Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
MAJOR INDUSTRIES, INC. / 888-759-2678 / 715-842-4616 / WWW.MAJORSKYLIGHTS.COM
Guardian 275® 2 ¾” Single Slope
Endwall Installation Manual
This instructional manual provides “General Installation Instruction.” Installers should refer to
the "as-built" shop drawings for specific guidance as it relates to your system. For additional
information, contact Major Industries.
-
Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
MAJOR INDUSTRIES, INC. / 888-759-2678 / 715-842-4616 / WWW.MAJORSKYLIGHTS.COM
INTRODUCTION
Quality installation in a timely manner requires
careful attention to planning and detail. We need
your help to ensure a successful weather-tight
installation.
We produce our custom-fabricated daylighting
products to precise dimensions under factory-
controlled conditions. Everything has been checked
and verified to meet shop drawings and the
architectural requirements. Your job is perhaps the
most important step yet to be completed. Our
analysis of warranty claims indicates that over 85%
of all field complaints are the result of improper
installation or - equally damaging - an improper
assembly during installation. All Major Industries
daylighting products are designed as a system - you
must assemble the parts and pieces in exact
sequence. Any effort to “freelance” or do it in a new
way risks our common goal of ensuring weather-
tightness and owner satisfaction.
Finally, our warranty commitment sold with this job
is predicated on satisfactory site conditions. Please
take the time to perform a thorough site audit prior
to starting your installation, and ask yourself the
following questions before installation. If even one
of them is false, you are almost guaranteed to have a
less than optimal installation.
UNLOADING
Unloading should be organized to minimize material
handling. If hoisting is required by either crane or
forklift, the skylight’s weight should be evenly
distributed to prevent distorting or damaging the
material. Use only approved nylon lift slings that are
in good condition and sized to the load. Crates are
for shipping purposes only and should not be relied
upon for hoisting or storage.
INSPECTION
Upon receipt, inspect the shipment to ensure that
materials were not damaged during shipping. If
damage is visible or suspected, note it on the bill of
lading and contact Major Industries as soon as
possible. Count material and check it immediately
against the packing list. If there is a shortage, note it
on the bill of lading and contact Major immediately.
STORAGE
While a single panel easily withstands exposure to
sunlight and the elements, a stack of panels will trap
heat and moisture, causing clouding in the panels.
To avoid this irreversible effect, panels must be
stored in a dry, shaded, well-ventilated area. Skids
should be elevated at one end by wood spacers. It is
the installer’s responsibility to protect materials until
they are installed - unless otherwise specified. When
placing materials on the roof, it is the installer’s
responsibility to make sure roofing materials are not
damaged. Failure to comply with recommended
storage procedures will negatively affect the
warranty on the panels.
INSTALLATION NOTES
Major Industries does not recommend walking on
the panels. If the installer must walk on the panels,
the panel surface MUST be protected by applying a
layer of foam carpet padding over the panel surface,
followed by a sheet of plywood or other similar
smooth material to distribute weight.
It is the installer’s responsibility to correctly install
and seal the entire unit. Always install only a
quantity of panels that can be fully protected with
glazing caps at the end of the day. Glazing panels are
not designed to be left unprotected from the
weather. Water damage during installation is not
covered by warranty. Always remember that water
can be drawn up into the skylight due to negative
interior building pressure. Properly clean all building
surfaces to be caulked with approved cleaning
solutions. Make sure caulking and sealants make
uniform contact with all surfaces being sealed. It is
important that all necessary sealants and caulking
are properly applied. Installers need to verify with
the sealant supplier and manufacturer as to the
proper sealant type required for the application.
Failure to do so may cause the system to fail, causing
possible interior damage.
The installer must have the sign-off sheet (supplied
with the Major Industries purchase order) signed by
the job site superintendent before leaving the job
site. No payments will be released to the contractor
until this sign-off sheet is forwarded to Major.
