    Town of Estes Park

    Residential Renewable Energy

    Reuben Bergsten

    Estes Park Light and Power

    10 October 2009

    American Planning AssociationColorado Chapter

  • 8/6/2019 Small Scale Renewable Distributed Generation

    2/23

    Intro

    Reliable electricity is an expectation. Every yearour economy becomes more efficient and

    productive. Electricity is the fundamental building

    block for those efficiencies.

    August 10, 1996 blackout in the Western US States: power was interrupted to approximately 7.5 million customers,

    durations ranged from a few minutes to about nine hours.

    costs to the regions economy ~ $2 b i l l ion .

    August 14, 2003 blackout, Midwest/Northeast US & Ontario

    50 million people Up to 4 days in the US

    Cost estimates range between $4 b i l l ion and $10 b i l l ion

    Is smal l sc a le w ind generat ion a feas ib leaddi t ion t o t he gr id ?

    2

  • 8/6/2019 Small Scale Renewable Distributed Generation

    3/23

  • 8/6/2019 Small Scale Renewable Distributed Generation

    4/23

    Technical Feasibility Siting

    Estes Park results

    Power Demand Just in time deliver

    Economic Feasibility

    Cultural Feasibility

    4

    Residential Renewable Energy

  • 8/6/2019 Small Scale Renewable Distributed Generation

    5/23

    Technical feasibility Siting (planning process of selecting a good wind generation site)

    5

    Residential Renewable Energy

    http://www.engr.colostate.edu/ALP/videos/WindGeneration.wmv

    Wind generation video from CSU & GEO

    http://www.engr.colostate.edu/ALP/videos/WindGeneration.wmvhttp://www.engr.colostate.edu/ALP/videos/WindGeneration.wmvhttp://www.engr.colostate.edu/ALP/videos/WindGeneration.wmvhttp://www.engr.colostate.edu/ALP/videos/WindGeneration.wmv
  • 8/6/2019 Small Scale Renewable Distributed Generation

    6/23

    Technical feasibility Siting- Estes Park Anemometer Results

    CSU Senior Researcher Michael Kostrzewa inconjunction with the Governors Energy Office(GEO) provided data collection & analysis.

    Estes Park is a number 2 wind class at60 FEET. The worst is 1. Kostrzewa/GEO results for EstesPark.

    Larimer County has a 40 foot height limit! Wind power classes 3 and higher are generally

    considered suitable for wind power development.

    6

    Residential Renewable Energy

    http://www.engr.colostate.edu/ALP/http://www.engr.colostate.edu/ALP/ALP_63_Estes_Park.htmhttp://www.engr.colostate.edu/ALP/ALP_63_Estes_Park.htmhttp://www.engr.colostate.edu/ALP/ALP_63_Estes_Park.htmhttp://www.engr.colostate.edu/ALP/ALP_63_Estes_Park.htmhttp://www.engr.colostate.edu/ALP/
  • 8/6/2019 Small Scale Renewable Distributed Generation

    7/23

    Technical feasibility Siting- Estes Park Anemometer Results

    7

    Turbine

    RotorDiameter

    meters

    RotorPower

    kW

    HubHeightmeters

    HubHeightWind

    Speedmph

    TimeAt

    ZeroOutputpercent

    TimeAt

    RatedOutputpercent

    AverageNet

    PowerOutput

    kW

    AverageNet

    EnergyOutputkWh/yr

    AverageNet

    CapacityFactor

    %

    Bergey Excel-R 6.7 7.5 12.2 10.14 40.52 3.09 1.1 9,500 14.4

    Bergey Excel-S 6.7 10 12.2 10.14 32.06 1.5 1.2 10,200 11.6

    Bergey XL.1 2.5 1 12.2 10.14 23.84 4.03 0.2 1,400 16.2

    Southwest Skystream 3.7 3.7 1.8 12.2 10.14 38.4 0 0.3 2,500 16.1

    Southwest Whisper 500 4.5 3 12.2 10.14 40.52 3.61 0.5 4,600 17.6

    Source: Data collection & analysis provided by Michael Kostrzewa (CSU) in conjunctionwith the GEO.

    Thats not good. PRPA will deliver renewable energyfrom Duke energys Silver Sage site having 40% net

    capacity factor.

    Residential Renewable Energy

  • 8/6/2019 Small Scale Renewable Distributed Generation

    8/23

    Technical Feasibility Siting

    Estes Park results

    Power Demand Just in time delivery (wind availability)

    Economic Feasibility

    Cultural Feasibility

    8

    Residential Renewable Energy

  • 8/6/2019 Small Scale Renewable Distributed Generation

    9/23

    Just In Time DeliveryElectricity is the worlds most unique Commodity

    Electricity must be produced exactly when it

    is needed.

    Diurnal Electric Demand

    kW

  • 8/6/2019 Small Scale Renewable Distributed Generation

    10/23

    Just In Time DeliveryElectricity is the worlds most unique Commodity

    Solar & wind energy generation is at Mother

    Natures mercy !

    Demand[kW]

    WindGeneration[kW]

    TIME [One Day]

    6 AM 6 PMNoonThere is no guarantee electric wind

    generation is coincident to customerdemand

  • 8/6/2019 Small Scale Renewable Distributed Generation

    11/23

    Just In Time DeliveryElectricity is the worlds most unique Commodity

    Renewable energy generation is at Mother Natures mercy

    Demand[kW]

    WindGeneration[kW]

    TIME [One Day]

    6 AM 6 PMNoonThere is no guarantee electric wind

    generation is coincident to customerdemand

  • 8/6/2019 Small Scale Renewable Distributed Generation

    12/23

    Just In Time DeliveryElectricity is the worlds most unique Commodity

    Renewable energy generation is at Mother Natures mercy

    Lets store it!

