simulation and compressor control case study

59
Confidential Property of Schneider Electric Turbomachinery Simulation and Compressor Control Case Study Presented by: Hector Buchelly

Upload: others

Post on 25-Dec-2021

4 views

Category:

Documents


0 download

TRANSCRIPT

Confidential Property of Schneider Electric

Turbomachinery Simulation and Compressor Control

Case Study

Presented by: Hector Buchelly

Compressor Components and Operational Safety

Dynamic Simulation

Case Study

Application of Dynamic Simulation

Agenda

Page 2 Confidential Property of Schneider Electric |

Compressor Components and Operational Safety

Page 3 Confidential Property of Schneider Electric |

– Compressor

– Piping

– Heat exchangers

– Knockout drums

– Anti-surge valves

– Instrumentation

– Control system

F T

P

T

Elements are designed to maintain throughput and

keep the compressor at a safe operating point.

Compressor System Components

Page 4 Confidential Property of Schneider Electric |

Surge

Surge is a condition at which the

compressor cannot raise the pressure

any higher without causing a complete

breakdown of steady flow.

Choke (Stonewall)

Because the compressor operates at a

very high mass flow rate, flow through

the compressor cannot be increased

after sonic velocity is reached.

Compressor Operational Safety

Page 5 Confidential Property of Schneider Electric |

Pd

Ps

hPs

Minimum Flow Control

Page 6 Confidential Property of Schneider Electric |

Pd

Ps

hPs

Maximum Pressure Control

Page 7 Confidential Property of Schneider Electric |

Page 8 Confidential Property of Schneider Electric |

• Defining the Operating Point

• Locating the Surge Limit

• Surge Acceleration (Curve

Shape)

• Interacting with Control Loops

• Meeting Load-Sharing

Requirements

Surge Control Application

Challenges

Page 9 Confidential Property of Schneider Electric |

What is Surge?

A condition wherein the compressor is unable to

maintain a greater force than system resistance.

The Surge Cycle

1. System resistance

increases discharge

pressure required

(operating point moves

up the curve)

2. Operating point nears

the Surge Limit

3. Operating point goes

into the Surge Region Flow

4

Pressure

1

2 3

5

Page 10 Confidential Property of Schneider Electric |

The Surge Cycle

4. Flow reverses as

discharge pressure drops

5. Drop in discharge

pressure re-establishes

forward flow (Compressor

resumes full flow)

Since resistance has

not changed, surge will

continue until cycle is

broken

Flow

4

Pressure

1

2 3

5

Page 11 Confidential Property of Schneider Electric |

Page 12 Confidential Property of Schneider Electric |

An operating point can move from stability

to surge in less than 100 milliseconds!

A complete surge cycle takes from ½ to 3 seconds,

depending on compressor size and piping volume.

Page 13 Confidential Property of Schneider Electric |

• The operator sees

process upset because

of flow reversals

• The machinery person

sees damage to seals

• The plant manager sees

catastrophic compressor

failure if surge is severe

Why is surge bad?

Several viewpoints:

What is dynamic simulation?

Page 17 Confidential Property of Schneider Electric |

How does simulation work across industries?

Page 18 Confidential Property of Schneider Electric |

Real Plane Virtual Plane

Real Plant Virtual Plant

How does simulation work in a plant?

Page 19 Confidential Property of Schneider Electric |

• Shows components and

thermodynamics

• Includes rigorous dynamic behavior

model of equipment and pipes

• Provides a high-fidelity rendering of

instruments and controls

• Enables testing of scenarios and

alarms

• Helps train operators

What is dynamic simulation?

Page 20 Confidential Property of Schneider Electric |

Safely study the integration of TMC equipment and controls

Boost system reliability

Avoid costly errors, thereby reducing expenses

Improve efficiency in real time

Reduce downtime during operation by debugging the system

Increase machinery availability

Why use simulation?