These instructions have been supplied to assist with
installation. They are correct to the best of our
knowledge - however, no warranty is expressed or
implied. Each installation is unique and attention
must be given to the approved shop drawings
supplied specifically for this project. Any
modifications require factory approval. Major
-
Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
Guardian 275® 2 ¾” Single Slope Endwall Install Manual - Page 3
MAJOR INDUSTRIES, INC. / 715-842-4616 / WWW.MAJORSKYLIGHTS.COM
Industries expects its installers to be knowledgable
and complete all work professionally and to industry
standards.
DAMAGE WARNING
Do not attempt to weld or cut any materials near an
installed skylight or wall system. Damage may occur
to the panel from flames, hot metal or sparks unless
they are fully protected by fireproof material.
We want our installers and customers to have the
best daylighting system possible, and we encourage
you to call us with your questions and concerns.
Major's experienced personnel can troubleshoot the
problem and help you choose the best option.
IF YOU NEED ADDITIONAL INFORMATION,
CONTACT MAJOR AT 888-759-2678.
APPROVED MATERIALS
Cleaning Solutions: Mild Soap & Water, Non-corrosive, Non-abrasive - NO Ammonia, NO Chlorine,
NO Acetone, NO MEK
Sealants: Tremco, G.E., Dow-Corning
Shims: Pressure Treated Wood, Metal, Plastic
TOOLS REQUIRED
Safety Glasses, Tape Measure, Framing Squarel Level, Hammer, Rubber Mallet, Chalk Linel Hacksaw, Circular Saw,
Drill and Drill Bits, Center Punch, Caulking Gun, Phillips Head Screwdriver (#2 and #3 Phillips Bit), Regular Head
Screwdriver, Screwgun with Clutch, Socket Wrench Set, Hex Head Driver Bits, Cleaning Supplies, OSHA Approved
Fall Protection
SITE AUDIT
1. I have checked all opening dimensions against the shop drawings
to confirm that they meet system and weather requirements of +0.25/-0 inches.
o True o False
2. All masonry/EIPS is in place for wall openings and single-ply membranes have been applied to roof curbs. (7 out
of 10 installations “leak” when this recommended installation sequence is reversed. Major will not provide an
unconditional warranty if we are forced to install our product before other responsible trades complete site
preparation according to architectural specification.) I will schedule other trades to minimize leaks by following the
recommended sequence.
o True o False
3. Sill, head and jamb conditions are plumb, straight and match the stated dimensions per the final field drawings.
o True o False
-
Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
Guardian 275® 2 ¾”
MAJOR INDUSTRIES, INC. /
Guardian 275® Endwall
1.1 - Skylight Curb
Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
Guardian 275® 2 ¾” Single Slope Endwall Install Manual - Page 4
MAJOR INDUSTRIES, INC. / 715-842-4616 / WWW.MAJORSKYLIGHTS.COM
Note: Use the endwall layout
to determine the correct
steps to follow in order to
complete the installation
process to the best of your
abilities. (Always assume this
layout is being viewed from
the exterior unless otherwise
noted).
STEP 1
1.1 DO NOT attempt to
install endwall system on an
improperly prepared curb.
Check all curb sizes. Make
sure that dimensions agree
with erection drawings.
Check all support sill and
steel for proper mounting.
Make sure that openings are
plumb, square, and/or
1.2 Place a tape measure
across the corners as a check
to make sure the opening is
square.
1.3 If there are any
discrepancies, please notify
Major Industries’
Engineering Department and
the general contractor
before proceeding.
Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
MAJORSKYLIGHTS.COM
te: Use the endwall layout
to determine the correct
steps to follow in order to
complete the installation
process to the best of your
abilities. (Always assume this
layout is being viewed from
the exterior unless otherwise
DO NOT attempt to
install endwall system on an
improperly prepared curb.
Check all curb sizes. Make
sure that dimensions agree
with erection drawings.
Check all support sill and
steel for proper mounting.
Make sure that openings are
plumb, square, and/or true.
