socialist republic of viet nam collaboration program with ...and communications white paper 2014...
TRANSCRIPT
Socialist Republic of Viet Nam
Socialist Republic of Viet Nam
Collaboration Program with the Private
Sector for Disseminating Japanese
Technology for strengthening ICT
management capacity in the Ministry of
Binh Duong
Dec.2015
Japan International Cooperation Agency (JICA)
Tokyu Corporation
OS
JR
15-110
Socialist Republic of Viet Nam
Socialist Republic of Viet Nam
Collaboration Program with the Private
Sector for Disseminating Japanese
Technology for strengthening ICT
management capacity in the Ministry of
Binh Duong
Dec.2015
Japan International Cooperation Agency (JICA)
Tokyu Corporation
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
- Contents -
Chapter 1.Background and Purpose of this Project
1-1. Background of this project...............................................................................................1
1-2. Purpose of the business.....................................................................................................4
1-3. Implementation details and structure .............................................................................5
Chapter 2.Operational Management
2-1. Outline................................................................................................................................9
2-2. Operation processes .................................................................................................9
2-3. Use of CRM system data analysis in problem management and the
development of the company’s KPI plan…………………...…..…………..…...10
2-4.Findings.............................................................................................................................12
Chapter 3.Construction Management
3-1. Outline...............................................................................................................................13
3-2. Check of construction management and construction skill……………...........13
3-3. Measurement of optical fiber signal loss.......................................................................15
3-4. Proposals for improving construction management....................................................18
3-5. Technical guidance for construction engineering.........................................................21
3-6. Findings.............................................................................................................................22
Chapter 4.Promotion of Understanding of ICT Project Operation Technologies in
Japan
4-1. Outline of invitation to Japan..........................................................................................23
4-2. Implementation status and evaluation of the invitation...............................................24
Chapter 5.Study of the Direction of Business Development after the Implementation
of this Project
5-1. Outline of business development...................................................................................31
Chapter 6.Clarification of Expected Effects of Development through the Business
after this Project
6-1. Beneficiaries of this project and expected effects of development…………….....33
Chapter 7.Considering the Possibility of Coordinating with the Local ODA Project
7-1. Need for coordination and expected effects.................................................................34
Chapter 8.Summary of the Project
8-1. Operational management………………..............................................................35
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
8-2. Construction management.............................................................................................35
8-3. Issues................................................................................................................................36
8-4.Direction of future business development……...........................................................36
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
1
Chapter 1. Background and Purpose of this Project
1-1. Background of this project
1) ICT environment in the country, region, and city concerned
The ICT environment in Vietnam consisted of about 33.19 million people using the Internet as
of 2013, a figure that corresponds to 36% of the country’s population according to the Information
and Communications White Paper 2014 published by the Ministry of Information and
Communication (MIC). In addition, the penetration rate of fixed broadband in 2013 had reached
5.6% of the country’s population, equal to about 5.15 million people.
The Vietnam Postal and Telecommunications Group (VNPT) holds 56.3% of the share of the
fixed broadband subscribers, FPT Telecom holds 26.8%, and Viettel has 9.7%.
The “Prime Minister Decision No. 1775 (Decision No.1755 / QD-TTg) for Approval to Make
Vietnam an ICT power in the Near Future,” which was published in September 2010, specified for
the following goals to be achieved by 2015:
• Development of broadband network in all local governments and districts.
• A mobile broadband network that covers 85% of the population
• Digital TV available to 80% of the households
In addition, the following goals were specified to be achieved by 2020:
• Development of broadband network in nearly all of the villages.
• A mobile broadband network that covers 95% of the population
• Digital TV available to nearly all of the households
According to the Prime Minister’s decision, the overall goal is for ICT to account for 8 to 10%
of the GDP by 2020. For this individual project, the following goals were specified to be achieved
by 2020.
• Development of a high level of human resources
• Spread of rural area broadband
• IT industrial development (particularly software development)
• e-government
• Spread of information and communication equipment in households
• Development of multimedia businesses
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
2
The enhancement of the ICT environment in the near future is one of the national policies of
Vietnam. This policy includes the development of the necessary environment as well as the
cultivation of industries.
2) Relationships with the country, region, and city concerned
Binh Duong Province in Vietnam is located next to Ho Chi Minh City. It has achieved the
country’s top level growth, posting annual average GDP growth rate of 14 to 15%. "Binh Duong
New City,” a large-scale development project, is being promoted to alleviate the concentration of
the population in Ho Chi Minh City. In February 2014, a new government office building was
completed at the center of the new city, and administration facilities were transferred from the old
city to the new government office building.
In the development of Binh Duong New City in the province, Tokyu Corporation utilizes the
comprehensive capabilities of Tokyu Group and the urban development know-how cultivated in
the development of Tokyu Tama Garden City. As a Japanese company, it exports the urban
development package and aims to deploy business in the largest development project in Vietnam.
3) Present condition of ICT business in the country, region, and city concerned
As described above, Tokyu Corporation has started this project to export the know-how of
Japanese urban development. However, currently there is an insufficient level of development in
infrastructure, which will serve as the foundation of urban development. This is an issue that must
be addressed.
The development of public transportation, the ICT environment, and medical institutions are
defined as the essential factors for making the export of Japanese urban development possible. In
fiscal 2013, Tokyu Corporation was entrusted with the “Japan Regeneration Business through the
Acquisition of New Middle Class Customers in Emerging Countries,” and examined the ICT
environment of the area.
The results showed that the communication environment of the city concerned did not have the
level of quality consistent with that of Japan, and that it is inferior to the environment in Ho Chi
Minh City, the major city next to it. This could be caused by the lack of or underutilization of
technology and service operation know-how by the local carrier, Vietnam Technology &
Telecommunication JSC (hereafter referred to as “VNTT”).
