/ CIN No. : L26943RJ1979PLC001935 Phone : 01462228101-6 Toll Free : 18001806003/6004 Fax: 01462228117/228119 E-Mail: [email protected] Website : www.shreecement.in SHREE CEMENT LTD. \~~~o.~ Regd.otffce: ~ BANGUR NAGAR, POST BOX NO.33, BEAWAR 305 901, RAJASTHAN, INDIA J;oA166S~" SCL/Nawalgarh/EC/2016-17 }) it, I To, The Director (Industry) Ministry of Environment, Forest & CC, Indira Paryavaran Bhawan, Jor Bagh Road, Ali Ganj, l'-lew Delhi- 110003 Date: 25/11/2016 Sub: - !~egording compliance of environmental clearance granted for establishment of 2.0 million TPA Clinker, 3.0 million TPA cement, 2*18 MW cpp, 10 MW WHR and 3.2 million TPA limestone mining at village-Gothra, Tehsil-Nawalgarh, District-Jhunjhunu (RajasH1an) of M/s. Shree Cement umited. I<ef: EC letter no. J-l1011/1173/2007-IA II (I) dated 15/07/2009 & 1l.09.2015. Deor Sir, Kindly refer to the above subject matter and referred letters. We are submitting herewith the compliance status of above EC conditions from April. 2016 to Sept. 2016. This is for your kind information please. Thanking you, Yours faithfully, For SHREECEMENT LIMITED, ~ (f~akesh Bhal avo) " t- Vice President (Environment) Copy to:- 1. Director, Ministry of Environment & Forest, Regional office (Central Region), Kendriya Bhawan, 5th Floor Sector 'H' ALiGANG, LUCKNOW (U.P.), Pin-226024. 2. Zonal Officer, Central' pollution Control Board, Zonal Office (Central) 3rd Floor, Sahkar Bhowon. North T.T. Nagar, Bhopal-462003, 3. The Member Secretary, Rajasthan Pollution Control Board, 4, Institutional Area, Jhalana Doongri, JAIPUR-302004 (Rajas1han). Page 1 of 13 JAIPUR OFFICE: SB-187, Bapu Na;'ir, Opp. Rajasthan University, JLN Marg, Jaipur-302 015 Phone: 0141 4241200,4241204, Fax: 01414241219 NEW.DELHI OFFICE: 122-123, Hans Bhawan, 1, Bahadurshah Zafar Marg, New Delhi 110002 Phone: 01123370828,23379218,23370776, Fax: 01123370499 CORP. OFFICE: 21, Strand Road, Kolkata 700 001 Phone: 033-22309601-4 Fax: 033 22434226

Upload: others

Post on 02-Nov-2019

5 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: SHREE CEMENT LTD. · mill, cement mill and boiler. SO2 and NOx analyzer shall be installed at the stack of boiler and kiln. Emission level shall be displayed and updated at the web

/CIN No. : L26943RJ1979PLC001935Phone : 01462228101-6Toll Free : 18001806003/6004Fax: 01462228117/228119E-Mail: [email protected] : www.shreecement.in

SHREE CEMENT LTD. \~~~o.~

Regd.otffce: ~BANGUR NAGAR, POST BOX NO.33, BEAWAR 305 901, RAJASTHAN, INDIA J;oA166S~"

SCL/Nawalgarh/EC/2016-17 } ) it,ITo,The Director (Industry)Ministry of Environment, Forest & CC,Indira Paryavaran Bhawan, Jor Bagh Road, Ali Ganj,l'-lew Delhi- 110003

Date: 25/11/2016

Sub: - !~egording compliance of environmental clearance granted for establishment of 2.0million TPA Clinker, 3.0 million TPA cement, 2*18 MW cpp, 10 MW WHR and 3.2 millionTPA limestone mining at village-Gothra, Tehsil-Nawalgarh, District-Jhunjhunu(RajasH1an) of M/s. Shree Cement umited.

I<ef: EC letter no. J-l1011/1173/2007-IA II (I) dated 15/07/2009 & 1l.09.2015.