    But WHERE?

  • 8/6/2019 Small Scale Renewable Distributed Generation

    13/23Batteries are Boring!

    Energy storage is the enabling technology for small scalerenewable energy.

    13

  • 8/6/2019 Small Scale Renewable Distributed Generation

    14/23

    Boring but RICH ! Today, 99 percent of batteries for hybrids are made in Japan Aug 2009, the US gave out $2.4 billion in grants for advanced battery

    manufacturing & research the largest battery investment in world history

    14

    ApplicantDOE Award (Dollars

    in Millions)Project

    LocationsTechnology

    Cell, Battery, and Materials Manufacturing Facilities

    Johnson Controls, Inc. $299.2Holland, MILebanon, OR

    (Entek)

    Production of nickel-cobalt-metal battery cells and packs, aswell as production of battery separators (bypartner Entek) for

    hybrid and electric vehicles.

    A123 Systems, Inc. $249.1Romulus, MIBrownstown, MI

    Manufacturing of nano-iron phosphate cathode powder andelectrode coatings; fabrication of battery cells and modules;and assembly of complete battery pack systems for hybrid andelectric vehicles.

    KD ABG MI, LLC (DowKokam) $161

    Midland, MI Production of manganese oxide cathode / graphite lithium-ionbatteries for hybrid and electric vehicles.

    Compact Power, Inc.(on behalf of LG Chem,Ltd.)

    $151.4St. Clair, MIPontiac, MIHolland, MI

    Production of lithium-ion polymer battery cells for the GM Voltusing a manganese-based cathode material and a proprietaryseparator.

    EnerDel, Inc. $118.5Indianapolis, IN Production of lithium-ion cells and packs for hybrid and electricvehicles. Primary lithium chemistries include: manganese

    spinel cathode and lithium titanate anode for high powerapplications, as well as manganese spinel cathode andamorphous carbon for high energy applications.

    General MotorsCorporation $105.9

    Brownstown, MI Production of high-volume battery packs for the GM Volt. Cellswill be from LG Chem, Ltd. and other cell providers to benamed.

  • 8/6/2019 Small Scale Renewable Distributed Generation

    15/23

    Where to put those batteriesTesla, NOW

    DOE

    Displacing foreign oil

    Chevy VOLT, 2011

  • 8/6/2019 Small Scale Renewable Distributed Generation

    16/23

    Time Line for Storage

    CO house bill 09-075Aug 2009 Tesla Model S

    2011

    Chevy Volt2011

    $2.4B US Grants forAdvanced BatteriesAug 5, 2009

    CAF 35.5 mpg2016

    President Obamas Goal

    1 million plug-in cars2015

    EESTOR Miracle ultracapacitor, promised aworking Proto type 2010

    EESTOR disruptive Technology

    http://www.allcarselectric.com/blog/1034854_zenn-motors-requests-doe-grant-to-build-us-based-eestor-powered-electric-car-facilityhttp://www.allcarselectric.com/blog/1034854_zenn-motors-requests-doe-grant-to-build-us-based-eestor-powered-electric-car-facility
  • 8/6/2019 Small Scale Renewable Distributed Generation

    17/23

    Technical feasibility Siting

    Estes Park results

    Power Demand Just in time deliver (wind availability)

    Economic feasibility

    17

    Residential Renewable Energy

  • 8/6/2019 Small Scale Renewable Distributed Generation

    18/23

    Economic feasibility Revenue expectations

    Colorados Net Metering legislation requires electric

    utilities to rollover excess energy generated eachmonth. Great customer SAVINGS, not revenue

    At the end of one year, the excess renewable energy

    generated is paid to the owner IN A MANNER DEEMEDAPPROPRIATE BY THE ELECTRIC ASSOCIATION Estes Park Light & Power pays customers an Avoided

    cost ~ $0.02 per kWh. Most utilities deem zero to bethe appropriate amount.

    18

    Residential Renewable Energy

  • 8/6/2019 Small Scale Renewable Distributed Generation

    19/23

    Economic feasibility Revenue expectations

    Net Metering A GREAT transitional incentive program to

    meet political pressures Not sustainable!

    19

    Residential Renewable Energy

  • 8/6/2019 Small Scale Renewable Distributed Generation

    20/23

    Economic feasibility Net Metering

    A GREAT transitional incentive program to meet political pressures

    Not sustainable!

    20

    Residential Renewable Energy

    $0.00746

    $0.02984

    $0.05559

    Net metering allows small scale renewable owners to use grid's

    transmission & distribution infrustructure, without paying for it.

    Transmission

    Generation

    Distribution

    Based on 2009 Estes Park Light & Power residential rates. Distribution from otherutilities will differ.

  • 8/6/2019 Small Scale Renewable Distributed Generation

    21/23

    Technical feasibility Economic feasibility

    Cultural Feasibility NIMBY issues

    21

    Residential Renewable Energy

  • 8/6/2019 Small Scale Renewable Distributed Generation

    22/23

    Cultural Feasibility NIMBY issues

    22

    Residential Renewable Energy

  • 8/6/2019 Small Scale Renewable Distributed Generation

    23/23

    Plan for the FUTURE

    SAEJ1772