sewage treatment and disposal feasibility study · treatment plant site and treatment process has...
TRANSCRIPT
163.11
SEWAGE TREATMENT AND DISPOSAL FEASIBILITY STUDY
DECEMBER 2010
OPUS DAYTONKNIGHT CONSULTANTS LTD.
163.11
THIRD PARTY DISCLAIMER AND COPYRIGHT
This document has been prepared by Dayton & Knight Ltd. for the benefit of the client to whom it is addressed. The information contained in this document represents Dayton & Knight Ltd.’s best professional judgment in light of the knowledge and information available to Dayton & Knight Ltd. at the time of its preparation. Except as required by law, this document is to be treated as confidential and may be used and relied upon only by the client, its officers and employees. Dayton & Knight Ltd. denies any liability whatsoever to other parties who may obtain access to this document for any injury, loss or damage suffered by such parties arising from their use of, or reliance upon, the document or any of its contents without the express written consent of Dayton & Knight Ltd. and the client. This document is for the sole use of the addressee and Dayton & Knight Ltd. This document contains proprietary and confidential information that shall not be reproduced in any manner or disclosed to or discussed with any other parties without the express written permission of Dayton & Knight Ltd. Information in this document is to be considered the intellectual property of Dayton & Knight Ltd. in accordance with Canadian Copyright Law.
163.11 ©2010 Page i
SEWAGE TREATMENT AND DISPOSAL – FEASIBILITY STUDY
TABLE OF CONTENTS
1.0 INTRODUCTION............................................................................................................ 1-1
1.1 Background .......................................................................................................... 1-1 1.2 Scope of Work ..................................................................................................... 1-3 1.3 Conduct of Study ................................................................................................. 1-3
2.0 EXISTING SEWAGE SYSTEM ..................................................................................... 2-1
2.1 Sewage System .................................................................................................... 2-1 2.1.1 Collection System .................................................................................... 2-1 2.1.2 Pumping Stations ..................................................................................... 2-2 2.1.3 Outfall ...................................................................................................... 2-5
2.2 Treatment and Disposal Requirements ................................................................ 2-6 2.3 Sewage Flows ...................................................................................................... 2-7
3.0 VILLAGE GROWTH AND DEVELOPMENT .............................................................. 3-1
3.1 Historical Population ........................................................................................... 3-1 3.2 Future Growth and Development ......................................................................... 3-1
4.0 DESIGN CONSIDERATIONS AND CRITERIA ........................................................... 4-1
4.1 Water Supply and Consumption .......................................................................... 4-1 4.2 Treatment and Disposal Standards/Guidelines .................................................... 4-2 4.3 Wastewater Flow Projections .............................................................................. 4-4 4.4 Wastewater Quality .............................................................................................. 4-5 4.5 Treatment Options ............................................................................................... 4-5 4.6 Effluent Disposal ............................................................................................... 4-12 4.7 Treatment Plant Siting Criteria .......................................................................... 4-14 4.8 Treatment Plant Site Options ............................................................................. 4-15
5.0 TREATMENT AND DISPOSAL OPTIONS .................................................................. 5-1
5.1 Treatment Plant Concept Design ......................................................................... 5-2 5.2 Option 1 – Smith Point Area ................................................................................ 5-3
TABLE OF CONTENTS (cont’d.)
163.11 ©2010 Page ii
5.3 Option 2 – Central Area ....................................................................................... 5-4 5.4 Option 3 – Skidegate Landing West .................................................................... 5-5 5.5 Option 4 – Skidegate Landing East ...................................................................... 5-6 5.6 Option 5 - Joint Treatment with Skidegate Band ................................................. 5-7 5.7 Evaluation .......................................................................................................... 5-10
6.0 SUMMARY, CONCLUSIONS AND RECOMMENDATIONS .................................... 6-1
6.1 Summary and Conclusions................................................................................... 6-1 6.2 Recommendations ................................................................................................ 6-2
APPENDICES 1 References 2 Environment Canada Inspectors Direction 3 Cost Estimates LIST OF TABLES 2-1 Pump Station Nos. 4 and 5 Recorded Flows .................................................................... 2-7 2-2 Pump Station No. 4 Unit Flows ....................................................................................... 2-8 3-1 Projected Population Growth ........................................................................................... 3-2 4-1 Standards tor Effluent Discharges to Marine Waters ....................................................... 4-3 5-1 Treatment and Disposal Cost Comparison .................................................................... 5-10 5-2 Cost to Provide Conveyance System from Skidegate Landing To Site
Options 1, 2 and 3 .......................................................................................................... 5-11 LIST OF FIGURES 2-1 Sheets 1 and 2 – Existing Sewer System 5-1 Sewage Treatment and Disposal, Options 1, 2, 3 and 4 5-2 Sewage Treatment and Disposal, Option 5
163.11 ©2010 Page 1-1
SEWAGE TREATMENT AND DISPOSAL – FEASIBILITY STUDY 1.0 INTRODUCTION
The Village of Queen Charlotte (Village) currently discharges untreated sewage into the marine
waters of Bearskin Bay. This feasibility study develops and evaluates several sewage treatment
and disposal options. The objective is to provide information to allow the Village to make an
informed decision on the best treatment and disposal option for its long term needs.
Sections that follow describe the existing sewage system, discuss community growth and
development, outline regulatory requirements and design criteria, and develop and evaluate
treatment and disposal options.
The study report concludes with recommendations for advancement of the preferred option to the
design stage.
1.1 Background
The Village, including Skidegate Landing, currently houses about 960 people. A sewage
collection system services most of the residents (about 870 people) and commercial
development in the Village core The unserviced area between Smith Point (existing
outfall) and Skidegate Landing, housing about 80 people, is serviced with septic tanks.
The ferry terminal in Skidegate Landing utilizes a holding tank.
163.11 ©2010 Page 1-2
Within the Village core, a series of four pumping stations convey the sewage to a fifth
pump station near Smith Point where the sewage is discharged into Bearskin Bay. No
treatment is provided. The discharge is authorized under Ministry of Environment
permit.
In 2000, a Long Term Water and Sewerage Plan (D&K 2000) was prepared for the
Village. It provided for a projected population of 1530 in 2021, developed four treatment
and disposal options and made three recommendations:
• Install standby generators at pumping stations to address the overflow issue on loss of
Hydro power.
• Video inspect the outfall to determine its condition.
• Initiate a public consultation process to assist Council in selecting a treatment plant
site and a treatment process; based on the four options developed in the report.
The generators have been installed at each pumping station. The outfall has not been
inspected (but is budgeted for inspection in 2010). The process for selection of a
treatment plant site and treatment process has not been initiated.
In 2009 Environment Canada issued an Inspector’s Direction under the Fisheries Act.
The Direction required the Village of submit a report outlining a strategy for development
of a plan to provide sewage treatment. The plan is to be finalized by December 31, 2010.
Council, in response to the Inspector’s Direction, authorized an update of the sewage plan
to include a Village owned and operated treatment plant and the option of joint treatment
using the neighbouring community treatment plant owned by the Skidegate Band.
163.11 ©2010 Page 1-3
1.2 Scope of Work
In a letter dated May 5, 2009, Dayton & Knight set out a terms of reference for this
feasibility study.
In summary, the study scope includes:
• Compile and review existing data.
• Meet with Council to review scope and agree on the service area, population
projections and potential treatment plant sites. Brief Council on treatment
technologies.
• Develop treatment and disposal options. Anticipated options are:
o Site near Smith Point (existing outfall)
o Site near Ferry Terminal (new outfall)
o Joint treatment with Skidegate Band (existing Band plant and outfall)
• Evaluate options and summarize findings in report.
• Present draft report to Council and finalize.
By letter dated February 16, 2010, the Village authorized the study to proceed.
1.3 Conduct of Study
Data were compiled and analyzed in preparation for the initial meeting with Council held
on March 15, 2010. At the meeting, Council members and staff were briefed on
treatment technologies and the Provincial standards for effluent disposal. Council and
staff also identified potential sites for a treatment plant.
