Project : 4-Laning of Chapra - Hazipur Section of NH - 19 in the state of Bihar (from Km. 143.200 to km.207.200)
Subject: Status of Geo technical reports for structures on the project road
S.
No.
Existing
Chainage
Design
Chainage
Type Span arrangement as
per schedules
Span arrangement
proposed by MELTECH
Status as on 11.10.2010 Remarks
13Shittalpur
byepass185.921 MNB 1 x 10 1 x 10 Soil report is submitted on 20-09-2010
Awaiting for final soil report with corrections as per the
discussions had with soil consultant
14Shittalpur
byepass187.037 MNB 1 x 40 4x10 Soil report is submitted on 20-09-2010
Awaiting for final soil report with corrections as per the
discussions had with soil consultant
15Shittalpur
byepass194.718 MNB 1 x 20 2x10 Soil report is submitted on 20-09-2010
Awaiting for final soil report with corrections as per the
discussions had with soil consultant
16 200.400 203.175 MNB 1x46.67 4x11.2
Soil report for pile foundation system is submitted on 07-09-
2010 Soil report is required for raft foundation system
17 201.750 204.535 MNB 1x43.65 8.3+25+8.3 Soil report is submitted on 20-09-2010Awaiting for final soil report with corrections as per the
discussions had with soil consultant
1Chappra
bye pass143.974 ROB 3x26.230 3x26.230 Soil report is submitted on29-09-2010 Closed
2Chappra
bye pass150.984 ROB 13.230+26.230+13.230 13.230+26.230+13.230 Soil report is submitted on29-09-2010 Closed
3Chappra
bye pass157.860 ROB 26.23+31.23+26.23 26.23+31.23+26.23 Soil report is submitted on29-09-2010 Closed
4
Digwara
byepass 177.182 ROB 26.23+31.23+26.23 26.23+31.23+26.23 Soil report is submitted on 07-09-2010 Closed
5 206.555 209.318 ROB 6x26.230 6x26.230 Soil report is submitted on 14-08-2010Meltech Expressed doubt on Lateral capacity and asked to
submit revised soil soil report with increased lateral capacity