4) Five issues
The following five issues provide an overview of the insufficient level of service operation
know-how and utilization of technology needed for improving VNTT’s ICT environment.
(Figure1)
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
3
① Shortage of international line capacity
There is not enough international line capacity. The company in charge of the communication
between Vietnam and other countries is expected to make improvements.
② Inadequate automation of traffic processing
When a problem occurs with a communication line, the system cannot automatically switch to
an optimum line. Improvement is expected from the perspective of ensuring the continuity of
service.
③ Lack of data center facilities that can compete in the future
Enhancement (reinforcement) in the current facilities is expected, such as the establishment of
an advanced data center environment capable of responding to the demands of foreign
companies that are expected to enter the Vietnamese market in the future.
④ Lack of awareness among employees about the importance of service
Most of the employees are not aware of the importance of service. Improvement in this area is
expected because it poses a challenge common to all issues.
⑤ Non-uniform quality of the last-mile
The last-mile is the direct connection with the users, and the precision of its construction will
affect the service in the later stage. Measures are expected to be made to improve the precision
of construction.
Figure 1. Issues to address for improving the ICT service quality
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
4
1-2. Purpose of the business
1) Purpose of the business
Tokyu Corporation focuses on providing technical guidance and know-how, promotes the use of
technology, and aims to improve the ICT business management of VNTT, taking the five
previously discussed issues into consideration. Of these five issues, it specifically aims to address
the 4) lack of awareness among employees about the importance of service and 5) non-uniform
quality of the last-mile.
The reasons Tokyu Corporation has decided to focus on these two specific issues is to improve
the promotional activities that are needed to promote structure and policy proposals to VNTT, and
to directly convey know-how and technology to VNTT’s employees. In regards to the three other
issues, a certain degree of progress can be made through investment.
2) Effect of the business
This project will improve the ICT environment of Binh Duong Province as well as its new urban
area. It will also contribute to sustained urban development.
Efforts for improvement in the previously mentioned issues and enhancements to ICT
environment can help promote new business advancement in the industrial parks that have
contributed to the development of Binh Duong Province. These kinds of efforts can also help
improve the possibility of promoting investment and the living environment in the new urban area.
In regards to promoting investment, Binh Duong New City has the potential to become an
operating base for leading IT companies in the ASEAN region.
There is a vast site on the outskirts moderately removed from the urban area that is home to a
cluster of companies from Silicon Valley in the US. This site offers a sophisticated business
environment and well-prepared living environment, such as high-quality residential and
commercial facilities.
Binh Duong New City is located 30 km north of Ho Chi Minh City. The specs for the future
image of the city and the location satisfy the requirement for Tokyu Corporation and its group
companies, allowing them to take fully apply the know-how cultivated in Japan and move
forward with a high quality, sophisticated form of urban development (Figure 2-1 and Figure 2-2).
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
5
1-3. Implementation details and structure
1) Implementation outline
Looking at the issues of the lack of awareness among employees about the importance of
service and the non-uniform quality of the last-mile, we concluded that there was room for
improvement in the operational management of inquiries from users as well as in the general
construction management, such as construction skills and the confirmation of the results of
construction. Therefore, we focused our activities on operational management and construction
management. (Figure3)
In the area of operational management, the documents that an employee is to refer to when
he/she encounters a problem were in place. We proposed improvements, such as creating a base
of knowledge by recording and organizing the measures taken, from receiving inquiries to solving
the issue indicated.
Activities to propose improvements helped to objectively assess the current conditions. This in
turn led to the effective improvement of operations through visualization by preparing documents
and quantifying levels of service by analyzing the corresponding user records.
Similar developments were seen in efforts to address the non-uniform quality of the last-mile.
We focused on construction management from the perspective of whether construction itself was
properly carried out, and whether construction records and cables were properly organized, in
order to understand the current situation and propose improvements.
Business improvement proposals were made and efforts to disseminate technology were
conducted in the field. Local staff members were invited to Japan to deepen their knowledge
about ICT operations in Japan.
Figure 2-2. Positional relationship of
industrial parks
Figure 2-1. Location of Binh Duong Province
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
6
2) Details of implementation (Table 1)
(1) Field activity
Activities to promote the design of operational management and construction management at
VNTT were conducted three times each, for a total of six times, between December 2014 and
July 2015.
In the area of operational management, efforts were made to assess the condition and make use
of ITIL that forms the framework of the IT Service Management for managing the facility and
system configuration information as well as inquiries from users. Technical guidance and
know-how were provided to deepen understanding.
ITIL (Information Technology Infrastructure Library):
Books that describe the best practice (success stories) of IT Service Management.
Published by the CCTA of the British government in 1989.
In the area of construction management, the configurations of the transmission path facilities
were confirmed in the interviews with VNTT personnel. Reviews and preliminary surveys on
the state of construction of the data center and service points were conducted, applying the
information obtained from the interviews.
Next, the level of signal loss in the transmission path, starting from the data center to the user,
was measured to locate abnormal positions and identify the cause of the loss. Improvements
were proposed for ways to identify the cause, and technical guidance was provided to raise the
level of construction engineering.
Fig.3. Points required to improve service quality
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
7
(2) Inviting staff members to Japan
In April 2015, three local staff members were invited to visit the NTT Communications
Corporation, one of Japan's leading communication companies, and its group company its
Communications Inc. (hereinafter referred to as “iTSCOM”), which runs the cable television
business. Facility tours, discussion sessions with the persons in charge, and practical training
were conducted at the construction engineer training facility.
3) Schedule
The project was carried out according to the schedule shown in Table 1.
Two teams, “Operation Management” and “Construction Management,” were organized. They
took turns carrying out activities to ensure there was sufficient preparation time.
