single-cycle mixed-fluid lng (prico) process

21
1 Single-cycle mixed- fluid LNG (PRICO) process Part I: Optimal design Sigurd Skogestad & Jørgen Bauck Jensen Qatar, January 2009

Upload: goro

Post on 18-Mar-2016

50 views

Category:

Documents


3 download

DESCRIPTION

Single-cycle mixed-fluid LNG (PRICO) process. Part I: Optimal design Sigurd Skogestad & Jørgen Bauck Jensen Qatar, January 2009. Single-cycle mixed fluid LNG (PRICO) process. 45 kg/s 30 °C 40 bar. Natural gas : 45 kg/s (1.3 MTPA) Feed at 40 bar and 30 °C - PowerPoint PPT Presentation

TRANSCRIPT

1

Single-cycle mixed-fluid LNG (PRICO) process Part I: Optimal designSigurd Skogestad & Jørgen Bauck JensenQatar, January 2009

2

Single-cycle mixed fluid LNG (PRICO) process

Natural gas:• 45 kg/s (1.3 MTPA)• Feed at 40 bar and 30 °C

– 89.7 mol% C1, 5.5% C2, 1.8% C3, 0.1% C4, 2.8% N2

• Cooled to ~ -156 °C• Expansion to ~ 1 bar

– Flash gas may be used as fuel

• Liquefied natural gas (LNG) product at -162C

-162 °C

1 bar

45 kg/s30 °C40 bar

-156 °C 35 bar

3

Single-cycle mixed fluid LNG (PRICO) process

Refrigerant:• Mixed fluid: ~ 33mol% C1, 35%

C2, 0% C3, 25% C4, 7% N2

• Partly condensed with sea water to ~ 30 °C

• Subcooled to ~ -156 °C• Expansion to ~ 4 bar• Evaporates in NG HX• Super-heated ~ 10 °C• Compressed to ~ 22 bar

4 barSup 10 °C

-156°C 19 barsubcooled

22 bar45 kg/s30 °C40 bar

475 kg/s30 °C22 bar

-156 °C

Sat. liquid

4

Compressor:• Max. pressure: 22 bar / 30 bar• Max. compressor suction

volume*: 317000 m3/h• Max. compressor head*: 263.6

kJ/kgOr: Max. compressor ratio* Pr, e.g. 5.5 (Price)

4. Max. compressor work: 77.5 MW / 120 MW

5. Minimum superheating: 10C

Design constraints

-162 °C

30 °C40 bar

1 bar

3.33 kg/s (7%) * Design constraint only

30 °C

6

Optimal design: TAC

min JTAC = Joperation + Jcapital

subject to c ≤ 0• Joperation [$/year] is the annual operating cost

– Joperation = Jutility + Jfeeds + Jproducts

• Jcapital [$/year] is the annualized cost of the equipment

• Total annualized cost (TAC) is minimized with respect to the design variables

– Flowsheet structure – Areas, sizes– Operating parameters (pressures etc.)

• Requires mixed integer non-linear programming• Our case Fixed structure Try a simpler approach

Maximize total profit = Minimize Total Annualized Cost (TAC):

7

Idea: Specify ΔTmin to balance between

• operating costs (favoured by a low value)

• capital costs (favoured by a high value)

Simpler approach: Specify ΔTmin

-162 °C

30 °C40 bar

1 bar

3.33 kg/s * Design constraint only

ΔTmin=2C*

30 °C

8

Simple ΔTmin-method (Approach 1)

• ΔTmin (=2C) is added as an extra design constraint + minimize compressor work (Ws)

• BUT: The resulting design parameters (pressure etc.) are not optimal for the resulting process! – Reoptimizing reduces ΔTmin to about 1C and reduces work by about

5% (!)– Cannot be fixed by iterating on ΔTmin

• Therefore: Approach 1 NOT USED

9

Simplified TAC (sTAC)

Capital costJcapital = Σi (Cfixed,i + Cvariable,i·Si

ni) / TT – capital depriciation time, e.g. 10 years

1. Structure of plant given Cfixed,i = 0 2. Main equipment: Heat exchangers and compressor 3. Scaling exponent

• n = 1 for compressor • use largest compressor available• can then combine operation and capital cost!

