Contents1. 2010- 2014 SEVEN OUTCOMES OF THE TURN-AROUND
STRATEGY
2. PERFORMANCE METRICS IN RAG
3. IMPROVEMENT IN THE QUALITY OF SERVICE - SCM
4. SAPS SPECIFIC SCM IMPACTS
5. IMPROVEMENT IN THE QUALITY OF SERVICE – Proposals and SLA
6. QUALITY OF SERVICE INTERVENTIONS
7. PROFICIENT LEAD AGENCY
8. E- GOVERNMENT
9. SAPS SPECIFI E-GOVERNMENT INITIATIVES
10. IFMS PROJECT
2
Contents (cont)11. ROLE OF SAPS wrt IFMS
12. ICT SUPPLY CHAIN MANAGEMENT
13. SAPS SPECIFIC ICT SCM BENEFITS
14. PRICING
15. STAKEHOLDER RELATIONSHIP MANAGEMENT
16. OUTCOME OF THE SAPS-SITA JOINT STRATEGIC PLANNING SESSION
17. PROGRESS ON THE IMPLEMENTATION OF THE JOINT SESSION RESOLUTION
18. EXPENDITURE AND PROGRESS OF NATIONAL NETWORK UPGRADE PROGRAMME
19. EXPENDITURE AND PROGRESS ON ICDMS
20. PRICING FOR SUPPORT SERVICES
21. QUESTIONS
3
2010- 2014 SEVEN OUTCOMES OF THE TURN-AROUND STRATEGY
1. Quality ICT service delivery to the public sector
2. Proficient lead agency in the public sector ICT
3. Integrated public sector ICT Supply Chain Management
4. Competitive pricing and financial sustainability
5. Effective ICT Regulator
6. Effective governance and monitoring
7. Employer of choice
4
PERFORMANCE METRICS IN RAG
Colour Description Symbol
Red Unsatisfactory performance
Amber Room for improvement
Green Satisfactory performance
5
IMPROVEMENT IN THE QUALITY OF SERVICE
INITIATIVE STATUS AS PRIOR TAS
YEAR 1 (2010/11) TARGETS
YEAR 2 (2011/12) TARGETS
PROGRESS TO DATE
Non-Compliance with SCM Processes
Non-rotation of Evaluation teams
Rotation of members with of evaluation teams & representation from client Departments.Shift from procurement to SCM processes
Establish SCM Committee system- Bid Evaluation Committee with Subject Matter & Technical Expertise
SCM Policy due for approval with clarity on roles, responsibilities and requirements specifications for bid committees
Non-disclosure of business interests
Compulsory disclosure of interests by members of evaluation & adjudication panels
Internal controls & procedures defined
SCM Procedure Manual in place
6
IMPROVEMENT IN THE QUALITY OF SERVICE cont.
INITIATIVE STATUS AS PRIOR TAS
YEAR 1 (2010/11) TARGETS
YEAR 2 (2011/12) TARGETS
PROGRESS TO DATE
SCM Turn- Around times (working days)
Requests for Bids (RFBs) = 280 days
RFBs = 208 daysfinalisation = 100 days
RFBs = 78 days from close tender
RFBs (2011) = 119 daysBacklog RFBs= 260 days
Closed Bids (Preferred List) Request for Quotes (RFQs) = 190 days
RFQs = 145 days Preferred List RFQs = 100 days
Preferred List RFQs = 94.9 daysBacklog RFQs =
Ad-hoc RFQs = 100 days
Ad-hoc RFQs = 78 days
Ad-hoc RFQs = 30 days
Ad-hoc RFQs = 18. 2 days
Contract finalisation = 2 years
Contract finalisation = 120 days
Contract finalisation = 60 days
Contract finalisation = 83 days
7
SAPS SPECIFIC SCM IMPACTS
INITIATIVE YEAR 1 (2010/11) TARGETS
YEAR 2 (2011/12) TARGETS
PROGRESS TO DATE
SCM Turn- Around times (working days)
RFBs = 74 days RFBs = 78 days from close tender
RFBs (2011) = none requested
Backlog RFBs= 432 days