Draft No. 1 of the report was submitted for staff review on July 29, 2010. Comments
were received and Draft No. 2 was submitted for review by Council on August 17, 2010.
Council then held a meeting with the Skidegate Band Council to discuss the joint
163.11 ©2010 Page 1-4
treatment option. A copy of the section of the report on the joint treatment option was
left with the Band Council for their review and response.
At a Council meeting on December 1, 2010 review comments on Draft No.2 were
received and report finalization was authorized in order to comply with the December 31,
2010 completion date established by Environment Canada.
The review comments awaited from the Skidegate Band Council will be addressed as a
follow up action to this report.
163.11 ©2010 Page 2-1
SEWAGE TREATMENT AND DISPOSAL – FEASIBILITY STUDY 2.0 EXISTING SEWAGE SYSTEM
A brief description of the sewage system, discharge Permit requirements and the analysis of
sewage flows are set out in this section.
2.1 Sewage System
Since their construction in 1984 only minor extensions to the sewer collectors have been
constructed to accommodate new development. In spring 2010, a forcemain was
constructed from the new Honna River water treatment plant to the existing sewer at 10th
Street to allow discharge of backwash residuals.
Figure 2-1, Sheets 1 and 2, illustrate the sewage system within the Village core.
2.1.1
Collection System
The collection system comprises 150, 200 and 250 mm PVC pipe. Forcemains range in
size from 100 mm to 200 mm and are PVC pipe. Service connections are 100 mm diameter
PVC to residential connections and 150 mm PVC to larger commercial connections.
Where homes/businesses are too low to be serviced by gravity, individual pumps were
provided to allow the property to be pumped into the sewage collection system. Property
owners are responsible for the ongoing operation and maintenance of the pumps. There
are approximately 20 pumped serviced connections.
School
0 50 100 200 metres
3rd Ave
Wharf St
Ca
us
ew
ay
St
1st Ave
3rd Ave
3rd
St
2nd Ave
2n
dS
t
1st
St
3rd Ave
H
City Centre
Bay St
2nd Ave
Ald
er
St
Highway 33
Bk 8 Bk 9Bk 1 Bk 6
Bk 7
Bk 8Bk 11
Bk 10
Bk 2 Bk 51 1
28 28
14 14
1
1 1
12
12 12
13
13
11
11
2
24
3
3
Plan 12752
13
Plan 13123
2
DBC
24
24 2415
15
Bk 11
12
12 12
1212
1 1 20
1
10 11
2
8Bk 10
A
15 1313
18
13 13 29 21
1313
24 40
24
A B
C
Plan11864
L. 309
Pla
n3452
L.2872
L. 2974
Plan
A
8570
Plan
Blk. D
1571
Plan
1571
Blk E
Blk ABlk GPlan 1571Blk A
Plan 1684
163
45371
2
Plan 163Blk C
Plan 15372
Plan 8612
Plan 1415 Plan 6873
4515
BeattiePoint
Bearskin Bay
SmithPoint
70 6962-2
62-1 62
6160
76 75
7265
66
6768 78 79
73 74
4142
4344
45
46
57
5859
47
48
49
50
51
52
53
63
54 55 5640 39 33 3837
34
32
64
30
29
31 36
LS4
LS
28
27
26
35
25
24
23 2213 14 15
16
17
17-1
17-2 17-3
17-417-5 17-6
18
19
20
21
12
11
10
9
8
7
6
32
4
5
1
LS3
250
250
250
200
200
200
200
250
250
250
250 250
200
200
200
200
200
200
200200200
200
200
250
200 200
200
20000
P:\PRODWGS\QUEEN-CHARLOTTE\163-11\163.11 FIGURE 2-1 10-07-27
Asphalt Road Surface
Gravel Road Surface
Force Main (size in mm)
Manhole
Lift Station
Sewer Lines (size in mm)
LEGEND
30
200
200
LS4
VILLAGE OF QUEEN CHARLOTTE
EXISTING SEWAGE SYSTEM
SHEET 1 OF 2
FIGURE 2-1
Note:
Sewers are 150mm diameterunless shown otherwise.
HaidaPoint
SkidegateLanding
Outfall extends 500mbeyond this point
Outfall PumpingStation
200
Outfa
ll
N
DL 16 School
0 50 100 200 metres
3rd Ave 3rd
St
6th
St
8th
St
9th
St
3rd Ave
Highway 33
2nd Ave
10th
St
5th Ave
6th Ave
7th
St
Highway 33
Cem
etery
Rd
Honna Rd
Queen Charlotte Mainline
4th
St
Bay
5th
St
Plan14055
Plan 9663
Plan 8853
Plan10697
Plan5608
Plan
4564
Plan5673
11870
APlan 11122
Plan 11213
1
2
3
Bk I
Bk HBk G
Bk 35 Plan 10371A B C D E F
Bk 1 Bk 2 Bk 3
Bk 16
Bk 21
Bk 18 Bk 17
Bk 19
Bk 31
DCB
APlan 10371
AQCMC
Plan 14485
Plan11911
Bk 20
Bk30
Bk 29
Bk27
Bk 29
Bk A
Bk 4 Bk 5Bk 6 Bk 7
Bk 15
Bk 14 Bk 13 Bk 12
Bk 24Bk 25
Bk 23Bk 22
13
1
A
Plan 10563
9 13
12
12
1212 12
12 1212
1
1 1 1 1
1
1
11
11
10 1A
15 13
18
10
1
13
1313 13 13
13 131324
24 24 24
2424
24 24 2424
Plan
9307
Haydn Turner Campground
Cemetery
Log Sort
L. 81924 9
Plan 14832
10
Ctb
Bearskin Bay
142
141140
138
139
137 136
135
134
133 132
131 130
123
124129
125144-2144-1143145146146-1146-2
149
148
147 LS1
LS2
127
126
128
116
115 114
113
112
111 110118 109
117
92919093
81
8089
82
83 84
8887
86
8597 71 70 69
62-2
94
95
96 77 76 75
7265
68
122
121 119102
103
104120 105
106107
101
100
99108 200
200
200
200
200200
200
200
200200
200
200100
100
200
200
200
200
200
200
200200
Asphalt Road Surface
Gravel Road Surface
Force Main (size in mm)
Manhole
Lift Station
Sewer Lines (size in mm)
LEGEND
30
200
200
LS4
VILLAGE OF QUEEN CHARLOTTE
EXISTING SEWAGE SYSTEM
SHEET 2 OF 2
FIGURE 2-1
Residuals Forcemain FromWater Treatment Plant
N
100
Note:
Sewers are 150mm diameterunless shown otherwise.
P:\PRODWGS\QUEEN-CHARLOTTE\163-11\163.11 FIGURE 2-1 10-07-27
163.11 ©2010 Page 2-2
There are 402 service connections serving residential and commercial properties in the
Village core. Most residences and businesses are connected to the sewer system.
As noted previously, the unserviced area between Smith Point and Skidegate Landing is
serviced with septic tanks and the Ferry Terminal with a holding tank.
2.1.2
Pumping Stations
All pumping stations are duplex submersible fibreglass reinforced plastic (FRP) stations
with emergency overflows and kiosks to house electrical equipment and controls. The
stations contain Flygt pumps, initially installed in 1984. In 2000, Flygt provided the
following data (which differs significantly from the pump data shown on the as
constructed drawings). Since 2000, the pumps are reported to have undergone annual
servicing with some pump replacement, but no model changes.
1. Pumping Station No. 1, located at Highway 33 and 8th
Street.
• 2 Pumps – Flygt Model CP 3085 MT
3 in. inlet/outlet
6.52 inch impeller #434
3.0 HP, 208/3/60
225 USgpm (180 gpm) at 26 ft TDH
• 6 ft. diameter wet well
• 4 inch forcemain
• 8 inch overflow
163.11 ©2010 Page 2-3
2.
Pumping Station No. 2, located at 3rd Avenue and 5th Street.
