shear behavior and failure pattern of precast wall panel
TRANSCRIPT
Shear Behavior and Failure Pattern of Precast Wall Panel
Connections with Full and Semi
Blockouts (Slots)
Dr.K.Ramadevi1* and S. Parkavi2
1Professor, Civil Engineering Department, Kumaraguru College of Technology,
Coimbatore
2Assistant Professor, Civil Engineering Department, United Institute of Technology,
Coimbatore
1Email: [email protected] 2Email: [email protected]
Abstract
In the growing infrastructure, the amount of savings in labour and material, enhanced
product quality and workmanship and to improve rate of construction, precast industry serves
an important role. To improve the structural integrity and to provide continuity to the precast
elements, precast connections plays an important role. Earthquake loads or other disasters
contribute to the major structural damages to the connections. This study aims to propose four
different types of wall – to – wall connections – Loop connection with full and semi blockouts
(slots) and Toothed connection with full and semi blockouts in order to determine the shear
characteristic of the wall panels. The fibre reinforced concrete (FRC) wall panels and the base
slab with semi and full blockouts were casted in the precast plant and tested in the laboratory
until failure. All specimens were subjected to monotonic lateral loading to find the load
capacity and deflection at ultimate load due to the failure of the connection. The load-deflection
behaviour, mode of failure and maximum deflection of wall panels were determined for all the
four different types of connections.
Keywords: Precast concrete structures, FRC wall panels, Wall connection, Blockout,
Monotonic Loading, Energy absorption.
1. Introduction
Precast concrete is a substitute to cast-in-situ concrete. While cast-in-situ concrete is
cast in its site, precast concrete is cast at casting plant, either at the building site or in a factory,
and is then lifted to its final resting place and fixed securely. This means that unlike cast-in-
situ construction, which is monolithic or continuous, precast concrete buildings are made of
separate pieces that are connected together.
*Corresponding Author
Vol 41, 2021
313
Tierärztliche Praxis
ISSN: 0303-6286
The main objective of the structural connection is to transfer forces among the precast
concrete elements in order to attain structural interface once the system is loaded. By the ability
to transfer forces, the connections should have the intended structural behaviour of the
superstructure and the precast subsystems that are combined in it. Therefore, the structural
connections should be regarded as an important part of the structural system and they should
be designed properly as the same for the precast concrete elements. To understand the structural
behaviour of fibre reinforced wall to wall connections on any lateral loading such as earthquake
or wind loading.
The wall connections are subjected to in-plane lateral ground movement. Cracks
occurred at the bottom and wall interface. The results can assert that the common connection
has also low efficiency in terms of capacity against lateral loading [1]. Connection between the
exterior and interior precast concrete walls by loops and gap between walls are filled by
concrete. Crushing and spalling was concentrated at the joint. The connection showed a ductile
behavior - few line cracks and large deflection occurred to give a warning before failure [2].
Studied behaviour of tension joint using direct overlapping loops, evaluating the influence of
the addition of steel fibres to the in-situ concrete [3].
Connection design is one of the most significant considerations for a successful
construction of precast reinforced concrete structures in terms of the structural behaviour [4].
Proposed a new connection in order to recover rotational loading capacity and develop a finite
element model of precast wall with connections by considering all details of different parts for
a contemporary connection, as well as the proposed connection [5].
Investigation on flexural behaviour of precast concrete (PC) wall – steel shoe composite
assemblies with various dry connection details at mid-span is done [6]. An innovative
horizontal wall-to-wall connection using FE model for precast shear wall systems was
developed and compared with cast-in-situ wall system [7]. The use of shear key is to connect
two separate precast components to improve the shear resistivity of the joint surfaces. The
proposed shear key shape in this study comprises of triangular, composite rectangular, semi-
circular and trapezoidal [8].
The evaluation of the out-of-plane response of confined masonry walls with toothed
connections when damaged due to in-plane forces was studied. The confined masonry walls
with or without toothing enhanced the interaction between masonry walls and RC confining
elements and were able to postpone the failure by controlling out-of-plane deflections even
after an in-plane drift cycle of 1.75% [9].
The enhancement in the strength of the M35 grade concrete mix by the addition of
polypropylene fibres on different percentages was observed [10]. By providing fibres in the
critical zones, it is possible to improve the performance of the frames against lateral loading
[11]. Behaviour of cast in-situ hybrid fibre-reinforced concrete frames [12] & [13] with infills
against lateral reversed loads were investigated.
