shine iron ore project - der.wa.gov.au
TRANSCRIPT
Works Approval Application
Shine Iron Ore Project
Processing or beneficiation of metallic or non-metallic ore
Works Approval
Mount Gibson Mining Limited
September 2020
Document No.:
Works Approval Application
Prepared for
Department of Water & Environmental Regulation
8 Davidson Terrace
JOONDALUP
Western Australia 6027
September 2020
Works Approval Application
Table of Contents 1.0 Premises Details 6
1.1 Occupier of the Premises 6 1.2 Name and Location Details of the Premises 6 1.3 Legal Land Description 6 1.4 Prescribed Premise Category 6
2.0 Description of Activity 10 2.1 Project Overview 10 2.2 Outline of Prescribed Activities 10 2.3 Crushing and Screening Plant 10
2.3.1 Summary of Environmental Controls within the Prescribed Premises 10 2.3.2 Major Infrastructure 11
2.4 Fuel Farm and Workshops 11 2.4.1 Summary of Environmental Controls within the Prescribed Premises 11
3.0 Other Approvals 17 3.1 Part IV Environmental Protection Act 1986 17 3.2 Part V Environmental Protection Act 1986 17 3.3 Other Decision Making Authorities 17 3.4 Other Legislation and Guidance Material 18
4.0 Existing Environment 19 4.1 Climate 19 4.2 Topography 19 4.3 Soil Quality, Stability and Land Systems 19
4.3.1 Soils 19 4.3.2 Land Systems 20
4.4 Surface Water 20 4.5 Groundwater 20 4.6 Air Quality 20 4.7 Vegetation 21
4.7.1 Vegetation Associations 21 4.7.2 Floristic Community Types 21
4.8 Fauna 22 4.9 Aboriginal Heritage Sites 22 4.10 Potentially Sensitive Receptors 22
5.0 Assessment of Environmental Risks from Emissions and Discharges 25 5.1 Risk Identification 25 5.2 Risk Assessment 25
6.0 Environmental Objectives, Legislative Standards and Measurement Criteria 29 7.0 References 32
List of Tables
Table 1 Abbreviations
Table 2 Prescribed Premises Category from Schedule 1 of the Environmental Protection Regulations
1987
Table 3 Environmental Approvals Schedule pertaining to the prescribed premises
Table 4 Vegetation Associations within SIOP (Department of Agriculture and Food Western
Australia, 2007)
Table 5 Summary of Floristic Community Types (FCT’s) impacted by plant (Woodman, 2012)
Table 6 Impacts of operating the crushing and screening plant under normal and abnormal operating
conditions
Table 7 Descriptors for Likelihood
Table 8 Descriptors for Consequence
Table 9 Risk matrix
Table 10 Risk Assessment
Table 11 Environmental Objectives, Legislative Standards and Measurement Criteria
Works Approval Application
List of Figures
Figure 1 Project Regional Location
Figure 2 Prescribed Premises Footprint
Figure 3 Process Plant Layout
Figure 4 Crushing and Screening Flowchart
Figure 5 ROM and Crushing and Screening Precinct
Figure 6 Fuel Farm Layout
Figure 7 Prescribed Premise Disturbance Footprint on Floristic Community Types
Works Approval Application
Table 1 Abbreviations
AHD Australian Height Datum
API Assessment on Proponent Information
AWS Automatic Weather Station
AS Australian Standard
BIF Banded iron Formation
BOM Bureau of Meteorology
DRF Declared Rare Flora
DAWE Department Agriculture, Water and the Environment
DBCA Department of Biodiversity, Conservation and Attractions
DWER Department of Water and Environmental Regulation
DMA Decision Making Authority
DMIRS Department of Mines, Industry Regulation and Safety
EP Act Environmental Protection Act 1986
EPBC Act Environment Protection and Biodiversity Conservation Act 1999
EP Regs Environmental Protection Regulations 1987
EPA Environmental Protection Authority
FCT Floristic Community Type
IBRA Interim Biogeographic Regionalisation for Australia
GBG Gindalbie Metals Limited
OES Outback Ecology Services
RIWI Rights in Water Irrigation Act 1914
ROM Run of Mine
SIOP Shine Iron Ore Project
SMU Soil Mapping Units
SWL Standing Water Level
WAA Works Approval Application
Works Approval Application
Page | 6 MGM Works Approval Submission
1.0 Premises Details
1.1 Occupier of the Premises
Mount Gibson Mining Ltd (MGM)
Level 1, 2 Kings Park Road
West Perth, Western Australia 6005
ABN: 32 074 575 885
1.2 Name and Location Details of the Premises
Name:
Shine Iron Ore Project (SIOP) Crushing and Screening (C&S) Plant
Location:
The SIOP Crushing and Screening plant (‘prescribed premises’) is located within the Mid-West Region of
Western Australia, approximately 60 km south-east of Yalgoo (Figure 1). The SIOP is located within
three mining leases (M59/406, M59/421 and M59/731), of which MGM holds full iron ore rights. Minjar
Gold owns leases.
Description of the premises:
The Crusher will be fed from stockpiles on the ROM via a Front End Loader (FEL). Feed rate for plant will
be capped at seven hundred and fifty wet metric tonnes per hour (750 wmt/h). The primary crusher will be
a single toggle jaw crusher. Screening of primary crushed feed will produce a lump product (+6.4mm/-
32mm) and a fines product (+0mm/-6.3mm). All oversize material will go to a secondary cone crusher
with a Closed Side Setting. Feed from the secondary crusher will go to a final product screen producing a
final lump and fines product. Stockpiles of lump and fines products will be in the order 15,000 wmt each.