Non Requested Preferred List RFQs = 100 days
None requested
RFQs = 81 days RFQs = 30 days None Requested
Contract finalisation = 51 days
Contract finalisation = 60 days
Contract finalisation = 57 days
8
IMPROVEMENT IN THE QUALITY OF SERVICE (QoS)
9
INITIATIVE STATUS AS PRIOR TAS
YEAR 1 (2010/11) TARGETS
YEAR 2 (2011/12) TARGETS
PROGRESS TO DATE
Responses to Request for Proposals
06 – 07 months 03 months 14 days from receipt of request
25 days
Guarantee Service Levels on across the SITA services
Guaranteed 98% service availability on hosting and network services
Service availability for Hosting, Network & Service management centre (SMC) = 98%
98% Service availability on hosting, network & SMC
Hosting = 100%Networks =99.80%SMC = 99.9%
SAPS SPECIFIC QoS IMPACTS
10
INITIATIVE STATUS AS PRIOR TAS
YEAR 1 (2010/11) TARGETS
YEAR 2 (2011/12) TARGETS
PROGRESS TO DATE
Responses to Request for Proposals
3 months 14 days from receipt of request
1 month
Guarantee Service Levels on across the SITA services
Service availability for Hosting, Network & Service management centre (SMC/ARS) = 98%
98% Service availability on hosting, network & SMC/ARS
Hosting = 99.9%Networks =99.95%ARS = 83%
QUALITY OF SERVICE INTERVENTIONS
• Finalising the SITA Service Strategy with performance metrics in all services within the SITA service catalogue
• To improve Contract Management– Instituted Report on contract management to
the Procurement Sub-Committee of the Board
11
PROFICIENT LEAD AGENCY (VALUE ADD TO GOVT IT)
• Established a function dedicated to government solutions under the leadership of an Executive
• Approved that 2% of Operational Expenditure be dedicated to innovation on government solutions
• Commenced the process to partner industry on innovation, e.g. Smart government solutions inclusive of war rooms, smart cities & e-government
12
E-Government• Broad definition of e-government: The use of information technology to
enable government to:– Perform efficiently (government to government –G2G- services)– Render services to citizens at their convenience (government to
citizens -G2C- and government to business –G2C) • G2G initiatives include:
– Integrated Financial Management System– System to assist with the disclosure and verification of business
interests by members of the Senior Management Staff of government : The Minister for the Public Service and Administration will perform a test run of this system during the 2011 Public Service week
• SITA has identified 10 key government services to be made immediately available online to citizens including business upon Cabinet approval
• Together with Home Affairs, SITA is offering connectivity for the banks to verify the identities of bank clients through the National Population Register (NPR) that is hosted by SITA
13
SAPS SPECIFIC E-GOV INITIATIVES
INITIATIVE Description YEAR 2 (2011/12) TARGETS
PROGRESS TO DATE
eForms as part of ICDMS Project
Provides for an electronic statement which can be submitted on line.