• 2 Pumps – Flygt Model CP 3127 HT
4 inch inlet/outlet
9.12 inch impeller #483
10 HP, 208/3/60
400 USgpm (320 gpm) @ 56 ft TDH
• 6 ft diameter wet well
• 6 inch forcemain
• 8 inch overflow
3.
Pumping Station No. 3, located on Bay Street.
• 2 Pumps – Flygt Model CP 3127 HT
4 inch inlet/outlet
9.12 inch impeller #483
10 HP, 208/3/60
400 USgpm (320 gpm) at 56 ft TDH
• 6 ft diameter wet well
• 6 inch forcemain
• 10 inch overflow
4.
Pumping Station No. 4, located on Wharf Street.
• 2 Pumps – Flygt Model CP 3127 HT
4 inch inlet/outlet
9.12 inch impeller #483
10 HP, 208/3/60
550 USgpm (440 gpm) at 45 ft TDH
• 8 ft. diameter wet well
163.11 ©2010 Page 2-4
• 8 inch forcemain
• 10 inch overflow
5.
The Outfall Pumping Station No. 5, located near Smith Point on Highway 33.
• Comminutor
• 2 Pumps – Flygt Model CP 3127 HT
4 inch inlet/outlet
9.12 inch Impeller #483
10 HP, 208/3/60
580 USgpm (460 gpm) at 42.6 ft TDH
Average = 490 gpm
650 USgpm (520 gpm) at 36.1 ft TDH
• 10 ft diameter wet well
• 8 inch outfall
• 10 inch overflow
Staff advise the pumping stations have adequate capacity for present day connections and
that annual servicing remains in effect. The stations appear to be in good condition.
In 2003, standby diesel generator sets were installed at each of the pumping stations to limit
overflow during power outage. Each generator (supplied by Simson Maxwell) is identical
as follows:
Model: 25PS-U2G-63
Standby Service: 25kW, 31.25 kVA, 3Ph., 120/208 V, 60 Hz., 1800 RPM
Engine Model: CM51029
Gen. Model: UC1224C
ATC Model: TS853MS3-100A-208
Control Panel: EGC-PV-ES52-M
163.11 ©2010 Page 2-5
Battery Charger: CH12V3AE
Battery: Group 27C, 850 CA, 700CCA, 135R/C
Since the installation of the gensets, there have been no reported overflows of sewage from
the pumping stations.
An odour control unit (supplied by Sanitherm Engineering) was also added to Pump Station
No. 4 in 2003. It is a Calgon Centaur HSV granular activated carbon unit as follows:
VentSorb Model: HF400, 120 USgal, 170 lbs activated carbon
Regeneration Time: 24 hours (1200 US gallons at 1-USgpm)
Fabco Blower Model: HFR 160-17D, 1/2 HP, 200 cfm @ 4” w.c., 230/3/60.
Ongoing maintenance of the odour control unit includes the requirement to regenerate the
activated carbon on an annual or bi-annual basis.
2.1.3
Outfall
The outfall Pumping Station No. 5 discharges sewage through an approximately 1200 m
long 200 mm HDPE Series 45 outfall. The pipe is reported to be buried in a trench to just
below the low tide mark and it then continues on the sea bottom to terminate at a depth of
20 m below low water. The outfall terminus reduces to 100 mm HDPE Series 60 pipe in
the form of a single port angled upward diffuser that discharges at the 17.2 m depth below
low water. Concrete anchor blocks are spaced along the outfall to weight the pipe and
prevent its movement.
163.11 ©2010 Page 2-6
2.2 Treatment and Disposal Requirements
There is no treatment of sewage prior to its discharge into Bearskin Bay.
The discharge is authorized by Ministry of Environment Permit No. 6427, issued March 15,
1989. The Permit includes the following important requirements:
• Maximum Day Flow = 2295 m3
• Effluent quality = comminuted raw domestic sewage.
/d
• Sufficient land to be acquired for future treatment plant.
• Outfall to be 1200 m seaward of low water and at 20 m depth below low water.
In a letter dated August 6/09 (Appendix 2) Environment Canada issued an Inspector’s
Direction under the Fisheries Act to the Village. The Direction noted the Village discharges
untreated sewage to Bearskin Bay in violation of the Fisheries Act. The Inspector directed
the Village as follows:
1. Submit written report by October 31/09 that outlines strategy for development of a Plan.
2. Beginning January 30, 2010, submit quarterly reports to the Inspector outlining
measures taken in previous quarter to meet the Inspector’s Direction.
3. By June 1, 2010 finalize the Plan to provide sewage treatment for the Village.
The Direction was amended May 31, 2010 to extend the date to finalize the Plan to
December 31, 2010.
163.11 ©2010 Page 2-7
2.3 Sewage Flows
Village staff records the pump hour readings at each of the five pumping stations Monday
through Friday. The design flow rate for each pump is then multiplied by the pump run
hours to estimate the daily, weekly, or monthly flow from each pump station. Pump
Station No. 5 discharges the total Village flow into the outfall.
Flow records for 2008 and 2009 for Pump Station Nos. 4 and 5 were analyzed and along
with precipitation data and are summarized in Table 2-1.
TABLE 2-1 PUMP STATION NOS. 4 AND 5 RECORDED FLOWS
Month
2008 2009
Flow (m3Precipitation
(mm) /mo) Flow (m3
Precipitation (mm)
/mo)
P.Stn. 4 P.Stn. 5 P.Stn. 4 P.Stn. 5
Jan 19,120 17,514 116.4 12,290 23,946 96.2
Feb 11,750 23,162 112.8 10,730 25,973 76.6
Mar 16,770 55,257 103.4 1 10,010 21,608 88.1
Apr 13,830 12,959 73.0 9,500 18,432 19.4
May 12,820 19,851 58.5 8,100 13,460 41.4
June 10,900 9,770 56.8 8,470 14,189 26.0
July 11,450 17,757 71.0 8,900 15,014 5.6
Aug 9,360 18,230 33.0 9,460 16,865 61.0
Sept 9,740 19,973 80.0 10,090 12,717 103.6
Oct 13,590 30,500 109.0 9,230 22,162 86.8
Nov 11,790 24,014 197.8 16,720 53,419 114.8 2
Dec 13,900 22,176 58.4 9,820 11,878 56.4
TOTALS 155,020 271,163 - 123,320 249,663 3
1 Monthly flow not valid as pump controls malfunctioned from March 5 to 20. 2 Monthly recorded flow not valid. 3 Excludes November 2009.
163.11 ©2010 Page 2-8
Tributary to Pump Station No. 4 is about 95% of the Village sewer connections. Flow from
Pump Station No. 5 should be about 5% higher than the flow from Pump Station No. 4. As can
be seen in Table 2-1, flow from Pump Station No. 5 is generally two times the flow from Pump
Station No. 4. We conclude the flow records at Pump Station No. 5 are not reliable; possibly due
to the pumps not producing the pump rated flow.
The flow records for Pump Station No. 4 have been used to calculate the unit flows; summarized
in Table 2-2.
TABLE 2-2 PUMP STATION NO. 4 UNIT FLOWS
Flow 2008 2009
m3 lpcd /d m3 lpcd /d
Average Annual (AAF) 425 524 338 417
Maximum Month (MMF)
617 (Jan.) 761 557 (Nov.) 688
Maximum Day (MDF) 1160 (Oct 22) 1432 710 (Oct. 29) 877
Unit flows were calculated using an estimated 810 people tributary to Pump Station No. 4 (950
people less 100 in Skidegate Landing times 95%).
163.11 ©2010 Page 3-1
SEWAGE TREATMENT AND DISPOSAL – FEASIBILITY STUDY 3.0 VILLAGE GROWTH AND DEVELOPMENT
Historical population data and the Village’s outlook for future development are highlighted in
this section.
3.1 Historical Population
Census data for the Village (including Skidegate Landing) shows a decrease in population
in recent years.