Works Approval:
A submission for a Works Approval (Crushing and Screening Plant) has previously been submitted by
MGM and approved by DWER in 2014 (W5670/2014/1). This approval has since lapsed given the project
being undeveloped and the site placed into care and maintenance under Mining Act provisions.
MGM is making the current submission without any substantive changes to the scope originally approved,
nor the environmental management requirements.
1.3 Legal Land Description
The prescribed premises will be located entirely on Mining Lease M59/406 and is depicted in Figure 2.
The prescribed premises is a subset of both the mining tenement and development envelope approved
by Statement 940.
1.4 Prescribed Premise Category
This Works Approval application (WAA) is for a ‘Prescribed Premises’ Category Number 5 and 73 under
Schedule 1 of the Environmental Protection Regulations 1987 (Table 2).
Works Approval Application
Page | 7 MGM Works Approval Submission
Table 2 Prescribed Premises Categories from Schedule 1 of the Environmental Protection Regulations 1987
Category
Number
Category Description Category Production or Design
Capacity
Production or design capacity
5 Processing or beneficiation of
metallic or non-metallic ore 50, 000 tonnes or more per year Up to 3,000,000 tonnes per annum
73 Bulk storage of chemicals etc:
premises on which acids, alkalis
or chemicals that (a) contain at
least one carbon to carbon bond
and (b) are liquid at standard
temperature and pressure
1,000 m3 in aggregate Up to 200,000 L per annum
Works Approval Application
Page | 8 MGM Works Approval Submission
Figure 1 Project Regional Location
Works Approval Application
Page | 9 MGM Works Approval Submission
Figure 2 Prescribed Premises Footprint
Works Approval Application
Page | 10 MGM Works Approval Submission
2.0 Description of Activity
2.1 Project Overview
The SIOP lies within the Shire of Yalgoo and is located within Badja Station, a pastoral lease owned and managed by Greg and Cindy Payne. The pastoral lease area is subject to mining tenements held by Minjar Gold, with full iron ore rights held by MGM. The mine site area is isolated with the closest town being Yalgoo, approximately 60 km northwest. The nearest residence is Badja Homestead, approximately 30 km to the northwest. SIOP is a project designed to produce at least 8.2 Mtpa of hematite iron ore resource, mined at a rate of up to 3 Mtpa from a surface pit that will result in a land disturbance area of approximately 200 ha. The project will require the mining of three small pits located within the SIOP disturbance footprint. The prescribed premise will be located within this footprint, on the Run of Mine (ROM) pad (Figure 2).
The life of SIOP will depend on the market demand for different grades and types of iron ore products.
The production rate for the operation will be up to 3 Mt of crushed hematite ore per annum. The likely life
of the operations, based on the current resource forecast and with a relatively slow supply rate to the
market, may be up to 6 years. Therefore, this works approval (and ultimately licence) is for the plant to be
operating for a period of up to 6 years, inclusive.
2.2 Outline of Prescribed Activities
This Works Approval Application has been submitted to cover the environmental approval of the following
prescribed premises, as per the Environmental Protection Regulations 1987:
• Processing or beneficiation of metallic or non-metallic ore (Category 5); and
• Bulk Storage of chemicals (Category 73).
The scope of the prescribed activity will include processing or beneficiation related activities that are
undertaken within the prescribed premises. This includes iron ore that is loaded into the plant, processed
through the crushing circuit, conveyed to final product stockpiles and minor supporting infrastructure such
as fuel and water that is required for the operation of the plant (Figure 3 and Figure 4). It does not include
transportation on access roads that are outside of the prescribed premises boundary and resident on
mining tenements and approved by a mining proposal.
2.3 Crushing and Screening Plant
The prescribed premise as described in this application is to crush and screen iron ore (generally hematite material) that will be extracted as part of SIOP. The plant will consist of a primary and secondary crushing circuit, product screening and lump and fines product stockpiles (Figure 3 and Figure 4).
2.3.1 Summary of Environmental Controls within the Prescribed Premises
The prescribed premises will incorporate a range of environmental controls within the processing system, including:
• Bunding of reagents to minimise the potential impacts on soil and groundwater resources;
• Stormwater controls to separate potentially contaminated stormwater from uncontaminated
stormwater;
• Dust suppression sprays on transfer points at conveyors and stockpiles; and
• Minimising light overspill.
Works Approval Application
Page | 11 MGM Works Approval Submission
The environmental risks and control measures are outlined in more detail in Section 5.
2.3.2 Major Infrastructure
2.3.2.1 Water Supply
Water for the prescribed premises will be sourced from licensed abstraction bores at the SIOP mine site.
MGM has a current licence (GWL179363) which allows up to 950,000 kL of water from abstraction bores
to be utilised for onsite activities as per the following assignments:
• Construction – 225,000 kL
• Operation – 250,000 kL annually
• Dust suppression and contingency – 475, 000 kL annually
As mining below the water table is not yet anticipated and produced water will be consumed on site, a
Works Approval and Licence under Part V of the EP Act Schedule 1, Category 6 (Mine Dewatering) will
not be required. Water from two production bores has been produced at site according to the GWL held
by MGM and in relation to an approved Groundwater Operating Strategy.
2.3.2.2 Power Supply and Requirements
During operation of the prescribed premises, power will be generated by on-site diesel generators. No
gas pipelines are available near site, making the use of diesel generators the most economically viable
option to supply power. Diesel generators will be located within a specified bunded area within the
prescribed premises.