Table 1. Overall schedule (Actual project)
Field activity Date Outline
First field activity
(Operational management (1))
Dec. 8 to 9, 2014 - Interview about the operation process
Second field activity
(Construction management (1))
Dec. 10 to 12, 2014 - Inspection of data center and service points
- Interview about construction management
Third field activity
(Operational management (2))
Feb. 2 to 6, 2015 - Report on the results of the first interview and the
proposal of improvements based on the results
Fourth field activity
(Construction management (2))
Mar. 18 to 21, 2015 - Measurement of level of signal loss in the data
center, service point, and transmission path
Fifth field activity
(Operational management (3))
Apr. 8 to 11, 2015 - Proposal to quantitatively assess the situation of
customers who are using CRM data and the specific
improvement plan
Invitation to Japan Apr. 21 to 25, 2015 - Tour of telecom company’s facilities in Japan
- Tour of the communication construction engineer
training facility
- Practical guidance in construction engineering
Sixth field activity
(Construction management (3))
May 19 to 23, 2015 - Report on the results of measurements on the level
of signal loss
- Proposal of improvements in construction
management
- Practical guidance in construction engineering
Seventh field activity Jun. 23 to 25, 2015 - Preliminary adjustments for the final report
Eighth field activity Jul. 14 to 18, 2015 - Final report
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
8
4) System for implementing project
Tokyu Corporation asked NTT Communications Corporation for technical assistance and
obtained the consent and cooperation of NTT Communications (Vietnam) Corporation and NTT
Com-Solutions Corporation in carrying out this project.
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
9
Chapter 2. Operational Management
2-1. Outline
Activities in operational management were conducted a total of three times. The present
conditions were checked, and proposals for improvement were submitted to VNTT regarding
"configuration management", "change management", "problem management" and "capacity
management." These are all operation processes based on the ITIL framework.
In regards to problem management, which was considered to be particularly important for
VNTT's actual situation, the importance of VNTT using the data analysis of the CRM system as
well as the analysis results was explained.
KPIs, which are quantitative indicators required for data analysis, were jointly set with VNTT.
Cases of Japanese telecom companies were used for reference when setting the KPIs.
* CRM: Customer Relationship Management
* KPI: Key Performance Indicators
2-2. Operation processes
The maintenance conditions of different operation processes are shown in Table 2.
Table 2. Present conditions of operation processes and quality improvement points
Operation
process
Present situation Quality improvement points
Configuration
management
- The necessary documents are
available.
- Prepare a list of documents.
- Add management items (equipment
support date and maintenance period)
Change
management
- The change history and configuration
information are managed, and operation
procedures are available for each item
of equipment.
- Changes due to failure must be
authorized by a manager.
- Prepare a list for all change
management.
- Prepare manuals for trouble shooting,
which does not require the manager’
authorization.
Capacity
management
- Threshold value is set and monitored,
and is enhanced at the proper time.
- None
Problem
management
- The underlying causes are analyzed
by a team when problems occur.
- Describe the problems (underlying
causes) on a list.
- Analyze data and understand the
causes of the problems.
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
10
For operation processes, documents for reference are generally available as shown in Table 2.
However, the readability of these documents is poor because there are not enough management
items and no list of documents. The quality and level of efficiency need to be improved.
In regards to improvement, we taught VNTT about the index process for documents and about
how Japanese communication companies share management items internally.
For problem management, proposals were made by analyzing and using the data from CRM
system.
VNTT’s Service Level Agreement (SLA) claims to fully respond and address user inquiries and
needs within 3 hours. History data from the start to the end of the response process is recorded, but
is not analyzed periodically. Instead, a summary of the present situation is prepared when needed.
In general, the data obtained from the CRM system is be used to review the operation process
for shortening the response time to the users, or to enhance the operation efficiency and improve
the service quality, such as identifying fundamental issue from trends in the inquiries. However, as
was stated before, the data was not used in this way.
Based on this fact, a proposal was made for improving the problem management through
specific data analysis of the CRM system.
* SLA: Service Level Agreement
2-3. Use of CRM system data analysis in problem management and the development of the
company’s KPI plan
1) Proposal to improve problem management
The effectiveness of data analysis in problem management and the use of analysis results were
explained. The idea for developing the company’s KPI plan to guide data analysis was proposed.
2) Effectiveness of data analysis and the use of analysis results
VNTT was told about three cases in which analyzing the data obtained from CRM system was
effective in improving the service quality as well as the operation efficiency.
① Quantification of service recovery time
Analyzing the response time to the inquiries from the users allows VNTT to identify times
when service cannot be provided to the users. This enables VNTT to assess the state of service
quality. For example, this makes it possible to confirm the fulfillment rate of “Full response within
3 hours” that VNTT sets in the SLA, which enables VNTT to determine which process needs to
be improved in order to enhance the fulfillment rate. In addition, it also helps to find useful
information that leads to better operation, identifying specific trends such as the response status
and inquiry details.
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
11
② Understand the inquiries and prioritize responses
Understanding the inquiries from the users and classifying them quantitatively makes it
possible to confirm the number of occurrences. It also allows for the difficulty level in solving the
problem to be determined, helping to prioritize the order in which inquiries are to be addressed. As
a result, VNTT can develop effective ways for restoring service and improve the service level for
users by understanding the situation, instead of merely responding based on the order in which
inquiries are received.
③ Understand the response to the inquires and study the underlying causes
Analyzing the details of responses to users’ inquiries can help uncover the underlying causes.
For example, if replacing cables proves to be an effective solution to a user’s inquiry, there may be
a problem with the quality of the actual cables, or construction may not have been performed
properly due to the lack of skill of the workers. If it is the former, VNTT should consider changing
the cable. If it is the latter, technical guidance should be provided or other measures need to be
taken for improvement.