1.2 Place a tape measure
across the corners as a check
to make sure the opening is
1.3 If there are any
discrepancies, please notify
Major Industries’
Engineering Department and
the general contractor
before proceeding.
-
Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
Guardian 275® 2 ¾”
MAJOR INDUSTRIES, INC. /
2.1 - Endwall Curb Flashing
3.1 - Endwall Support Angle
Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
Guardian 275® 2 ¾” Single Slope Endwall Install Manual - Page 5
MAJOR INDUSTRIES, INC. / 715-842-4616 / WWW.MAJORSKYLIGHTS.COM
STEP 2
2.1 Set endwall curb flashing
on the top of the curb using
approved sealant (see page
3).
2.2 Nip the drip edge and
condensation gutter from
the flashing and bend at 90°
to ensure a watertight seal
at all corners.
2.3 Overlap adjoining pieces
of flashing by six inches at
splices (if necessary). Clean
any excess caulking from all
exposed surfaces.
STEP 3
3.1 Apply a bead of caulk on
the sill flashing and set the
endwall support angle per
project erection drawings
and fasten at the pre
holes as shown above.
3.2 Caulk as necessary on
the front and back of the
support angle where it
meets the sill flashing to
ensure a watertight seal.
Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
MAJORSKYLIGHTS.COM
2.1 Set endwall curb flashing
on the top of the curb using
approved sealant (see page
2.2 Nip the drip edge and
condensation gutter from
the flashing and bend at 90°
to ensure a watertight seal
at all corners.
2.3 Overlap adjoining pieces
of flashing by six inches at
splices (if necessary). Clean
any excess caulking from all
exposed surfaces.
3.1 Apply a bead of caulk on
the sill flashing and set the
endwall support angle per
project erection drawings
and fasten at the pre-drilled
holes as shown above.
3.2 Caulk as necessary on
the front and back of the
support angle where it
meets the sill flashing to
ensure a watertight seal.
-
Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
Guardian 275® 2 ¾”
MAJOR INDUSTRIES, INC. /
4.1 - Endwall Sill Corner Angle Connection
4.1 - Endwall Head Frame Connection
Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
Guardian 275® 2 ¾” Single Slope Endwall Install Manual - Page 6
MAJOR INDUSTRIES, INC. / 715-842-4616 / WWW.MAJORSKYLIGHTS.COM
Sill Corner Angle Connection
STEP 4
In the following steps you
will be assembling the
endwall separately from the
condition and setting it into
place once it has been
erected.
4.1 Secure sill and jamb
mitered corners of interior
perimeter
using P-1108 corner angles.
4.2 Apply sealant to mitered
ends of perimeter frame and
slide corner angles into
extruded slots until they fit
snugly.
Endwall Head Frame Connection
4.3 Secure head and jamb
mitered corners of interior
perimeter frame together
using P-1108
angles.
4.4 Apply sealant to mitered
ends of perimeter frame and
slide corner angles into
extruded slots until they fit
snugly.
Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
MAJORSKYLIGHTS.COM
In the following steps you
will be assembling the
endwall separately from the
condition and setting it into
place once it has been
4.1 Secure sill and jamb
mitered corners of interior
perimeter frame together
1108 corner angles.
4.2 Apply sealant to mitered
ends of perimeter frame and
slide corner angles into
extruded slots until they fit
4.3 Secure head and jamb
corners of interior
perimeter frame together
1108-1 corner
4.4 Apply sealant to mitered
ends of perimeter frame and
slide corner angles into
extruded slots until they fit
-
Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
Guardian 275® 2 ¾”
MAJOR INDUSTRIES, INC. /
4.5 - Perimeter Frame Assembly
5.3 - Head Perimeter Frame Attachment
Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
Guardian 275® 2 ¾” Single Slope Endwall Install Manual - Page 7
MAJOR INDUSTRIES, INC. / 715-842-4616 / WWW.MAJORSKYLIGHTS.COM
4.5 Once steps 4.1 thru 4.4
are finished a complete
perimeter frame assembly
should exist.