2.4 Fuel Farm and Workshops
MGM propose to move the Fuel Farm (FF) currently licenced (DGS021414) and located at the MGM
Extension Hill site, to the Shine site. The farm is proposed to be located within the crushing and loadout
precinct (Figure 5). The FF comprises 2 tanks for storage of diesel (55, 000 L and 110, 000 L) and will be
fully bunded (Figure 6).
Hydrocarbons and assorted chemicals will also be appropriately stored in the workshop areas and any
potential contamination from spills managed through hydrocarbon collection and separation, bunding and
spill response controls.
2.4.1 Summary of Environmental Controls within the Prescribed Premises
A summary of environmental controls is contained within the Shine Site Work Instruction (SWI) for fuel
storage and includes the following:
• Site induction;
• Surface Water Management Procedure and Site Work Instruction;
• Site emergency procedure;
• Safety Eye Wash station
• Check suction points and hoes for leaks prior to discharge;
• Ignition sources must be at least 50 m away from both tanks;
• Traffic Management Plan;
• Two Way Radio;
• Appropriate PPE at all times (gloves, eye protection etc);
• Fully bunded area around the main fuel storage tanks to limit potential contamination from spills and
leaks
• Tyre bay, HV & LV workshop, wash down pad equipped with an appropriate oil separation system;
Works Approval Application
Page | 12 MGM Works Approval Submission
• Surface water drainage system designed to culminate in 2 x stormwater storage ponds located on the
southeast corner of the crushing precinct (Figure 5); and
• Appropriate signage within the FF and workshop areas.
The environmental risks and control measures are outlined in more detail in Section 5.
Works Approval Application
Page | 13 Doc Ref: 12217_4
Figure 3 Process layout for crushing and screening plant
Works Approval Application
Page | 14 Doc Ref: 12217_4
Figure 4 Project Crushing and Screening Flowchart
ROM PAD
ORE
STOCKPILE
PRIMARY
CRUSHER SCREEN FEED
CONVEYOR PRODUCT
SCREEN
SECONDARY CRUSHER
FEED CONVEYOR
SECONDARY
CRUSHER
LUMP
TRANSFER
CONVEYOR
FINES
TRANSFER
CONVEYORS
FINES
PRODUCT
STOCKPILE
LUMPS
PRODUCT
STOCKPILE
UNCRUSHED
PRODUCT
PRODUCT
SCREEN
LUMPS/FINES
BLEND
Works Approval Application
Page | 15 Doc Ref:
MGM Works Approval Application
Figure 5 ROM and crushing precinct
Works Approval Application
Page | 16 Doc Ref:
MGM Works Approval Application
Figure 6 Fuel farm layout
Works Approval Application
Page | 17 Doc Ref:
MGM Works Approval Application
3.0 Other Approvals
3.1 Part IV Environmental Protection Act 1986
The environmental impact assessment for SIOP was assessed at the level of Assessment on Proponent
Information (API) by the Environmental Protection Authority (EPA), with the report released in May 2013
(Report 1472). Gindalbie Metals Ltd (GML) received ministerial approval for the project on 25 June 2013
(Ministerial Statement No. 940) and MGM acquired the project from Gindalbie Metals Limited in March
2014 and subsequently advised the EPA of the change to proponency.
Since this time, MGM have submitted a s45C amendment (reduction to development area from 646 ha to
595 ha given excision of land for Minjar Gold tailings dam extension) and a new Ministerial Statement
released (MS 1132) which also amended the time authorisation limit until June 2023.
The ministerial statement did not include any conditions directly relating to factor or aspect management
at the prescribed premises.
3.2 Part V Environmental Protection Act 1986
Additional supporting facilities, such as accommodation village and its wastewater treatment plant, will be
provided from existing regional facilities including through commercial arrangements with neighbouring
approved mine site facilities owned by Minjar Gold Pty Ltd or Golden Grove Pty Ltd.
As the prescribed premises will be located entirely within the approved Ministerial Statement envelope, a
Native Vegetation Clearing Permit will not be required.
3.3 Other Decision Making Authorities
Other Decision Making Authorities (DMAs) for the project include the Department of Water and
Environmental Regulation (DWER), Department of Mines, Industry Regulation and Safety (DMIRS),
Department of Planning, Lands and Heritage (DPLH) and the Department of Biodiversity, Conservation
and Attractions (DBCA). Table 3 provides a summary of approvals required and delivery schedule.
Table 3 Environmental Approvals Schedule pertaining to the prescribed premises
Agency Approval Required Approval Date
DWER 5C Licence to abstract water Approved GWL 179363 up to 950,000klpa
DAWE Environment Protection & Biodiversity Conservation (EPBC) Approval (Reference Number 2012/6331)
Not controlled
DMIRS Mining Proposal Reg ID 50930 was approved 30 September 2014. An addendum for revised design layout will be made in 2020.
DPLH Section 18 Application (Ref. No. 34-17909) A Section 18 Ministerial consent for registered sites on the SIOP was issued 21 May 2012.
DBCA Licences to Take Fauna;
• Shield-backed Trapdoor Spider (SBTS)
• Western Spiny-tailed Skink (WSTS)
• Malleefowl (MF)
To be obtained as required. Note the known SBTS taxon for the site has been de-listed. WSTS do not occur within the disturbance footprint of the premises. MF mounds are authorised for disturbance according to MS940 and there are none known within the prescribed premises footprint.
