short term testing mod 65_08 modification committee 25 th november 2010

22
Short Term Testing Mod 65_08 Modification Committee 25 th November 2010

Upload: helen-bishop

Post on 16-Jan-2016

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Short Term Testing Mod 65_08 Modification Committee 25 th November 2010

Short Term TestingMod 65_08

Modification Committee

25th November 2010

Page 2: Short Term Testing Mod 65_08 Modification Committee 25 th November 2010

Modification Objective To modify SEM rules to allow Within-Day testing to be

settled through SEM Within-Day testing currently not considered in SEM,

even though it provided for in Grid Code Current workaround:

DIs with test flags issued in EDIL DIs with test flags do not get sent to and profiled in

SEM systems This results Uninstructed Imbalance Payments by

Generators Modification is to remove this cost for generators

© EirGrid & SONI 2010 2

Page 3: Short Term Testing Mod 65_08 Modification Committee 25 th November 2010

Background Mod 65_08 was submitted in November 2008 Mods meeting on December 1st 2008: a working group was

established Two working group sessions were arranged during 2009. The final working group report concluded that further

investigation and discussion of the issues be investigated by SEMO and the TSOs.

An impact assessment was carried out Changes to the original drafted Modification (V2)

Modifications Committee unanimously recommended for approval at Dec. 3rd 2009 Modifications Meeting (#25) Subject to further investigation of wording, full costs &

implementation Insufficient information available for FRR

3

Page 4: Short Term Testing Mod 65_08 Modification Committee 25 th November 2010

Mod 65_08 Application for Short Term Test Status

Application for Short Term Test status Subject to approval by TSO Generator does not make any submission to the Market Operator. TSO approval for single contiguous number of Trading Periods in a single

Trading Day is required. Can be approved any time up until the end of the relevant Trading Day.

Short Term Test status must: Last at least 4 Trading Periods in a given Trading Day. If spanning two Trading Days, be submitted for each Trading Day.

Units under Short Term Test Variable Price Makers, Variable Price Takers, Pumped Storage,

Interconnector Units, Demand Side Units, IRCU and Autonomous Units cannot have Short Term Test status.

If Unit has Short Term Test status, it cannot be considered as Under Test.

© EirGrid & SONI, 2009.4

Page 5: Short Term Testing Mod 65_08 Modification Committee 25 th November 2010

Mod 65_08 Submission and Publication Requirements

Participant to provide COD for all Price Maker Generator Units, even if they

have Under Test status (allows for within day change to Short Term Test).

TSO to provide (Ex-Post): TEST dispatch instruction and TSTO dispatch

instruction for each Generator Unit in the relevant Trading Day.o To the Market Operator by 14:00 on TD+1.o Market Operator to publish Short Term Test Notifications as submitted

by the relevant TSO by 14:00 on TD+1.

© EirGrid & SONI, 2009.5

Page 6: Short Term Testing Mod 65_08 Modification Committee 25 th November 2010

Mod 65_08 Impacts on MSP Software

Calculation of Availability and Minimum Stable

Generation for Price Makers

– Availability = Minimum Stable Generation = DQ during Short Term Test.

Calculation of Schedule Demand for Ex Post MSP

Software Runs

– Add Short Term Test status where ‘Under Test’ is referenced.

Calculation of MSQs for use in Settlement

– MSQ=DQ during Trading Periods where a Unit has Short Term Test

status.

© EirGrid & SONI, 2009.6

Page 7: Short Term Testing Mod 65_08 Modification Committee 25 th November 2010

Mod 65_08 Impacts on MSP Software

© EirGrid & SONI, 2009.7

100

200Short Term Test status

80

MSP Scheduling(between Min Avail

And Max Avail)

MSP Scheduling(between Min Avail

And Max Avail)

MSP Scheduling fixed to DQ during Short TermTest Trading Periods

Availability

Minimum Stable

Generation

Dispatch

Quantity (DQ)