Deor Sir,

Kindly refer to the above subject matter and referred letters. We are submitting herewith thecompliance status of above EC conditions from April. 2016 to Sept. 2016.

This is for your kind information please.

Thanking you,Yours faithfully,For SHREECEMENT LIMITED,

~

(f~akesh Bhal avo)" t- Vice President (Environment)

Copy to:-1. Director, Ministry of Environment & Forest, Regional office (Central Region), Kendriya

Bhawan, 5th Floor Sector 'H' ALiGANG, LUCKNOW (U.P.), Pin-226024.

2. Zonal Officer, Central' pollution Control Board, Zonal Office (Central) 3rd Floor, SahkarBhowon. North T.T. Nagar, Bhopal-462003,

3. The Member Secretary, Rajasthan Pollution Control Board, 4, Institutional Area,Jhalana Doongri, JAIPUR-302004 (Rajas1han).

Page 1 of 13

JAIPUR OFFICE: SB-187, Bapu Na;'ir, Opp. Rajasthan University, JLN Marg, Jaipur-302 015Phone: 0141 4241200,4241204, Fax: 01414241219

NEW.DELHI OFFICE: 122-123, Hans Bhawan, 1, Bahadurshah Zafar Marg, New Delhi 110002Phone: 01123370828,23379218,23370776, Fax: 01123370499

CORP. OFFICE: 21, Strand Road, Kolkata 700 001 Phone: 033-22309601-4 Fax: 033 22434226

Page 2: SHREE CEMENT LTD. · mill, cement mill and boiler. SO2 and NOx analyzer shall be installed at the stack of boiler and kiln. Emission level shall be displayed and updated at the web

Page 2 of 13

Compliance Status of Environment ClearanceEC Letter No. J-11011/1173/2007- IA II (I) Dated 15/07/2009.

S.No. Condition ComplianceSpecific Conditions

I No construction work withoutapprovals from IBM and Raj Govt.Submission of copy of approvals

No construction works have beenstarted at the site.Approval of mine lease from IBM shallbe submitted.

II To provide ESPs to clinker cooler andCPP, Bag house to raw mill/kiln, coalmill and cement mill to controlparticulate matter within 50 mg/Nm3from cement plant and 100 mg/Nm3from Boilers.

Installation of Bag filters at all transferpoints.

Following measures shall be taken:S.No. Source PCM1. Raw Mill &

KilnBag House

2. Coal Mill Bag House3. Clinker

CoolerESP

4. CementMill

Bag House

5. Boiler I & II ESPBag filters will be provided to alltransfer points.Dust collector shall be designed tomeet the PM as per norms.

III Installation of CEMS. Update the dataof ambient air quality, stack emissionand fugitive emissions at the web siteof Company and on line and hardcopy submission to the Ministry’sRegional Office, RPCB and CPCBonce in six months.

Opacity meters shall be installed atthe stack of kiln, clinker cooler, coalmill, cement mill and boiler. SO2 andNOx analyzer shall be installed at thestack of boiler and kiln.Emission level shall be displayed andupdated at the web site of Shreecement and shall be submittedonline and hard copy to the MOE&F,CPCB and RPCB regularly.

IV Explore the possibilities for installationof waste heat recovery boiler (WHRB)

WHRS of 15 MW will be installed

V Installation of adequate dustcollection and extraction system tocontrol fugitive dust emission atvarious transfer points

Covering of conveyor beltsCovered sheds for storage of rawmaterials

Silo for the storage of cement, fly ash

All measures shall be taken.

Page 3: SHREE CEMENT LTD. · mill, cement mill and boiler. SO2 and NOx analyzer shall be installed at the stack of boiler and kiln. Emission level shall be displayed and updated at the web

Page 3 of 13

and clinkerPneumatic system for fly ash handling.

VI & VII Dust suppression by regular watersprinkling in cement plant, CPP,limestone mine lease such as haulroad, loading and unloading points.

To ensured the ambient air qualitywithin the norms prescribed by theCPCB.

Water sprinkling arrangements shallbe provided at loading, unloadingpoints and on haul roads.