Works Approval Application
Page | 18 Doc Ref:
MGM Works Approval Application
Other approvals not deemed necessary for the project under Part V of the EP Act (1986) include:
- Dewatering (Category 6) – above water table mining proposed and/or forecast on-site water
consumption;
- Sewage (Category 85) – using a nearby established camp;
- Landfill (Category 64) – expected not to trigger the 100 m3 pa threshold, therefore no works
approval or licence will be applied for. As a comparator, the MGM Extension Hill operation was
significantly larger than what is proposed at Shine and, in 2016, it generated only 69 tonnes of
waste for the year (equivalent to ~55 m3) to be contained within landfill (AACR 2016, Licence
Number L8495/2010/2). MGM will contain any waste generated onsite within landfill cells located
within the waste dump proper. The activity has been addressed in Mining Proposal Reg ID
40384.
3.4 Other Legislation and Guidance Material
The following guidance and legislation material also may apply is specific to this WAA:
• Environment Protection and Biodiversity Conservation Act 1999;
• Environmental Protection Act 1986;
• Mining Act 1978;
• Aboriginal Heritage Act 1972;
• Biodiversity Conservation Act 2018; and
• Rights in Water and Irrigation Act 1914.
Works Approval Application
Page | 19 Doc Ref:
MGM Works Approval Application
4.0 Existing Environment
4.1 Climate
The climate in the area of SIOP is classed as semi-arid with a mean annual rainfall of approximately
258 mm with monthly average rainfall as recorded at the Yalgoo Bureau of Meteorology (BoM) automatic
weather station (AWS) (BoM, 2012).
This region experiences a hot Mediterranean climate, characterised by a rainfall regime similar to that of
the south-west region of WA, that is, the majority of rainfall received occurs from May – August (BoM,
2012). Annual evaporation far exceeds annual rainfall throughout the region although some minor
subsurface recharge does occur during intense rainfall events (BoM, 2012).
Average daily minimum and maximum temperatures during the warmer months (November – April) are
18 °C and 34 °C respectively, while in the cooler months (May – October) average daily minimum and
maximum temperatures are 8 °C and 22 °C respectively (BoM, 2012).
Extreme rainfall events (i.e. a 1-in-100-year, 72-hour rainfall event) can be expected to generate more
than 160 mm, while a 1-in-20-year, 72-hour rainfall event can generate over 100 mm of rain (BoM, 2012).
The prevailing winds at the minesite are (BoM, 2012):
• Summer - the dominant wind direction is from the south south-east through to the south south-west;
• Autumn - the dominant wind direction is from the east;
• Winter - the dominant wind direction is from the south-east and east south-east; and
• Spring - the dominant wind direction is from the south.
4.2 Topography
The SIOP area covers exposed Banded Iron Formations (BIF) and greenstone ranges that form part of
the Yalgoo-Singleton Greenstone Belt. The BIF at SIOP forms a series of isolated peaks, hills and ranges
in a generally topographically subdued regional landscape (Prodemas, 2008).
The mine site occurs on the Karara formation, which is approximately 440 m Australian Height Datum
(AHD) (Prodemas, 2008). The upper slopes of the side of the SIOP ridge are steep at 20° to 25°. The
foothills and plains are generally of less than 5° slopes (Prodemas, 2008). Surrounding the hills are
relatively level plains (300 m to 350 m AHD). The lowest points in the local landscape are two clay pans
at 300 m AHD (Prodemas, 2008).
4.3 Soil Quality, Stability and Land Systems
4.3.1 Soils
Prior to MGM acquiring the project, Outback Ecology Services (OES) were commissioned by GML in
2009 to conduct a baseline assessment of surface soils within the SIOP area. Soils were re-interpreted
from the OES (2009) study based on review of the evolutionary history of the area and soil morphological
examination of OES (2009) photographs by Soil Water Consultants in their report titled “Shine Deposit
Waste Rock Landform Design and Preliminary Closure Criteria” (Soil Water Consultants, 2013).
At least three distinct Soil Mapping Units (SMUs) were identified within the project area that corresponds
to broad landform features of the typical Tallering land system sequence (Soil Water Consultants, 2013):
1. Gravelly red/brown loams over ironstone of the ridges (SMU 1);
Works Approval Application
Page | 20 Doc Ref:
MGM Works Approval Application
2. Deep red / brown clay loams of the slopes (SMU 2), further subdivided into:
a. > 40% gravel (2a – upper slopes);
b. < 40% gravel (2b – lower slopes); and
3. Deep red sands of the plains (SMU 3).
The prescribed premise is located within SMU2.
4.3.2 Land Systems
The SIOP area is located over six land systems, with the Tallering and Tealtoo being the dominant land
systems (OES, 2009). The Tallering land system represents the prominent ridges and hills and includes
the proposed SIOP pit and waste dump footprints (OES, 2009). The Tealtoo land system represents the
gently undulating plains of which the supporting infrastructure resides on (Payne et al, 1998).
4.4 Surface Water
The SIOP area sits within the 41,880 km2 Yarra Yarra Catchment Basin in the Mid-West region of
Western Australia and is noted to lack a defined river system (CRE, 2009). It is characterised by a
continuous range of hills surrounding a series of interconnecting, ephemeral salt lakes. There are no
permanent surface water features, gazetted water courses or wetlands in or near the SIOP area (CRE,
2009).
The following geomorphology and drainage aspects were identified:
• Minor gullies from the SIOP location down to the lowland areas; and
• Minor drainage paths flowing northwest from SIOP.
Existing catchment areas at SIOP and the expected direction of water flows (prior to the construction of
engineered structures including culverts, diversion channels and sediment basins for surface water and
stormwater management purposes) are detailed within the “Desktop Surface Water and Stormwater
Management Study for the Shine Project” by Pritchard Francis Consulting in 2012. In accordance with
the report’s recommendations, appropriately sited stormwater diversion channels will be constructed to
ensure that the prescribed premises footprint, of approximately 0.28 km2, does not contribute to the
potential impact of any downstream receptors.
