sol4
DESCRIPTION
aaTRANSCRIPT
CHAPTER 4
CHAPTER 4Solution
1. ELM COMPANY
Completed Table
Elm Co. Sales and Operations Planning SpreadsheetHistorySalesOctoberNovemberDecemberForecast(in Million $)0.800.850.90(in units)800850900Actual(in units)826851949Diff: Month26149Cumulative2776OperationsPlan(in units)800800800(in # employees)688Number Working Days/Mo.231919Actual(in units)798802800Diff: Month-2+20Cumulative00 InventoryPlan(in units)1501000(in 000 $)105700Actual(in units)12273-76Days of Supply3.41.6-1.5-2
2. TRAPPER LAWN EQUIPMENT COMPANY
Revised plan: Trapper Lawn Equipment Company Sales and Op's Planning Spreadsheet - Riding Mowers Product Group (Make-to-Stock)
HistoryPlanSalesOctNovDecJanFebMarForecast(M$)12.5010.0016.255.005.007.50(units)500040006500200020003000Actual(units)438436266065Diff: Month-616-374-435Cumulative-990-1425OperationsPlan(units)50004000650005563250(# employ)72701140947# Work Days/Mo.231919202123Actual(units)564940917279Diff: Month64991779Cumulative7401519Target DOS Inv: 5500500750InventoryPlan(units)1270127012701944500750(000$)22232223222334028751313Actual (units)226527303944Days of Supply1015131955
a) Target inventory levels for the three months based on 5 days of supply:
January = 5 x 2000 / 20 = 500; February = 5 x 2000 / 20 = 500; March = 5 x 3000 / 20 = 750
Planned build for each month required to achieve the target accounting for the forecast demand and the inventory in the previous period:
Build plan = forecast demand + target inventory previous month inventory
January planned build is zero since 3944 units remain in inventory at the end of December.February planed build = 2000 + 500 1944 = 556March planned build = 3000 +750 500 = 3250
b) Qualitative factors:
The plan indicates no production in January and very light production in February.
This could be implemented as a plant shutdown that may be very disruptive to work force moral and cause an employee retention problem.
It can also have quality and productivity issues as more problems are likely at shutdown and start-up. Key skills are not practiced.
A better alternative might be to maintain some production below customer demand and gradually reduce inventory levels.
Consider going to a 4 day or other form of shorten workweek. Restrict the use of overtime. Consider the use of a planned shutdown during the summer vacation season or force the use of accrued vacation time to reduce the number of workers available.
3. TRAPPER LAWN EQUIPMENT COMPANY REVISITED
a) The average forecast error is calculated as the difference between the total forecast and actual demand divided by the total forecast. In this case, since the 3 month cumulative error is given in the table:
Forecast error % = -1425 / (5000 + 4000 + 6500) x 100 = -9.2%
Reducing each of the forecast values by 9.2% for January to June yields the projected values units sales and resulting inventory levels and days of supply shown in the table below.
Trapper Lawn Equipment Company Sales and Operations Planning Spreadsheet Riding Mowers Product Group (Make-to-Stock)HistoryPlanSalesOctNovDecJanFebMarAprMayJunForecast(M$)12.5010.0016.255.005.007.5010.0012.5017.50(units)500040006500200020003000400050007000Actual / Projected(units)438436266065181618162724363245406356Diff: Month-616-374-435Cumulative-990-1425Avg % Error-9.2%OperationsPlan(units)500040006500200020003000400050007000(# employ)72701143332436776106# Work Days/Mo.231919202123202222Actual(units)564940917279Diff: Month64991779Cumulative7401519 InventoryTarget DOS Inv: 5500500750100012501750Plan / Projected(units)127012701270412843124588495654166060(000$)2223222322237224754680288672947610602Actual (units)226527303944Days of Supply / Projected 101513465039272621
b) Options for consideration
Change the forecast. This would require the marketing and production mangers coming to agreement on what the new forecast should be.
Adjust the production plan to compensate for the fact that the forecast seems to have a relatively consistent negative bias. This option has little risk in the near term since inventory levels are relatively high.