Page 21 Confidential Property of Schneider Electric |

Case Study

Page 22 Confidential Property of Schneider Electric |

Page 23 Confidential Property of Schneider Electric |

Let’s consider a new field

unit consisting of:

• Elliot Steam Turbine

(1200 HP, 660# inlet

pressure)

• Atlas Copco Ethane

Kickback

Compressor (TP-

14/10)

Case Study

System Overview

Page 24 Confidential Property of Schneider Electric |

Control Hardware:

• Two-chassis Tricon System

• Bently Nevada BN3500

Control Software (Tristation 1131):

• Turbine – Compressor Start Stop Control

• Turbine Speed Control

• System Shutdowns

• Compressor Surge Control

• Decoupling

• Lube Oil Aux Pump Control

DCS: Suction Pressure Control in DCS (Guide Vanes)

Scope of Supply

Page 25 Confidential Property of Schneider Electric |

SimSci products:

• DynSim for the dynamic model

• TriSim to connect model to control program (PT2)

via Tristation Emulator

Modeling Software

Page 26 Confidential Property of Schneider Electric |

• Local Operator

Panel

• Wonderware HMI

• Honeywell DCS

(represented in

model)

Operator Interface

Page 27 Confidential Property of Schneider Electric |

Simulation Architecture

Page 28 Confidential Property of Schneider Electric |

System: Turbine and

Process

Control

System

Application

Human

Machine

Interface

Simulation: Dynsim Trisim Tristation

Emulator

Wonderware

Recycle valve critical flow

Motor torque curves

Shaft rotating inertia WK2

Piping and KO drum volumes for accurate

transients

Performance curves

Fluid feed composition

Intercoolers

Vapor-liquid equilibrium “flash”

Dynamic Simulation: Rigorous Model

Page 29 Confidential Property of Schneider Electric |

Model Flow Sheet

Page 30 Confidential Property of Schneider Electric |

We start with the P&IDs, and then complete data input for each component.

Building the Model

Page 31 Confidential Property of Schneider Electric |

Building the Model: Added Controls

Page 32 Confidential Property of Schneider Electric |

Application of Dynamic Simulation

Page 33 Confidential Property of Schneider Electric |

Process Design

Controls Configuration

Start Up

Plant Operation

Applying the Model

Page 34 Confidential Property of Schneider Electric |

Before completing the Front End Engineering

Design study or beginning commissioning,

verify elements of the compressor system:

• Compressor specifications

• Anti-surge valve sizing

• Compressor trips, driver failure, loss of instrument air, etc.

• Valve opening time

Field Hardware Verification

Page 35 Confidential Property of Schneider Electric |

• Ascertain the best anti-surge &

performance control approaches

• Design and prove the value of Triconex

decoupling control algorithms

• Establish start-up and shut-down

sequencing

• Position the startup guide vane

• Position T&T valve

Control Strategy Definition

Page 36 Confidential Property of Schneider Electric |

Universal Surge Line

20 40 60 80 100 0

1

2

3

4

5

Pd

Surge Line

Ps

__

h Ps

__ %

Speed

Curves

Page 37 Confidential Property of Schneider Electric |

Setpoint Hover

20 40 60 80 100 0

1

2

3

4

5

Pd

Surge Line

Ps

__

h Ps

__ %

Control Line

Current Operating

Point

Setpoint Hover

Hover Setting

Page 38 Confidential Property of Schneider Electric |

Control Line Recalibration

20 40 60 80 100 0

1

2

3

4

5

Pd

Surge Line

Ps

__

h Ps

__ %

Control Line

Current

Operating

Point

Recalibrated

Control Line

Page 39 Confidential Property of Schneider Electric |

20 40 60 80 100 0

1

2

3

4

5

Pd

Control Line

Surge Line

Ps

h Ps

%

0%

100%

Valve Output

Surge

Override Line

Surge Override

Page 40 Confidential Property of Schneider Electric |

Decoupling Capacity Control

Breakpoint is stationary if Surge

Margin is between 1% and 3%:

• Speed is not reduced further, since

this would drive the compressor into

surge

• Further decrease in Process

Controller Output will immediately

open recycle valve

Breakpoint moves to right if Surge

Margin < 1%:

• Increases speed setpoint to speed

up compressor, keeping Surge

Margin >1% Page 41 Confidential Property of Schneider Electric |

Process Design

Controls Configuration

Start Up

Plant Operation

Applying the Model

Page 42 Confidential Property of Schneider Electric |

• Closed loop testing during

FAT

• Software testing independent

of hardware

• Loop tuning before

commissioning

Page 43 Confidential Property of Schneider Electric |

Testing

h/P1

Max

Gain

Normal

Gain

Min

Gain

Surge

Line

Control

Line

Adaptive Tuning

Page 44 Confidential Property of Schneider Electric |

Quickly responds to surge condition but doesn’t exceed response time of system

Fast Opening

Allows turbine speed controller/ process cascade controller to smoothly adjust to new process operating conditions

Slow Closing

Fast Opening, Slow Closing

Page 45 Confidential Property of Schneider Electric |

Manual Recycle Valve Control

• Operator can open the recycle valve only when above the surge controller demand

• Operator cannot close the recycle valve below the surge controller demand

Partial Authority

• Operator can close and open the recycle valve with no surge protection

• Useful to stroke test recycle valve prior to startup

• Useful in some fallback scenarios

Full Authority

Page 46 Confidential Property of Schneider Electric |

• Determine effectiveness of

controls

• Debug any control logic on the

system rather than on the

actual machine in field

• Establish initial controller

tuning

• Evaluate overrides that may

be necessary for particular

upsets

Pre-startup Controller Tuning

Page 47 Confidential Property of Schneider Electric |

Discovery:

• Speed couldn’t be

well controlled during

startup

Why?

• Design minimum stop

on IGV meant too little

mechanical load

Fix?

• Use model to find

optimum minimum

stop for IGV

Tune Speed Controller Pre-commissioning

Page 48 Confidential Property of Schneider Electric |

Process Design

Controls Configuration

Start Up

Plant Operation

Applying the Model

Page 49 Confidential Property of Schneider Electric |

Shorter

Commissioning

Schedule

Error-free

Startup

Operator

Training

Page 50 Confidential Property of Schneider Electric |

Benefits: Initial Startup Phase

• Final software

testing

• Controller tuning

using normal

field techniques

• Surge line

testing

Final Verification Pre-startup

Page 51 Confidential Property of Schneider Electric |

Discovered:

• Even though a full FAT

was performed,

simulation allowed us to

find and correct minor

logic errors. We also

made changes to the

HMI as requested by

operations.

Result:

• Saved time during

commissioning. Normal

schedule for a unit is 4–

5 days. Actual time

spent: less than 1 day.

Pre-commissioning Logic and HMI Checkout

Page 52 Confidential Property of Schneider Electric |

Process Design

Controls Configuration

Start Up

Plant Operation

Applying the Model

Page 53 Confidential Property of Schneider Electric |

Operator Training

Event Analysis

Process Modifications

Control Modifications

Page 54 Confidential Property of Schneider Electric |

Discussion:

How can we use the model when the system is online?

Page 55 Confidential Property of Schneider Electric |

Perform Transient Tests Offline

Page 56 Confidential Property of Schneider Electric |

Offline Test

With simulation, we are able to perform

multiple system upsets that would be

impossible to test in the field.

Results: we can tune the system

accurately and gain confidence in the

controls.

What concerns has simulation identified in actual situations?

• Recycle valve too small

• Recycle valve too slow

• One stage surges on shutdown

• EPC control strategy is “not optimum”

Before implementation, simulation can verify process

changes. Even with basic models, simulation enables more

effective closed loop software and HMI testing.

Page 57 Confidential Property of Schneider Electric |

Identifying Concerns Via Simulation

Page 58 Confidential Property of Schneider Electric |

KEY TAKEAWAYS

•Simulation saves money and time.

•It improves safety and increases availability.

•We have extensive experience with dynamic simulation modeling.

•Our model ties directly to the actual controls and HMI—a huge differentiator.

Questions?

Page 59 Confidential Property of Schneider Electric |

THANK YOU.

Page 60 Confidential Property of Schneider Electric |

Page 61 Confidential Property of Schneider Electric |