Vol 41, 2021
314
Tierärztliche Praxis
ISSN: 0303-6286
2. Objectives The main objectives of this research work are listed as under.
• To propose four different types of connections in order to improve shear
characteristic of the pre cast wall panels connected to base slab with semi and full
blockouts.
• To determine ultimate strength of the wall panels tested for lateral monotonic
loading with four different types of connections.
• To find the ultimate deflection of the wall panels.
• To investigate the failure behaviour of wall panels with different types of
connections
3. Properties of Materials used in this Research work
Both the wall panel specimens were casted with ready-mixed concrete of grade of M40. Recron
3S fibres were used which acts like tributary reinforcement in concrete which seizures cracks,
increases resistance to impact/abrasion and significantly improves quality of construction in
walls, it also improves resistance to plastic & drying shrinkage/cracking. The properties of
fibres used in this research work are shown in Table 1.
Table 1. Properties of fibres used
S.No. Properties of Recron 3S Fibre Values
1 Effective Diameter 20 - 40 μ
2 Specific gravity 1.34 - 1.39
3 Melting point 250 - 265 Deg.C
4 Elongation 20 - 60%
5 Alkaline stability Very good
6 Acid resistance Excellent
7 Soundness by Le Chatlier test (mm) 10
8 Tensile strength (N/mm2) 28007
9 Percentage elongation (%) 29.8
10 Denier 64.285
In this research work, concrete mix design for M40 grade of concrete with
polypropylene fibre (Recron 3s) is done, as per IS 10262:2009. The mix proportion arrived for
M40 grade concrete adopted is shown in Table 2.
Table 2. Mix proportion arrived for M40 grade concrete
Cement
Kg/m3
Fine
aggregate
Kg/m3
Coarse
aggregate
(12mm) kg/m3
Coarse
aggregate
(16mm) kg/m3
Water
content
Kg/m3
Polypropylene
fibre
g/m3
400 750 400 800 140 600
Vol 41, 2021
315
Tierärztliche Praxis
ISSN: 0303-6286
The materials used for grouting the wall-to-wall connection are 1 kg of non-shrink grout
(CONBEXTRA GP 2) and 500 g of stone chips with 100 ml of chemical bond (Emaco SBR)
with required amount of water.
4. Tests on Companion Specimens
The compressive strength, split tensile strength and flexural strength of concrete were
determined by casting cubes of size 150×150×150 mm, cylinders of size 300 × 150 mm and
prisms of size 500 mm × 100 mm × 100 mm and allowed for 14, 21, 28 days curing. The results
of compressive strength, split tensile strength and flexural strength with Polypropylene fibres
(Recron 3s) are shown in Table 3.
Table 3 Test results on companion specimens
S. No No. of
days
Compressive
strength
(MPa)
Split tensile
strength
(MPa)
Flexural strength
(MPa)
1 14 26 2.06 1.725
2 21 32.38 2.67 2.29
3 28 42 3.19 3.34
5. Experimental Work
5.1 Specimen detailing
Four different types of connections are adopted for interconnecting two walls
horizontally by Looped Connection with semi and full blockouts and by Toothed Connections
with semi and full blockouts in base slab. The height, width and thickness of walls were 1300
mm, 1000 mm and 75 mm respectively. The base slab is of 2860 mm length and 860 mm with
and 150 mm in thickness. Thickness dimensions corresponded to a prototype scale of the
precast panel typically used for medium rise construction. The detailing for wall to wall
connection is shown in Figures. 1 to 4. Along 1300 mm height of wall, six looping bars of 8
mm diameter were placed at a spacing of 200 mm centre to centre. A longitudinal bar was then
inserted in the loop between the two walls. This area created a gap of 100 mm width which
then was filled with non-shrink grout to produce moment resisting connection between the two
walls. Tooth connection consists of three numbers of tooth of dimension shown in figures 3
and 4. Reinforcement provided for wall panels are 8 mm diameter rod with 300 mm c/c and for
base slab 8 mm diameter rod with 360 mm c/c.