1986 1996 2001 2006
1090 1222 1045 948
Discussion with Village staff indicates the 2010 population is about 960, including
approximately 80 residents between Smith Point and Skidegate Landing and 20 or so
residents in Skidegate Landing.
3.2 Future Growth and Development
The Official Community Plan (OCP) is dated 1993. The Village is presently in the
process of updating the OCP. The update is scheduled to be completed by end of 2010 or
early 2011.
163.11 ©2010 Page 3-2
Populations projections in the draft OCP include a low, medium and high growth rate
over 25 years as follows:
TABLE 3-1 PROJECTED POPULATION GROWTH
Year Population Growth
Low Medium High
2008 1000 1000 1000
2033 1250 1500 2000
Based on discussions with Village staff, it is apparent there is considerable uncertainty on
the rate of future growth, and there is even the possibility of further decline in population
in the near future.
For the purpose of developing concept designs for this feasibility study, the 2010
population is estimated at 960 people, and the 2030 population is predicted to increase to
1250 people.
163.11 ©2010 Page 4-1
SEWAGE TREATMENT AND DISPOSAL – FEASIBILITY STUDY 4.0 DESIGN CONSIDERATIONS AND CRITERIA
In this section water supply protection is discussed, treatment and effluent disposal
standards/guidelines are summarized, wastewater flow projections are made, and wastewater
quality criteria are selected. Also included in this section is a description of the treatment plant
site options.
4.1 Water Supply and Consumption
It is important that wastewater facilities are sited in a location that will prevent
contamination of the community water supply. The Village water sources are two wells
at Tarundl Creek and the Honna River. Both these sources are treated.
Both sources are to the west of existing and proposed OCP development. No sewage
treatment plant sites are proposed near the water sources (Section 4.5).
The proposed sewage treatment plant and disposal facilities will not adversely affect the
water supply sources.
Water consumption records provide a check on sewage flow estimates. Water used
within a home or business forms the dry weather base sewage flow. In wet weather,
sewage flows increase due to inflow and infiltration (I&I) into the sewage collection
system.
163.11 ©2010 Page 4-2
Water meter flow records for 2008 and 2009 show average annual consumption of 512
lpcd for 2008 and 526 lpcd for 2009. These unit flows are normal relative to other British
Columbia coastal communities. The average annual sewage flows (Table 2-2) in 2008
were 524 lpcd and in 2009 were 417 lpcd. The relationship between water consumption
and sewage flows is reasonable.
4.2 Treatment and Disposal Standards/Guidelines
The Municipal Sewage Regulation (MSR) issued in 1999 under the Province’s then
Waste Management Act (now Environmental Management Act) establishes Province
wide standards for effluent quality, for design and construction of wastewater facilities
and for effluent and environmental monitoring.
The Organic Matter Recycling Regulation (OMRR) issued in 2002 under the Waste
Management Act establishes Province wide standards for biosolids reuse.
Effluent quality standards for use of reclaimed water, for discharge to receiving waters
and for discharge to ground are set out in the MSR. Applicable to the Village are the
effluent standards for discharges to marine waters. Discharge to ground and the use of
reclaimed water are not feasible options for the Village. The standards for effluent
discharges to marine waters are summarized in Table 4-1
163.11 ©2010 Page 4-3
TABLE 4-1 STANDARDS FOR EFFLUENT DISCHARGES TO MARINE WATERS
Parameter Receiving Water
Open Embayed
Treatment Requirement Secondary Secondary
Effluent Quality
• BOD5 45 , mg/l 45
• TSS, mg/l 45 45
• pH 6.0 – 9.0 6.0 – 9.0
• Disinfection (1)
• Total P, mg/l
(1)
- 1.0
• Ortho P – mg/l
(2)
- 0.5
• Ammonia
(2) (3)
(3)
(1)
Recreational waters; MPN = 200/100 ml fecal coliform at edge of IDZ.
Shellfish bearing waters ; MPN = 14/100 ml fecal coliform at edge of IDZ.
(2) Requirement may be waived if environment impact study so justifies. (3)
Maximum concentration to ensure non toxic effluent based on “back calculation” from end of outfall
pipe to edge of IDZ.
Embayed waters are defined as marine waters located shore side of a line up to 6 km long
drawn between two points on a continuous coastline; or located so that the maximum
width of sea access by any route is less than 1.5 km wide; or marine waters in which
flushing action is considered inadequate by the manager.
The initial dilution zone (IDZ) in marine waters refers to the area within a 100 m radius
of the end of the outfall pipe.
163.11 ©2010 Page 4-4
4.3 Wastewater Flow Projections
Based on the Section 2.3 pump station flow analysis, the following unit flows have been
selected for concept design purposes:
• Average Annual Flow (AAF) = 500 lpcd
• Maximum Month Flow (MMF) = 750 lpcd
• Maximum Day Flow (MDF) = 1200 lpcd
MDF is used for process design of treatment plants (other than aerated lagoons that utilize
MMF). Plants are sized for the projected 20 year design flow with due consideration for
performance during initial years of operation and for equipment useful life.
The treatment plant concept design will utilize the following design criteria.
Design Population = 1250
Design Flow (MDF) = 1500 m3
/d
Sewers and pumping stations must be designed for the projected 20 year Peak Flow,
calculated as follows:
• Peak Flow = P x a x f + C + I
• Where: P = tributary population
a = ADWF (per capita)
f = peaking factor =
10004
100018
P
P
+
+ to maximum of 4
C = institutional / commercial / industrial flow
I = infiltration and inflow = 46 L/mm dia./km/day
163.11 ©2010 Page 4-5
4.4 Wastewater Quality
There are no data that can be used to quantify the Village’s raw sewage (BOD5, TSS,
NH3
, etc.).
For treatment plant concept design the following design criteria, representative of normal
domestic sewage, will be used.
• Influent BOD5
• Influent TSS = 200 mg/l
= 200 mg/l
• Influent NH3 = 25 mg/l
• Influent Total P = 6.0 mg/l
• Influent Fecal Coliform = 5 x 106
• Secondary Effluent Fecal Coliform = 500,000 MPN/100 ml
MPN/100 ml
4.5 Treatment Options
There are a number of technologies that can provide a secondary level of treatment to
produce effluent that will meet the MSR criteria for BOD5
/TSS = 45 mg/l and the 96 hr
LC50 = 100% toxicity criteria.
Most wastewater treatment systems include some form of physical pre-treatment to
remove trash (plastics, rags, etc.) from the raw wastewater. Many also include primary
gravity settling tanks to separate crude biological solids from the raw wastewater
(primary treatment). Crude solids that are collected at the bottom of the primary settling
tank require further treatment, usually by biological processes. The settled wastewater
leaving the primary tanks enters the biological (secondary) treatment process train. For
some smaller systems, septic tanks may be used to provide primary treatment. Primary
treatment normally removes about 50% of the solids and 30% of the oxygen demand
(BOD5) from the raw wastewater.
163.11 ©2010 Page 4-6
Biological (secondary) processes in wastewater treatment systems rely on bacteria to
metabolize oxygen-demanding degradable organic material(BOD5) in the wastewater.
The process bacteria may be cultured in suspension in the process liquid (usually referred
to as activated sludge systems), or in a slime layer attached to some solid media
(sometimes referred to as fixed or attached growth systems). Secondary treatment
removes up to 95% of the solids and the BOD5
from the wastewater.
Depending on the treatment requirements, the system may also be designed to achieve
filtration of the effluent to remove residual solids, disinfection, and /or removal of
nitrogen and phosphorus.
Bacteria that are produced in secondary treatment are usually separated from the treated
process liquid in secondary gravity settling tanks (often referred to as clarifiers). The
clarified, treated liquid flows out of the secondary clarifier over a weir, and the settled
biological (bacterial) solids are collected at the bottom of the settling tank. Biological
solids must be periodically removed from the system and subjected to further treatment
(e.g., composting or digestion prior to beneficial use), or disposed of to landfill.
Many variants of suspended growth and fixed growth biological treatment are available.
