementation

Modifications possible based on evaluation (including feedback)

Page 5: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

CORRIDOR INFORMATION

Corridor Safety HistoryReported Crashes Requiring EMS Transport, 2015-2016

5

Page 6: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

6

CORRIDOR INFORMATION

People Bicycling

Throughout the entire corridor length, users experience the second lowest level of comfort.

Page 7: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

People Walking

7

CORRIDOR INFORMATION

Local and regional destinations and connections

Evaluating ease and comfort of crossing at and between intersections

Walking in this corridor:

Page 8: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

Transit Service AnalysisMBTA Bus Route 1*: AM Peak

8

Composite Grade*

Excellent (A)

Good (B)

Satisfactory (C)

Unsatisfactory (D)

Poor (E)

Failing (F)

N/A

CORRIDOR INFORMATION

Areas of most concern

*Route 1 is ranked in top 5 MBTA bus routes for ridership.

*Criteria:Excess vehicle travel time compared to a minimumPassenger time (travel time x riders)Reliability (how much the travel time varies)

Page 9: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

Transit ServiceMBTA Bus Route 1: PM Peak

9

Method: Automatic Passenger Counter (APC) Data (MBTA)

CORRIDOR INFORMATION

Composite Grade

Excellent (A)

Good (B)

Satisfactory (C)

Unsatisfactory (D)

Poor (E)

Failing (F)

N/A

Areas of most concern

Page 10: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

Project Goals Address safety

issues and reduce crashes - Vision Zero

Reduce transit delays

Enable/encourage people of all ages and abilities to choose sustainable transportation

Page 11: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

Public ProcessAppointed Advisory Committee

Wikimap online

Survey online and at public meetings

Outreach to Businesses Direct meetings with XX local businesses

Coordination with CSBA

Individual Stakeholder meetings

Transit/Ped/Bike Committees

Communitywide Meetings

Posted and electronic

announcements

Page 12: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

Public FeedbackNeed for safer conditions for bicyclists

Motorists and delivery vehicles block bike lanes Desire for greater separation from moving vehicles

Need for additional crosswalks traversing Mass Ave

Desire to improve transit operations

Concerns about unpredictable ridesharing, tour bus, food truck, commercial loading & pick-up/drop-off activity

Relocate MIT-related tour buses loading/unloading

Concerns about long vehicle queues, traffic at Vassar Street

Minimize conflicts, bus/bike conflicts and bike/ped conflicts at 77 Mass Ave.

Page 13: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

Actions Since Last Public Meeting

• Additional outreach – 3 farmers markets, 2 senior coffees, 1 senior town meeting, 2 Central Fleas, 1 Taste of Cambridge,

• Review curb use changes with MIT• Investigate additional queue jumps for the bus in NB

direction• Coordination with state agencies on additional

measures in short and long-term on state facilities• Additional review of traffic analysis

• Ascertain that design does not negatively impact corridor bus service prior to implementation

13

Page 14: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

South Mass. Ave. CorridorDraft Design – Before and After

Before After

Page 15: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

15

Proposed Design Three Main Sections

Section 1:Sidney St to Albany St

Page 16: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

16

Proposed Design Section 1: Sidney St to Albany St (A)

Sid

ney

St

Bla

nche

St

DRAFT

Page 17: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

17

Proposed Design Section 1: Sidney St to Albany St (B)

DRAFT

New Crosswalk& RRFB (rectangular rapid flash beacon

Page 18: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

18

Proposed Design Section 1: Sidney St to Albany St (C)

DRAFT

New Crosswalk& Rectangular Rapid Flash Beacon

Page 19: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

19

Proposed Design Section 2: Albany St & Vassar St

DRAFT

Bike signal&

Right-turn lane

Page 20: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

20

Proposed Design

Mass. Ave

DRAFT

Potential future opportunity to increase space for bicyclists by modifying curb extensions

Bike signal &right-turn laneseparate movements

Page 21: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

21

Proposed Design

Mass. Ave

DRAFT

Bike signal &right-turn laneseparate movements

Vehicle Movement

Page 22: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

22

Proposed Design

Mass. Ave

DRAFT

Bike signal &right-turn laneseparate movements

Bicycle MovementPedestrian Movement

Page 23: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

23

CORRIDOR INFORMATION

Proposed Design Three Main Sections

Section 3:MIT

Page 24: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

24

Proposed Design Section 3: MIT (A)

DRAFT

Page 25: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

25

Proposed Design Section 3: MIT (B)

Mem

oria

l Dr

DRAFT

Am

hers

t St

Remove MBTA Bus Stop, consistent with MBTA Service Plan

Page 26: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

Project Evaluation Questions & Data Collection

• User Feedback• On-line survey; hard copies available• Wikimap• Intercept surveys

• Technical Data• Counts: motor vehicles, pedestrian, cyclists• Speeds• Travel times along corridor

• Transit vehicles• Motor vehicles

• Safety Data• Crash analysis (requires 3 years for statistical validity, but will

monitor for issues and trends 26

Page 27: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

Project Evaluation Questions & Data Collection

• Signal intersections• Vehicle queues• LOS for Pedestrians• Conflicts

• New Pedestrian Crossing• Counts: number of users• Yield study (based on standard protocols)

• Parking/Loading/Ride Hail• Parking study• Delivery vehicles• Observations: where are ride hail vehicles stopping?

27

Page 28: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

ScheduleBicycle, pedestrian,traffic countsApril

Refine DesignMay - August

Public Meeting #1May 3

Parking studyWeek of April 30

Anticipated ImplementationFall/Oct 2018

Evaluation

AdvisoryCommittee Meetings #2-3May, Sept.