Head Perimeter Frame Attachment
STEP 5
5.1 Apply sealant to the
endwall tube prior to setting
perimeter frame in place.
Attach the head
frame to the endwall tubes
using tek screws. Pay
attention to the location of
the perimeter frame on the
tube per the erection
drawings.
Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
MAJORSKYLIGHTS.COM
Once steps 4.1 thru 4.4
are finished a complete
perimeter frame assembly
should exist.
5.1 Apply sealant to the
endwall tube prior to setting
perimeter frame in place.
Attach the head perimeter
frame to the endwall tubes
using tek screws. Pay
attention to the location of
the perimeter frame on the
tube per the erection
-
Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
Guardian 275® 2 ¾”
MAJOR INDUSTRIES, INC. /
5.2 - Perimeter Frame Anchor Option
5.3 - Endwall Tube Shelf Angle
Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
Guardian 275® 2 ¾” Single Slope Endwall Install Manual - Page 8
MAJOR INDUSTRIES, INC. / 715-842-4616 / WWW.MAJORSKYLIGHTS.COM
Perimeter Frame Anchor Option
5.2 In the event where there
is a lower slope
perimeter frame corner will
not have the corner angles
mentioned in step 4.1. Use
(2) PH Pan HD SS tek screws
through factory drill holes in
sill framing at the corners
into the endwall tube. Caulk
all fastener heads with
approved sealant (see pa
3).
5.3 Attach the endwall shelf
angle support to the wall
condition using (2) fasteners
provided by installer. Locate
the angle support properly
so it slides inside of the
endwall tube.
Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
MAJORSKYLIGHTS.COM
5.2 In the event where there
is a lower slope endwall a
perimeter frame corner will
not have the corner angles
mentioned in step 4.1. Use
(2) PH Pan HD SS tek screws
through factory drill holes in
sill framing at the corners
into the endwall tube. Caulk
all fastener heads with
approved sealant (see page
5.3 Attach the endwall shelf
angle support to the wall
condition using (2) fasteners
provided by installer. Locate
the angle support properly
so it slides inside of the
endwall tube.
-
Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
Guardian 275® 2 ¾”
MAJOR INDUSTRIES, INC. /
6.1 - Shelf Angle Attachment
6.3 - Endwall Frame Placement
Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
Guardian 275® 2 ¾” Single Slope Endwall Install Manual - Page 9
MAJOR INDUSTRIES, INC. / 715-842-4616 / WWW.MAJORSKYLIGHTS.COM
STEP 6
6.1 Apply caulk to the top of
the angle and flashing
already in place where you
will be setting the endwall
framing assembly.
6.2 Set the endwall framing
assembly in place according
to the project erection
drawings. Slide the endwall
tube over the shelf angle
support and attach using (2)
PH FL HD SS tek screws
through factory drilled holes.
6.3 Butt the back of the
perimeter frame against the
support angle
using hex HD SS tek screws.
Fasten the endwall tubes
using PH FL HD SS tek screws
as shown above, (2) per end.
Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
MAJORSKYLIGHTS.COM
6.1 Apply caulk to the top of
the angle and flashing
already in place where you
will be setting the endwall
framing assembly.
6.2 Set the endwall framing
assembly in place according
to the project erection
drawings. Slide the endwall
tube over the shelf angle
support and attach using (2)
PH FL HD SS tek screws
through factory drilled holes.
6.3 Butt the back of the
perimeter frame against the
support angle and attach
using hex HD SS tek screws.
Fasten the endwall tubes
using PH FL HD SS tek screws
as shown above, (2) per end.
-
Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
Guardian 275® 2 ¾”
MAJOR INDUSTRIES, INC. /
6.4 - Jamb Frame Attachment
7.1 - Panel Setting Block Location
Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
Guardian 275® 2 ¾” Single Slope Endwall Install Manual - Page 10
MAJOR INDUSTRIES, INC. / 715-842-4616 / WWW.MAJORSKYLIGHTS.COM
6.4 Install jamb frame
fasteners (supplied by
installer) and check framing
members for squareness.
