smithfield street bridge preservation...project team design division direct questions to: michael p....

16
PENNDOT PROJECT INFORMATION Smithfield Street Bridge Preservation SR 3027, Section A05 City of Pittsburgh, Allegheny County

Upload: others

Post on 11-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Smithfield Street Bridge Preservation...PROJECT TEAM Design Division Direct questions to: Michael P. Sokol, P.E. - Project Manager at 412.429. 4898 Engineering District 11-0 | Project

PENNDOT PROJECT INFORMATION

Smithfield Street Bridge

PreservationSR 3027, Section A05

City of Pittsburgh, Allegheny County

Page 2: Smithfield Street Bridge Preservation...PROJECT TEAM Design Division Direct questions to: Michael P. Sokol, P.E. - Project Manager at 412.429. 4898 Engineering District 11-0 | Project

PROJECT TEAM

Design Division Direct questions to:

Michael P. Sokol, P.E. - Project Manager at 412.429. 4898Engineering District 11-0 | Project Delivery Unit,45 Thoms Run Road | Bridgeville, PA 15017or [email protected].

Mark J. Young - District Environmental Planning Manager

Todd C. Crouch - Environmental Supervisor - NEPA

Press Office Steve Cowan - District Press Officer

Please complete survey at end of presentation

Page 3: Smithfield Street Bridge Preservation...PROJECT TEAM Design Division Direct questions to: Michael P. Sokol, P.E. - Project Manager at 412.429. 4898 Engineering District 11-0 | Project

PURPOSE OF PRESENTATION & PROJECT INTRODUCTION

SR 3027, Section A05 (Smithfield Street Bridge) Project

The purpose of this presentation is to introduce the project to the public, gather feedback, and present the proposed traffic control and associated detours.

The purpose of this project is to address structural deficiencies to preserve the functional integrity of the bridge and to maintain the current level of vehicular and pedestrian services provided by the Smithfield Street Bridge.

Page 4: Smithfield Street Bridge Preservation...PROJECT TEAM Design Division Direct questions to: Michael P. Sokol, P.E. - Project Manager at 412.429. 4898 Engineering District 11-0 | Project

PROJECT LOCATION

Project Location

Page 5: Smithfield Street Bridge Preservation...PROJECT TEAM Design Division Direct questions to: Michael P. Sokol, P.E. - Project Manager at 412.429. 4898 Engineering District 11-0 | Project

PROPOSED PROJECT IMPROVEMENTS

Bridge Preservation Project

Retrofitting/repairing deficiencies present in various steel members and components

Repairing areas of painted-over pitted section loss and other deficiencies in floorbeam and girder webs

Replacing the steel orthotropic sidewalks on both sides of the truss spans

Replacing the bridge deck epoxy wearing surface of the truss spans

Repairing spalled concrete in bridge support bearing pedestals and the bases of pedestrian railing posts

Page 6: Smithfield Street Bridge Preservation...PROJECT TEAM Design Division Direct questions to: Michael P. Sokol, P.E. - Project Manager at 412.429. 4898 Engineering District 11-0 | Project

PROPOSED PROJECT IMPROVEMENTS

Bridge Preservation Project (Cont’d)

Replacing/tightening bearing anchor bolts and resetting bronze sliding plate bearings

Repairing shotcrete (gunite) on the underside of the east (upstream) pony truss span over the CSX railroad tracks

Repairing Deck Joints and Replacing Deck Joint Seals

Power washing the truss chords to remove rust packing and pigeon waste

Cleaning/flushing deck expansion dams, neoprene drain troughs, scuppers, and down spouting

Page 7: Smithfield Street Bridge Preservation...PROJECT TEAM Design Division Direct questions to: Michael P. Sokol, P.E. - Project Manager at 412.429. 4898 Engineering District 11-0 | Project

PROPOSED PROJECT IMPROVEMENTS

Other Proposed Work Concrete pavement and island patching / joint sealing repairs,

drainage improvements, new Pavement Markings, upgrades to the Traffic Lane Control System on Smithfield Street Bridge, including Signal Controller and other Hardware, and new Countdown Signal Heads at Pedestrian Crossings.

Work will occur during daytime hours and work at off-peak or nighttime hours with single lane closures required for work on north approach spans over the Parkway West (I-376) and Fort Pitt Boulevard.

For work on south approach spans over Private Roads traffic will be maintained through flagging operations.

Work will be done within existing Legal Right-of-Way with some work within Temporary Easements for Contractor Access.

Construction anticipated to begin in Spring / Summer 2021 with anticipated completion in Spring / Summer 2022.

Page 8: Smithfield Street Bridge Preservation...PROJECT TEAM Design Division Direct questions to: Michael P. Sokol, P.E. - Project Manager at 412.429. 4898 Engineering District 11-0 | Project

PROPOSED TRAFFIC CONTROL

Lane Restrictions on the Bridge

Work on the bridge will not require long-term lane closures to car and truck traffic. Traffic will be maintained with a three-phased plan.

Phase 1: Two lanes (Northbound & Southbound) on the west roadway of the bridge during sidewalk, overhead steel repairs, and deck overlay work on the east roadway of the bridge.

Phase 2: One lane of Northbound traffic on the east roadway of the bridge and one lane of Southbound traffic on eastern side of the west roadway during sidewalk and overhead steel repairs for the western Southbound lane of the west roadway.

Phase 3: One lane of Northbound traffic on the east roadway of the bridge as in Phase 2, but Southbound traffic on the west roadway will shift to the western Southbound lane during repairs for the eastern Southbound lane.