Ambient air quality shall bemaintained well within the prescribednorms.

VIII & X Transportation of raw materials in theclosed containers only and should notbe overload. Vehicular emission shallbe regularly monitored.

Transportation of raw materials shallbe done in closed containers withoutoverloading. Vehicular emission shallbe monitored regularly.

IX Explore the possibility for thetransportation of pet coke and fly ashby rail

Possibilities shall be explored and ifpossible.

XI Concreting of roads and water sprayall around the critical areas

All movement area shall be madecemented. Water sprinklingarrangements shall be provided atloading, unloading points and onhaul roads.

XII Max water requirement is 1200 KLD.Use of rain water collected in minepits. Installation of Air CooledCondenser. Recycling of effluentwater.

Max water requirement will be is 1200KLD. Rain water collected in mine pitshall used in process.Air Cooled Condenser shall beinstalled. All effluent water shall bereused.

XIII& XVI. Installation of STP for treatment ofdomestic effluent. Use of treatedwater for gardening

Installation of soak pits in mine leasearea.

Installation of ETP for mine workshop.

To ensure no discharge of effluentwater in water body

STP will be installed for the treatmentof domestic effluent generated fromplant and colony and treated watershall be used for plantation.Soak pits and septic tanks shall beinstalled at mine office.ETP shall be installed for mineworkshop for separation of oilcontents and clean water shall beused for spray in crusher.

XIV. To carry out hydrological study andimplementation of recommendations

Hydrological study has been carriedout and recommendations shall beimplemented.

XV. To ensure no obstruction in natural No obstruction in natural water

Page 4: SHREE CEMENT LTD. · mill, cement mill and boiler. SO2 and NOx analyzer shall be installed at the stack of boiler and kiln. Emission level shall be displayed and updated at the web

Page 4 of 13

water course due to miningoperations.

course shall be ensured due tomining operations.

XVII Suitable conservation measures toaugment ground water resources

Rain water harvesting measures,including construction of check damand roof top rain water harvesting inand around shall be implemented foraugmentation of ground waterresources.

XVIII Recycled and reused of dustcollected in PCB for cementmanufacturing.

To use domestic solid waste asmanure

Waste oil shall be provided to theauthorized recyclers.

Dust collected in PCM shall berecycled in cement manufacturingprocess.

STP solid waste shall be used asmanure.

Used oil shall be sold to theauthorized recyclers.

XIX Use of fly ash as per Fly AshNotification, 1999 subsequentlyamended in 2003.

Efforts shall be made to use fly ashmaximum in making PPC.

Fly ash shall be stored in silos andother materials in covered sheds.

Fly ash will be utilized in making (PPC)and will be stored in fly ash silo.

XX An effort shall be made to use of highcalorific hazardous waste in thecement kiln.

High calorific hazardous wasteavailable in the area shall be utilizedas alternate raw material and fuel.

XXI Efforts shall be made to use low gradelime, more fly ash and solid waste inthe cement manufacturing.

Low grade lime stone of mine shall beblended with good quality oflimestone. Fly ash will be utilized formanufacturing of PPC.

XXII. Open cast fully mechanized methodof mining shall be adopted and nochange in mining technology andscope of working shall be madewithout prior approval of the Ministryof Environment & Forests.

We shall obtain prior approval beforeany change in mining technology.

XXIII Wet drilling, blasting method andprovision for the control air emissionsduring blasting using dust collectorsetc. shall be used.

Wet drilling and dry drilling with dustextractor arrangement shall be used.Water spray on haul roads shall bepracticed.

XXIV Blasting operation shall be carried outonly during the daytime and one

Controlled Blasting will be doneduring the daytime with Shock Tube

Page 5: SHREE CEMENT LTD. · mill, cement mill and boiler. SO2 and NOx analyzer shall be installed at the stack of boiler and kiln. Emission level shall be displayed and updated at the web

Page 5 of 13

bench at a time shall be blasted.

Controlling blasting shall bepracticed.

No objection certificate from theChief Controller of Explosives shall beobtained.

