INTRODUCTION
Industry of construction is one of sector that has a high risk in working. A lot of damage could be happen in death, money, and production delay. So, we need implementation of Safety and Health Environment (SHE) system to prevent this kind of problem.
DEFINITION
SHE
Is an activity begin with planning, implementation, and controlling to prevent risk in safety and health of work
GENERAL PURPOSES
- Avoid Risk
- Prevent accident at work
- Decrease consequences because accident
SPECIAL PURPOSES
In order to ensure that PT. Total BangunPersada policies about Safety and Healthy in Construction can be implemented in Central Park project well.
FUNDAMENTAL LAW
SHE MANAGEMENT SYSTEM-CENTRAL PARK Page 1
A. PT. Total Bangun Persada SHE Prosedure
B. PT. Total Bangun Persada SHE standard
C. PT. Total Bangun Persada cleanliness and tidiness standard
D. Minister Regulation No.01/Men/1980, about SHE in Building construction
E. Joint decision of PU Ministry & Labor minister number :KEP.174/MEN/1986 & No 104/KPTS/1986
F. PT.Total Bangun Persada SHE pocket book
G. Regulation of Labor Minister No.PER.05/MEN/1996
H. Decision of Indonesian Health Minister Number 1405/MENKES/SK/XI/2002 about Health requirements for office work environments and industries
I. Occupational Health and safety Assessment Series-OHSAS 180001:1999
PROJECT OVERVIEW
PROJECT DATA
Project Name : Central Park Project
Various : Mixed (Mall-Apartment-Office-Hotel)
Owner : PT Tiara Metropolitan Jaya
Area : 86,000 m2
Building : 652,000 m2
Area of work : SAME (Mall) + Structure (Tower)\
Access of time : 25 months (01 August ’07 – 31 August ’09)
Time remaining : 9,5 months
Job Progress : 34% (Progress Oct ’08)\
SHE MANAGEMENT SYSTEM-CENTRAL PARK Page 2
MAIN CONTRACTORS : PT TOTAL BANGUN PERSADA
CONCEPT ARCHITECTS : DP ARCHITECTS PTE LTD
LEAD ARCHITECTS : PT ARKIPURI INTRA NASIONAL
CIVIL & STRUCTURAL ENGINEER : PT GISTAMA INTI SEMESTA
MECHANICAL & ELECTRICAL CONSULTANT : PT SKEMANUSA KONSULTAMA TEKNIK
GEOTECHNICAL ENGINEERS : PT PRATAMA WIDYA
SITE SURVEYORS : PT MARMOYA BARUNA PERSADA
SOIL INVESTIGATION : PT PRATAMA WIDYA
QUANTITY SURVEYORS : PT WILDE & WOOLARD
TRAFFIC CONSULTANT : PT PAMINTORI CIPTA
SHE MANAGEMENT SYSTEM-CENTRAL PARK Page 3
Writer limited this explanation in Safety only.
SHE MANAGEMENT SYSTEM-CENTRAL PARK Page 4
ORGANIZATION CHART
SCOPE OF SHE PLANNING
Include provisions for administrative and managerial control as well as deal with safety and environmental health projects working at the Central Park area of Jakarta, assigned to all employees and workers who work the Central Park project, or guests as well as representatives / workers and other companies working in the Central Park project.
SAFETY PROGRAM
1. TRAINING
Head of safety must meet the competency of personnel safety and emergency response team planned and implemented in coordination with the HRD (training center level). The training is tailored to the specific needs of the project.
SHE MANAGEMENT SYSTEM-CENTRAL PARK Page 5
2. SAFETY INDUCTION
Done to give directions to workers and every guest who comes. Can be made in writing on a board shown on each worker, workers should be given induction has signed a statement following the induction.
3. SAFETY TALK
Briefing in groups according to the work area or job discipline. Conducted in the morning before work began (for about 10-15 minutes).
Briefing materials:
- Potential dangers of the job that day & precautions
- Order
- Information events that often occur in the field
- Material handling to prevent accidents on the condition that must be observed.
