DPWandYOU.com | Making a difference, together SHIPLEY’S CHOICE DAM REHABILITATION PROJECT Shipley’s Choice Elementary School September 13, 2018 Larry Mathena – Project Manager Anne Arundel County Dept. of Public Works Preconstruction Community Meeting

Upload: others

Post on 08-Mar-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SHIPLEY’S CHOICE DAM REHABILITATION PROJECT ......Larry Mathena Project Manager Watershed Protection and Restoration Program Anne Arundel County Department of Public Works 2662 Riva

DPWandYOU.com | Making a difference, together

SHIPLEY’S CHOICE DAM REHABILITATION PROJECT

Shipley’s Choice Elementary School September 13, 2018

Larry Mathena – Project Manager Anne Arundel County Dept. of Public Works

Preconstruction Community Meeting

Page 2: SHIPLEY’S CHOICE DAM REHABILITATION PROJECT ......Larry Mathena Project Manager Watershed Protection and Restoration Program Anne Arundel County Department of Public Works 2662 Riva

DPWandYOU.com | Making a difference, together

Agenda

2

1. Project Background

2. Preconstruction Activities

3. Construction Phases & Features

4. Road Closure

5. Planting Plan

6. Construction Schedule

7. Project Updates

8. Questions * Please sign in & grab a handout

Page 3: SHIPLEY’S CHOICE DAM REHABILITATION PROJECT ......Larry Mathena Project Manager Watershed Protection and Restoration Program Anne Arundel County Department of Public Works 2662 Riva

DPWandYOU.com | Making a difference, together

Project Background – Shipley’s Dam

3 • Dam built in 1981

• Seepage & Settlement Issues

• MDE deemed dam unsafe & directs County to remove

• County worked w/ JMT to complete design for Dam Removal

• Construction Contract awarded to Paydirt

Page 4: SHIPLEY’S CHOICE DAM REHABILITATION PROJECT ......Larry Mathena Project Manager Watershed Protection and Restoration Program Anne Arundel County Department of Public Works 2662 Riva

DPWandYOU.com | Making a difference, together

Preconstruction Activities – Overhead Line Relocation on West Benfield Road

4 • Temp. Relocate OH Line around New Culvert

• Street light relocated (Pole to be removed)

• BGE, Comcast, Verizon to relocate lines

• OH lines replaced after Culvert construction

Page 5: SHIPLEY’S CHOICE DAM REHABILITATION PROJECT ......Larry Mathena Project Manager Watershed Protection and Restoration Program Anne Arundel County Department of Public Works 2662 Riva

DPWandYOU.com | Making a difference, together

Construction Phases

5

Phase 1 Culvert Replacement

Phase 2 Shipley’s Dam Removal

• Construction in 2 Phases

• Zoning - R2 - OS

Page 6: SHIPLEY’S CHOICE DAM REHABILITATION PROJECT ......Larry Mathena Project Manager Watershed Protection and Restoration Program Anne Arundel County Department of Public Works 2662 Riva

DPWandYOU.com | Making a difference, together

Phase 1 – Stream Diversion + Erosion & Sediment Control

• Place ESC Features

• Install stream diversion

Page 7: SHIPLEY’S CHOICE DAM REHABILITATION PROJECT ......Larry Mathena Project Manager Watershed Protection and Restoration Program Anne Arundel County Department of Public Works 2662 Riva

DPWandYOU.com | Making a difference, together

Phase 1 – Public Utility Relocations Gas, Water, Force Main, Sanitary/Storm Sewers

• Utility Bypasses

• No interruption in service

• Existing/New Culverts in Red

Page 8: SHIPLEY’S CHOICE DAM REHABILITATION PROJECT ......Larry Mathena Project Manager Watershed Protection and Restoration Program Anne Arundel County Department of Public Works 2662 Riva

DPWandYOU.com | Making a difference, together

Phase 1 – Remove Ex. Culvert + Install New Culvert

New 7’x10’ Concrete Box

Culvert

Page 9: SHIPLEY’S CHOICE DAM REHABILITATION PROJECT ......Larry Mathena Project Manager Watershed Protection and Restoration Program Anne Arundel County Department of Public Works 2662 Riva

DPWandYOU.com | Making a difference, together

Phase 1 – New Culvert Profile

Page 10: SHIPLEY’S CHOICE DAM REHABILITATION PROJECT ......Larry Mathena Project Manager Watershed Protection and Restoration Program Anne Arundel County Department of Public Works 2662 Riva

DPWandYOU.com | Making a difference, together

Pile Driving & Preconstruction Home Surveys

10 • Home surveys conducted by County’s contractor Seismic Surveys

• Preconstruction survey of homes and other structures – Document existing conditions

• Post-construction survey also conducted

• Need pre/post surveys to help determine if damage occurred during construction

Pile Driving for Culvert • Required due to soft subsoil • 78 Concrete Piles to be used • Daytime work only • Vibration levels will be monitored

Page 11: SHIPLEY’S CHOICE DAM REHABILITATION PROJECT ......Larry Mathena Project Manager Watershed Protection and Restoration Program Anne Arundel County Department of Public Works 2662 Riva