Detonator i.e. Non-Electric BottomInitiation & use of rock breaker forsecondary breaking.

NOC shall be obtained from ChiefController of Explosives

XXV. Top soil, if any, shall be stacked withproper slope at earmarked non-mineralized site(s) only and shall beused for reclamation andrehabilitation of mined out areas.

Top soil shall be stacked with properslope at earmarked site(s) and shallbe used for reclamation andrehabilitation of mined out areas.

XXVI. The inter burden and other wastegenerated shall be stacked atearmarked dump site(s) only andshould not be kept active for longperiod. The total height of the dumpsshall not exceed 30 m in the threeterraces of 10 m each and the overallslope of the dump shall bemaintained to 28 degree. The interburden dumps shall be scientificallyvegetated with suitable nativespecies to prevent erosion andsurface run off. Monitoring andmanagement of rehabilitated areasshould continue until the vegetationbecomes self-sustaining. Compliancestatus shall be submitted to theMinistry & Forests and its RegionalOffice, Lucknow on six monthly bases.

Inter burden and OB will be stackedat earmarked dump site(s). The totalheight of the dumps will be 30 m inthree terraces of 10 m each and theoverall slope of the dump will bemaintained to 28°. The inter burdendumps will be vegetated with nativespecies. Compliance status will besubmitted to the Ministry ofEnvironment & Forests and itsRegional Office on six monthly bases.

XXVII. As proposed, green belt shall bedeveloped in at lease 6.5 acres (33%), out of 16 acres area in the cementplant area and all the mined out areaexcept used for reservoir.

Green belt shall be developed in 33%of total plant within 5 years and 53%of mining lease area at the end ofmine life. Native species shall beplanted.

XXVIII. The void left unfilled in the mining areashall be converted into water body.The higher benches of excavatedvoid/mining pit shall be terraced andplantation done to stabilize the slopes.The slope of higher benches shall bemade gentler for easy accessibility bylocal people to use the water body.

Void left unfilled in the mining areawill be converted into water body.Higher benches of excavatedvoid/mining pit will be terraced andplantation will be done to stabilizethe slopes.Slope of higher benches will be madegentler for easy accessibility by local

Page 6: SHREE CEMENT LTD. · mill, cement mill and boiler. SO2 and NOx analyzer shall be installed at the stack of boiler and kiln. Emission level shall be displayed and updated at the web

Page 6 of 13

Peripheral fencing shall be carried outalong the excavated area.

people to use the water body.Peripheral fencing will be carried outalong the excavated area.

XXIX. Catch drains and siltation ponds ofappropriate size shall be constructedfor the working pit, inter burden andmineral dumps to arrest flow of slit andsediment. The water so collected shallbe utilized for watering the mine area,roads, green belt development etc.The drains shall be regularly desilted,particularly after monsoon, andmaintained properly.

Catch drains and siltation ponds shallbe constructed.

Rain water collected in mine pit willbe utilized for plantation, road sprayand process.

XXX. Garland drain of appropriate size,gradient and length shall beconstructed for both mine pit andinter burden dumps and sumpcapacity shall be designed keeping50% safety margin over and abovepeak sudden rainfall ( based on 50years data) and provide adequateretention period to allow propersettling of silt material. Sedimentationpits shall be constructed at thecorners of the garland drains anddesilted at regular intervals.

Garland drain along withsedimentation pits shall beconstructed for both mine pit andinter burden dumps.

XXXI. Regular monitoring of ground waterlevel and quality shall be carried outby establishing a network of existingwells and constructing newpizometers at suitable locations by theproject proponent in and aroundproject area in consultation withRegional Director, Central GroundWater Board. The frequency ofmonitoring shall be four times a year –pre-monsoon (April/May), monsoon(August), post-monsoon (November),and winter (January). Data thuscollected shall be sent at regularintervals to Ministry & Forests and itsRegional Office, Lucknow, CentralGround Water Board.