end Dec 2011for completion
60% complete in terms of URS
14
IFMS Project • September 2005, Cabinet mandated National Treasury, DPSA and
SITA to proceed with the IFMS project with the following objectives:
– Integrate and renew Financial, Supply Chain and Human Resource Management systems used by National and Provincial Departments
– SITA will use the IFMS as a catalyst to become the Prime Systems Integrator (PSI) for government
– PSI Benefits for government
• Improve quality of service clients
• Reduce the cost of IT to government through partnership with industry in the development and acquisition of government IT goods and services
• Eliminate duplication of information systems and thus reduce wastage of resources
• Lower the prices of IT services
15
Product Scope
16
• Health and Safety Management
• Education Training Development
• Labour Relations
• HR Planning
• Organization Management
• Recruitment Management
• Employee Movement
• Performance Management
• HR Reporting
• Career Management
• Remuneration Management
• Termination of Service
• HR Administration
• Catalogue Management
• Procurement Management
• Inventory Management
(not available now)
• Asset Management
• MTEF Budget Preparation
• Departmental Financial Management
• Treasury Financial Management
• Payroll Management
• Reporting
• Analysis
• Dashboards
• Data mining
Supply Chain
Management
Human Resource
Management
Financial
Management
Business
Intelligence
Product Status
17
Supply Chain
Management
Human Resource
Management
Financial
Management
Business
Intelligence
Core SCMAsset Management, Item Master, Catalogue Mgt , Procurement Mgt, and Integration BAS
None NoneHRM Generic Template
Del
iver
edT
o D
ate
Fu
ture
Inventory Management Enterprise Asset
Management Full SCM Integration
Capability Service Delivery
Management
Potential Customisation / Configuration at future sites
Fin Core Product DevelopmentIn
P
roce
ss Integration to Master Data
BI Legacy Replacement
Payroll Product Development
Lead Site Implementation Status
18
Supply Chain
Management
Human Resource
Management
National Treasury Asset Management, Catalogue Management, IT
Master, Basic Inventory, Procurement Management, and BAS Integration (SCM Core)
Asset Management (Limpopo) Provincial Treasury, Local Govt and Housing,
Roads and Transport and Agriculture
Department of Public Service and Administration
Imp
lem
ente
d
Free State Department of Education
In
pro
cess
SCM Core
Department of Defense
Limpopo Dept of Health & Social Development
ROLE OF SAPS wrt IFMS
• SAPS is a member of the IFMS Project Steering Committee
• Participate in all IFMS Business Forums and provide inputs towards IFMS user requirements
• All the SAPS ERP-related solutions have been assessed in terms of functionality and business rules
• In 2005, SAPS indicated that they will be the last Department to roll-out IFMS
19
ICT SUPPLY CHAIN MANAGEMENT
• Transforming the organisation from Procurement function to SCM
• Commenced the implementation of the SITA Industry Partnership model, we have engaged with OEMs on:
– Telecommunications
– Network Communications devices
– Desktop and peripheral devices such as printers, scanners etc
– Storage (Data Centres)
– Software development
• Objectives of the industry partnership
– Development of the local & indigenous IT industry
– Improve the quality of service through government friendly product support and maintenance
20
ICT SUPPLY CHAIN MANAGEMENT cont.• Objectives of the industry partnership cont.
– Contribute to the growth of innovative IT solutions for government
– Contribute to the IT skills development within government and country in general
– Reduce the cost of government business through IT
– BEE and SMME development through fostering participation friendly OEM resellers or partners accreditation terms/ requirements
– Lower prices of IT goods through bulk purchasing and preferred discounts for government
• The partnership with industry to be based on risk and revenue sharing models
21
SAPS SPECIFIC ICT SCM BENEFITS
• Benefits from cloud computing (Data centres & storage)• Lower prices for the War Room installation – better
prices & advanced technology options (Network communication devices)
• Lower cost for the National Network Upgrade Programme (Network communication devices)
• More bandwidth, disaster recovery and redundancy on the government network ( dependent on SAPS on SITA Next-Generation Network)