4.5 Groundwater
The depth of wet samples in exploration holes and production bores indicate that the standing water level
(SWL) is 53 to 60 m below ground level (mbgl) at the SIOP (Rockwater, 2008). There is a low
groundwater mound centred on the BIF ridge indicating that recharge occurs along the ridge and there is
lateral flow of groundwater into adjoining mafic and sedimentary rocks (Rockwater, 2008).
The rate of flow is restricted by the low permeability of the hanging wall rocks (Rockwater, 2008). Given
the large distance to the water table and the low permeability of the groundwater between sedimentary
rocks, it provides a suitable buffer for ingress into groundwater and thus a low risk is posed by the
prescribed premises.
4.6 Air Quality
The SIOP is located within a semi-arid environment, with a mean annual rainfall of approximately
258 mm, as recorded at the Yalgoo Bureau of Meteorology (BoM, 2012). Soils in the area are associated
with that of a rural environment, relatively well covered with vegetation or are of stony composition.
Works Approval Application
Page | 21 Doc Ref:
MGM Works Approval Application
There are no existing potential sensitive receptors in the vicinity of the prescribed premises. The nearest
residence is a homestead located on Badja Station (owned and managed by GML with one permanent
GML resident only) and is approximately 30 km northwest of SIOP. There is no site specific or site
representative air quality data for SIOP.
The location of the prescribed premises is within the designated footprint of the SIOP ROM pad, which
has sufficient separation to SIOP active mining areas. Given the remoteness of the premises, there is
low risk of any significant impact to air quality for any persons not involved with the project.
4.7 Vegetation
Vegetation within the prescribed premises (up to 28 ha) will be cleared as required, within the approved
disturbance footprint granted as per Ministerial Statement 940. There are seven broad vegetation
communities identified within SIOP, being;
• Scrub of Acacia aneura/A.ramulosa over Thryptomene decussata,
• Open mallee of Eucalyptus loxophleba over dwarf scrub of Ptilotus obovatus,
• Low woodland of Acacia aneura/A. ramulosa over mixed dwarf scrub,
• Low woodland of mixed Acacias over low scrub of Drummondita fulva (P3) /Stylidium longibracteatum
on BIF,
• Open scrub of Acacia assimilis /A. ramulosa over mixed dwarf scrub on breakaway,
• Low woodland of Acacia effusifolia very open low grassland of Monachather paradoxus and
• Open scrub of Acacia grasbyi over Aluta aspera subsp. Hesperia /Thryptomene costata (Botanica
Consulting, 2012).
4.7.1 Vegetation Associations
The SIOP is located within the Avon Wheatbelt Interim Biogeographic Regionalisation for Australia (IBRA)
region, and there are two Vegetation Associations reported under Beard (1976) Vegetation Association
represented by Yalgoo 202 and Yalgoo 420 at the site. Both of these vegetation associations are well
represented in the region and are detailed in Table 4.
Table 4 Vegetation associations within SIOP (Department of Agriculture and Food Western Australia, 2007)
Vegetation
Association
Vegetation Description Pre-European Extent
(hectares)
Current Extent
(hectares)
Remaining (%)
Yalgoo 202 Shrublands; mulga and Acacia
quadrimarginea scrub 45,051.15 45,051.15
100
Yalgoo 420 Shrublands; bowgada and jam scrub 457,001.83 457,001.83 100
4.7.2 Floristic Community Types
Woodman Environmental Consulting (WEC, 2012) completed an assessment of Floristic Community
Types (FCTs) located within the regional setting of the SIOP. The FCTs that will be cleared by the
prescribed premises are described in Table 5. It should be noted that these FCT’s are restricted to the
total area permitted for clearing under Ministerial Statement 940.
Works Approval Application
Page | 22 Doc Ref:
MGM Works Approval Application
Table 5 Summary of Floristic Community Types (FCT’s) cleared by proposed premise footprint (Category 5)
FCT Description of FCT
FCT 12
(98.3 ha
clearing)
Tall shrubland of mixed Acacia species including Acacia ramulosa var. ramulosa, A. sibina and A. effusifolia over
mid open shrubland to mid sparse shrubland of mixed species including Aluta aspera subsp. hesperia,
Philotheca brucei subsp. brucei, Eremophila latrobei subsp. latrobei, E. clarkei, E. forrestii subsp. forrestii over
low isolated clumps of ferns of Cheilanthes sieberi over low isolated clumps of grasses of Monachather
paradoxus on red, brown or red-brown silty clay loam or silty loam on flats to lowerslopes.
FCT 25
(12.5 ha
clearing)
Tall shrubland to tall open shrubland of mixed species including Acacia ramulosa var. ramulosa, A.
tetragonophylla, A. effusifolia and Hakea recurva subsp. recurva with low isolated clumps of trees of Callitris
columellaris and/or Eucalyptus spp. over low sparse shrubland of mixed species including Eremophila georgei
over low isolated clumps of grasses of Monachather paradoxus on red or orange sandy loam or clay loam on
flats to midslope.
Neither of these Floristic Community Types represent components of the Priority Ecological Community
(PEC) as mapped by Woodman Environmental Consulting Pty Ltd (2012) (Figure 7). Clearing of FCTs
forming part of the PEC has been approved un the MS and will occur through the development of the
main mining pit and part of the waste rock dump (Figure 7).
4.8 Fauna
As part of the Environmental Impact Assessment process for SIOP, Bamford Consulting Ecologists (BCE)
was commissioned to conduct a desktop review and a detailed fauna assessment of the SIOP area.