Regular monitoring of ground waterlevel and quality shall be carried outby establishing a network of existingwell and constructing newpiezometer. The frequency ofmonitoring will be four times a year-pre-monsoon (April / May), monsoon(August), post-monsoon (November),and winter (January). Data collectedshall be sent to MOEF and its RegionalOffice, Central Ground WaterAuthority and State Ground WaterBoard annually.

XXXII. Suitable conservation measures toaugment groundwater resources inthe area on long term basis shall be

Various rain water rechargemeasures such as construction ofcheck dams and roof top harvesting

Page 7: SHREE CEMENT LTD. · mill, cement mill and boiler. SO2 and NOx analyzer shall be installed at the stack of boiler and kiln. Emission level shall be displayed and updated at the web

Page 7 of 13

planned and implemented inconsultation with Regional Director,Central Ground Water Board.

etc shall be implemented in andaround the project site.Rain water collection pit shall bedeveloped in plant and mines areaand will be used for ground waterrecharge and also direct use forplant operation

XXXIII. Rain water collected from the roof topshall be injected into the groundthrough injection wells to rechargethe ground water table.

Rain water collected from the rooftop shall be injected into the groundthrough injection wells to rechargethe ground water table.

XXXIV Bench height. Width and slope forindividual bench shall be properlyassessed and implemented.Adequate measures shall be adoptedto stabilize the slope beforeabandonment. The fencing aroundthe reservoir shall be provided toprevent accidents.

Bench Height will be 10 m and widthwill be 20 m. Adequate measures willbe adopted to stabilize the slope.Fencing will be provided to preventaccidents.

XXXV. Dimensions of the retaining wall at thetoe of inter burden dumps and interburden benches within the mine tocheck run-off and siltation shall bebased on the rain fall data.

Retaining wall having suitabledimensions at the toe of inter burdendumps and inter burden benches willbe provided to check the run-off andsiltation.

XXXVI. As proposed, green belt shall bedeveloped in at least 50 ha (33 %) outof total 152.5 ha. In the cement plantarea and in 332.82 ha (53 %), out oftotal 624 ha. In the mine lease are asper the CPCB guidelines inconsultation with local DFO tomitigate the impact of fugitiveemissions A 7.5 meter wide green beltshall also be developed all around themine area. A long term action plan forthe plantation / afforestation / greenbelt development etc. shall beprepared and submitted to theMinistry and its Regional Office atLucknow and implemented. Furtherefforts shall be made to maintain thearea properly already afforested.

Green belt shall be developed in 33%of total plant within 5 years and 53%of mining lease area at the end ofmine life. Native species shall beplanted.

XXXVII Action plan for the mining,management of over burden(removal, storage, disposal etc.),reclamation of the mined out area

Action plan for the mining,management of over burden(removal, storage, disposal etc.),reclamation of the mined out area

Page 8: SHREE CEMENT LTD. · mill, cement mill and boiler. SO2 and NOx analyzer shall be installed at the stack of boiler and kiln. Emission level shall be displayed and updated at the web

Page 8 of 13

and mine closure shall be submittedto the Ministry and its Regional Officeat Bangalore and implemented in atime bound manner.

and mine closure will be submitted tothe Ministry and its Regional Office.

XXXVIII A fine mine closure plan along withdetails of Corpus Funds shall besubmitted to the Ministry ofEnvironment & Forests 5 years inadvance of final mine closure forapproval.

Mine closure plan along with CorpusFunds shall be submitted to theMinistry of Environment & Foreststimely.

XXXIX The project proponent shall modifythe mine plan of the project at thetime of seeking approval for the nextmining scheme from the IndianBureau of Mines so as to reduce thearea for external over burden dumpby suitable increasing the height ofthe dumps with proper terracing. Itshall be ensured that the overall slopeof the dump does not exceed 28degree.

Mine plan shall be modified at thetime of approval for the next miningscheme to reduce the area forexternal over burden dump bysuitably increasing the height of thedumps with proper terracing. Theoverall slope of the dump will bemaintained to 28°.