Brief descriptions of some of these are outlined hereafter.
1.
Activated Sludge Process
In the activated sludge process, primary treated (2 hours detention) wastewater flows to a
basin where it is mixed with a culture of bacteria that grow and develop in suspension in
the process liquid. Dissolved oxygen is normally provided to the process liquid by a
submerged grid of aeration piping with diffusers that continuously supply fine bubbles of
air to the process liquid (floating mechanical aerators/mixers that entrain air from the
atmosphere may also be used). The aeration basin (typically 6-8 hours detention) is
163.11 ©2010 Page 4-7
followed by a clarifier where the process bacteria are separated from the treated liquid by
gravity settling. The bacteria that settle to the bottom of the tank are collected and
pumped back to the aeration basin, and the treated water exits the clarifier via a surface
overflow weir. In some cases, primary treatment is not used, and the aeration basin is
made larger (typically 18-24 hours detention) to compensate for the additional load; this
is referred to as extended aeration activated sludge. Excess process bacteria are removed
(wasted) from the process to maintain steady-state conditions; the excess bacteria mass is
commonly referred to as waste activated sludge (WAS).
Activated sludge processes can produce relatively high quality effluent. However, careful
attention to process operation is needed to control the biological solids inventory in the
system. Nuisance surface foams may develop, especially with extended aeration process
variants. The bacterial solids are also subject to infestation by filamentous organisms,
which inhibit gravity settling and may degrade effluent quality.
Conventional activated sludge is used at Comox and Kimberley.
2.
Sequencing Batch Reactor (SBR)
The Sequencing Batch Reactor (SBR) system is a version of the extended aeration
activated sludge process. SBR systems (also called fill and draw reactors) operate on the
same basic principles as extended aeration activated sludge systems; that is, the process
bacteria and the wastewater are mixed and aerated in the aeration basin, followed by
gravity settling to separate the solids from the treated liquid. However, in activated
sludge systems, aeration and gravity settling are carried out in two separate basins; in
SBRs, both processes occur in sequence in a single basin. The benefit is a “small
footprint” area requirement for the treatment works.
The SBR system normally includes five steps in sequence in a single basin, as follows:
163.11 ©2010 Page 4-8
a) fill/react (intermittent mixing and aeration during filling);
b) react (mixing and aeration);
c) settle (mixers and aerators shut off);
d) decant or draw (decanting of the clarified liquid from the surface of the tank); and
e) idle.
Excess solids are removed from the bottom of the tank during the decant step. Since the
system can only accept raw wastewater during the fill step, more than one basin (or a
storage basin) is required to treat a continuous flow of wastewater. A programmable
control system automatically controls the five step process. The SBR does not require
recycling of settled biological solids to the aeration basin; this eliminates the need for the
return pumping loop that is required for conventional activated sludge process.
Otherwise, advantages and disadvantages of the SBR process are similar to conventional
activated sludge.
The SBR process is used at Britannia Beach.
3.
Ecofluid Process
The Ecofluid system includes an extended aeration activated sludge process, followed by
an upflow sludge blanket for separation of the biological solids from the treated liquid
instead of a clarifier. Raw wastewater enters an aerated trap for removal of debris, and
then flows to the aeration basin, where suspended growth bacteria metabolize oxygen-
demanding substances (BOD5). The liquid leaving the aeration tank is directed to flow
upward through the bottom of a V-shaped weir located near the surface of the liquid in
the aeration tank. A layer of settled biological solids (sludge blanket) develops at the
bottom of the V. Biological solids in the process liquid leaving the aeration basin are
retained as the liquid passes upward through the sludge blanket, and the treated clarified
liquid flows out over the top of the weir. Waste biomass from the process is said to be
completely stabilized, due to the long sludge age of the process. High hydraulic flows
163.11 ©2010 Page 4-9
may cause the sludge blanket solids to be carried over the weir with the effluent,
degrading effluent quality. Otherwise, advantages and disadvantages of Ecofluid are
similar to those described for activated sludge and SBR.
Ecofluid technology is used at several ski resorts and strata housing developments in
British Columbia.
4.
Rotating Biological Contactor (RBC)
The rotating biological contactor (RBC) is a series of closely-spaced plastic disks
attached to a central shaft. The shaft is mounted so that the disks are partially submerged
in the wastewater. Fixed growth bacteria develop in a slime layer attached to the plastic
disks. Turning of the shaft alternately contacts bacteria with the wastewater and the air.
An anaerobic (un-aerated) primary section for gravity settling/digestion of crude solids
and equalization of flows is normally included upstream of the tank containing the RBC,
with a clarifier downstream of the RBC for separation of biological solids from the
treated liquid. Settled biological solids may be re-circulated to the RBC tank.
Fixed growth processes such as RBC are reported to be more resistant to toxic shocks
than suspended growth (activated sludge) processes. The RBC process also requires
relatively little operator attention compared to activated sludge and its variants, power
demand is lower, and the settling qualities of the bacterial solids are better. On the other
hand, the RBC process takes more space than an equivalent activated sludge system.
RBC units are in use at Lund and at several Indian reserves within British Columbia.
5.
Integrated Fixed Film Activated Sludge (IFAS)
IFAS is a hybrid version of the activated sludge process that includes both suspended
growth and fixed growth components. Neutrally buoyant solid media particles are added
163.11 ©2010 Page 4-10
to the aeration basin, and fixed growth bacteria develop in a slime layer attached to the
media; this supplements the BOD5
removal by suspended bacteria. Clarifiers are
required to separate the biomass from the treated liquid. The media is prevented from
flowing to the secondary clarifiers by tubular screens installed in the aeration tanks.
Biomass separated from the treated liquid may or may not be returned to the bioreactor.
All IFAS systems require adequate preliminary treatment design. Primary treatment or
fine screening will avoid ragging and material build-up on the media in the aeration basin,
and clogging of the dispersed media and retaining screens. Proper mixing is required for
solids suspension and oxygen diffusion.
The IFAS system requires less space than conventional activated sludge, and effluent
quality is typically higher. However, the cost of IFAS is greater than for an equivalent
activated sludge or RBC system.
6.
Membrane Bioreactor (MBR)
The membrane bioreactor (MBR) consists of a biological reactor with suspended
(activated sludge) biomass and separation of bacterial solids from the treated liquid by
fine-pore membranes. The treated wastewater is separated from the mixed liquor by the
process of membrane filtration rather than in a secondary clarifier as in conventional
systems. High concentrations of biological solids can be maintained in the aeration basin,
which reduces the aeration basin size compared to conventional activated sludge. The
treated effluent is drawn through the membrane by pumping. By replacing secondary
clarifiers, membranes avoid issues of filamentous sludge bulking and other settling and
clarification problems. However, membranes require adequate scouring, chemical
cleaning and upstream fine screening to prevent solids from adhering to the membrane
fibres causing fouling or plugging. Energy demand is higher than for other processes, and
membranes must be replaced on a regular basis; these factors lead to higher treatment
costs than for most other processes. Effluent quality is excellent due to the fine-pore
filtration.
163.11 ©2010 Page 4-11
The City of Powell River utilizes a membrane plant.
7.
Aerated Lagoons
This technology requires about 25 days hydraulic detention time and consequently a large
area is needed. The benefit is a low construction cost (providing ground conditions are
suitable) and simple, reliable, low cost operation and maintenance. A two cell, balanced
cut and fill construction with polyethylene liner is normally provided along with a
submerged diffused aeration system. Effluent clarification takes place at the end section
of the second operating cell. TSS levels are typically higher in lagoons than other
technologies; thus the MSR allows lagoon effluent to have TSS = 60 mg/L.
Biosolids are left to accumulate in the bottom of the cells. Normally removal is needed
after 10-20 years. Removal involves dewatering the cells, removal and drying of the
biosolids and their disposal to landfill.
Aerated lagoons service many communities in the Province, including the City of Duncan
and the Town of Smithers.
163.11 ©2010 Page 4-12
8.
