Page 1: Slum Rehabilitation

SLUMS REHABILITATION

Page 2: Slum Rehabilitation

TECHNICAL PROBLEM AREAS

• VACATION OF SLUMS FOR PROTRACTED PERIOD WILL LEAD TO CREATION OF SLUMS ELSEWHERE.

• DISPLACEMENT IS LIKELY TO AFFECT RESIDENTIAL ACCOMODATION AS ALSO VOCATIONAL BUILDINGS.

Page 3: Slum Rehabilitation

PLAUSIBLE SOLUTION• PLAN THE COMPLETE SLUM REHAB

SCHEME.

• VACATE ONLY A SMALL PART OF THE SLUM.

• CONSTRUCT HOUSES QUICKLY AND BRING BACK THE DISPLACED PERSONS.

• PROCEED TO THE NEXT SMALL POCKET; AND THE NEXT ONE AND SO ON.

Page 4: Slum Rehabilitation

BROAD CALCULATIONS FOR CONSTRUCTION

• VACATE A HYPOTHETICAL AREA OF 100 x 100 M = 10,000 Sq M.

• LIKELY FOOT PRINT OF CONSTRUCTED AREA = 10,000 x 0.5 = 5,000 Sq M.

• BALANCE 5,000 Sq M WOULD BE LEFT FOR ROADS, SERVICES, WALKWAYS, LANDSCAPING AND SO ON.

Page 5: Slum Rehabilitation

SIZE OF DWELLIG UNITS

• EACH DWELLING UNIT WOULD COMPRISE OF:-– TWO LIVING / BED ROOMS.– ONE KITCHEN.– ONE STORE ROOM.– ONE BATH ROOM.– ONE TOILET.

• TOTAL SUPER BUILT UP AREA OF ONE DWELLING UNIT = 50 Sq M.

Page 6: Slum Rehabilitation

SIZE OF EACH BUILDING

• RESIDENTIAL BUILDINGS WOULD BE OF G + 3 CONFIGURATION.

• EACH FLOOR WOULD HAVE EIGHT DWELLING UNITS (DUs).

• SUPER BUILT UP AREA OF EACH FLOOR WOULD BE 8 X 50 = 400 Sq M.

• TOTAL NUMBER OF DUs IN EACH BUILDING WOULD BE 8 X 4 = 32 DUs.

Page 7: Slum Rehabilitation

CALCULATION FOR NUMBER OF BUILDINGS

• TOTAL FOOT PRINT OF CONSTRUCTED AREA – 5,000 Sq M.

• FOOT PRINT OF EACH BUILDING – 400 Sq M.

• NUMBER OF BUILDINGS THAT WOULD BE CONSTRUCTED – 5,000/400 = 12.5 SAY 12 BUILDINGS.

• TOTAL NUMBER OF DUs CONSTRUCTED – 12 X 32 = 384 DUs.

Page 8: Slum Rehabilitation

RECOMMENDED METHOD OF CONSTRUCTION

• CONSTRUCTION IS RECOMMENDED BY USE OF ALUMINIUM ALLOY FORMS BECAUSE OF:-– HIGH SPEED OF CONSTRUCTION.

CONSTRUCTION IS THREE TO FOUR TIMES FASTER THAN TRADITIONAL METHOD.

– CHEAPER CONSTRUCTION. 15 TO 20% LOWER THAN TRADITIONAL METHOD.

Page 9: Slum Rehabilitation

TIME FRAME FOR CONSTR OF ONE BLDG

• PROCURE ONE SET OF FORMS FOR EIGHT DUs VIZ. ONE FLOOR.

• CARCAS FOR EIGHT DUs IS CONSTRUCTED IN ONE WEEK.

• CARCAS FOR ONE BUILDING COMPRISING FOUR FLOORS IS CONSTRUCTED IN – FOUR WEEKS (ONE MONTH).

• FINISHING WILL TAKE – ONE MONTH.

Page 10: Slum Rehabilitation

TIME FRAME FOR CONSTRUCTION OF TWELVE

BLDGS• ASSUMPTION – FOUR SETS OF

ALUMINIUM FORMS ARE AVAILABLE.

• EACH SET OF THE FORMS CAN CONSTRUCT ONE FLOOR OF EIGHT DUs AT A TIME.

• WE HAVE FOUR SETS OF TRAINED CREW TO CONSTRUCT WITH THESE FORMS.

Page 11: Slum Rehabilitation

TIME FRAME FOR CONSTRUCTION

CONSTRUCT CARCAS

MONTH ONE

BLDGS Nos 1 TO 4

MONTH TWO

BLDGS Nos 5 TO 8

MONTH THREE

BLDGS Nos9 TO 12

MONTH FOUR

FINISHING BLDGS Nos 1 TO 4

BLDGS Nos 5 TO 8

BLDGS Nos9 TO 12

Page 12: Slum Rehabilitation

LIKELY ACHIEVEMENT

• 384 FAMILIES; AVERAGE SIZE – 6 MEMBERS = 2,304 PERSONS WOULD HAVE BEEN HOUSED IN FOUR MONTHS.

• NUMBER OF PERSONS HOUSED WOULD BE AT LEAST TWICE THE NUMBERS DISPLACED.

• ENTIRE AREA WOULD HAVE ROADS AND OTHER ACCEPTABLE LEVEL OF MODERN AMENITIES.

• FOR BALANCE OF SLUM AREAS, NO ONE WILL HAVE TO BE DISPLACED OUT OF THE SLUM.

Page 13: Slum Rehabilitation

GRADUATED PROGRESS OF WORK

• HAVING SUCCESSFULLY REHABILITATED THE FIRST 100 M X 100 M = 10,000 Sq M OF THE SLUM, PROGRESS TO THE NEXT 10,000 Sq M.

• FOR THIS SPACE WE MAY NOT HAVE TO DISPLACE ANYONE OUT OF THE SLUM AREA.

• WORK ON SERVICES & OTHER AMENITIES CAN BE UNDERTAKEN SIMULTANEOUSLY SO AS TO BE IN TIME WITH HOUSE CONSTRUCTION.

Page 14: Slum Rehabilitation

PURE STATISTICS

• 384 DUs ARE CONSTRUCTED IN FOUR MONTHS (122 DAYS).

• 384 X 6 = 2,304 PERSONS ARE HOUSED IN 122 DAYS.

• RATE AT WHICH THE DEPRIVED PERSONS OF THE SOCIETY ARE HOUSED: -

2,304/122 = 18.88 SAY 19 PERSONS PER DAY. (THIS IS A GOOD ACHIEVEMENT)

Page 15: Slum Rehabilitation

FINAL COMMENTS

• HIGH SPEED CONSTRUCTION USING ALUMINIUM ALLOY FORMS HAS BEEN TRIED OUT AND FOUND TO BE SUCCESSFUL.

• IT IS TECHNICALLY AN ACHIEVABLE PROJECT AT THE SPEED AND COST INDICATED.

• ALUMINIUM FORMS, IF PROPERLY HANDLED & MAINTAINED, CAN BE USED 1000 TIMES.

Page 16: Slum Rehabilitation

CONTACTS

• BRIGADIER PRAVEEN KAPUR (RETIRED).

• E MAIL Id – [email protected]