XXXX The project proponent shall take allprecautionary measures during miningoperation for conservation andprotection of endangered fauna.Action plan for conservation of floraand fauna shall be prepared andimplemented in consultation with theState Forest and Wildlife Department.Necessary allocation of funds forimplementation of the conservationplan shall be made and the funds soallocated shall be included in theproject cost. Copy of action plan maybe submitted to the Ministry and itsRegional office within 3 months fromthe date issue of this letter.

There is no endangered fauna in theproject area. However local speciesshall be planted in and around theproject area.

XXXXI Rehabilitation and Resettlement Planfor the project affected populationincluding tibals as per the policy of theState Govt. shall be implemented.Compensation paid in any case shallnot be less than norms prescribedunder the National Resettlement andRehabilitation Policy, 2007

Not applicable.

XXXXII Permission and Recommendations of There is no reserved forest in study

Page 9: SHREE CEMENT LTD. · mill, cement mill and boiler. SO2 and NOx analyzer shall be installed at the stack of boiler and kiln. Emission level shall be displayed and updated at the web

Page 9 of 13

the State Forest Departmentregarding impact of cement plantand mining activities on thesurrounding reserves forests, if any,shall be obtained and implemented,Further, Conservation Plan for theConservation of wild fauna inconsultation with the State ForestDepartment shall be prepared andimplemented.

area.

XXXXIII All the safety norms stipulated by theDirector General, Mine & Safety(DGMS) shall be implemented.

All the safety norms stipulated by theDirector General, Mine & Safety(DGMS) shall be implemented.

XXXXIV ‘Consent to Operate’ shall beobtained from Rajasthan StatePollution Control Board (RSPCB)before starting enhanced productionfrom the mine.

Consent to operate shall be obtainedfrom Rajasthan State Pollution ControlBoard (RSPCB).

XXXXV Acoustic enclosures shall be providedto control noise wherever necessary,Mine machine shall be provided withsilencers, Noise shall also be controlledfrom cooler fans, compressor house,cement mill and raw mill, cementplant and drilling machines,excavator, blasting at mine site usingappropriate noise control measures.

Turbines, compressors and DG setshall be installed in closed building.

Plantation will be done all around theplant boundary.

Proper maintenance and lubricationshall be done of all machines tomaintain the noise level of 85 dB(A) inplant premises and 75 dB(A) (daytime) and 70 dB(A) (night time) at theplant boundary.

XXXXVI All the recommendations made in theCharter on Corporate Responsibilityfor Environment Protection (CREP) forthe Steel plants shall be implemented.

Corporate Responsibility forEnvironment Protection (CREP) shallbe implemented.

XXXXVII The company shall be comply withthe commitments made during publichearing / public consultation held on27 February, 2009.

Commitments made during publichearing / public consultation held on27 February, 2009 shall be complied.

XXXXVIII The company shall provide housing forconstruction labor within the site withall necessary infrastructure andfacilities such as fuel for cooking,mobile toilets, mobile STP, safedrinking water, medical health care,crèche etc. The housing may be in

Housing, fuel, toilets with soak pits &septic tank, safe drinking water,medical healthcare etc shall beprovided to labors.

Page 10: SHREE CEMENT LTD. · mill, cement mill and boiler. SO2 and NOx analyzer shall be installed at the stack of boiler and kiln. Emission level shall be displayed and updated at the web

Page 10 of 13

the form of temporary structures to beremoved after the completion of theproject.

General conditionsI The project authority shall adhere to the

stipulations made by Rajasthan StatePollution Control Board (RSPCB) andState Government.

All recommendation of RajasthanState Pollution Control Board(RSPCB) and State Governmentshall be implemented.

II No further or modification of the plantshall be carried out without priorapproval of this Ministry.

Prior permission will be taken forfurther expansion.

III The gaseous and particulate matteremission from various units shall conformto the standards prescribed by theRSPCB. At no time, particulate emissionsfrom the cement plant including kiln,coal mill, and cement mill, cooler shallexceed beyond the permissible limit.Interlocking facility shall be provided inthe pollution control respective unit (s) isshut down automatically.

Emission from various units shall bewell within the standards prescribedby the RSPCB.

Interlocking shall be provided withpollution control equipments.