3) Draw up the company’s KPI plan
After VNTT learned how data analysis is effective for improving service quality and operations,
we worked with VNTT’s employees to examine service quality indicators (KPI), which serve as
the goal for actual data analysis.
We discussed the service quality indicators with VNTT’s employees and drew up the KPI plan
(Table 3), using the KPIs of a Japanese communication company prepared in advance as
reference.
Table 3. Details of the KPI (The study result of VNTT’s employees)
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
12
2-4. Findings
For operational management, the documentation and management systems needed to ensure the
service quality are generally in place, as was mentioned earlier. It was confirmed that a system for
acquiring data from the CRM system has been built for problem management. However, there is
still room for improvement in how information is used, such as CRM system documentation and
data analysis.
To ensure the things that are taught become firmly established in the company, the employees
must understand the essential purpose of operational management and make a conscious effort to
improve service quality within their everyday operations.
In the series of field activities conducted in this project, we saw VNTT's employee actively
participate in the study of KPIs. We also saw them become conscious of improving service
quality.
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
13
Chapter 3. Construction Management
3-1. Outline
Activities in construction management were conducted a total of three times. The
communication equipment in VNTT was confirmed, and the level of signal loss in the optical
fiber cables that were actually laid was measured.
Proposals for improvement and technical guidance in network construction were given after
checking the communication facilities and confirming the results of the measurement of signal
level loss.
3-2. Check of construction management and construction skill
1) Items checked
Construction management is checked as follows.
- Discussion with VNTT’s employees (Photo 1)
- Check of the construction of the communication facilities at the e-Data Center and Service Point
of VNTT. (Photo 2)
- Confirmation of the collective housing where communication facilities have already been
installed by VNTT
- Tour of closures assembly by VNTT's construction engineers, and a demonstration of the user
terminal connection
2) Construction management
The discussion confirmed that the management documents necessary for construction
management are in place, and that in general the concept of construction management is generally
the same as that in Japan. However, one major difference was identified: the test method for
laying the optical fiber cables. In Japan, all cables are checked for normality at each specified
interval while the optical fiber cables are being laid. In VNTT, measurements are performed when
optical fiber cables begin to be used after all the intervals are connected, and repairs are performed
whenever a problem is identified.
In Japan, tests are generally performed when the optical fiber cables are laid to avoid additional
costs that may arise if construction needs to be redone or if work is postponed due to line
problems at the time of opening. At VNTT, the general attitude is to avoid addressing defects that
are found during construction. The reason for this is to ensure a sufficient level of work efficiency
to achieve a balance between the yield rate and line operation rate. This attitude is not seen in
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
14
Japan.
We felt this kind of thinking is deeply rooted at VNTT. As the urban development of Binh
Duong Province continues in the future, the line usage rate will increase, which means there will
be a greater chance of selecting a defective line. This gives rise to concern about the repair
capacity. (Refer to the proposals for improvement in 3-4.)
When we checked the current state of the data center, we found that the data center facilities and
wiring are generally organized, just as they are in Japan. There were only few places where
improvement was needed.
On the other hand, we felt that the outdoor line accommodation where user lines change
frequently is not well managed. We found temporary labels for the connection destinations of
optical fiber cables were in certain places. These can cause problems in identifying the cause of
communication failures because these labels might be unclear or in some cases missing. (Photo 2,
Photo 3)
Photo 1. Engaging in discussion Photo 2. Checking the facility
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
15
3) Construction skill
We checked the work of construction engineers through demonstrations. They are highly skilled
personnel and perform their work efficiently, but have no manual providing them with
instructional guidance. In speaking with the construction engineers, we learned that they received
technical guidance in the form of personal know-how from network facility manufacturers after
they completed their basic training. (Photo 4)
3-3. Measurement of optical fiber signal loss
1) Loss measurement
After confirming the state of construction, we measured the level of signal loss by inputting
signals of different wavelengths into the optical fiber cable. (Photo 5, Photo 6) This test was
performed to determine how well the optical fiber cables were laid.
Photo 4. Engineer giving demonstration
of his work
Photo 6. Measuring signal loss ②
(Outdoor Connection Point) Photo 5. Measuring signal loss ①
(Service Point)
Photo 3. Inside of outdoor
connection facility
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
16
An example of the measurement results is provided below. (Figure 4-1, Figure 4-2)
The following figure shows signal loss occurred at two points, the 0.3 km point and the 12.1 km
point.
At the 0.3 km point, the comparison of the level of signal loss between the two wavelengths
shows that there was a large loss in the long wavelength (1,550 nm) signal.
This point exhibits a bending loss, with a large loss in the long wavelength measurement and a
small loss in small wavelength measurement. One probable cause is that the optical fiber bend
radius exceeded the allowable range.
The signal loss at the 12 km point exhibits a loss that occurred in the connection between optical
fiber cables.
Figure 4-1. Example of signal level loss (1,310 nm wavelength),
(Output from a measurement instrument)
Figure 4-2. Example of signal level loss (1,550 nm wavelength),
(Output from a measurement instrument)
0.3km: Bending/connection loss of 1.4dB
12.1km: Connection loss of 1.4dB
File name
0.3km: Bending/connection loss of 5.7dB
File name
12.1km: Connection loss of 1.1dB
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
17
In addition, 57 optical fiber cables were also measured. The results of these measurements are as
follows.
2) Check of how optical fiber cables are laid
The points where the loss occurred were identified from the measurement result, and the actual
manner in which the optical fiber cables were laid was visually checked. Some of the points
where signal loss was detected were confirmed at the actual site.
Unlike Japan, manholes in Vietnam are rectangular in shape with a concrete lid and body.
