Site C Clean Energy Project
Regional Community Liaison Committee
Project Briefing
September 6, 2017
![Page 2: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/2.jpg)
British Columbia Utilities Commission
review
2
The provincial government has asked the BCUC to review Site C. The review began on August 9,
2017. The terms of reference require a preliminary report from the BCUC within six weeks (by
September 20, 2017), and a final report within 12 weeks (by November 1, 2017). Construction and
procurement activities will continue during the review; however, no major contract awards will be
made until the review has been completed and the government has made a decision.
Image: http://www.bcuc.com/SiteCProcess.html
![Page 3: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/3.jpg)
3
Construction update
![Page 4: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/4.jpg)
Site C progress at two-year mark
Drone footage shows project components at the dam site
4
![Page 5: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/5.jpg)
Voith Hydro
![Page 6: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/6.jpg)
6
Voith manufacturing facility frame (May 2017)
![Page 7: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/7.jpg)
7
Exterior of Voith manufacturing facility (June 2017)
![Page 8: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/8.jpg)
8
Exterior of Voith manufacturing facility (August 2017)
![Page 9: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/9.jpg)
Right (south) bank excavation
& roller-compacted concrete
(RCC) placement for
powerhouse buttress
![Page 10: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/10.jpg)
10
South bank cofferdam, excavation and sediment
storage area (May 2017)
![Page 11: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/11.jpg)
11
Powerhouse buttress excavation (May 2017)
![Page 12: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/12.jpg)
12
Aerial view of the stilling basin (June 2017)
![Page 13: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/13.jpg)
13
RCC placement for powerhouse buttress (August
2017)
![Page 14: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/14.jpg)
14
RCC placement for powerhouse buttress (August
2017)
![Page 15: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/15.jpg)
Right (south) bank roller-
compacted concrete (RCC)
preparation
![Page 16: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/16.jpg)
16
RCC conveyor construction (June 2017)
![Page 17: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/17.jpg)
Right (south) bank
aggregate crushing
facility
![Page 18: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/18.jpg)
18
Aggregate crushing facility (July 2017)
![Page 19: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/19.jpg)
CN rail siding
![Page 20: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/20.jpg)
20
Septimus siding unloading pad (May 2017)
![Page 21: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/21.jpg)
Left (north) bank
tension crack
![Page 22: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/22.jpg)
22
Tension crack stabilization work area (May 2017)
![Page 23: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/23.jpg)
23
North bank haul road upgrade work (May 2017)
![Page 24: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/24.jpg)
24
North bank excavation (July 2017)
![Page 25: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/25.jpg)
Left (north) bank inlet
cofferdam
![Page 26: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/26.jpg)
26
North bank inlet cofferdam (May 2017)
![Page 27: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/27.jpg)
Site C viewpoint
![Page 28: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/28.jpg)
28
Viewpoint (August 2017)
![Page 29: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/29.jpg)
Current/upcoming construction activities
Other work areas
• Main civil work continues at the dam site.
• Upgrade work on 271 Road continues.
• Upgrade work on Old Fort Road is substantially complete.
• Geotechnical investigations for the Hudson’s Hope shoreline protection work
were completed in early May. Work on the preliminary design is underway.
• Transmission line work continues in the right-of-way.
• Wuthrich quarry & West Pine quarry:
o Riprap will be produced for use in construction at the dam site.
![Page 30: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/30.jpg)
30
Procurement
update
![Page 31: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/31.jpg)
Procurement update
Procurement approach designed to achieve value for money to ratepayers
31
Procurements underway:
• Generating Station and Spillways Civil
Works – RFP phase
• Hydro-mechanical Equipment Supply –
RFP phase
• Powerhouse Bridge Crane Supply – RFP
phase
• Site C Substation – Construction – RFP
phase
Future procurements:
• Transmission Line – Construction
• Transmission Line – Supply contracts
• Site C Substation – Supply contracts
• Other infrastructure / supporting activities
![Page 32: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/32.jpg)
Jobs and Businesses
Update
![Page 33: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/33.jpg)
Site C jobs snapshot
33
Site C Employment Statistics – June 2017
# of Total
Workers
# of PRRD
Workers
Construction and Non-Construction
Contractors1
Excludes work performed outside of B.C.
(e.g. manufacturing)
2,224 PRHP: 465
ATCO: 62
Other: 244
Total: 771
Engineers and Project Team2
(engineering, consulting and project staff)
409
Total Workforce 2,633
1. Includes work performed on Site C dam site, transmission corridor, reservoir clearing area, public roadwork, worker
accommodation and services.
2. Project Team includes consultants, BC Hydro Construction Management and other offsite Site C project staff. An estimate
is provided where possible if primary residency is not given.
![Page 34: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/34.jpg)
Site C jobs snapshot
34
690 677 749 709
648 736 771
560 671 695 708
809 923
973
254 291 311 324 324
456 440
27 32 31 38 30 45 40
1,531
1671 1786 1779 1811
2,115 2,224
0
500
1000
1500
2000
2500
Dec 2016 Jan 2017 Feb 2017 Mar 2017 Apr 2017 May 2017 Jun 2017
December 2016 - June 2017 Site C Construction and Non-Construction Contractors
By Primary Residency
PRRD Rest of BC Rest of Canada Outside of Canada Totals
OUTSIDE CANADA
REST OF CANADA
REST OF B.C.
TOTAL
PRRD
![Page 35: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/35.jpg)
2017 Q2 Regional Business Participation
Companies engaged to provide goods & services in relation to Site C construction
35
Community Number of Businesses
Baldonnel 1
Cecil Lake 1
Charlie Lake 12
Chetwynd 6
Dawson Creek 21
Fort St. John 256
Moberly Lake 2
Pouce Coupe 1
Prince George 18
Rose Prairie 1
Taylor 4
Tumbler Ridge 2
Wonowon 1
Total 326
PRRD businesses provide a
range of services:
• Equipment rentals and sales
• Vehicle rentals
• Office supplies
• Accommodation and
hospitality
• Safety and first aid services
• General contracting
• Trucking
![Page 36: Site C Clean Energy Project€¦ · 2017-09-06 · Right (south) bank roller-compacted concrete (RCC) preparation . 16 RCC conveyor construction (June 2017) Right (south) bank aggregate](https://reader035.vdocuments.us/reader035/viewer/2022071023/5fd7cb80ab508869f93ce41d/html5/thumbnails/36.jpg)