IV At least four ambient air qualitymonitoring stations shall be established inthe down wind direction as well aswhere maximum ground levelconcentration of SPM, SO2 and NOx areanticipated in consultation with theRSPCB. Ambient air quality includingambient noise levels shall not exceedthe standards stipulated under EPA orregularly in consultation with RSPCB anddata on ambient air quality and stackemission shall be regularly submitted tothis Ministry including its Regional Officeat Lucknow, RSCPB and CPCB once in sixmonths. The instruments used forambient air quality monitoring shall becalibrated time to time.

4 ambient air quality monitoringstations shall be established for themeasurement of PM2.5, PM10, SO2and NOX in consultation with theSPCB.

Data on ambient air quality andstack emissions shall be submittedto the MoEF including its RegionalOffice and SPCB / CPCB once in sixmonths.

V Industrial wastewater shall be properlycollected and treated so as to conformto the standards prescribed under GSR422 (E) dated 19 May, 1993 AND 31December, 1993 or as amended fromtime to time. The treated wastewatershall be utilized for plantation purpose.

Domestic sewage of plant andcolony will be treated in STP andtreated water will be used forplantation.

RO reject water will be reused forash quenching.

VI The overall noise levels in and around Turbines, compressors and DG set

Page 11: SHREE CEMENT LTD. · mill, cement mill and boiler. SO2 and NOx analyzer shall be installed at the stack of boiler and kiln. Emission level shall be displayed and updated at the web

Page 11 of 13

the plant area shall be kept well withinthe standards (85Dba) by providingnoise control measures includingacoustic hoods, silencers, enclosures etc.on all sources of noise generation. Theambient noise levels shall conform to thestandards prescribed underEnvironmental (Protection) Act, 1986Rules, 1989 viz. 75 dBA (day time) and 70dBA (night time).

will be installed in closed building.

Plantation will be done all aroundthe plant boundary.Proper maintenance andlubrication of all machines shall bedone to maintain the noise level of85 dB(A) in plant premises and 75dB(A) (day time) and 70 dB(A)(night time) at the plant boundary.

VII Proper housekeeping and adequateoccupational health programmes shallbe taken up. Occupational HealthSurveillance Programme shall be doneon regular basis and records maintainedproperly for at least 30-40 years. Theprogramme shall include lung functionand sputum analysis taste once in sixmonth. Sufficient preventive measuresshall be adopted to avoid directexposure to dust etc.

Proper housekeeping of the entireplant will be maintained.

Occupational health programmeswill be organized on a regular basisand records will be maintained.The programme will be organizedonce in six months.PPEs shall be provided.

VIII The company shall harvest the rainwaterfrom the roof tops and storm waterdrains to recharge the ground waterand use the same water for the variousactivities of the project to conserve freshwater.

Rain water harvesting measuressuch as construction of earthenpond inside the plant and minearea and roof top harvesting etcshall be implemented.

IX The company shall undertake eco-development measures includingcommunity welfare measures in theproject area.

Plantation in and around the plantarea shall be done. Variouscommunity welfare measuresincluding education, healthcareand infrastructure etc shall bedone for betterment of thesurrounding area.

X The project proponent shall also complywith all the environmental protectionmeasures and safeguardsrecommended in the EIA /EMP.

Environmental protectionmeasures and safeguardsrecommended in EIA/ EMP shall beimplemented.

XI A separate environmental managementcell with full fledged laboratory facilitiesto carry various management andmonitoring function shall be set up underthe control of senior executive.

A separate environmentalmanagement cell with full fledgedlaboratory facilities will be set up tocarry out various managementand monitoring functions under thecontrol of unit head.

XII As proposed Rs. 30.00 Crores and Rs. 1.00crores earmarked towards the capital

Adequate funds are available forthe implementation of the

Page 12: SHREE CEMENT LTD. · mill, cement mill and boiler. SO2 and NOx analyzer shall be installed at the stack of boiler and kiln. Emission level shall be displayed and updated at the web

Page 12 of 13

cost and recurring cost/annum forenvironment pollution control measuresand Rs. 50.00 Lakhs/annum for CSRactivities shall be used judiciously toimplement the conditions stipulated bythe Ministry of Environment and Forestsas well as the State Government. Timebound implementation schedule forimplementing all the conditionsstipulated herein shall be submitted tothe Ministry. The funds so provided shallnot be diverted for any other purpose.

conditions stipulated by theMinistry of Environment and Forestsas well as the State Government.All recommendation shall beimplemented along with the plantcommissioning.