Page 8: Short Term Testing Mod 65_08 Modification Committee 25 th November 2010

Mod 65_08 Settlement

No Start Up Cost recovered during Short Term Test period

No Make Whole Payments apply during periods of Short Term Test status

MSQ=DQ during Short Term Test period Specific provision: MSQ for PPTGs equal to DQuh during

Short Term Test period Subject to Testing Charges during Short Term Test period No Constraint Payments during Short Term Test period

(as DQ=MSQ) Eligible Availability set as normal

© EirGrid & SONI, 2009.8

Page 9: Short Term Testing Mod 65_08 Modification Committee 25 th November 2010

Mod 65_08 Version 2 • Definition of Short Term Test: May only occur where it is

initiated and proposed by a Participant

• Eligible Availability: EA is set to the Availability Profile for the Generator Unit for duration of Short Term Test

• Only applicable to Predictable Price Makers and Predictable Price Takers

• TEST and TSTO dispatch instructions to indicate the start and the end of the Short Term Test period.

© EirGrid & SONI, 2009.9

Page 10: Short Term Testing Mod 65_08 Modification Committee 25 th November 2010

Impact Assessments

• SEMO: In the region of €467k

• EirGrid and SONI: €60k approximately

10

Page 11: Short Term Testing Mod 65_08 Modification Committee 25 th November 2010

Benefits of Mod 65_08:• Grid Code caters for Within Day Test, but currently not provided

for in SEM. Mod 65_08 would align SEM with Grid Code

• Avoid current workaround

• Avoid Uninstructed Imbalance Payments by Generators

• Submission of COD for Generator Unit Under Test

• Enable a generator to come off test in SEM earlier than the Unit Under Test End date with the relevant System Operator’s approval.

• Greater testing flexibility

© EirGrid & SONI, 2009.11

Page 12: Short Term Testing Mod 65_08 Modification Committee 25 th November 2010

• Thank you

12

Page 13: Short Term Testing Mod 65_08 Modification Committee 25 th November 2010

Scenarios

13

Page 14: Short Term Testing Mod 65_08 Modification Committee 25 th November 2010

Scenarios1. Unit is on and reduces Output for Short Term Test

2. Unit is on and increases Output for Short Term Test

3. Unit is on and goes off for Short Term Test

4. Unit is off and comes on for Short Term Test only

5. Unit comes on for Short Term Test and stays on in market and dispatch

6. Unit comes on for Short Term Test and stays on in market but not in dispatch

7. Unit comes on for Short Term Test and stays on in dispatch but not in market

© EirGrid & SONI, 2009.14

Page 15: Short Term Testing Mod 65_08 Modification Committee 25 th November 2010

Scenario 1 – Unit is on and reduces Output for Short Term

Test

© EirGrid & SONI, 2009.15

Unit is on prior to Short Term Test.

Unit Output is reduced for Short Term Test period:

No Start-Up = No Start Up Costs.

No Make Whole Payments.

MSQ=DQ, hence no Constraint Payment.

Testing Charges due.

No issues with the Modification for this Participant-supplied Scenario.

Out

put

Time

DQ=MSQ

Short Term

Test

Page 16: Short Term Testing Mod 65_08 Modification Committee 25 th November 2010

Scenario 2 – Unit is on and increases Output for Short

Term Test

© EirGrid & SONI, 2009.16

Unit is on prior to Short Term Test.

Unit Output is increased for Short Term Test period:

No Start-Up = No Start Up Costs.

No Make Whole Payments.

MSQ=DQ, hence no Constraint Payment.

Testing Charges due.

No issues with the Modification for this Participant-supplied Scenario.

Out

put

Time

DQ=MSQ

Short Term

Test

Page 17: Short Term Testing Mod 65_08 Modification Committee 25 th November 2010

Scenario 3 – Unit is on and goes off for Short Term Test

© EirGrid & SONI, 2009.17

Unit is on prior to Short Term Test.

As a result of test initiated by the Participant, the Unit goes off for Short Term Test period and returns at the

end of the test:

Participant decision to go off for the Short Term Test, hence no Start Up Costs should be

applicable.

No Make Whole Payments.