Vol 41, 2021
316
Tierärztliche Praxis
ISSN: 0303-6286
Figure 1. Loop with Semi Blockouts Figure 2. Loop with Full Blockouts
Figure 3. Tooth with Semi Blockouts
Casting, transportation and erection of required precast elements were fully sponsored
by M/S Velan Concast, Avinashi Road, Neelambur, Coimbatore. The precast factory has
special plant for the manufacture and maintenance of moulds. Casting and curing of specimens
was done in the plant. The mould was cleaned and shuttering was done to keep the mould in
position. The reinforced cage was positioned in the partly assembled mould, then the remaining
mould section is completed. Before pouring the concrete, the mould was checked. From ready
mix concrete (RMC) unit, the fibres of dosage 0.6% by volume were added to the concrete.,
The specimens were compacted using high-frequency external needle vibrators of diameter 35
mm with 1300 rpm. The specimens were transported from the plant to Structural Technology
Centre of Kumaraguru College of Technology after28 days of curing for testing. The specimens
were unloaded using 12 T capacity crane and erected in the test floor in the lab. The wall panels
were fitted to the base slab by grouting using FOSROC CONBEXTRA GB2 and
Vol 41, 2021
317
Tierärztliche Praxis
ISSN: 0303-6286
MASTEREMACO SBR 2 as shown in Figure 5. After grouting the joint, the strength of the
grout and the wall panels were checked by Rebound Hammer in order to verify whether both
the wall panel and the grout have the equal amount strength.
Figure 4. Tooth with Full Blockouts
Figure 5. Grouting the joints of wall panels
6. Test set-up
In order to determine the shear stress at the interface of the connection, two fibre reinforced
walls were connected together and the connected wall panels are fixed to the base slab. The
shear loading was applied horizontally to the face of the wall panel. Wall panels are denoted
as wall 1 and wall 2 respectively. The base slab is fixed to the test floor of capacity 200 tones.
To prevent any movement, wall 1 (unloaded wall) was restrained by a fixed support with mild
Vol 41, 2021
318
Tierärztliche Praxis
ISSN: 0303-6286
steel jockey while wall 2 (loaded wall) was set free. The test setup and the location of LVDT
and DG are shown in Figures 6, 7 and 8.
Figure 6. LVDT and DG position
Figure 7. LVDT and DG position (SIDE VIEW)
A load cell of capacity 50 Tones was positioned at the distance of 115 mm from the top
of the wall panel in order to apply the shear load on the sample. The load cell was bolted to the
load frame of capacity 100 Tones. A common console controlled all the jacks. Data acquisition
system with 10 channels was used to measure the load and deflections at various positions on
Vol 41, 2021
319
Tierärztliche Praxis
ISSN: 0303-6286
the specimen. Lateral monotonic loading was applied at the wall panel using hydraulic jack of
capacity 100 T. LVDTs (Linear Variable Differential Transducer) of least count 0.01mm were
used for measuring deflections at the wall panels at various locations. A total number of three
(LVDT) and three Dial Gauges (DG) were placed on both the wall panels and base slab in order
to record the displacement when the load was applied to the specimen.. LVDTs 1, 2 and 3 and
DG 1,2 and 3 were used to determine the displacement of specimen once load was applied. In
this test, the load was progressively increased up to the failure of the specimens when no further
load could be sustained. At each load interval, the crack patterns, width and length of cracks
were noticeable. Damage crack pattern was observed during testing for all types of connections.
The entire set up with data acquisition is shown in Figure 8.
Figure 8. Test set up with data acquisition
7. Experimental results and discussions
7.1 Load Vs lateral displacement
The lateral load was applied to the wall panel by means of hydraulic jack. The
deflections of each load value are measured by means of LVDT till ultimate load. The load-
displacement relationship of tooth connection with full blockouts and semi blockouts and loop
connection with full blockouts are shown in Figures 9 to 11. All specimens have shown
consistent displacements at the free end as well as near the connection. However, less
displacement was measured on fixed end as compared to the free end, which allowed more
movement. The lateral displacement of the wall was measured by four LVDTs. Tooth
connection with full slotted connection was shown with no displacement measured until 4 kN.
The maximum displacement occurred in wall 1 at position LVDT 3 is 19.5 mm. In Tooth
connection with semi slotted connection, the maximum displacement occurred in wall 2
(loaded wall) at position LVDT 3 is 1.85 mm. In loop connection with full blockouts the
maximum displacement occurred in wall 2(loaded wall) at position LVDT 3 is 7.11 mm.