Phase 1

West East

Clo

sed

for

Con

stru

ctio

n

Phase 2

West East

Clo

sed

for

Con

stru

ctio

n

Phase 3

West East

Clo

sed

for

Con

stru

ctio

n

Page 9: Smithfield Street Bridge Preservation...PROJECT TEAM Design Division Direct questions to: Michael P. Sokol, P.E. - Project Manager at 412.429. 4898 Engineering District 11-0 | Project

PROPOSED TRAFFIC CONTROL

Lane Restrictions on the Bridge (Cont’d)

Bus traffic will continue to use the structure while Southbound traffic lanes receive a new wearing surface overlay, by using alternating 2-way traffic on the single lane at the east roadway of the bridge.

All other (non-bus) traffic will be detoured for two (2) weekends and will need to use the designated detour route.

Full bridge closure may be implemented by the contractor between 12:45 AM and 5:50 AM Monday to Saturday and between 11:40 PM and 5:50 AM on Sundays, when there is no bus traffic. The designated detour route will be implemented during these times.

During nighttime restrictions, emergency vehicles will still have access to the bridge.

Bus Traffic

West East

Clo

sed

for

Con

stru

ctio

n

Page 10: Smithfield Street Bridge Preservation...PROJECT TEAM Design Division Direct questions to: Michael P. Sokol, P.E. - Project Manager at 412.429. 4898 Engineering District 11-0 | Project

PROPOSED TRAFFIC CONTROL

Other Lane Restrictions

North Approach Span work over lanes of the SR 279 Southbound Ramp and adjacent Fort Pitt Boulevard Ramp will require stop sign controlled shifts from the one ramp to the other ramp and in reverse.

North Approach Span work over the Grant Street to I-376 Westbound Ramp (Ramp A) will require ramp closure during off-peak hours or at night with traffic detoured to Fort Pitt Boulevard.

North Approach Span work over lanes of the Parkway (I-376) Eastbound and Westbound may require off-peak and/or nighttime single lane closures.

North Approach Span Deck Repairs – Fort Pitt Boulevard may need to be reduced to a single lane during off-peak hours (e.g. weekday nights between 7 PM and 5 AM), or under flagging.

Page 11: Smithfield Street Bridge Preservation...PROJECT TEAM Design Division Direct questions to: Michael P. Sokol, P.E. - Project Manager at 412.429. 4898 Engineering District 11-0 | Project

PROPOSED TRAFFIC CONTROL

Other Lane Restrictions (Cont’d)

Traffic on Private Roads beneath the Southern Approach Spans will be maintained through flagging operations.

Railroad Traffic

Work on Span 7 over CSX Railroad will be coordinated with the Railroad.

Page 12: Smithfield Street Bridge Preservation...PROJECT TEAM Design Division Direct questions to: Michael P. Sokol, P.E. - Project Manager at 412.429. 4898 Engineering District 11-0 | Project

PROPOSED PEDESTRIAN DETOURS

Smithfield Street Bridge

Sidewalk decking replacement on Truss Spans 3 & 4 requires sidewalk closure – only one bridge sidewalk closure at a time will be permitted during construction. Pedestrians will be detoured to the open sidewalk on other side of the bridge.

Repair work on Truss Span 7 will require Temporary Protective Pedestrian Tunnel to be built over the Three Rivers Heritage Trail beneath the span to provide protection from the work above.

North Approach Spans at Great Allegheny Passage (GAP) Trail –The switchback ramp will remain open during construction. During bridge sidewalk reconstruction directly in front of it and bridge work over the switchback ramp, access will be maintained with flagging operations.

Span 7

Page 13: Smithfield Street Bridge Preservation...PROJECT TEAM Design Division Direct questions to: Michael P. Sokol, P.E. - Project Manager at 412.429. 4898 Engineering District 11-0 | Project

SR 3027 NORTHBOUNDDETOUR PLAN

SR 3027 Work Zone

SR 3027 Northbound Detour RouteDetour Length – 2.0 miles

Traffic Flow

Traffic Detour Required for All Traffic Except Port Authority & Emergency Vehicles

Page 14: Smithfield Street Bridge Preservation...PROJECT TEAM Design Division Direct questions to: Michael P. Sokol, P.E. - Project Manager at 412.429. 4898 Engineering District 11-0 | Project

SR 3027 SOUTHBOUNDDETOUR PLAN

SR 3027 Work Zone

SR 3027 Southbound Detour RouteDetour Length – 2.0 miles

Traffic Flow

Traffic Detour Required for All Traffic Except Port Authority & Emergency Vehicles

Page 15: Smithfield Street Bridge Preservation...PROJECT TEAM Design Division Direct questions to: Michael P. Sokol, P.E. - Project Manager at 412.429. 4898 Engineering District 11-0 | Project

NATIONAL ENVIRONMENTAL POLICY ACT (NEPA)

Public outreach begins with PennDOT Connects and extends into the NEPA (National Environmental Policy Act) process:

PennDOT Connects is a project planning and development approach that engages local and planning partners by collaborating with stakeholders before project scopes are developed.

NEPA requires agencies to integrate environmental values into their decision-making processes by considering the environmental impacts of their proposed actions and reasonable alternatives to those actions

NEPA also includes public involvement activities and gathering feedback from the public

This PowerPoint presentation is part of District11-0’s coordination with the public to obtain feedback on the project and to meet NEPA requirements.

Image courtesy of MDOT

Page 16: Smithfield Street Bridge Preservation...PROJECT TEAM Design Division Direct questions to: Michael P. Sokol, P.E. - Project Manager at 412.429. 4898 Engineering District 11-0 | Project

PROJECT SURVEY

https://www.surveymonkey.com/r/5YL2KLX