Optimizing the Order Quantity, Quality and Service Level by using Six Sigma Tools at Mikey’s Way Foundation PROJECT BY : ADITYA KAMBLE PRIYANKA GHOLAP PUNIT MAHESHWARI RAHUL BANTHIA ROHAN NAIK SHRENIK LUNIYA GROUP # 9

Upload: rohan-naik

Post on 27-Jul-2015

86 views

Category:

Engineering


1 download

TRANSCRIPT

Page 1: Six sigma  Project at Mikey's Way an WNY NGO - optimizing the order quantity, quality and service

Optimizing the Order Quantity, Quality and Service Level by using Six Sigma Tools

atMikey’s Way Foundation

PROJECT BY:

ADITYA KAMBLE

PRIYANKA GHOLAP

PUNIT MAHESHWARI

RAHUL BANTHIA

ROHAN NAIK

SHRENIK LUNIYA

GROUP # 9

Page 2: Six sigma  Project at Mikey's Way an WNY NGO - optimizing the order quantity, quality and service

INTRODUCTION

A DAY AT MIKEY’S WAY…..

Page 3: Six sigma  Project at Mikey's Way an WNY NGO - optimizing the order quantity, quality and service

“We are not the pill for a cure, we are a blanket for their comfort” – Mr. Les Freidman

GOAL

The foundation strives to help children face the emotional and physical hardship of long term, debilitating treatment by staying connected with their loved ones even when they are far apart in the hospitals for their treatment.

What they do?

Mikey’s way organization people goes on a visit to hospital and do the donation work. they call it as a Mikey’s Way Day.

How they do?

In Mikey’s way organization the purchasing of products for the distributing goes on a continuous basis as and when the funds flow from the sponsors and then they schedule the visits with the hospitals they have tie up with for distribution of the gifts to the child cancer patient.

In a year they nearly do 18-20 Mikey’s way day.

Page 4: Six sigma  Project at Mikey's Way an WNY NGO - optimizing the order quantity, quality and service

PROJECT GOAL

The project is aimed to increase the no of Mikey’s Way day for the organization from their current no. of days visited i.e. 18-20 to 20-24 days/year.

Outcomes from the initial Meeting

o Utilization of the fund raised from the sponsors for the purchase of the products which are to be distributed.

o Analyzed that in almost all the Mikey’s way day, the amount purchased for the products that were distributed

to the children was almost double.

Conclusions

o Lack of analysis of the data of previous serving done at the hospitals.

o No centralized purchase system of the organization.

Actions

o DMAIC

Page 5: Six sigma  Project at Mikey's Way an WNY NGO - optimizing the order quantity, quality and service

DMAIC

D- DEFINEM- MEASUREA-Analyze I-ImproveC-Control

Page 6: Six sigma  Project at Mikey's Way an WNY NGO - optimizing the order quantity, quality and service

DEFINE Defining the process improvement at Mikey’s Way

o Increasing Mikey’s Way Day.

o Increasing no. of patient covered in the single Mikey’s way day.

o Improve the analysis of the pre event survey.

Six sigma tool:

o Project Selection Matrix.

The project selection matrix shows the Givens, wants and threats of the three potential

project choices.

o Project Charter.

Helped us in creating a high-level view of the process, and to understand the needs of the

customers of the process.

Page 7: Six sigma  Project at Mikey's Way an WNY NGO - optimizing the order quantity, quality and service

Project Selection Matrix

Page 8: Six sigma  Project at Mikey's Way an WNY NGO - optimizing the order quantity, quality and service

PROJECT CHARTER

Page 9: Six sigma  Project at Mikey's Way an WNY NGO - optimizing the order quantity, quality and service

MEASURE Measures the performances of the process or the processes in an organization.

Tools used in this phase of DMAIC are the data collection plan, benchmarking, measure system analysis, voice of customer gathering, process flow chart.

Analyzing the current process, the new improved process flow was recommended: Value added process flow:

1. creating a calendar for organizing the events.2. Taking a beforehand survey on the hospital for the event organized.3. Purchasing according to the age group and gender.4. Less in transit time for product deliver as the order is pre placed.5. Distribution of goods in hospital.6. Storing of balanced inventory at warehouse.

Page 10: Six sigma  Project at Mikey's Way an WNY NGO - optimizing the order quantity, quality and service

Process Flow Chart

Page 11: Six sigma  Project at Mikey's Way an WNY NGO - optimizing the order quantity, quality and service

ANALYZE Analysis stage consists of analyzing the collected data and finding out the route cause and critical

parameters affecting the system.

Key Factors:

o Identify potential root causes for the process problem.

o Confirm actual root causes with data available.

o Analyze data to establish the baseline performance of the transactional process, relative to the

critical to quality measures established based on customer input.

Six Sigma Tool used:

o 5-Why Analysis

o Cause and Effect Diagram

o Pareto Chart

Page 12: Six sigma  Project at Mikey's Way an WNY NGO - optimizing the order quantity, quality and service

WHY – WHY ANALYSIS

Page 13: Six sigma  Project at Mikey's Way an WNY NGO - optimizing the order quantity, quality and service

IMPROVE The problem in its core was found to be Improper planning & scheduling of events.

Key Factors:

o Improper planning & mapping of required area for listing of appropriate hospitals.

o Periodic meetings with the employees to discuss the targets, aims & goals.

o Procurement of the statistical data at least one week before the distribution day.

o Pre arrange the transportation of products from facility to the hospitals.

Six Sigma Tool used:

o Product Failure mode & Effects Analysis (PFMEA)

Page 14: Six sigma  Project at Mikey's Way an WNY NGO - optimizing the order quantity, quality and service

PRODUCT FALIURE MODE EFFECT AND ANALYSIS

Page 15: Six sigma  Project at Mikey's Way an WNY NGO - optimizing the order quantity, quality and service

CONTROL Control phase of DMAIC is to make sure the new way of working is sustained over time.

Key Factors:

o Standardizing and documenting the new process.

o Training and creating a plan to monitor the process.

o Procurement of the statistical data at least one week before the distribution day.

o Pre arrange the transportation of products from facility to the hospitals.

Control Measures suggested:

o Proper utilization of funds.

o Records of Mikey's Way Day.

o Proper Inventory Management.

Page 16: Six sigma  Project at Mikey's Way an WNY NGO - optimizing the order quantity, quality and service

CONCLUSION Six sigma tools helped to understand their individual importance and application at Mikey’s Way

Foundation.

six sigma DMAIC methodology assisted to systematically define and highlight the problem areas

within the scope of the project.

six sigma methodology helped to find out the various causes affecting the failure modes of the

organizational operations and results are seen by comparison of before condition with present

condition.

Upon implementation and controlling the recommended actions, we expect that at least 20%

increase in Mikey’s way day so that they serve more customers and with 40% reduction in the cost

of arranging a Mikey’s way Day.

Page 17: Six sigma  Project at Mikey's Way an WNY NGO - optimizing the order quantity, quality and service

Thank You