Vol 41, 2021
320
Tierärztliche Praxis
ISSN: 0303-6286
Figure 9. Load Vs Displacement of tooth connection with full
blockouts
Figure 10. Load Vs Displacement of tooth connection with semi blockouts
Figure 11 Load Vs Displacement Loop connection with full blockouts
0
5
10
15
20
25
30
0 5 10 15 20 25 30
Load
(kN
)
Deflection (mm)
LVDT 1 (mm) LVDT 2 (mm) LVDT 3 (mm)
D.G 1 (mm) D.G 2 (mm)
0123456789
10111213
0 1 2 3 4 5 6 7
Load
(K
n)
Deflection ( mm)
LVDT 1 LVDT 2
0
1
2
3
4
5
6
7
0 2 4 6 8
Load
(kN
)
Deflection(mm)
LVDT 1 LVDT 2 LVDT 3D.G 1 D.G 2 D.G 3
Vol 41, 2021
321
Tierärztliche Praxis
ISSN: 0303-6286
7.2 Failure Pattern - Observations
The post-test observations showed that the shear force from one precast element to the
other was transferred by the friction along the interface between precast wall and Grout joint.
When shear loading was applied, slip developed along the joint interface and caused joint
separation at the interface. Figures 12 and 13 shows the failure of connections in the
specimens.
i)Tooth Connection with Full Blockouts
First crack appeared at 8.7 kN. Crack at the wall and the base slab connection appeared
at the load of 14 kN. The ultimate load at the load reversal took place at 19.5 kN.
ii)Tooth Connection with Semi Blockouts
First crack appeared at 6.5 kN. Spalling of concrete at the connection of base slab to
wall panel was observed. Crack at the wall and the base slab connection appeared. Cracking of
bottom base slab grout occurred and the tooth connection separated at 10 kN.
iii)Loop Connection with Full Blockouts
First Vertical crack at grout appeared at 3 kN and propagated up to middle portion and
widened Mild cracks at wall slab joints back side were observed. Horizontal cracks at loaded
face of the panel appeared and propagated to the lateral side of the wall. Spalling of concrete
was observed in the wall and the ultimate load was 9 kN.
iv)Loop Connection with Semi Blockouts
Loop connection with semi blockouts is tested a lateral loading. Due to the uplift of
wall from the base slab through semi slot long the loading side, crack patterns and deflections
were not able to be are measured. Hence it was decided to change the loading pattern. Lateral
load was applied on the face of the wall panel (115 mm from top) instead of applying lateral
load along the thickness of wall panel.
Figure 12. Failure of tooth connection with full blockouts
Vol 41, 2021
322
Tierärztliche Praxis
ISSN: 0303-6286
Figure 13. Failure pattern of loop connection with full blockouts
8. Conclusions
This experimental study was conducted to study about the shear characteristics of four set of
wall panels with different type of connections between two adjacent walls. The following
conclusions are drawn from present investigation.
• The wall-to-wall connection was subjected to shear loading (Lateral monotonic
loading) ie., one wall panel keeping the other wall panel arrested from lateral
displacement. The load was applied up to failure.
• The behaviour of wall panels resting on full blockouts is found to be better than that
resting on semi blockouts.
• Tooth connection with full blockouts withstood an average lateral load of 19.5 kN and
a maximum sway of 24.12 mm. Initial stiffness and ultimate stiffness observed are
157.895kN/mm and 808.46 N/mm respectively. Energy absorption in this type of
connection is 346.168 kN-mm. This type of connection showed a very good resistance
against uplift from base slab along the loading side which increased the shear resistance
of the connection.
• Tooth connection with semi blockouts withstood an average lateral load of 6.5 kN and
a maximum sway of 1.85 mm. Initial stiffness and ultimate stiffness observed are
1000.00 kN/mm and 35.1351 N/mm respectively. Energy absorption in this type of
Vol 41, 2021
323
Tierärztliche Praxis
ISSN: 0303-6286
connection is 9.89 kN-mm. The uplift of wall panel from the base slab along the loading
side reduced the shear resistance of wall in this type of connection.
• Loop connection with full blockouts withstood a maximum lateral load of 10 kN and a
maximum sway of 7.11 mm. Energy absorption in this type of connection is 31.268
kN-mm. This loop bar connection is categorised as brittle connection.
• It was also noted that in the loop connection the uplift of wall panel from base slab
along the loading side was similar to that of tooth connection with full blockouts.
8. Scope for future work
• To increase the shear behaviour of the connection, the ratio of the transverse bar,
overlapping length and grout joint strength should be increased.
• The wall portion inside the slot shall be strengthened and reinforced with sufficient bars
connecting both the wall panels and base slab to avoid uplift.