NEXT STEPS

AdvisoryCommittee Meeting #1April 11

Public Meeting #2/Open HouseJune 19

Page 29: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

Blank Slide

29

Page 30: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

30

CORRIDOR INFORMATION

Transportation/Traffic AnalysisThree Main Sections

The corridor has been divided into 3 sections for clarity

Section 1:Sidney St to Albany St

Section 2:Albany St to Vassar St

Section 3:MIT

Sidn

ey S

t

Page 31: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

31

CORRIDOR INFORMATION

Transportation/Traffic AnalysisCross Sections

• The three general cross sections (intersections vary)

3131

Section 1:Sidney St to Albany St

Section 2:Albany St to Vassar St

Section 3:MIT

31

Most Complicated

Page 32: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

32

Section 1:Sidney St to Albany St

Section 2:Albany St to Vassar St

Section 3:MIT

Sidn

ey S

t

32

CORRIDOR INFORMATION

Transportation/Traffic AnalysisBus Facilities

Bus lanes proposed for two sections, to address the key areas of delay

Page 33: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

33

CORRIDOR INFORMATION

Transportation/Traffic AnalysisBus Facility Details - After

Page 34: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

34

CORRIDOR INFORMATION

Transportation/Traffic AnalysisBus Facility Details - Before

Page 35: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

35

CORRIDOR INFORMATION

Transportation/Traffic AnalysisBus Facility Details

Bus lanes at intersections: Right turning motorists may use bus lane

National Precedent

Design Sample

Page 36: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

36

CORRIDOR INFORMATION

Transportation/Traffic AnalysisBicycle Facilities

For most of the corridor, separated bike lanes can be created using on-street parking and flex posts

36

Section 1:Sidney St to Albany St

Section 2:Albany St to Vassar St

Section 3:MIT

Sidn

ey S

t

36Flexpost/Parking ProtectionBike Lanes

Page 37: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

37

CORRIDOR INFORMATION

Transportation/Traffic AnalysisBus Facility Details

Bus lanes at intersections: Right turning motorists may use bus lane

National Precedent

Design Sample

Page 38: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

38

CORRIDOR INFORMATION

Transportation/Traffic AnalysisBus Facility Details

Bus Lanes with Parking

Boston, MA - Wikimedia Commons

Page 39: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

Bicycle FacilitiesSeparated Bike Lane –Parking Protected

DESIGN OVERVIEW

Parking Protected Bicycle Lanes

Page 40: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

Bicycle FacilitiesBike Lane with Curbside Parking

DESIGN OVERVIEW

Curbside parking/Accessible Parking

Page 41: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

41

DESIGN OVERVIEW

Parking FacilitiesAccessible Parking

414141Denver, CO

Page 42: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

Bus Stop OptionsDESIGN OVERVIEW

Bus stop at curb Floating bus stop(possible future item)

Page 43: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

43

CORRIDOR INFORMATION

Bus Stop Options

Potential for a future modular floating bus stop under evaluation

Page 44: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

44

CORRIDOR INFORMATION

Transportation/Traffic AnalysisThree Main Sections

• Detailed Design

Section 1:Sidney St to Albany St

Page 45: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

45

CORRIDOR INFORMATION

Transportation/Traffic AnalysisSection 1: Sidney St to Albany St (A)

Sid

ney

St

Bla

nche

St

DRAFT

Page 46: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

46

CORRIDOR INFORMATION

Transportation/Traffic AnalysisSection 1: Sidney St to Albany St (B)

DRAFT

New Crosswalk& RRFB

Page 47: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

47

CORRIDOR INFORMATION

Transportation/Traffic AnalysisSection 1: Sidney St to Albany St (C)

DRAFT

New Crosswalk& RRFB

Page 48: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

49

CORRIDOR INFORMATION

Transportation/Traffic AnalysisSection 2: Albany St & Vassar St

DRAFT

Bike signal&

Right-turn lane

Page 49: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

50

Vassar Street

Design Analysis

Mass. Ave

Potential future opportunity to increase space for bicyclists by modifying bulb-outs

DRAFT

Bike signal &Right-turn laneSeparates movements

Page 50: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

51

CORRIDOR INFORMATION

Transportation/Traffic AnalysisThree Main Sections

Other Design Details

Section 3:MIT

Page 51: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

52

CORRIDOR INFORMATION

Transportation/Traffic AnalysisSection 3: MIT (A)

DRAFT

Page 52: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

53

CORRIDOR INFORMATION

Transportation/Traffic AnalysisSection 3: MIT (B)

Mem

oria

l Dr

DRAFT

Am

hers

t St

Remove MBTA Bus Stop, consistent with MBTA Service Plan

Page 53: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

Existing Conditions Mass. Ave. Cross-Section (at Amherst Street)

88’ wide

On-street bike lane

On-street vehicle parking

Mix of meters and other parking

Bus stops

Curb extensions at multiple locations

14’Sidewalk

9’Parking

12’Travel

11’Travel

8’Parking

13’Sidewalk

5’BikeLane

11’Travel

5’BikeLane

CORRIDOR INFORMATION

Page 54: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

CORRIDOR INFORMATION

Safety History Reported Bicycle Crashes, 2015-2016

57

Project Limits

Page 55: South Massachusetts Avenue Corridor Safety Improvements/media/Files/CDD/Transportation/Projects/southmassave/s...• Review of Project Background & Goals • Recent Process • Review

58

CORRIDOR INFORMATION

Transportation/Traffic Analysis

• Corridor-wide transportation analysis to determine where:

• Bus lanes can be added• Vehicle lanes can be repurposed• Signal operations can be modified• Bicycle lanes can be separated• Bicycle buffers can be added• Parking can be re-located for better operations