Surveys were conducted in 2008, 2011, 2012 and recently in August 2020, including targeted surveys for
the Western Spiny-tailed Skink (Egernia stokesii badia), Malleefowl (Leipoa ocellata) and what was
identified at the time as Shield-backed Trapdoor Spider (Idiosoma nigrum).
No conservation significance fauna were identified to be located within the prescribed premises footprint
(BCE, 2012). Records of fauna within the development envelope at site have been updated in 2020
(BCE, 2020). However, where MGM records the location of significant fauna and habitats prior to ground
disturbance, these shall be taken into account during construction and operation activities with the
objective of avoiding these areas. This is to be managed through an internal management process,
Ground Disturbance and Approval Procedure.
4.9 Aboriginal Heritage Sites
Section 18 consent (Ref. No. 34-17909) for the project was received on the 21st May 2012 under the
Aboriginal Heritage Act 1972 to disturb registered sites for the purpose of this Project.
The prescribed premises footprint does not co-occur nor disturb the ground on any identified heritage site.
Elsewhere, mining domains (main pit) co-occur with sites covered by the S18 consent.
4.10 Potentially Sensitive Receptors
The closest non-mining sensitive receptor to the mine site is approximately 30 km northwest of SIOP,
being Badja Homestead (owned and managed by Greg and Cindy Payne). The Golden Grove mining
operation and village are approximately 7 km from SIOP.
Works Approval Application
Page | 23 Doc Ref:
MGM Works Approval Application
No Drinking Water Source Areas, sensitive premises or other industries will be affected by the prescribed
premises. Traffic moving along the Minjar Haul Road are mining fleet operating with approval of the
tenement holders for the purpose of approved mining operations.
Works Approval Application
Page | 24 Doc Ref:
MGM Works Approval Application
Figure 7 Prescribed Premise Disturbance Footprint on Floristic Community Types
Works Approval Application
Page | 25 Doc Ref:
MGM Works Approval Application
5.0 Assessment of Environmental Risks from Emissions and
Discharges
5.1 Risk Identification
This section details the potential environmental effects from the prescribed premises and its associated
infrastructure.
Table 6 provides a summary of the potential environmental impacts of the prescribed premises outside of
the boundary under normal and abnormal (e.g. where one or more controls fail) operating conditions.
Table 6 Impacts of the operating prescribed premises under normal and abnormal operating conditions
Activity
Possib
le E
mis
sio
ns
Opera
tio
n C
onditio
n
Environmental Factors
Air D
egra
datio
n
Surf
ace W
ate
r
Gro
undw
ate
r
Conta
min
atio
n
Soil
Conta
min
atio
n
Excess N
ois
e
Excess L
ight
Vegeta
tio
n D
egra
dation
Impacts
on F
auna
Com
munity Im
pacts
Clo
sure
Operation of
Crushing and
Screening
Plant
Air Emission Normal N N N N N N N N N N
Abnormal Y N N N N N Y Y N N
Liquid
Emission
Normal N N N N N N N N N N
Abnormal N Y Y Y N N Y Y N N
Noise
Emission
Normal N N N N N N N N N N
Abnormal N N N N N N N Y N N
Light
Emission
Normal N N N N N N N N N N
Abnormal N N N N N Y N Y N N
Storage and
Use of
Hydrocarbons
Liquid
Emission
Normal N N N N N N N N N N
Abnormal N Y Y Y N N Y Y N N
5.2 Risk Assessment
The risk assessment was undertaken using a process based on AS4360:2004 Risk Assessment and
using definitions and descriptors standardised by GBG’s environmental division for all aspects of
construction and operation. Scales of Likelihood and Consequence are provided as Tables 7 and 8
respectively, whilst Table 9 provides the Risk Matrix.
Works Approval Application
Page | 26 Doc Ref:
MGM Works Approval Application
Table 7 Descriptors for Likelihood
Abbreviation ID Descriptor
Almost
Certain
A Incident is expected to occur on this project, possibly several times
Likely B Incident may easily occur on this project
Possible C Incident has occurred on a similar project
Unlikely D Incident unlikely to occur during this project
Rare E Incident highly unlikely to occur on this project
Table 8 Descriptors for Consequences
Abbreviation ID Descriptor
Insignificant 1 No Impact on baseline environment. Localised to point source.
Minor 2 Localised within site boundaries. Recovery measurable within 1 month of impact.
Moderate 3 Moderate harm with possible wider effect.
Major 4 Significant harm with local effect.
Catastrophic 5 Significant Impact that is widespread, unconfined impact, requiring long-term recovery,
leaving major residual damage.
Table 9 Risk Matrix
Risk Matrix
Likelihood
Consequences
1 2 3 4 5
Almost certain
(A)
HIGH (11) HIGH (16) EXTREME (20) EXTREME (23) EXTREME (25)
Likely
(B)
MEDIUM (7) HIGH (12) HIGH (17) EXTREME (21) EXTREME (24)
Possible
(C)
LOW (4) MEDIUM (8) HIGH (13) EXTREME (18) EXTREME (22)
Unlikely
(D) LOW (2) LOW (5) MEDIUM (9) HIGH (14) EXTREME (19)
Rare
(E)
LOW (1)
LOW (3) MEDIUM (6) HIGH (10) HIGH (15)
Works Approval Application
Page | 27 Doc Ref: 12217_4
A risk assessment, as described in Section 5.2, was undertaken to assess the management issues for the environmental factors as described in Table
6. The risk assessment is shown in Table 10 with the correlating management measures that will be implemented to mitigate the operational risks to an
acceptable residual level.