Oxidation Ditch
Between 18 to 24 hours detention time is used for oxidation ditch treatment. Two ditches
and two clarifiers are normally provided for liquid treatment. The ditches can be either
concrete or lined earthen cells. An aerobic digester is needed for biosolids treatment and
the biosolids requires dewatering for disposal.
This facility is similar to the plant that serves Port Edward and Campbell River.
4.6 Effluent Disposal
In the Long Term Water and Sewerage Plan report (D&K 2000), a section on effluent
disposal was presented. It is repeated hereafter because it remains relevant to siting of a
Village outfall.
Previous reports (Stanley 1979, 1980, 1981) included oceanographic studies and
discharge modelling for two outfall location options; off Smith Point and off the log
dump. The 1981 report noted the following:
“In discussion with physical oceanographers, local fisherman and upon review of the
bathymetrics of Skidegate Inlet and Bearskin Bay, in particular, it became apparent that
an outfall from the MacMillan Bloedel location (log dump) would discharge the sewage
to a point where adequate flushing cannot occur. The sewage would impinge on the
shoreline very soon after discharge in the flood and would not be able to flush out of the
funnel shaped bay on the ebb tide.
The marine studies were therefore concentrated on the Smith Point outfall site because it
was closer to the mouth of the inlet and could discharge in deep water well clear of land.
The oceanographic studies included sea bottom profiling, water column analysis for
temperature and conductivity, current drogue tracking and current meter measurements.
163.11 ©2010 Page 4-13
Of note, the currents generally parallel the shoreline. On the flood tide, the currents are
westward into Bearskin Bay. On the ebb tide, the currents are eastward out of Bearskin
Bay toward Skidegate Inlet.
Also of note and importance was the that inshore of 900 m from Smith Point, the ebb tide
directed the drogues onto the beach at the south west side of Haida Point. Considerable
driftwood was also noted in this area. For this reason the existing outfall was extended
to 1200 m offshore from Smith Point. On the flood tide, drogues released 1100 m from
Smith Point tracked south of Maple Island toward Mandle Channel.
Current meter readings at the 1100 m location from Smith Point showed a typical current
of 0.4 to 0.25 knots.
Dye studies conducted at the 1100 m station indicated that if the effluent plume surfaced
(following initial dilution), the dispersion before reaching Maple Island on the flood
would be 10 to 20 fold and greater than 34 times before reaching Haida Point on the ebb.
At the time of the oceanographic studies (March 4, 1981) there was little stratification in
the water column. Summer conditions would likely result in stratification. Bottom
profiling along the existing outfall alignment indicates 1.5 to 2.0 m of soft “mud”
underlain by “firmer material” that is 2.0 to 3.0 m thick which is underlain by bedrock.
Biological composition of the sea bottom was reported as limited to “in faunal benthic
organisms” (worms and clams). No organisms living on the sea bottom were noted.
Dilution and dispersion modelling indicated an initial dilution following discharge
ranging from 120:1 to 2210:1 (stratified conditions). Under un-stratified conditions the
initial dilution ranged from 140:1 to 840:1. Total dilution (initial and dispersion) would
be a minimum of 1200:1 at Maple Island, the nearest land mass. It should be recalled,
163.11 ©2010 Page 4-14
however, that the drogue studies indicate the effluent plume will pass south of Maple
Island and not impact on the Island.
The 1981 studies were thorough and well done. The selection of the outfall discharge
1100 m off South Point is supported and complies with the requirements in the MSR.
Any new outfall within Bearskin Bay should discharge in similar water conditions.”
4.7 Treatment Plant Siting Criteria
The site for a treatment plant should be isolated from residential development and public
use areas. Ideally a site within industrial zoned land or within agricultural land should be
selected. The status of First Nations lands must be considered in site selection.
Because influent and effluent pipes to and from the site will have useful lives of over 50
years the site should be sized for a long term use; 50 years minimum, 100 years desirable.
For the Village, as noted in Section 3.2, Table 3-1, the 25 year high growth population
projection is 2,000 people. A site suitable for minimum 3,000 people should be selected.
Based on a “small footprint” type of treatment plant (SBR, Ecofluid, etc.) the useable
portion of the site should be about 0.11 ha in size for a long term population of 3,000.
With a 30 m buffer area around the treatment units the area requirement increases to 0.86
ha. Long detention treatment such as aerated lagoons requires considerable more area, a
minimum of 6.0 ha for 3,000 people, including 30 m buffer zone.
To minimize pumping, the site should be near sea level. To minimize groundwater
control the site should be above the 200 year flood level or be capable of being
economically floodproofed.
Site topographically should be gently sloping. Soil conditions must accommodate plant
structural loading and should allow conventional excavation and dewatering.
163.11 ©2010 Page 4-15
The inter-relationship between influent sewers to the plant and the effluent pipeline and
ocean discharge location must be considered to achieve a cost effective pipeline system.
Also important, is the outfall must be located in an area that provides good integration of
the effluent into the seawater mass. The outfall location must minimize impact on
fisheries resources and recreational use of the water.
The potential use of reclaimed water (industrial process water, irrigation water, etc.)
should be considered in siting the plant to maximize potential reuse opportunities.
Siting must consider the potential for odour and noise nuisance at the nearest residential
or public use area. The impact of plant construction on surface water and groundwater
and on fisheries and wildlife resources must be considered.
The site must not impact archaeological sites.
4.8 Treatment Plant Site Options
The siting criteria were reviewed with Council members and staff at the initial meeting
held March 15, 2010. A number of sites were considered. There is no obvious preferred
site. Only small sites are available near the existing outfall (Smith Point). A relatively
large site exists on the log sort property that would allow a less expensive form of aerated
lagoon treatment for an initial stage plant, however, a part of the conveyance system
needs to be rebuilt, a new outfall would be required and this site remains active and is not
for sale. A site may be found in the area between Smith Point and Skidegate Landing
(Central Area) that requires about a 1.2 km extension of the conveyance system. Two
sites in the Skidegate Landing may be found that require a 3 to 4 km extension of the
conveyance system and a new outfall. The extension of the conveyance system has the
benefit of allowing service to properties between Smith Point and Skidegate Landing.
163.11 ©2010 Page 4-16
In order to provide information needed to make a decision on the best general location for
a future Village owned treatment plant, four siting options were selected as follows:
1. Smith Point Area
2. Central Area
3. Skidegate Landing West Area
4. Skidegate Landing East Area
In addition, joint treatment and disposal with the Skidegate Band will be considered.
163.11 ©2010 Page 5-1
SEWAGE TREATMENT AND DISPOSAL – FEASIBILITY STUDY 5.0 TREATMENT AND DISPOSAL OPTIONS
In this section, a concept level design is developed for each of the four potential sites for a
Village owned treatment plant. The option of joint treatment and disposal with the Skidegate
Band is also concept designed. The section concludes with an evaluation of the treatment and
disposal options.
Finding a large parcel of land that meets the treatment plant siting criteria will be challenging.
For the purpose of this feasibility level study the “small footprint” treatment technologies (SBR,
Ecofluid, etc.) have been selected. Even so, in order to provide for a long term service
population of 3,000, a site should desirably be minimum 0.9 ha (allows 30 m setback) and at the
very least 0.3 ha (reduces setback to 10 m). It is assumed the Village will be able to acquire a
minimum 0.6 ha parcel. Included in the cost estimates is $500,000 for land purchase.
The concept designs for the Village owned options are based on an initial stage design population
of 1,250 people. Included are the needed extensions/modifications to the sewage conveyance
system, a “small footprint” treatment plant for the site, and either use of the existing outfall at
Smith Point or the provision of a new outfall.
For the Skidegate Band joint treatment option; the extension of the conveyance system to
Skidegate, the upsizing of the Skidegate conveyance system to also include the Village’s sewage
flows and the apportionment of the Band’s treatment plant and outfall costs (based on the relative
design population/flow for the Skidegate Band and Village) are included in the concept design.