The conduits are commonly made of 110 mm piece of resin. The conduits as well as manholes
are the same as those found in Ho Chi Minh City. Inside the manhole, the cables (with the extra
length removed) and closure are inserted directly, but the inside of closure was found to be
flooded. A full inspection is performed periodically. However, a lack of construction management
was confirmed because in principle the facility should be constructed in a way that prevents
flooding from occurring. (Photo 7, Photo 8)
Photo 7. Inside the manhole Photo 8. Inside the closure
- Abnormality caused by problems in construction found in 7 optical fiber cables
(total of 12 points) of the 57 optical fiber cables measured.
- Breakdown of the abnormalities at the12 points are as follows:
・Improper connection: 4 points
・Optical fiber bend radius exceeded the allowable range: 8 points
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
18
Photo 9 shows a closure installed by hanging it from a cable. That was the point where signal
loss was confirmed from the measurement results. The weight of the closure was acting on the
optical fiber, possibly causing the optical fiber bend radius to exceed the permissible range. This
finding supports the measurement results.
3) Findings
In regards to construction skill, the demonstrations revealed that the works possess a certain
degree of skill. However, the fact that the construction of closure allowed flooding to occur shows
that manuals are not well prepared or properly followed, and that the problem can be attributed to
the unstable construction quality. Manuals on operational procedures and a uniform level of
quality are needed.
In the area of construction management, quality is not managed properly, and there is no way to
check the state of construction. Therefore, operational procedures for quality management, such
as records on the state of construction, are needed.
The cable destination labels and manhole management numbers have yet to be made.
Management of the cables and manholes at the facilities is needed because problems can occur in
construction management when the number of facilities increases.
Proposals for improvement and technical guidance were made based on these facts.
3-4. Proposals for improving construction management
The following proposals for improving construction management were made to managers.
Proposals were made in six chapters. (Photo10, Photo11 and Photo 12)
Photo 9. A closure of an aerial line
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
19
Proposal regarding the visualization of operation for future needs
- With the development of the new city area of Binh Duong Province, there will be an increase
in the number of communication facilities constructed. At the same time, there will be a need
to deal with the increase in the number of construction personnel and instances of outsourcing
to other companies. In order to maintain the construction quality and communication quality, a
proposal was made to organize the infrastructure design and manuals.
- (Material used) “Direction of proposal for improvement”
Engineer training in Japan
- The concept related to the development of construction engineers in communication
construction companies and the activities of the entire communication industry in Japan were
explained, using the history of communication construction in Japan as the context.
- (Material used) “Engineer development in Japan”
Preparation of operational procedures and manuals
- Provided explanation, from the content to be put into the manuals to how the manuals are
prepared.
Proposals for preparing the necessary manuals to maintain service quality and construction
quality were made.
- (Material used) “Preparing construction manuals and achieving consistent quality by
standardizing the construction content”
Optimization of the extra length and labels on the cables
- The extra length (wound up and secured) of optical fiber cable found in the field survey can
cause communication failures. A proposal was made on how to eliminate the extra length and
install the closure.
- A proposal was made on how to reduce human errors, such as using then wrong cable when
performing work in the field, by displaying information such as the cable destination and
cable specifications.
- (Material used) “Wiring and display methods”
Record on state of construction
- Operation manuals can help achieve a standard level of skill. To ensure that construction is
performed as written in the manuals, a proposal was made to take photos as records of
construction after procedures are performed.
- Keeping photos as records of construction helps to secure a uniform level of construction
quality and ensure that construction was carried out correctly.
- (Material used) “Proposal for taking photos as records”
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
20
Test manual of optical fiber cable
- A test manual was prepared and submitted for measuring the signal loss (OLTS) and
reflection (OTDR) in the optical fiber construction.
- VNTT is expected to update the manual and make it consistent with the actual conditions so
that it can be used as the initial operation manual for construction.
- (Material used) “Optical fiber cable test manual”
Photo 10. Presenting proposals for improving
construction management ①
Photo 11. Presenting proposals for improving
construction management ②
Photo 12. Presenting proposals for improving
construction management ③
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
21
3-5. Technical guidance for construction engineering
Construction engineers were given technical guidance on construction engineering.
Information related to technical guidance was provided in three chapters.
< Overview of technical guidance>
1. Lecture
Fundamentals of optical fibers (Photo 13)
- Explained the basic characteristics of optical fibers.
- Explained the theory on how the signal loss was actually caused by the occurrence of bending
loss.
- (Material used) Fundamentals of optical fibers
Causes of connection loss
- Explained measures to prevent connection loss due to the accumulation of dirt or dust that may
easily occur when the optical fibers are sealed.
- (Material used) Causes of loss
Introduction to Skill Olympics
- Introduced the international competition for construction skills in which Japanese
communication construction companies participate.
- (Material used) Introduction to Skill Olympics
2. Practical guidance
- Jacket stripping of loose tube cable
- Learning to seal connections faster
- Storage inside the closure (Photo 14)
Photo 13. Explanation of optical fiber characteristics
Photo 14. Practical guidance
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
22
3-6. Findings
In the area of construction management, proposals were made regarding the concept as well as
specific work methods, such as human resource development and the preparation of manuals for
the network design policy and equipment management method. These kinds of methods will be
needed in the future as the new city area of Binh Duong Province continues to develop.
The proposals were prepared based on the current issues that we shared with the personnel in the
field by actually visiting the sites where they work. The information and content were well
received by the participants. One-way explanations of skills and know-how were avoided, and the
factors behind the proposals were explained so that the participants could deepen their
understanding. These efforts led to active discussions.
In the area of construction skills, the fundamentals of optical fibers and sealing work were
explained to help the participants understand what causes signal level loss to occur. In addition,
specific technical guidance was given on the closure assembly. Inconsistency in the level of
construction skills was once again confirmed because the general technical skill of the optical
fiber construction was clearly evident in the closure assembly.
Closure assembly is a daily operation, and there is a lot of basic know-how that we can share
with each other. The participants were very enthusiastic about this topic, and despite the language
gap raised many questions.