Table 10 Risk Assessment
Item Environmental
Factor
Potential Environmental
Impact
Inherent Risk Risk Management
Residual Risk
L C R L C R
1. Operation of Crushing & Screening Plant
1.1
Air Degradation –
Dust Causing Air
Degradation
Potential for dust produced to
impact air quality B 2 High
▪ No sensitive receptors (accommodation camps, local landholders) within the area.
▪ Dust suppression water at primary crusher dump bin, lump product stockpile and fines product stockpile.
▪ Dust suppression on access roads and ROM area. Dust Management to be in line with SWI.
C 2 Med
1.2
Air Degradation-
Dust Causing
Vegetation
Degradation
Potential for excessive dust to
cause vegetation degradation B 2 High
▪ Dust suppression water at primary crusher dump bin, lump product stockpile and fines product stockpile.
▪ Dust suppression on access roads and ROM area. ▪ Dust Management to be in line with SWI.
C 2 Med
1.3 Excess Light
Light overspill from 24-hour
mining activities, potentially
impacting amenity and native
fauna
C 2 Med
▪ All lighting to be in line with AS4282 – 1997: Control of obtrusive effects of outdoor lighting.
▪ Limit light spill where practicable. ▪ Use of downward-directed lights, shrouded
D 2 Low
1.4 Surface Water
Contamination
Spill of hydraulic oil and
lubricants to the environment,
impacting on vegetation and
downstream and groundwater
environment.
C 2 Med
▪ Surface water management to be in line with Surface Water Management Procedure and Site Work Instruction (SWI)
▪ Appropriate handling and disposal of hydrocarbons as per Storage and Use of Hazardous Substances Procedure.
▪ Appropriate drainage design within crushing precinct terminating in two stormwater detention ponds (southeast corner of the precinct)
D 2 Low
1.5 Noise & Vibration
Noise and vibration from
equipment movement impacting
on the amenity of the
surrounding environment.
B 1 Med ▪ No sensitive receptors within area. D 1 Low
1.6 Surface Water
Degradation
Sediment laden water
discharged to the environment,
impacting on vegetation and
downstream environment.
C 2 Med
▪ Water collected in detention ponds and reused in process. ▪ Sump sized to provide adequate collection of runoff and spray water. ▪ Surface water management to be in line with Surface Water
Management Procedure. ▪ Surface water management to be in line with Surface Water
Management Procedure
D 1 Low
2. Diesel Genset Fuel Storage
2.1 Surface Water
Contamination
Discharge of oily water to
environment. C 3 High
▪ Internal drainage system ▪ Surface water management to be in line with Surface Water
Management Procedure D 2 Low
Works Approval Application
Page | 28 Doc Ref: 12217_4
Item Environmental
Factor
Potential Environmental
Impact
Inherent Risk Risk Management
Residual Risk
L C R L C R
▪ Appropriate handling and disposal of hydrocarbons as per Storage and Use of Hazardous Substances Procedure
2.2 Soil Contamination Accidental spillage of
hydrocarbons D 3 Med
▪ All hydrocarbons to be stored within bunding that meets Dangerous Goods Safety Act 2004.
▪ Appropriate handling and disposal of hydrocarbons as per Storage and Use of Hazardous Substances Procedure and Waste Management Procedure
E 2 Low
Works Approval Application
Page | 29 Doc
Ref: 12217_4
6.0 Environmental Objectives, Legislative Standards and
Measurement Criteria This section details the legislative standards and measurement criteria to appropriately manage the risks
identified in Section 5. The risk assessment did not identify any discharges from the prescribed premises
and, where appropriate, the risk of emissions and discharges can be managed and regulated through site
management practices.
Table 11 provides a summary of environmental factors, objectives, legislative standards and
measurement criteria.
It is noteworthy that no non-standard conditions were contained in Statement 940, meaning that no
significant factors or aspects were identified during the Part IV assessment, and no management plans
were conditioned into the Statement.
Works Approval Application
Page | 30 Doc Ref: 12217_4
Table 11 Environmental Objectives, Standards and Measurement Criteria
Risk Factor
Significance of emissions Risk Assessment
Standards (ie legislation, agencies, EMS)
DER Regulation (EP Act – Part V)
Measurement Criteria
Air emissions (point source)
Construction During construction there will be no point source air emissions directly related to the construction of the prescribed premises, with the exception of vehicle exhaust fumes and generators. No offensive odours are expected to be produced as a result of the construction of the prescribed premises. Operations Point source air emissions directly related to the operation of the prescribed premises are from the plant, generators and vehicle exhaust fumes. No offensive odours are expected to be produced as a result of the operation of the prescribed premises.
No regulation required
▪ Site Environmental Management Plan
▪ Dust SWI
WA – No conditions required
N/A
Dust Emissions Construction Dust is likely to be generated from vehicle movement, clearing and construction works. Potential impacts may include visual amenity, deposition on surrounding vegetation, adverse impact and disturbance to fauna and flora, risk to human health. Operation There is the potential that dust will be generated from the handling and processing of ore.
Other management mechanisms
▪ General provisions of the Environmental Protection Act 1986
▪ National Environment Protection Measure (NEPM) for Ambient Air Quality1998
▪ Environmental
Management Plan
▪ Dust SWI
WA – General condition in relation to works being undertaken in accordance with works approval application documentation.
▪ Dust Suppression water at conveyors and screens.
▪ Dust Suppression water at primary crusher dump bin, lump product stockpile and fines product stockpile.
▪ Dust suppression on access roads and ROM area.