163.11 ©2010 Page 5-2
5.1 Treatment Plant Concept Design
For the purpose of this feasibility study, it has been assumed that a small site may be
acquired for a Village owned treatment plant. A “small footprint” SBR technology has
been selected for the treatment plant.
Included in the treatment works are the following:
• Influent mechanical screening with screenings dewatering;
• Provision for future grit removal, if needed;
• Two SBR tanks, each sized for 75% of MDF;
• One aerobic digester;
• Biosolids dewatering press and storage bin;
• Control building to house influent screen; biosolids dewatering equipment, office
area, washroom, work bench area, electrical/control room, blower room;
• Outside standby generator;
• Odour control works for influent screening and biosolids dewatering;
• Roof structure over SBR and digester tanks.
Tankage for the SBR and digester would be cast-in-place concrete. Building construction
would be architectural concrete block with metal roof.
Initial stage (1250 people) capital and operation and maintenance (O&M) costs are
detailed in Appendix 3 and summarized as follows:
• Capital Cost $4,550,000
• O&M Cost $96,500/year
163.11 ©2010 Page 5-3
5.2 Option 1 – Smith Point Area
The benefit of a treatment plant site near Smith Point is that the required extension of the
sewer system is minimum and the existing outfall can be used. The challenge will be to
find a site that is sufficiently large to provide for even a “small footprint” treatment
technology.
Existing Pump Station No. 5 can be used to pump sewage to the treatment plant. At the
treatment plant site an effluent pump station is needed along with a section of land outfall
to connect to the existing 200 mm marine outfall.
This option is illustrated on Figure 5-1. Initial stage construction (1,250 people) cost
estimates follow. Details are provided in Appendix 3.
Capital Costs
• Treatment Plant $4,550,000
• Conveyance System and Outfall $649,000
• Treatment Plant Site
Total $5,699,000
$500,000
O&M Costs
• Treatment Plant $96,500 / year
• Conveyance System and Outfall $18,000
Total $114,500 / year
/ year
163.11 ©2010 Page 5-4
5.3 Option 2 – Central Area
The sewage collection system must be extended about 1.2 km to service a site in the
Central Area. Existing Pump Station No. 5 can be re-used along with a 200 mm
forcemain extension to the treatment plant. The existing outfall at Smith Point can be
used by pumping the treatment plant effluent in a 200 mm land section of outfall that is
placed in the influent forcemain trench.
Figure 5-1 illustrates this option, cost estimates are provided in Appendix 3 and are
summarized as follows.
Capital Costs
• Treatment Plant $4,550,000
• Conveyance System and Outfall $1,255,000
• Treatment Plant Site
Total $6,305,000
$500,000
O&M Costs
• Treatment Plant $96,500 / year
• Conveyance System and Outfall $18,600
Total $115,100 / year
/ year
163.11 ©2010 Page 5-5
5.4 Option 3 – Skidegate Landing West Area
A site near Haida Point is assumed. This allows for a new outfall to be constructed near
Haida Point to the 30 m depth in Skidegate Inlet. The existing outfall would revert to an
emergency overflow status for Pump Station No. 5.
Pump Station No. 5 would be fitted with new pumps. A 200 mm forcemain will extend
3.1 km from Pump Station No. 5 to the treatment plant site. The treatment plant site is
assumed to be at a high enough elevation to allow gravity discharge of effluent to the
outfall.
Figure 5-1 illustrates this option. Cost estimates are detailed in Appendix 3 and are
summarized hereafter.
Capital Costs
• Treatment Plant $4,555,000
• Conveyance System and Outfall $2,108,000
• Treatment Plant Site
Total $7,158,000
$500,000
O&M Costs
• Treatment Plant $96,500 / year
• Conveyance System and Outfall $16,600
Total $113,100 / year
/ year
5.5 Option 4 – Skidegate Landing East Area
163.11 ©2010 Page 5-6
Similar to Option 3, Pump Station No. 5 will be fitted with new pumps and a new 200
mm forcemain will extend 4.2 km to discharge to the treatment plant.
A new outfall will be constructed near Image Point to discharge into 30 m of water in
Skidegate Inlet. The treatment plant site is assumed to be at a high enough elevation to
allow gravity discharge of effluent to the outfall.
Figure 5-1 illustrates this option. Cost estimates are detailed in Appendix 3 and are
summarized as follows:
Capital Costs
• Treatment Plant $4,550,000
• Conveyance System and Outfall $2,753,000
• Treatment Plant Site
Total $7,803,000
$500,000
O&M Costs
• Treatment Plant $96,500 / year
• Conveyance System and Outfall $18,800
Total $115,300 / year
/ year
DL 16 School
0 100 200 400 metres
RelaxRd
Husband Rd
3rd Ave
Wharf St
Ca
us
ew
ay
St
1st Ave
3rd Ave3rd Ave
3rd
St
2nd Ave
2n
dS
t
1s
tS
t6th
St
8th
St
9th
St
3rd Ave
Highway 33
2nd Ave
10
thS
t
5th Ave
6th Ave
7th
St
Highway 33
Cem
etery
Rd
Honna Rd
Queen Charlotte Mainline
3rd Ave
H
City Centre
4th
St
Bay St
2nd Ave
Ald
er
St
Highway 33
5th
St
Plan14055
Plan 9663
Plan 8853
Plan10697
Plan5608
Plan
4564
Plan5673
11870
APlan 11122
Plan 11213
1
2
3
Bk I
Bk HBk G
Bk 35 Plan 10371A B C D E F
Bk 1 Bk 2 Bk 3
Bk 16
Bk 21
Bk 18 Bk 17
Bk 19
Bk 31
DCB
APlan 10371
AQCMC
Plan 14485
Plan11911
Bk 20
Bk30
Bk 29
Bk27
Bk 29
Bk A
Bk 4 Bk 5Bk 6 Bk 7
Bk 8 Bk 9Bk 1 Bk 6
Bk 7
Bk 8Bk 11
Bk 10
Bk 2 Bk 51 1
28 28
14 14
1
1 1
12
12 12
13
13
11
11
2
24
3
3
Plan 12752
13
Plan 13123
2
DBC
24
24 2415
15
Bk 15
Bk 14 Bk 13 Bk 11Bk 12
Bk 24Bk 25
Bk 23Bk 22
13
1
A
Plan 10563
9 13
12
12
1212 12
12 12
12 12 1212
1
1 1 1 1
1 1 20
1
11
11
10 11
2
8Bk 10
A
15 1313
18
10
1
13
1313 13 13 13 29 21
13 131313
24
24 24 24
2424 40
24 24 2424
Plan
9307
Haydn Turner Campground
Cemetery
Log Sort
A B
C
Plan11864
L. 819
L. 309
Pla
n3452
L.2872
L. 2974
24 9
Plan 14832
10
Plan11921
Plan
5464
PlanA
9420
Plan
11436
I
Blk. J
Plan
1
9182
Plan
1793
Plan
Blk. C
1483
Plan
Blk. F
1571
Plan
1
1796
Plan
1
4206
Plan
A
8570
Plan
Blk. D
1571
Plan
1571
Blk E
Blk ABlk GPlan 1571Blk A
Plan 1684
163
45371
2
Plan 163Blk C
Plan 15372
Plan 8612
Plan 1415 Plan 6873
10857
8378
451510742
Ctb
BeattiePoint
Bearskin Bay
Bearskin Bay
SmithPoint
142
141140
138
139
137 136
135
134
133 132
131 130
123
124129
125144-2144-1143145146146-1146-2
149
148
147 LS1
LS2
127
126
128
116
115 114
113
112
111 110118 109
117
92919093
81
8089
82
83 84
8887
86
8597 71 70 69
62-262-1 62
6160
94
95
96 77 76 75
7265
66
6768 78 79
73 74
4142
122
121 119102
103
104120 105
106107
101
100
99108
4344
45
46
57
5859
47
48
49
50
51
52
53
63
54 55 5640 39 33 3837
34
32
64
30
29
31 36
LS4
LS
28
27
26
35
25
24
23 2213 14 15
16
17
17-1
17-2 17-3
17-417-5 17-6
18
19
20
21
12
11
10
9
8
7
6
32
4
5
1
LS3
250
250
250
200
200
200
200
250
250
250
250 250
200
200
200
200
200
200
200200200
200
200
250
200 200
200
1
1
15
1
Bk 4
1
34
Bk 2
Bk 3
12
Bk 1
Plan 948
Plan8489
Plan1663
Plan
9735
DL 18
8490
Plan 5962
Plan9447
2
A
1
Plan
948
Plan
31Bk 6
Bk 8
Bk 7
Bk 5
1
36
1 Bk 9 11
Bk 28 Bk 27Bk 16
Bk 15
Bk 14Bk 17Bk 26Bk 29
Bk 30 Bk 25 Bk 18Bk 13
L. 2972
L. 2968
L. 2777
BCFerries
M
ni
d
arty
uk
R
Eagl
eHill Rd
OutfallPumping Station
LS4
VILLAGE OF QUEEN CHARLOTTE
SEWAGE TREATMENT AND DISPOSAL
OPTION 1, 2, 3 & 4
FIGURE 5-1
SkidegateIndian
Reserve
200
200
Outfa
ll
ø
(Optio
n1
&2)
�
�
Forcemain ± 200m
Outfall - Existing�
�
Forcemain ± 1200m
Outfall - Existing
�
�
Forcemain ± 3100m
New Outfall
�
�
Forcemain ± 4200m
New Outfall
OPTION 4 - Skidegate East:
OPTION 3 - Skidegate West:
SkidegateLanding
ImagePoint
OPTION 2 - Central Area
OPTION 1 - SMITH POINT:
N
HaidaPoint
200
Asphalt Road Surface
Gravel Road Surface
Force Main (size in mm)
Manhole
Lift Station
Sewer Lines (size in mm)
LEGEND
30
200
200
Proposed Forcemain200
P:\PRODWGS\QUEEN-CHARLOTTE\163-11\163.11 FIGURE 5-1 10-07-27
163.11 ©2010 Page 5-7
5.6 Option 5 - Joint Treatment with Skidegate Band
This option entails conveying the Village’s sewage to the Skidegate Band’s wastewater
treatment plant (WWTP) that is located at the north end of the Reserve, some 11 km from
the Village’s sewer system.