DPWandYOU.com | Making a difference, together

Phase 1 – In Stream Work + Grading

Page 12: SHIPLEY’S CHOICE DAM REHABILITATION PROJECT ......Larry Mathena Project Manager Watershed Protection and Restoration Program Anne Arundel County Department of Public Works 2662 Riva

DPWandYOU.com | Making a difference, together

12

Road Closed between Pixie Dr & Severnside Dr

Phase 1 Road Closure Detour Plan

• W Benfield Road closed 6+ months

• Sign posted 2 weeks before closing

• Paydirt proposing change to Precast Culvert – Could save time

• County Traffic Engineer will consider signal changes (will monitor traffic during construction)

Page 13: SHIPLEY’S CHOICE DAM REHABILITATION PROJECT ......Larry Mathena Project Manager Watershed Protection and Restoration Program Anne Arundel County Department of Public Works 2662 Riva

DPWandYOU.com | Making a difference, together

• Install Filter Logs + Silt Fence

• Install Haul Road down to stream

• Begin removal of dam embankment

Phase 2 Dam Removal

Oak Stump Dr Cul-de-Sac

Shipley’s Choice Dam

Page 14: SHIPLEY’S CHOICE DAM REHABILITATION PROJECT ......Larry Mathena Project Manager Watershed Protection and Restoration Program Anne Arundel County Department of Public Works 2662 Riva

DPWandYOU.com | Making a difference, together

Phase 2 Dam Removal

• Earth fill from Dam placed along east hillside

• Drain along slope to intercept runoff

• Bear Branch channel reestablished after outlet pipe removal

Page 15: SHIPLEY’S CHOICE DAM REHABILITATION PROJECT ......Larry Mathena Project Manager Watershed Protection and Restoration Program Anne Arundel County Department of Public Works 2662 Riva

DPWandYOU.com | Making a difference, together

Phase 1 & 2 – Planting Plan

• Seed & Plant disturbed areas

• 141 Trees

• 493 Shrubs

• 1676 Live Stakes

Page 16: SHIPLEY’S CHOICE DAM REHABILITATION PROJECT ......Larry Mathena Project Manager Watershed Protection and Restoration Program Anne Arundel County Department of Public Works 2662 Riva

DPWandYOU.com | Making a difference, together

Tentative Construction Schedule

16 • Oct 2018 Ph 1 Construction begins w/ Erosion & Sediment Control Utility Relocations/Road Closure

• Winter Ph 1 Culvert Installation

• Spring 2019 Ph 1 Culvert completed/Road Opened

• Summer Ph 2 Dam removal begins

• Late Fall 2019 Ph 2 Construction complete

* Paydirt will provide Construction Schedule by late Sep

Page 17: SHIPLEY’S CHOICE DAM REHABILITATION PROJECT ......Larry Mathena Project Manager Watershed Protection and Restoration Program Anne Arundel County Department of Public Works 2662 Riva

DPWandYOU.com | Making a difference, together

Project Updates

17 • Monthly Updates on the Shipley’s Dam Project are emailed to the following HOAs & Organizations:

- Shipley’s Choice HOA & Community Assoc, Greater Severna Park Council, Point Field Landing Community Assoc, Crain West, Ben Oaks/Severn River Assoc

• Monthly Project Update will include: - Updated construction schedule, latest activities, road closure updates

• Project Updates may also be found on the County’s Website - For web address, see Handout

Page 18: SHIPLEY’S CHOICE DAM REHABILITATION PROJECT ......Larry Mathena Project Manager Watershed Protection and Restoration Program Anne Arundel County Department of Public Works 2662 Riva

DPWandYOU.com | Making a difference, together

Contact Info (on Handout)

Larry Mathena Project Manager Watershed Protection and Restoration Program Anne Arundel County Department of Public Works 2662 Riva Road, MS 7217 Annapolis, MD 21401 (410) 222-7908 [email protected]

Alternate POC: Greg LeBlanc Same Address (410) 222-0043 [email protected]

Page 19: SHIPLEY’S CHOICE DAM REHABILITATION PROJECT ......Larry Mathena Project Manager Watershed Protection and Restoration Program Anne Arundel County Department of Public Works 2662 Riva

DPWandYOU.com | Making a difference, together

Questions or Comments? 19

Page 20: SHIPLEY’S CHOICE DAM REHABILITATION PROJECT ......Larry Mathena Project Manager Watershed Protection and Restoration Program Anne Arundel County Department of Public Works 2662 Riva

DPWandYOU.com | Making a difference, together

Bureau of Utility Operations

24-Hour Emergency Water Services: (410) 222-8400 Billing Inquiries: (410) 222-1144

Bureau of Waste Management Services

Bulk Trash Service/Curbside Collections: (410) 222-6100

Bureau of Highways

Northern District: (410) 222-6120 Central District: (410) 222-7940 Southern District: (410) 222-1933 Traffic Lights/Signs: (410) 222-1940

Bureau of Engineering

General Inquiries: (410) 222-7500