XIII The project authorities shall inform theRegional Office as well as the Ministry,The date of financial closure and finalapproval of the project by theconcerned authorities and the date ofcommencing the land developmentwork.

Financial closure and finalapproval of the project shall beinformed the Regional Office aswell as the Ministry.

XIV. The project proponent shall inform thepublic that the project has beenaccorded environmental clearance bythe Ministry and copies of the clearanceletter are available with the RajasthanState Pollution Control Board and mayalso be seen at Website of the Ministry ofEnvironment AND Forests athttp:/envfor.nic.in. This should beadvertised within seven days from thedate of issue of the clearance letter atleast in two local newspapers that arewidely circulated in the region of whichone shall be forwarded to the RegionalOffice at Lucknow.

Advertised in two local newspapers widely circulated in theregion namely, Rajasthan Patrika &Dainik Navjyoti on 22/7/2009.Copies have been submitted tothe Ministry.

XV. A Copy of clearance letter shall be sentby the proponent to concernedPanchayat, Zila Parishad / MunicipalCorporation. Urban Local Body and thelocal NGO, if any from whom suggestion/representations, if any, were receivedwhile processing the proposal. Theclearance letter shall also be put on theweb site of the company by proponent.

Copy of environment clearanceletter has been sent on 26/07/2009.

EC letter has been put on our website:- www.shreecement.in

XVI. The project proponent shall upload thestatus of compliance of the stipulatedenvironmental clearance conditions,

Compliance status shall beuploaded to company websiteand also sent to the Regional

Page 13: SHREE CEMENT LTD. · mill, cement mill and boiler. SO2 and NOx analyzer shall be installed at the stack of boiler and kiln. Emission level shall be displayed and updated at the web

Page 13 of 13

including results of monitored data ontheir website and shall update the sameperiodically. It shall simultaneously besent to the Regional Office of the MOEF.The respective Zonal Office of CPCB andthe SPCB. The criteria pollutant levelsnamely; SPM, RSPM, SO2, NOX)ambientlevels as well as stack emissions) orcritical sectroal parameters, indicatedfor the projects shall be monitored anddisplayed at a convenient location nearthe main gate of the company in thepublic domain.

Office of the MOEF, Zonal Office ofCPCB and the SPCB.

PM10, PM2.5, S02 and NOx levelshall be monitored on regular basisand data shall be submitted to theauthorities timely.

Monitored data shall be uploadedon the website of the company aswell as displayed near main gatein public domain.

XVIIThe project proponent shall also submitsix monthly reports on the status of thecompliance of the stipulatedenvironmental condition including resultsof monitored data (both in hard copiesas well as by e-mail) to the respectiveRegional Office of MOEF, the respectiveZonal Office of CPCB and the SPCB. TheRegional Office of this Ministry atLucknow / CPCB /RSPCB shall monitorthe stipulated conditions.

Six monthly compliance reportsshall be submitted to RegionalOffice of MOEF, the respectiveZonal Office of CPCB and theSPCB.

XVIII The environmental statement for eachfinancial year ending 31 March in forms-V as is mandated to be submitted bythe project proponent to the concernedState Pollution Control Board asprescribed under the Environmental (Protection) Rules, 1986, as amendedsubsequently, shall also be put on thewebsite of the company along with thestatus of compliance of environmentalconditions and shall also be sent to therespectively Regional Officers of theMOEF by e-mail

Environmental statement for eachfinancial year ending 31st March inForm-V will be submitted to theState Pollution Control Board; alsoit will be put on the website of theCompany along with the status ofcompliance of EC conditions andshall be sent to the regional Officeof the MoEF by e-mail.