slide presentation assignment2,case study mrr2, group4, section5, session 201120121.new
DESCRIPTION
MRR2 case study. SEE4012. UTM, skudai. 2011TRANSCRIPT
MALAYSIA ETHICAL ISSUE:
MRR2NUR ASYRAF BIN ABDUL RAHIM (K)MUHAMMAD FAIZAL BIN ABDULLAHNUR HASANAH BINTI SHAFEI
OBJECTIVES
1 •To give a better insight of the unethical issues that occurred in Malaysia
2 •To educate people about the importance of adopting ethical conducts to prevent disastrous consequences
GROUP 4 2
OVERVIEW OF MRR2 [1]
Built by Malaysian Public Works Department (JKR)
To connect neighborhoods near Kuala Lumpur boundary
Cost RM238.8 million
Completed in 34 months (May 1999 to March 2002)
3GROUP 4
OVERVIEW OF MRR2
• Construction of MRR2 was divided by 3 phase : [1]
Kepong-Gombak
Gombak-Ampang
Ampang-Sri Petaling
Bumihiway (M) Sdn BhdKonsortium Kontraktor
Melayu (Wilayah)
CONTROVERSIAL ISSUES
Beam cracks
on the
Kepong
Flyover
5GROUP 4
CONTROVERSIAL ISSUES
Investigations were carried out by governmentAnti-Corruption Agency investigated possible fraud [2]
Fear about the safety on the faulty
Kepong Flyover
More than 7000 cracks detected
31 out of 33 pillars have obvious
cracks
1st
Closure
8 August2004
6GROUP 4
CONTROVERSIAL ISSUES
Works Minister,
Dato' Seri S Samy Vellu
7
P
W
D
'
s
c
o
n
s
u
lt
a
n
t
(
K
o
h
l
e
r
&
S
e
it
h
)
f
i
n
d
i
n
g
s
w
a
s
d
i
s
m
i
s
s
e
d
GROUP 4
CONTROVERSIAL ISSUES
12 August, 2004 The government of Malaysia then appointed British Halcrow Consultancy Ltd to study the cracks that have appeared on 31 of the 32 crossbeams since 2000.
findings from Halcrow Consultants Ltd suggested design deficiencies and the improper anchoring were responsible for cracks and were finally accepted by the ministry
The flyover closed in August 2004 >>waterproofed the bridge to prevent further cracks>>reopened in December 2004 [2]
8GROUP 4
CONTROVERSIAL ISSUES
I •On 4th Feb 2006, the Kepong Flyover was closed again after serious damages was confirmed
II •Many complaints arrived about the damages on MRR2
III •Traffic jam has rose due to incompletion of MRR2
IV •On 8 December 2006, the Kepong Flyover was reopened to light traffic [3]
2ndClosure
4 Feb 2006
9GROUP 4
HIGHLIGHTS
18/8/2004
RM20mil to repair within 3 months
Yet to determine the cause of cracks
Deny the possibility of design fault
1/2/2007
Repairs cost RM 40 mil RM70mil
22/2/2006 Repair cost more than RM 40 milllion
Work Minister called to explain expenditure
10GROUP 4
3 August 2008
11GROUP 4
ETHICAL THEORY
“Up to now, Malaysians still do not have a full and proper picture about the MRR2 flyover cracks. As two consultants, one from Australia by the contractor and a consultant from Germany appointed by the Public Works Department, have come out with different findings about the MRR2 flyover cracks, how could there be public confidence about the repair work undertaken in the past five days? “ Media Statementby Lim Kit Siang (14/8/2004)
12
GROUP 4
Definition: Balance between good and bad consequences of an action [4]
Utilitarianism
13GROUP 4
GOOD: MRR2
brought travel
within easy reach
BAD: Controversial Issues.
Right Ethics
• Definition: People have the fundamental rights that other people have a duty to respect [4]
GROUP 4 14
Right Ethics
The right to use the flyover safely
Do not want to keep stuck in traffic jam as a result from the closure of the MRR2
Do not want to see the few well-connected companies or individuals profit at the public expense
15GROUP 4
Duty Ethics
Definition •People have duties to protect the rights of others
Fidelity • the duty to keep promises
- Contractors and engineers have failed to
design and build the flyover in compliance with the
contract16GROUP 4
Duty Ethics
– “Samy Vellu is acting as if he is the Minister for Bumi Hiway, the
contractor for the MRR2, instead of being Minister for 25 million
Malaysians.”