4. Safety inspection
Aims to maintain consistency in the application of SHE and covers the entire project area. Safety managers must make inspection reports and discrepancy SHE reports, at least 60 minutes after the inspection is completed.
5. Safety Patrol
Conducted by safety supervisors, covering all areas of work and the areas where there is work that has identified a potential accident.
No. ACTIVITY PARTICIPANT/PLACE SCHEDULE PIC
SAFETY INDUCTION
1 Safety Induction Staff, workers & visitors Early in the project Safety officer
2 Tool Box Meeting Staff & workers As needed Safety officer
3 Safety Talks All safety staff Min. 1x/ week Safety officer
4 Safety Coordination Meeting TBP staff & subcon Min 1 x/ month Safety officer
INSPECTION
1 Safety Patrol Safety officer& Safety supervisor everyday Safety officer
2 Safety inspection PM, SM, Safety (TBP& subcontractor) Min. 1 x/month Project Manager
SHE MANAGEMENT SYSTEM-CENTRAL PARK Page 6
Monthly Reports
Safety Manager must make a monthly report. This report was sent to safety managers at headquarters, 05th date after the end of the month.
And also be equipped with the information that cases are still in progress (if any)
NO ACTIVITY PARTICIPANT/ PLACE
SCHEDULE PIC
REPORTS
1 Daily reports everyday Safety officer
2 SHE inspection reports From the results of inspection SHE (1x week)
Safety officer
3 Report mismatches of SHE, Near miss (near misses) & accident reports
If there is a discrepancy or an accident
Safety officer
4 Monthly reports Every 5th of every month Safety officer
HEALTH WORK
1 Employment medical examination of the Social Security
1 x year or as scheduled GA
HIRARC (Hazard Identification, Risk Assesment and risk control)
HIRARC include:
- All activities
- Prevention action plan to identify potential hazards are to be zero or becomes dangerous levels down as low as possible.
NO SELF PROTECTION EQUIPMENT TYPE OF JOB/ USE SPECIFICATION
1 Safety helm All the people on the project site, including
MSA, JSW
SHE MANAGEMENT SYSTEM-CENTRAL PARK Page 7
subcontractors
2 Safety shoes TBP staff Protective steel in the front end (safety toe)
3 Rubber Shoes / Work Shoes Workers in site Closed at the front end, at least a high ankle
4 Dust mask Used in a dusty work environment
May contain dangerous dust particles / smoke
5 Protective goggles Works with the risk of eye injury (grinding, workers who use the cutting wheel), etc.
help spark small debris & dust fine to the eye
6 Ear Plugs People who work in areas that high noise levels above 85 db, such as grinding, ramset, generators work in the area, erection
Decrease noise levels which is more than 85 desibel
7 Safety Belt/ Full Body Harness People who work at a height of 2 m / more, working in the elevator shaft, the gondola and being around the building or void parameter
Able to withstand the load in accordance specification, no defects (a reasonable use condition)
8 Masker Fume People who work with chemicals, such as painters, etc.
withstand chemical particles (such as chemical particles paints etc.)
9 Gloves A blacksmith, Made of fabric (kind
SHE MANAGEMENT SYSTEM-CENTRAL PARK Page 8
carpenter, rigger, etc.
of polka-dot)
10 Rubber gloves Workers who work with chemicals, such as fogging workers, working with electricity
(made of rubber / latex, isolator material
11 Protective clothing
- Welding apron
- Welding gloves
- Welding shields
welding & cutting and cutting torch
Can protect users from the dangers of a spark, to gloves made of leather, for welding shield can protect the eyes & face from sparks
Conclusion:
SHE MANAGEMENT SYSTEM-CENTRAL PARK Page 9
Central park is a huge project. PT Total Bangun Persada, as Main Contractor, give their best to reach construction goal. Succeed in Cost, Quality, Time, and Safety and Heath in work.
To achieve Safety in work, PT. Total Bangun Persada have their own policies such as in safety regulation, safety planning, safety program, safety control, etc.
These kinds of policies should be done by all people in construction site, worker, and visitor.
SHE MANAGEMENT SYSTEM-CENTRAL PARK Page 10