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
23
Chapter 4. Promotion of Understanding of ICT Project Operation Technologies in Japan
4-1. Outline of invitation to Japan
1) Outline of invitation to Japan
① Objective of invitation to Japan
The objective is to deepen the knowledge and understanding among the invited local staff
from Vietnam regarding the two points described below by showing them the facilities and
operations of the Japanese telecommunications carriers, and by holding question and answer
sessions and exchanging opinions with those concerned:
・Management items required for improving the ability to run the ICT project (facility
management, construction management, quality management, and problem management)
・Improvement of construction engineering levels and the development of engineers with the
aim of stably maintaining the quality of the ICT environment and enhancing it.
② Period of invitation and the invitees
・Period April 21 to 25, 2015
・Invitees Three individuals were invited: two from Department of Information and
Communication of Binh Duong Province, which is our local counterpart, and one
employee from VNTT, where we carry out our local activities.(Table.6)
Table 6. Invitees
Position and organization
Director -Department of Information and Communication of Binh Duong Province
Head of Post and Telecom Division-Department of Information and Communication of
Binh Duong Province
Operation Manager of VNTT data center
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
24
2) Schedule
The program was carried out according to the following schedule: (Table.7)
Table 7. Schedule
Date Morning Afternoon
April 21,
2015
Arrival
April 22,
2015
Tour of iTSCOM data center Tour of NTT Communications
Corporation data center
April 23,
2015
Tour of housing complex constructed by
iTSCOM
Tour of iTSCOM call center
Tour of iTSCOM smart home
April 24,
2015
Tour of NTT Communications
Corporation cable tunnel
Tour and practical guidance at the
communication construction
engineer training center
April 25,
2015
Departure
4-2. Implementation status and evaluation of the invitation
1) Responses of the invitees during the visit
①iTSCOM data center (Photo 15 and Photo 16)
Like VNTT, iTSCOM is a community-based telecommunications carrier and provides a
variety of ICT services, such as cable TV, telecommunication, and telephone services. The
invitees visited the iTSCOM data center and monitoring room that monitors and runs the
services and systems.
In the question and answer session, the invitees asked questions about detecting signs of
communication failures from the monitoring room, the flow for notifying the parties involved,
such as the users, of the detected failures, and the preventive measures for ensuring that
information which needs to be conveyed is not omitted when a successor takes over. During the
briefing on the system, they asked questions about the network monitoring system and
maintaining the service level (division of areas when the number of users increases, checking the
quality at the time of construction when the system is introduced). These questions were kindly
answered by the hosts.
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
25
②NTT Communications Corporation data center (Figure 5, Photo 17)
The invitees visited the data center owned by NTT Communications Corporation, which is
one of the leading telecommunications carriers in Japan. It is a large-scale data center that has
been expanded three times in the past. Because VNTT from Binh Duong Province also has its
own data center, the invitees seemed to have been comparing it with their own data center
during the course of the visit.
They showed great interest in the air current control inside the server room (air conditioners
take in the warm air after cooling down the equipment), and asked a lot of questions about
controlling different aspects of the facilities, such as the concept behind the air conditioning.
During the question and answer session, they asked about the facility grade of the data center
and about the acquisition of certificates and accreditation bodies. The hosts kindly answered
these questions.
Photo 15. Tour of the monitor room Photo 16. Briefing and question and answer
Photo 17. Interior of the data center Figure 5. View of the data center
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
26
③Housing complex constructed by iTSCOM and transmission path control
The invitees visited a large-scale housing complex for which the optical fibers were
constructed by iTSCOM. Observing the wiring processing and destination tagging of optical
fibers provided them with an opportunity to see an actual case of the wiring control that they
undertook in Vietnam. They actively asked questions about checking the construction status and
construction know-how (Photo 18).
The optical fibers in this complex are exclusively for TV (CATV signals), so the invitees asked
questions about other services, such as Internet connection and telephone services, and about
switching between service providers. The hosts kindly answered these questions.
iTSCOM provided an explanation on transmission path control. In their explanation, they used
a mapping system that lays out the information for transmission path control on an electronic
map and used a distribution diagram to show the method for controlling the path.
Transmission paths are not fully under control in Vietnam, and thus efforts are being made to
organize the pipe lines and control wiring in the new metropolitan area. The invitees showed
great interest in the method for controlling the transmission path explained by the host, and
asked a lot of questions about this matter (Photo 19).
④ iTSCOM call center (Photo 20, Photo 21)
In addition to its own users, iTSCOM handles call center operations for various other
customers, such as the call center operators of other cable TV stations. The invitees were given a
briefing about the call center and visited the place where real operators were actually working.
Photo 18. Tour of MDF room of the housing
complex
Photo 19. Explanatory session on control of
transmission path and monitoring
system
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
27
During the briefing session at the call center, they asked questions about the cost management
of operators and human resource development. The questions covered the following topics:
・Balance between the employment status of the operators and cost management (labor cost)
・Method and period for developing operators
・Limiting and minimizing the deterioration in quality that occurs during the operator training
period due to the lack of experience of new employees
・Follow up calls (performance of follow up calls at iTSCOM and their effect)
During the tour of the call center, the invitees asked a lot of questions about how to use the
Call Management System (CMS).
They actively exchanged opinions with the hosts about issues mainly related to the operational
side, such as operational management by the operators in response to different situations, the
manner in which the records of conversations with customers are used, and the way in which a
variety of entrusted services are managed.
⑤iTSCOM smart home (Figure 6, Photo 22)
iTSCOM provides a smart home service that controls home electronics and the locking and
unlocking of door keys through connections established between the house and network. The
invitees participated in the briefing and were given a demonstration.