• The wall panels with different fibres can be tested and the results may be compared to
determine the optimum fibre.
• Behaviour of tooth connection by introducing rebars at Transverse direction through
wall panels can be studied.
Acknowledgments
The authors would like to express their sincere gratitude to Er.K.M.Velumani, Proprietor,
M/S Velan Concast, Precast Concrete Manufacturers, Neelambur, Coimbatore, India. The
processes like Casting, transportation, and erection of required precast elements were fully
sponsored by them. The precast factory has special plant for the manufacture and maintenance
of moulds which enabled us to complete this research successfully.
References
[1] Ramin Vaghei, Farzad Hejazi Hafez Taheria, Mohd Saleh Jaafarb and Abang Abdullah
Abang Ali, “Evaluate Performance of Precast Concrete wall to wall Connection”,
APCBEE Procedia, vol. 9, no. 1, ( 2014 ), pp. 285 – 290.
[2] N. Rossley, “Behaviour Of Precast Walls Connection Subjected To Shear Load”,
Journal of Engineering Science and Technology, Special Issue on Applied Engineering
and Sciences, vol. 1, no. 1, (2014), pp. 142 – 150.
[3] Daniel de Lima Araújo et.al, “Loop connection with fibre-reinforced precast concrete
components in tension”, ELSEVIER, Engineering Structures, vol. 72, no. 1, (2014) pp.
140–151.
[4] Nabila Rossley, Farah Nora Aznieta Abdul Aziz, et.al Behaviour of Vertical Loop Bar
Connection in Precast Wall Subjected To Shear Load, Australian Journal of Basic and
Applied Sciences, vol. 8, no. 1, (2014), pp. 370-380.
[5] Hafez Taheri,Farzad Hejazi, Ramin Vaghei, Mohd Saleh Jaafar, Abang Abdullah
Aabang Ali et.al, “New Precast Wall Connection Subjected to Rotational Loading”,
Periodica Polytechnican Civil Engineering, vol. 60, no. 4, (2015), pp. 547–560.
Vol 41, 2021
324
Tierärztliche Praxis
ISSN: 0303-6286
[6] Xiangguo Wu, Xinlei Xia , Thomas H.-K. Kang , Jingcheng Han and Chang-Soo Kim,
“Flexural behavior of precast concrete wall – steel shoe composite assemblies with dry
connection”, Steel and Composite Structures, vol. 29, no. 4, (2015), pp. 545-555.
[7] Qiao JinaXin Duib , Weijian Zhaoc, Taogao Wud, Wannan Guoe, “Numerical analysis
of seismic behaviour of a new-type horizontal wall-to-wall connection for precast
concrete shear walls”, Applied Mechanics and Materials, vol. 353-356, no. 1, (2013),
pp. 3589-3592.
[8] Izni Syahrizal Ibrahim et,al, “Ultimate Shear Capacity and Failure Of Shear Key
Connection In Precast Concrete Construction”, Malaysian Journal of Civil
Engineering, vol. 26, no. 3, (2014), pp: 414-430.
[9] Vaibhav Singhaland Durgesh C. Rai, “Role of Toothing on In-Plane and out of Plane
Behaviour of Confined Masonry Walls, Journal of Structural Engineering, vol. 140, no.
9, (2014), pp. 0401-0453.
[10] Ridha Nehvi, Prashant Kumar and Umar Zahoor Nahvi “Effect of Different
Percentages of Polypropylene Fibre (Recon 3s) on the Compressive, Tensile and
Flexural Strength of Concrete”, International Journal of Engineering Research &
Technology (IJERT), vol. 5, no. 11, (2016), pp. 124-130.
[11] Tony Holden et.al, “Seismic Performance of Precast Reinforced and Prestressed
Concrete Walls”, Journal of Structural Engineering, vol.129, no. 3, (2003), pp. 286–
296.
[12] K Ramadevi, D.L. Venkatesh Babu, R Venkatasubramani, “Behaviour of hybrid fibre-
reinforced concrete frames with infills against lateral reversed loads”, Arabian Journal
for Science and Engineering, vol. 39, no. 10, (2014), pp - 6959-6967.
[13] K. Ramadevi and D.L. Venkatesh Babu “Behaviour of hybrid fiber reinforced concrete
slabs in frames under static loading”, Ecology. Environment. & Conservation, vol. 18,
no. 4, (2012), pp. 975-979.
Vol 41, 2021
325
Tierärztliche Praxis
ISSN: 0303-6286