south 12th street improvements - eads to clark · pdf filesouth 12th street improvements -...
TRANSCRIPT
South 12th Street Improvements - Eads to ClarkArlington County Department of Environmental Services
Project Area:
South 12th Street between S. Eads and S. Clark as depicted by the adjacent
Map.
Design and Construction Timeframe:
Design through early 2018. Construction 2019-20
Community Comments Requested:
The County needs your comments on the proposed S. 12th St. improvements.
The design is at the 30% complete level, and this is the time to voice your
questions and concerns before the County moves forward towards design
completion.
30% Plans, Comment Sheet and Contact Information:
Please visit www.arlingtonva.us; search 12th and Clark to view the project
plans, submit your comments (due by April 21), and sign up for project
updates.
If you have questions, please contact Mark Schnaufer, Capital Projects
Manager, at [email protected].
Arlington Countys Transportation Division is seeking your input on the future of S. 12th Street from S. Eads Street to S. Clark Street as we
plan to reconstruct it into a part of the future Transitway extension to Pentagon City.
30% Design Proposal
South 12th Street Existing
Condition
Visit www.arlingtonva.us; search 12th
and Clark for Project Updates and to
submit Comments
Project Boundary
Dedicated Center-Running
Transit LanesShared bike/vehicle Lane
2-way bike facility connection
future cycle track
On-Street Parking
Project Location
Dedicated Metroway lanes
in Potomac Yard
Future bike connections