Photo 20. Explanatory session on the operations
of call center
Photo 21. Invitees asking questions
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
28
Although the majority of the invitees agreed that it is too early to introduce this kind of service
in Vietnam where the GNI is not that high, they gained an understanding of why it is essential to
have a stable and high-quality communication infrastructure for introducing this service.
* GNI: Gross National Income
⑥ NTT Communications Corporation cable tunnel (Photo 23, Photo 24)
This cable tunnel is a large-scale facility located in the Tokyo metropolitan area, measuring
60,000 kilometers long with the deepest part being approximately 50 meters deep underground.
The invitees had been looking forward to the tour of this underground facility in the
metropolitan area since the time they heard about during the explanation of the visit schedule.
After the briefing session, they went down about 25 meters deep, after which they were given
an explanation about the tunnel.
They invitees were impressed by the high level of the facility itself, in addition to the high
level of the line control technology and line construction engineering. The tour of the tunnel
seemed to have deepened their understanding of the need of line control instead of simply
laying communication lines as is done in Vietnam.
Figure 6. System diagram
Photo 23. Briefing session
prior to the tour
Photo 22. Question and answer session
Photo 24. Group photo taken before the tour of the
cable tunnel
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
29
⑦ Communication construction engineer training center (Photo 25, Photo 26, Photo 27)
The communication construction engineer training center is a training facility where situations
identical to actual situations in the field are reproduced. At the outdoor facility of the center, the
invitees observed how construction is performed inside Japanese manholes and experienced
work on a power pole. At the indoor facility, they observed a demonstration by Japanese
construction engineers and received practical guidance, allowing them to deepen their
understanding about development of construction engineers. They asked many questions and
actively exchanged their views throughout the visit, such as during the hands-on field activities,
the demonstration, and the practical guidance session.
Photo 25. Hands-on activity at the
training facilities
Photo 26. Construction demonstration
Photo 27. Hands-on cable construction
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
30
2) Evaluation by the invitees
The invitees were impressed by this visit to Japan because it helped them clarify their awareness of
a range of issues in light of both current and future conditions. It also provided them with firsthand
experiences of the facilities and structures of iTSCOM, a community-based telecommunications
carrier like VNTT, as well as those of NTT Communications Corporation, one of the leading
telecommunications carriers in Japan. These experiences during their time in Japan were all made
possible thanks to the cooperation of these two companies. In addition, the explanatory sessions held
between the tours of different facilities allowed them to obtain a more concrete idea of construction
management.
They were particularly impressed with the training center of the telecommunication construction
company. The invitees appreciated the activities that incorporated hands-on experiences, such as the
activities at the facilities where real-life situations are reproduced and actual work constructing
optical fiber cables.
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
31
Chapter 5. Study of the Direction of Business Development after the
Implementation of this Project
5-1. Outline of business development
1) Objective of the project
The objective is to provide not only a stable communication environment, but also flexible
services and high-quality support suited to the needs involved in attracting enterprises. The main aims
are to attract enterprises of all sizes from a broader range of business fields and accelerate the urban
development of Binh Duong Province.
2) Improvement plan
The activities for conveying technologies to VNTT through this project deeply impressed the
counterpart. There is a need for ongoing support even after this project is completed.
The improvement and enhancement of the ICT infrastructure represent critical elements in
contributing to the urban development of Binh Duong Province. VNTT is expected to continue
improving its technical capabilities.
Currently the cooperating companies who provided the technical guidance in this project are
proposing providing VNTT with the technical guidance for a fee.
The benefit of the improved technical and supporting capabilities of VNTT is expected to help
attract enterprises of all sizes from a broader range of business fields and accelerate the urban
development of Binh Duong Province in the future.
3) Human resource development plan
The development of human resources aimed at improving technical capabilities is currently
underway. For this reason, the following table serves merely as an example of the development
schedule. (Table.8)
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
32
Table 8. Example schedule for human resource development
Jul Aug Sep Oct Nov Dec Jan Feb Mar
Project activities
Adjustment of needs with the
local communication carrier
Study of the framework in
Japan
Planning of curriculum
Proposal and contract
Local activities (example)
2015 2016
Local Domestic
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
33
Chapter 6. Clarification of Expected Effects of Development through the Business
after this Project
6-1. Beneficiaries of this project and expected effects of development
The beneficiaries of this project and the effects of development are as follows:
1) VNTT
There is a need for ongoing support for VNTT, even after the completion of this project, in order to
help it improve its technical capabilities. Because the improved technical capabilities are expected to
have a positive effect on the service quality, there will be opportunities to acquire new customers.
2) Local users
The local users can enjoy a more stable ICT environment, thanks to the enhanced service quality
stemming from the improved technical capabilities of VNTT. The stable ICT environment will serve
as a base for new services, and indirectly contribute to providing users with greater convenience.
3) Department of Information and Communication of Binh Duong Province
The improvement of the ICT environment is expected to increase the number of opportunities for
companies from new business fields to advance into the province because communication quality is
an incentive required for attracting enterprises.
The province is expected to flourish due to an increase in the tax revenue from the new companies
who move to Binh Duong, and from the people who come to the province in search of employment
opportunities.
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
34
Chapter 7 Considering the Possibility of Coordinating with the Local
ODA Project
7-1. Need for coordination and expected effects
The ICT environment is a form of infrastructure that supports urban areas. For this reason,
coordination with other urban development-related projects is vital.
Mobile communication devices such as smartphones are rapidly spreading throughout the
populace in Vietnam. Broad coordination with BRT, which is currently conducting a PPPFS study,
and other traffic fields that play key roles in urban functions will help improve the convenience of
public transportation, such as by providing people with real-time information about transportation
services. This will contribute to promoting a modal shift to public transportation systems as a solution
to urgent issues, such as chronic traffic congestion and environmental problems. As a result, the
socioeconomic benefits are expected to increase.