MSQ=DQ, hence no Constraint Payment.

Testing Charges due during Short Term Test.

No issues with the Modification for this Participant-supplied Scenario.

Out

put

Time

DQ=MSQ

Short Term

Test

Page 18: Short Term Testing Mod 65_08 Modification Committee 25 th November 2010

Scenario 4 – Unit is off and comes on for Short Term Test

only

© EirGrid & SONI, 2009.18

Unit is off prior to Short Term Test.

As a result of a test initiated by a Participant, the Unit comes on for Short Term Test period and goes off at

the end of the test:

Participant decision to come on for the Short Term Test, hence no Start Up Costs should be

applicable.

No Make Whole Payments.

MSQ=DQ, hence no Constraint Payment.

Testing Charges due during Short Term Test.

No issues with the Modification for this Participant-supplied Scenario.

Out

put

Time

DQ=MSQ

Short Term

Test

Page 19: Short Term Testing Mod 65_08 Modification Committee 25 th November 2010

Scenario 5 – Unit stays on

© EirGrid & SONI, 2009.19

Unit is off prior to Short Term Test, with MSQ=DQ=0.

As a result of test initiated by the Participant, the Unit comes on for Short Term Test period:

No Make Whole Payments.

MSQ=DQ, hence no Constraint Payment.

Testing Charges due during Short Term Test.

Unit stays on in the market (MSQ>0) and physically (DQ>0), Start Up Costs not paid but no forced loss.

TSO may dispatch the Unit at the end of the Short Term Test as required. As already ON, no Dispatch

Start will have occurred. Unit will receive Constraint Payments after the test, if applicable (MSQ ≠ DQ).

Out

put

Time

DQ=MSQ

Short Term

Test

Page 20: Short Term Testing Mod 65_08 Modification Committee 25 th November 2010

Scenario 6 – Unit stays on in market

© EirGrid & SONI, 2009.20

Unit is off prior to Short Term Test, with MSQ=DQ=0.

As a result of test initiated by Participant, the Unit comes on for Short Term Test period:

No Make Whole Payments.

MSQ=DQ, hence no Constraint Payment.

Testing Charges due during Short Term Test.

MSQ>DQ after test, hence constrained down.

After the Short Term Test period, the Unit is scheduled in the market (MSQ>0) and is dispatched off (DQ = 0).

TSO may dispatch the Unit at the end of the Short Term Test as required, including dispatching OFF. Unit will receive Constraint Payments (down in this case)

after the test, if applicable.

Out

put

Time

DQ=0

Short Term

Test

MSQ>0

Page 21: Short Term Testing Mod 65_08 Modification Committee 25 th November 2010

Scenario 7 – Unit stays on in dispatch

© EirGrid & SONI, 2009.21

Unit is off prior to Short Term Test, with MSQ=DQ=0.

As a result of test initiated by Participant, the Unit comes on for Short Term Test period:

No Make Whole Payments.

MSQ=DQ, hence no Constraint Payment.

After test, Unit is dispatched up and will receive Constraint Payments – no Dispatch Start is

relevant (no avoidable loss).

Testing Charges due during Short Term Test.

After the Short Term Test period, the Unit is scheduled off in the market (MSQ=0) and is dispatched by the

TSO (DQ>0).

TSO may dispatch the Unit at the end of the Short Term Test as required. Unit will receive Constraint Payments after the test, as in this case (DQ>MSQ

after test).

Out

put

Time

DQ>0

Short Term

Test

MSQ=0

Page 22: Short Term Testing Mod 65_08 Modification Committee 25 th November 2010

Outcome of Scenario Consideration

The definition of a Short Term Test: May only be initiated by a Participant. Agreed by the relevant System Operator.

If the System Operator requires to test a Unit from a Grid Code perspective, this will not be performed via a Short Term Test: Dispatch Instructions will be supplied to match the required test. If a Unit is required to start, a Dispatch Start will be paid (not a Short

Term Test).

Unit will receive Constraint Payments if applicable.

© EirGrid & SONI, 2009.22