• n = 0.65 for heat exchangers

4. Cvariable,i = C0 for all heat exchangersApproach 2: Adjust C0 to get ΔTmin = 2C

11

“Max feed” sTAC:

• Minimization with respect – Heat exchanger areas (AHOT and ANG),

• ANG: NG / cold refrigerant

• AHOT: hot refrigerant / cold refrigerant

– refrigerant composition – operating parameters (Ph, Pl, mLNG)

• Here: Adjust C0 to obtain ΔTmin = 2C• Other constraints c: depend on specific case

12

Case 1 – Price and Mortko (1983)• Data

– LNG outlet temperature (before expansion) = -144 °C– 77.5 MW compressor power– Maximum Ph = 22 bar

– Maximum Pr = Ph/Pl = 5.5

• Differences / uncertainties– Feed composition – Neglected removal of heavy components– Pressure losses (especially important at low pressure, e.g. compressor

suction)– Heating of fuel gas produces some LNG “for free”

• 3.7 % higher production compared with Price & Mortko– 44.6 kg/s LNG production– Gives too much fuel gas (7.7 kg/s, ~230 MW)

• Want to limit fuel to 3.33 kg/s, ~100 MW

13

Case 2 – Limited fuel flow• Limitation on fuel flow instead of outlet temperature

– Maximum 3.33 kg/s of fuel (7.7. kg/s in Case 1)– Outlet temperature down from -144 °C to -156 °C to get sufficient

cooling with less flash gas (fuel)– Production (with Ws=77.5 MW and Pr=5.5) reduced by 6 % compared

with case 1• From 44.6 kg/s to 41.7 kg/s

3.33 kg/s

77.5 MW

-162C41.7 kg/s

-156C

22 bar

4 bar

45 kg/s30C

475 kg/s30C

14

Case 3,4 – Super-heating• Wish to find the optimal degree of super-heating

– 10.0 °C super-heating used for all cases except 3 and 4– Case 3; 11.6 °C super-heating increases production by 0.8 % compared with

case 2– Case 4; 25.7 °C super-heating decreases production by 1.3 % compared with

case 3

• Optimum is very flat in terms of super-heating• Some super-heating is necessary to protect the compressor• Some super-heating is optimal due to

– Internal heat exchange in the main heat exchanger

• However, the heat transfer coefficient in the super-heating region is lower than in the evaporating region

– This has not been considered here– Will tend to reduce the optimal amount of super-heating

15

Case 5 – No pressure constraint• We have removed the following constraints

– Maximum Ph = 22 bar– Maximum Pr = Ph/Pl = 5.5

• Ph is increased to 50.4 bar and Pr is increased to 22• LNG production is increased by 11 % (from case 2)• The high pressure ratio is not possible with a single compressor

casing– The compressor head is too high– Two compressors in series will do the job

• Higher head [kJ/kg] gives lower refrigerant flow– Cooling duty per kg of refrigerant closely related to head– Less heat transfer area is needed since less warm refrigerant needs cooling

• The cost of an additional compressor casing is at least partly offset by the decreased heat transfer area and increased production

16

Case 6,7 – Real GE Compressor• GE MCL1800 series compressor

– Centrifugal compressor with 1800 mm casing diameter– Maximum suction volume is 380 000 m3/h active constraint– Maximum discharge pressure Ph = 30 bar active constraint

• Case 6 – 77.5 MW; Same production as case 5 – Compressor head is 216 kJ/kg may be feasible with a single

compressor casing

• Case 7 – 120 MW; 71.1 kg/s of LNG product– Compressor head is 162 kJ/kg which is feasible with a single

compressor casing– Corresponds to 2.0 million tons per annum (MTPA) with 330

operating days per year

17

Case 8 – Liquid turbines• Expansion in liquid turbines

– Takes the pressure down to 2 bar above the saturation pressure

– Avoid vapour in the turbines– Possible with two phase turbines?

• Production increased by 6.6 % compared with case 7– 75.8 kg/s ~ 2.2 MTPA per train

18

Production vs. feed pressure• Results for case 8• Achievable feed

pressure depends on – Location of heavy extraction

• Up-front or integrated• Recompression after heavy

extraction– Feed compressor?

• Complicates the optimization problem– Very important for production

19

Comment

• All the results presented here are with a minimum approach temperature ΔTmin = 2.0 °C– This is achieved by adjusting C0 in the optimization problem

• An alternative is to find a reasonable C0 and the use the same value for all cases– These results are presented in the paper

20

Conclusion

• sTac method – better than specifying ΔTmin

• Superheating is optimal• Feed pressure very important for the achievable

production• A large PRICO train of 2.2 MTPA is feasible with a

single compressor casing– 2.0 MTPA without liquid turbines

21

Additional material

1. Table with results for all cases2. Table with results for the alternative design method

with constant C0

22

23

Fixed C0 for all cases