4. SKI & SEA, INC.a. Level PlanAggregating the forecastQuarter1234Total
Jet Skis10,00015,00016,0003,00044,000
Snowmobiles9,0007,00019,00010,00045,000
Total19,00022,00035,00013,00089,000
Determining the production rate:(Total forecast - beginning inventory) / 4 quarters(89,000 - 1,000) / 4 = 22,000 units per quarter
The Plan and its costs:
Quarter1234Total
Demand19,00022,00035,00013,00089,000
Production22,00022,00022,00022,00088,000
Beginning Inventory1,0004,0004,0000
Ending Inventory4,0004,00000
Average Inventory*2,5004,0002,00008500
Backorders009,00009000
*(beginning inventory + ending inventory) / 2
CostsTotal
Regular time$15.00 88,000= $ 1,320,000
Inventory$ 3.00 8,500= $ 25,500
Backorders$24.00 9,000= $ 216,000
Total $ 1,561,500
Consequences:Low levels of inventorySubstantial back order in quarter 3b. Cumulative Chart
c. Inventory Space = 20 cubic feetx 4000 = 80,000 cubic feet
d. Investment = $ 600.00 x 4,000 = $ 2,400,000
5. IVAR JORGENSONa. Overtime
Quarter1234Total
Jet Skis10,00015,00016,0003,00044,000
Snowmobiles11,0007,00019,00010,00047,000
Total21,00022,00035,00013,00091,000
Production rate = (91,000 - 1,000) / 4 = 22,500 units per quarter
Quarter1234
Demand21,00022,00035,00013,00091,000
Overtime5005005005002,000
Regular22,00022,00022,00022,00088,000
Output22,50022,50022,50022,50090,000
Beginning Inventory1,0002,5003,0000
Ending Inventory2,5003,00000
Average Inventory*1,7502,7501,50006000
Backorders009,50009500
*(beginning inventory + ending inventory) / 2
CostsTotal
Regular time$15.00 88,000= $ 1,320,000
Overtime$22.50 2,000= $ 45,000
Inventory$ 3.00 6,000= $ 18,000
Backorders$24.00 9,500= $ 228,000
Total $ 1,611,000
b.Subcontracting
Subcontracting Cost $ 30.00 2,000= $ 60,000
Overtime Cost $ 22.50 2,000= $ 45,000
Net Increase/(Decrease)$ 15,000
New Total Cost $ 1,626,000
c.Hiring a New Worker
Hiring$ 300.00 1= $ 300
Regular$ 15.00 2,000= $ 30,000
Overtime Cost22.5 2000= $ 45,000
Net Increase/Decrease $ (14,700)
New Total Cost $ 1,596,300
10. JOAN'S JOYOUS NATURE FOODa. Joan should produce 135 units each month. [(120 + 160 - 10)/2 = 135]
b. The ending inventory for month 4 is 180 units. [(10 + (4 135) - 370) = 180]
c. Joan should produce 90 units each month. [(120 + 160 + 20 + 70 - 10) / 4 = 90]
d.
Month:1234
Beginning Inventory10000
Production90909090
Demand1201602070
Ending inventory0000
Average inventory5000
Carrying cost$25$0$0$0
Backorders (cumulative)2090200
Backorder cost$160$720$160$0
Total Inventory Cost = $5 5 = $25Total Backorder Cost = $8 130 = $1040
11. ORO DEL MAR CO.
a.
b. A production rate of 100 units per month is required in order to avoid backorders and result in no ending inventory in March. [(100 + 300 - 100) / 3]
18. GENERAL AVIONICS AGAIN
Chase Sales PlanEndingOvertime
QuarterSalesProductionWorkforceInventoryProduction
28,0007,000701,0000
36,4006,400641,0000
41,6001,600161,0000
16,00015,0001503,0000
Cost ItemCost
Inventory Carrying Cost (3000 x $2)$ 6,000
Overtime Cost0
Firing Cost (54 x $400)21,600
Hiring Cost (20 x $200)4,000
Regular Payroll Cost (150 x $1,200)180,000
Total Cost$211,600
Level Production PlanEndingOvertime
QuarterSalesProductionWorkforceInventoryProduction
28,0007,000501,0002,000
36,4006,400501,0001,400
41,6005, 000503,4000
16,00018,4001505,4003,400
Cost ItemCost
Inventory Carrying Cost ($2 x 5,400)$ 10,800
Overtime Cost ($14* x 3,400)47,600
Firing Cost0
Hiring Cost0
Regular Payroll Cost(150 x $1,200)180,000
Total Cost$238,400
*$14 = $12 for regular + $2 overtime premium
4-10
4-9