Noise Emissions Construction Noise from construction works, including vehicle movement. Operations During operations, there will be noise from pumping equipment and plant equipment that has the potential to impact the amenity of the surrounding environment.
Other management mechanisms
▪ Environmental Protection (Noise) Regulations 1997
▪ Site Environmental
Management Plan
WA – No conditions
required
▪ No sensitive receptors within area. ▪ Noise attenuating equipment used, where
practicable.
Light emissions Construction Light overspill from 24-hour construction activities. Operations Light overspill from 24-hour mining activities.
Other management mechanisms
▪ Provisions of the Environmental Protection Act 1986
WA – No conditions required
▪ Minimise lighting, subject to safety requirements.
▪ Light overspill associated with works will be in accordance with AS4282-1997: Control of the Obtrusive Effects of Outdoor Lighting.
Discharges to Construction Other ▪ Provisions of the WA – No conditions ▪ Water from hardstand areas to be
Works Approval Application
Page | 31 Doc Ref: 12217_4
Risk Factor
Significance of emissions Risk Assessment
Standards (ie legislation, agencies, EMS)
DER Regulation (EP Act – Part V)
Measurement Criteria
water During construction, there is the potential for sediment laden water to run-off from cleared areas, with the potential to impact on the receiving environment. Vehicle failure and spills could also result in oily water or soil / water contamination to occur. Site development is proposed in the summer-autumn period of 2021 which runoff is unlikely. Operations Runoff and spray drift from the processing facility may potentially enter the receiving environment. Unplanned or accidental spill of hydrocarbons could also result in ground and/or surface water contamination.
management mechanisms
Environmental Protection Act 1986
▪ Environmental Protection (Unauthorised Discharges) Regulations 2004
▪ Dangerous Goods
Licence administered by DMIRS
▪ Site Environmental
Management Plan
required
harvested and reused within premises for dust suppression purposes.
▪ All bunding to meet Dangerous Goods Safety Act 2004
▪ Appropriate maintenance on vehicles and machinery to minimise spillage.
▪ Drainage runoff into detention ponds downstream from ROM precinct.
Discharges to land
Construction During construction, vehicle leaks and fuel spills could result in soil contamination. Operations The accidental spill of hydrocarbons or hazardous chemicals could result in soil and/or surface water contamination.
Other management mechanisms
▪ Provisions of the Environmental Protection Act 1986
▪ Environmental Protection (Unauthorised Discharges) Regulations 2004
▪ Dangerous Goods
Licence administered by DMIRS
▪ Site Environmental
Management Plan
▪ WA – No conditions required
▪ All bunding to meet Dangerous Goods Safety Act 2004
▪ Appropriate maintenance on vehicles and machinery to minimise spillage risks
▪ Conduct or spill response training ▪ Register of incidents and events, and
information of clean-up and disposal actions.
Works Approval Application
Page | 32
Doc Ref: 12217_4
7.0 References Australian Standard (1997). AS 4282-1997: Control of the Obtrusive Effects of Outdoor Lighting (AS
1997), Standards Australia, Sydney.
Australian Standard (2004). AS4360:2004 Risk Assessment, Standards Australia, Sydney.
Bamford Consulting Ecologists (2012). Shine Project Area Fauna Assessment. A Report Prepared for
Gindalbie Metals Limited. February 2012.
Bamford Consulting Ecologists (2020). Shine Project Area Fauna Assessment. A Report Prepared for
Mount Gibson Iron. August 2020.
Beard JS (1976). Vegetation Survey of Western Australia. Murchison 1: 1 000 000 Vegetation Series.
Map Sheet 6 and Explanatory Notes to Sheet 6. Published by UWA Press, Perth.
Botanica Consulting (2012). Level 2 Flora and Vegetation Survey and Priority Search of the Shine
Project, Tenements: M59/0730, M59/0406, M59/0421 & P59/1800, Prepared For Karara Mining Ltd.
January 2012.
Bureau of Meteorology (2012). Accessed http://www.bom.gov.au/.
CRE (2009). Draft Shine Iron Ore Project Surface Water and Drainage Assessment. March 2009.
Department of Agriculture Food and Western Australia (2007). Pre-European Vegetation - Western
Australia (NVIS Compliant Version GIS file). Department of Agriculture and Food Western Australia.
Department of Water (2002). Water Quality Protection Note; Stormwater Management at Industrial
Sites, November 2002
Outback Ecological Services (2009). Gindalbie Metals Limited. Shine Project. Baseline Soil Survey.
March 2009.
Payne AL, Van Vreeswyk AME, Pringle HJR, Leighton KA, and Hennig PH (1998). An inventory and
condition survey of the Sandstone-Yalgoo-Paynes Find area, Western Australia. Technical Bulletin
No. 90. Agriculture Western Australia, Government of Western Australia. Perth.
Pritchard Francis Consulting (2012). Desktop Surface Water and Stormwater Management Study for
the Shine Project Shire of Yalgoo Western Australia. March 2012.
Prodemas (2008). Economic Evaluation Study Report. Chapter 3: Geology and Resources.
Unpublished report prepared for Warriedar Joint Venture - Shine Iron Ore Project. Prodemas
International Limited.
Rockwater (2008). Assessment of Groundwater Conditions and Availability, Shine Iron Ore Deposit.
December 2008.
Soil Water Consultants (2013). Shine Deposit Waste Rock Landform Design and Preliminary Closure
Criteria. Report prepared for Gindalbie Metals Limited. June 2013.
Woodman Environmental Consulting Pty Ltd (2012). Regional Flora and Vegetation Survey of the
Karara to Minjar Block, June 2012.