In addition, the improvement of the ICT infrastructure occupies an important place in the medical
and academic research fields as well. These fields are two critical elements in the urban development
of Binh Duong Province. The improvement of the ICT infrastructure, particularly a stable
communication environment capable of sending and receiving large amounts of information, is
indispensable to the academic field, where research data needs to be transmitted, to the medical field,
where images are used to help coordinate between hospitals, and to remote medical care.
Efforts to attract medical organizations and academic research institutes comprise a field eligible to
receive public aid, such as ODA. Thus, the preparation of the ICT infrastructure, which will
ultimately serve as a base for promoting projects in this field, will allow for quick coordination with
ODA projects in the future.
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
35
Chapter 8. Summary of the Project
8-1. Operational management
1) Outline of the activities
This project enabled those VNTT to understand the significance of operational management in
improving service quality. This understanding was gained through the analysis of CRM data, the
identification of issues, and the review and implementation of effective measures. We worked
together with VNTT to set KPIs (key performance indicators) for operational management.
We made the necessary modifications to CRM system so that these KPIs could be achieved within
the existing system. To ensure that they were achieved, we decided to carry out a three-month trial to
monitor the KPIs.
2) Results of the activities
These activities enabled VNTT to understand the fact that quantitatively summarizing and
analyzing acquired data helps to clarify issues and make it possible to take the adequate measures.
In addition, the specification and monitoring of KPIs allowed us to see a positive commitment
towards improving the service quality.
3) Possible additional improvements
Positive results were achieved in these activities, as was previously discussed. However, the service
quality can be improved even further by doing the following:
・Continuously analyzing the data for improving the service quality, sharing the analysis results
inside the company, and eventually studying measures for improvement
・Review the KPIs on a regular basis to establish proper awareness of service quality
・Construct a scheme that can apply feedback from customers and improve customer satisfaction
8-2. Construction management
1) Outline of the activities
In regards to construction management, we indicated that the cause for the lack of consistency in
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
36
construction standards lay in the insufficient standardization of work procedures and making records
of work. We checked the laying of the optical fibers, measured the signal loss level, gave facility
tours, and conducted demonstrations. We also made suggestions for improvement.
In addition, we organized practical guidance provided by Japanese construction engineers. The
purpose of this guidance was to improve the construction engineering levels.
2) Results of the activities
In the area of construction management, we were able deepen VNTT’s understanding of the
technical methods for stabilizing the quality of optical fiber construction through the provision of
technical guidance. Moreover, they understood that it is important to develop construction engineers
with a certain level of skill by standardizing work procedures, and by planning a development
curriculum to ensure technical skills remain at a certain level.
3) Possible additional improvements
Positive results were achieved in these activities, as was previously discussed. However, the service
quality can be improved even further by doing the following:
・Standardize construction work to achieve a uniform level of construction quality
・Prepare a curriculum to ensure the ongoing development of engineers.
・Establish a framework to check the skills of the engineers and review the development
curriculum on a regular basis.
8-3. Issues
It is essential that VNTT understands and applies the suggestions and recommendations that it is
given during the course of this project. Even after the applying the feedback it receives, VNTT must
maintain the cycle that begins with the identification of new issues and ends with their resolution,
while at the same time making this cycle an integral part of their daily operations and working on its
own to manage the application of this cycle.
The continuation of this cycle requires organizational efforts, such as establishing a framework and
creating a new sense of awareness.
8-4. Direction of future business development
This project is aims to improve the functions of the ICT environment as a basic infrastructure. The
starting point is the urban development project that Tokyu Corporation is conducting in the new
metropolitan area in Binh Duong Province.
Collaboration Program with the Private Sector for Disseminating Japanese Technology for strengthening ICT management capacity in the Ministry of Binh Duong ,VIETNAM
37
The activities of this project enabled us to deepen VNTT’s understanding of the significance of
operation management and construction management in improving the service quality. We believe
that the service quality and support quality will reach the level they are at in Japan if this
understanding becomes established and sustainably applied.
In the survey conducted in cooperation with the Ministry of Economy, Trade and Industry in fiscal
2014, five issues were identified as key to improving the stable ICT environment. The following
three issues, which were not examined in this project, need to be addressed: ①Shortage of
international line capacity ②Inadequate automation of traffic processing, and ③Lack of data center
facilities that can compete in the future.
Looking first at the shortage of international line capacity, currently a reasonable level of
communication speed is maintained in Vietnam. However, yet it cannot be said that this speed is
sufficiently good, partly because communication with other countries is provided by nationwide
communication carriers. This is likely to discourage companies from outside Vietnam from entering
the market. In addition, there is a need to secure redundancy by automating the traffic processing for
the upstream communication line carriers and enhancing business sustainability.
Various measures must also be taken to increase the competitiveness of local data centers and their
ability to meet the demands for coping with the emergence of cloud computing in recent years. The
support system for companies expanding their businesses into new metropolitan areas and
neighboring industrial complex needs to be reinforced, and facilities for meeting quality requirements
need to be enhanced. In addition, it will be important to develop a service grounded in the role of a
DR (disaster recovery) site that takes full advantage of the surrounding geographic features.
After the aforementioned problems are addressed and improvements are made to make the ICT
service environment as well as service quality consistent with a higher standard, a better environment
will be established. This environment will facilitate the advance of not only the conventional
companies and manufacturers, but also new businesses, such as software development and contents
production, which handle large volumes of data despite of their business size. The improved
environment can also be expected to play a supporting role for companies in Ho Chi Minh City.
Lastly, the improved ICT environment can be expected to make great contributions to enhancing
added value and developing new metropolitan areas in Binh Duong Province by promoting the
advance of educational organizations and medical organizations. At the same time, it will also
contribute by playing a major role as an infrastructure that enriches the daily lives of the local
residents, who are the individual users.
END