Justice•the duty to recognize merit work minister does not take any action against the irresponsible contractors and consultant
17GROUP 4
Duty Ethics
Repairs cost RM40 mil to RM70mil
Cause by improper planning and poor cost estimation and poor administrative of the Work Minister
This expenses could be reduced if he appointed a reliable contractor to build the flyover
Beneficence
•the duty to improve the conditions
18GROUP 4
Virtue Ethics
Engineers did not fully supervise the project
Minister did not give explanation of the RM70 million bill
No actions taken towards original contractors
Irresponsibility
19GROUP 4
Virtue Ethics
Denied cracks were due to design flaw
Did not build according to right specifications and designs
Dishonestly
20GROUP 4
Safety And Risk
Definition: Ensure safety of public
21GROUP 4
Safety And Risk
22GROUP 4
Safety design criteria
•“ ‘space-age carbon-fibre pre-stressed trusses’ would be used to repair the pillars, beams and girders of the flyover: a tensile strength five times stronger than that of steel” [5]
Risk-Benefit Analysis
•“Samy Vellu is giving the impression the repair work for the MRR2 flyover is very simple and straightforward, would not even require the three months mentioned by him.” [5]
Need = There must be a clear and important harm that can be avoided by blowing the whistle
MEANING: An act by an employee of informing the public or higher management of
unethical or illegal behavior by an employer or supervisor
WHISTLE BLOWING
Proximity = The whistleblower must be in a very clear position to report on the problem
Capability = The whistleblower must have a reasonable chance of success in stopping the harmful activity
OCCURS
23GROUP 4
Last Resort = Should be attempted only if there is no one else more capable and all other lines of action within the organization have been shut off
ANALYSIS OF THE MRR2 CASE
1) AUTHORITYS INVOLVEMENTKKR
(Kementerian Kerja Raya)
Agency
JKR (Jabatan Kerja Raya)
CIDB (Lembaga Pembangunan
Industri Pembinaan Malaysia)
BQSM (Lembaga Juruukur Bahan
Malaysia)
BEM (Lembaga Jurutera Malaysia)
BOA (Lembaga Arkitek Malaysia)
MHA (Lembaga Lebuhraya Malaysia)
24GROUP 4
ANALYSIS OF THE MRR2 CASE2) PERSONAL VS BUSINESS CONFLICT
MINISTERY(strong parties)
ENGINEER(responsibility)
CONTRACTOR(work)
HIGH COUNCIL BOARD
(reputation)
CITIZEN(daily usage)
MEDIA(news)
CONFLICT
Right and wrong ethics,Profitable and Loses,
Rules and Regulations,Cost-Benefit Analysis
25GROUP 4
ANALYSIS OF THE MRR2 CASE
3) AMONG RULES AND REGULATIONS1) Engineers Act 1967 (Rev 2007)2) Regulations 1990 (Rev 2003)3) Code of Professional Conduct
1) Architect Act 19672) Architect Rules 1996
1) Standard Specifications for Building Works 2005
1) QS Act Revised 20022) QS Rule Amendment 2004
1) Design Standard2) Maintenance
Manual and Guideline (civil, electrical and mechanical)
3) Guideline
1) Contractor Code of Ethics
26GROUP 4
CONCLUSION
1) CORE CODE OF ETHICS REFERRED FROM VARIES CODE OF ETHICS
A Professional shall at all times hold paramount the safety, health and welfare of the public
A Professional shall conduct himself honourably, responsibly, ethically and lawfully so as to enhance the
honour, reputation and usefulness of the profession
A Professional shall act for each employer or clients as faithful agent or trustee
A Professional shall undertake assignments only if he is qualified by education and experience in the specific
technical fields in which he is involved
A Professional shall issue public statements only in an objective and truthful manner
27GROUP 4
CONCLUSION
2) ACTION WHICH SUPPOSE TO BE AVOIDED
Bribery takenMiscalculation
TragedyBreach of contract
Doesn’t follow specificationLack communication link
Bad constructionLack team work
Unethical action takenBad media coverageBurden the countryBurden the citizen
Fired employeeAccusing responsibility
28GROUP 4
REFERENCES
[1] Maverick, SM., Project Report Middle Ring Road 2.
February, 2006 was retrieved from http://mavrkyprojectphoto.blogspot.com/2006/02/middle-ring-road-2.html
[2] Brandon, H., Controversial Issues Middle Ring Road 2, was retrieved from http://en.wikipedia.org/wiki/Kuala_Lumpur_Middle_Ring_Road_2
[3] Maverick, SM., Risk, Health & Safety. 2006 was retrieved from http://constructionrisk.blogspot.com/
[4] Charles B. Fleddermann., Engineering Ethics (3rd Edition), Pearson Practice Hall , University of New Mexico, 2008
[5] Lim Kit Siang, Media Statement. August, 2004 was retrieved from http://www.dapmalaysia.org/all-archive/English/2004/aug04/lks/lks3158.htm
[6] Main Portal for Kementerian Kerja Raya
http://www.kkr.gov.my/
29GROUP 4
Q & AQ & A
The End
30GROUP 4