social capital: secret of success of water supply
TRANSCRIPT
SOCIAL CAPITAL:
SECRET OF SUCCESS
OF WATER SUPPLY
SCHEMES
FAYYAZ BAQIR
COMMUNITY
ENGAGEMENT PROCESS
(PHED) Punjab adopts a policy to mobilize communities for
development, implementation, operation and management of
rural water supply schemes- 2005.
Establishes Community Development Unit (CDU) of PHED
An elaborate process of community engagement is designed
Existing Approaches to design and
implement a Rural Water Supply
Scheme
A) by elected representatives like Members of National and Provincial
Assemblies i.e. MNAs and MPAs; B) by surveys of engineering staff of
PHED or C) by community based need assessment conducted by CDU in
collaboration with the technical staff of PHED.
Traditionally politicians preferred to select the site of a scheme keeping in
view their vote bank; PHED gave preference to scheme at sites having
brackish underground water and a large size of population; community
based assessment focused on community’s willingness to takeover O&M
after completion of the scheme to ensure sustainability.
Component Sharing based on the
concept of Internal-External
DevelopmentInternal Development consists of infrastructure
development and service delivery at household and
lane level and External Development includes the
work at each tier above the lane. Under the
component sharing approach for provision of water
supply Government takes responsibility for External
Development. It includes the responsibility for
identifying, costing designing, financing, supervising,
managing and developing the source of water,
overhead reservoir and rising main.
Local CBO takes the responsibility for costing designing, financing,
supervising, managing, developing and maintaining distribution lines to
households, installing water connections, pumping water to beneficiary
households, issuing and collecting water bills and maintaining pipelines,
pumping machinery and overhead reservoirs. This provides the foundation
of Government
CRITICAL MILESTONES
1. CONTRACTOR’S OVERSIGHT
If WUC receives a copy of detailed estimates, it can conduct
technical oversight effectively and get the scheme completed
according to approved specifications. If the contractor
deviates from approved specifications, community may
refuse to take over the scheme.
2. BIDDING FOR CONTRACT
Lowest bidding is used as the sole criteria for awarding contracts. Track
record of the contractor and compliance with project specifications and
timelines are not factored in, in accepting the bids and releasing payments.
CONTRACTOR’S OVERSIGHT
When scheme implementation begins the contractor is required to perform
the Yield Test for trial bore. This test is the second most critical step for
ensuring access to clean source of water. If this test is not conducted and a
fake report is submitted contractor receives the payment without ensuring
the selection of appropriate water source.
CONTACTOR’S OVERSIGHT
After completion of the scheme, discharge capacity of water and
production is checked and entered in Measurement Book (MB). Without
entries in the MB contractor cannot receive payments. It is supposed to be
PHED’s confidential record but usually compiled by the contractors. This
is conflict of interest. It violates the spirit of community ownership and
leads to failed schemes.
If the contractor does not deliver according to the specification, department
might go for re tendering, take action against the contractor and recover the
payment made.
3. SELECTION OF SITE
One key flaw in most of the rural water supply schemes is selection of water
source far away from the village. This flaw can be overcome if water users
are consulted at the planning and inception of development phase. WASCO
has to endorse the water quality before release of payments and
subsequently take over the responsibility for regular water quality testing
4. COMPLIANCE WITH PROCEDURES
The procedures designed by PHED for ensuring community participation
and ownership is foolproof. It fails only where department functionaries
deviates from its own procedure. Community can check lack of compliance
with procedure if CDU performs its guiding and support functions
effectively.
CDU staff are contract employees, without communication budget and
without control on their vehicles. Support organization without any teeth.
5. Ensuring Sustainability
through water metering
Financial Indicator Amounts
Average Monthly Expense Rs. 170,000
Salaries
(2 pump operators, 1 meter
reader and bill distributor, 1
store keeper 1 maintenance
operator and 1record
keeper)
Rs. 50,000
Electricity Bills (2) Rs. 110,000
Maintenance, mobile phone
and petrol bills
Rs. 10,000
Average Monthly Income Rs. 175,000
6. TOOLS FOR COMMUNITY
MOBILIZATON
Dealing with contractors: Speak softly but keep a hard stick
in your hand
Water metering: an effective tool for revenue collection
Record keeping: another management tool for effective
community participation
7. Effective SUPPORT ORGANIZATION for technical
&social guidance