• Reduce the cost of Voice Communication through VoIP (dependent on SAPS on SITA NGN)
22
Pricing• The Cost and Pricing model is due to be finalised with the following
outlook:– Significant reduction in prices of SITA services– Guarantee continuous reduction of prices in certain commodities of
services• Lower cost through industry partnership• Infrastructure investment
– There were no investment in the IT infrastructure of SITA in the last 2 years due to a lack of infrastructure strategy
– The IT Infrastructure Strategy and plan has been finalised to support the Capital Expenditure over the next 5 years
– The infrastructure investment will be done through partnership with industry with the following objectives:o Lower the cost of technology services o Support the enablement of an electronic government (e-
government)o Benefit from continuous innovation
23
STAKEHOLDER RELATIONSHIP MANAGEMENT
• SITA was characterised by non-responsiveness to stakeholders
• We have since embarked on engagements with stakeholders through– Joint Strategic Planning sessions with clients such as
SAPS, DOD, DOJ & Depts of Education– Provincial visits and we have already visited WC, EC, KZN,
Limpopo, N Cape, NW & FS– Re-establishing good working relations with GITOC– Repositioning GOVTECH as an engagement platform with
our stakeholders to advance the government IT Agenda• The engagements with stakeholders have resulted in a
mechanism for stakeholder performance feedback and review of our provincial distribution model
24
OUTCOMES OF THE SAPS –SITA JOINT STRATEGIC PLANNING SESSION
• BA Agreement negotiations to be finalised by end Sept 2011
• SLA negotiations to be finalised by end Sept 2011• All services provided to SAPS to be converted to
“Service-based” as opposed to “Body-shopping”• SAPS to provide User requirements for ICDMS. • SITA to provide Proposal for NGN and VoIP
25
PROGRESS ON THE IMPLEMENTATION OF THE JOINT SESSION RESOLUTIONS
• BA discussions have commenced and due to complete end September as planned
• 5 x SLAs have been negotiated and concluded at a functional level
• 2 x New SLAs requested by SAPS and being drafted for negotiations (SCM & IT Security)
• Proposals for the service conversion underway
• ICDMS demo was presented to SAPS and the ICDMS backbone to complete in December 2011
• Additional ICDMS User Requirements to be submitted by SAPS e-Docket (scanning solution) was developed and deployed at 320
police stations in 8 provinces except for the Eastern Cape. Approximately 1,650 mil dockets having been scanned as at 5th Sept
2011• NGN and VoIP proposals submitted to SAPS
EXPENDITURE & PROGRESS OF NATIONAL NETWORK UPGRADE
PROGRAMME
27
YEAR SAPS Tasked Amounts SITA Contracted
Switching Centres
Sites Upgrades
2005 to 2008 R325,1m 26 386
2008/2009 R248.3m 272
2009/2010 R518.5m 388
2010/2011 R460.0m 314 (Telkom line outstanding in certain
areas)
2011/2012 Not yet tasked
TOTAL R1,551.8m 26 1,360
EXPENDITURE & PROGRESS ON ICDMS
28
YEAR SAPS Tasked Amounts Actual Expenditure
eDocket
Delivered as part of the Applications and Maintenance SLA . Excl network,
hardware and storage component costs R9.9m
2009/10 R 25,2m R 19 .9m
2010/11 R 26,8m R 19.2m
2011/12 R 25,3m
2012/13 R 27,0m
2013/14 R 28,9m
TOTALR 133,3m R 49.0m
Pricing for Support Services
29
Recurring ICT Support Services
Signed SLA Value 2010/2011(VAT Incl)
Proposed SLA Pricing 2011/2012
(VAT Incl)
Growth % Outstanding Billing April to August (VAT Incl)
Monthly Invoice values (Vat Incl)
APPLICATION MAINTENANCE SERVICES: R 191 220 732.00 R 203 617 151.72 6.5% R 99 838 544.17 R 14 810 693.02SPECIALISED CONSULTING SERVICES R 4 783 760.34 R 5 022 935.76 5.0% R 2 092 889.90 R 418 577.98BUREAU SERVICES R 4 316 924.00 R 4 316 924.00 0.0% R 1 804 322.42 R 359 743.67CENTRALISED DATA PROCESSING SERVICES R 242 235 053.71 R 237 892 939.73 -1.8% R 99 122 058.22 R 19 824 411.64NETWORK SUPPORT SERVICES R 321 723 501.66 R 304 134 448.15 -5.5% R 126 722 686.72 R 25 344 537.35DECENTRALISED SUPPORT SERVICES R 472 104 625.56 R 594 285 479.57 25.9% R 247 618 950.10 R 49 523 789.96
GRAND TOTAL R 1 236 384 597.27 R 1 349 269 878.93 9.1% R 577 199 451.27 R 112 439 156.58
Service Description
NOTE: - Monthly invoice values excludes the once off licensing fees-SITA requested Interim Orders based on the SITA proposed pricing
Thank you