Shim as required or if
necessary.
STEP 7
7.1 Install panel setting
blocks (P-1052) and attach
them to the interior surface
of the perimeter framing at
the sill using shop
two sided tape. Space
setting blocks at quarter
points within panel
openings.
Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
MAJORSKYLIGHTS.COM
6.4 Install jamb frame
fasteners (supplied by
installer) and check framing
members for squareness.
Shim as required or if
necessary.
7.1 Install panel setting
1052) and attach
them to the interior surface
of the perimeter framing at
the sill using shop applied
two sided tape. Space
setting blocks at quarter
points within panel
-
Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
Guardian 275® 2 ¾”
MAJOR INDUSTRIES, INC. /
Panel Setting Block Location
8.1 - Panel Installation
Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
Guardian 275® 2 ¾” Single Slope Endwall Install Manual - Page 11
MAJOR INDUSTRIES, INC. / 715-842-4616 / WWW.MAJORSKYLIGHTS.COM
NOTE: Use the factory label
on the side of the panel to
ensure that the panel setting
block is attached in the
correct direction.
CAUTION: It is important
that the setting blocks are
installed properly according
to the drawing above
without blocking the weep
holes.
STEP 8
8.1 Insert panel and hold in
place, space panel from
to-side at recommended
dimensions.
NOTE: Do not leave panel
perimeters exposed to the
weather. Retaining caps are
to be installed daily. Major
Industries, Inc. will not be
responsible for material that
is damaged due to failing to
comply with these
instructions.
Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
MAJORSKYLIGHTS.COM
NOTE: Use the factory label
on the side of the panel to
ensure that the panel setting
block is attached in the
direction.
CAUTION: It is important
that the setting blocks are
installed properly according
to the drawing above
without blocking the weep
8.1 Insert panel and hold in
place, space panel from side-
side at recommended
dimensions.
NOTE: Do not leave panel
perimeters exposed to the
weather. Retaining caps are
to be installed daily. Major
Industries, Inc. will not be
responsible for material that
is damaged due to failing to
comply with these
structions.
-
Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
Guardian 275® 2 ¾”
MAJOR INDUSTRIES, INC. /
9.1 - Perimeter Frame Cap
10.1 - Exterior Sealant Application
Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
Guardian 275® 2 ¾” Single Slope Endwall Install Manual - Page 12
MAJOR INDUSTRIES, INC. / 715-842-4616 / WWW.MAJORSKYLIGHTS.COM
STEP 9
9.1 After installation and
alignment of the panels,
install exterior perimeter
snap cover.
CAUTION: When installing
exterior wall system snap
caps, use a rubber mallet
and wood block to
denting or marring finish. DO
NOT hammer over
weatherstrip.
NOTE: Caution must be used
at sill. Weep holes must
remain open; obstructing
the weep holes could result
in water damage to the
panels or building. Seal all
exterior metal
joints and connections with
silicone.
STEP 10
10.1 Caulk the perimeter
framing to the opening and
caulk all exterior framing and
weatherstrip joints with
approved sealant See figure
10.1 (For approved
see page 3).
Guardian 275® 2 ¾” Single Slope Endwall Installation Manual
MAJORSKYLIGHTS.COM
9.1 After installation and
alignment of the panels,
install exterior perimeter
snap cover.
CAUTION: When installing
exterior wall system snap
caps, use a rubber mallet
and wood block to avoid
denting or marring finish. DO
NOT hammer over
weatherstrip.
NOTE: Caution must be used
at sill. Weep holes must
remain open; obstructing
the weep holes could result
in water damage to the
panels or building. Seal all
exterior metal-to-metal
d connections with
10.1 Caulk the perimeter
framing to the opening and
caulk all exterior framing and
weatherstrip joints with
approved sealant See figure
10.1 (For approved sealants
see page 3).