The Band’s sewage collection system (DNA 2004) starts at Second Beach (museum area)
where a small lift station and 100 mm forcemain convey sewage past First Beach to the
Band’s Lift Station No. 1. Lift Station No. 1 pumps through a 100 mm forcemain to a
gravity sewer with discharge to Lift Station No. 2. Finally, Lift Station No. 2 discharges
through a 200 mm and 250 mm forcemain to the Band’s WWTP.
At present, there are about 900 residents serviced by the Band’s WWTP. The treatment
plant is designed for 1200 people with provision to add a third treatment unit that will
increase the capacity to 1800 people. The associated effluent outfall is a combination of a
250 mm land section and a 200 mm marine section terminating in 50 m of water 1000 m
from shore. The outfall has capacity for about 2700 people. Pump Station No. 2 has a
design capacity for about 900 people.
Connected to the Village’s sewage system are about 860 people at present. The 20 year
design population is 1250 people.
Based on the design populations for the Village (1250 people) and the Band (1200
people), the Band’s pumped conveyance system is too small to also allow conveyance of
the Village’s sewage to the WWTP.
In order to convey Village sewage to the Band’s WWTP it will be necessary to upgrade
the Village’s Pump Station No. 5 (existing outfall) and extend a 200 mm forcemain to a
new Village Pump Station No. 6 located in the vicinity of the Band’s Lift Station No. 1.
163.11 ©2010 Page 5-8
From the Village’s new Pump Station No. 6, a 200 mm forcemain would extend along the
foreshore (near high tide line) to the Band’s WWTP.
Figure 5-2 illustrates this option. Cost estimates are detailed in Appendix 3 and are
summarized as follows:
• Conveyance System $5,857,000
Capital Costs
• Conveyance System $40,200 /yr
O&M Costs
The capital cost of the Band’s WWTP is reported to be $3.4 million (2007 construction)
and the current operating cost about $80,000/year (DNA 2010). The outfall (land and
marine sections) is estimated to cost $600,000. Based on contributing design
populations, the Village should pay about 50% of the costs to utilize the Band’s existing
WWTP and outfall.
• Existing WWTP $1,700,000
Capital Costs
• Existing Outfall
$2,000,000
$300,000
• Existing Treatment Plant $40,000 /yr
O&M Costs
• Existing Outfall
$41,000 /yr
$1,000 /yr
If the Village connects to the Band’s WWTP the existing serviced population will
increase to about 1800, which compares with the plant capacity of 1,200 people. The
163.11 ©2010 Page 5-9
outfall capacity is about 2700 people. Assuming the WWTP is expanded to service 2,400
people, then the cost will be in the order of $4.5 million. Cost sharing at 50% results in
the following added costs to the Village:
• Expand WWTP $2,250,000
Capital Costs
• Added Cost (allowance) $10,000 /yr
O&M Costs
In summary, the estimated cost to the Village to implement joint treatment and disposal
with the Skidegate Band is as follows:
• Conveyance System $5,857,000
Capital Costs
• Existing WWTP and Outfall $2,000,000
• Expand WWTP
$10,107,000
$2,250,000
• Conveyance System $40,200 /yr
O&M Costs
• Existing WWTP and Outfall $41,000 /yr
• Added Cost for WWTP Expansion
$91,200 /yr
$10,000 /yr
163.11 ©2010 Page 5-10
5.7 Evaluation
Cost estimates for the treatment and disposal options are compared in Table 5-1.
TABLE 5-1 TREATMENT AND DISPOSAL COMPARISON – INITIAL STAGE COSTS
Option Capital Cost ($) Operating Cost ($/yr) Life Cycle Cost ($)
1. Smith Point Area
1
5,699,000 114,500 7,126,000
2. Central Area 6,305,000 115,100 7,739,000
3. Skidegate Landing West 7,158,000 113,100 8,567,000
4. Skidegate Landing East 7,803,000 115,300 9,240,000
5. Joint Treatment Skidegate Band
10,107,000 91,200 11,243,000
1
20 year, 5% discount rate (pwf = 12.46)
For an initial stage, the least cost options are the Village owned treatment plant sites at
either the Smith Point Area or in the Central Area. The disadvantage of these two sites is
that when the Village elects to provide sewage service between Smith Point and
Skidegate Landing, there will be a need to provide a pumping station at Skidegate
Landing and to extend a forcemain to the treatment plant site.
The added cost to provide the Skidegate Landing pump station (5 HP pumps located near
ferry terminal) and forcemain (150 mm) (allows for 250 people) to connect to the Option
1, 2 and 3 treatment plant sites is noted in Table 5-2. Also presented in Table 5-2 are the
total costs for Options 1, 2 and 3 inclusive of the Skidegate Landing conveyance system.
163.11 ©2010 Page 5-11
TABLE 5-2 COST TO PROVIDE CONVEYANCE SYSTEM FROM SKIDEGATE LANDING
TO SITE OPTIONS 1, 2 AND 3
Option Capital Cost ($) Operating Cost ($/yr) Life Cycle ($)
Added Cost
1. Smith Point Area 1,712,000 15,000 1,899,000
2. Central Area 1,320,000 15,000 1,507,000
3. Skidegate Landing West 612,000 14,000 787,000
Total Cost
1. Smith Point Area 7,411,000 129,500 9,025,000
2. Central Area 7,625,000 130,100 9,246,000
3. Skidegate Landing West 7,770,000 127,100 9,354,000
If a pumped conveyance system is extended from Skidegate Landing, the Option 1 life
cycle cost increases to $9,025,000, the Option 2 life cycle cost increases to $9,246,000
and Option 3 to $9,354,000. Based on life cycle costs, site Options 1 to 4 are similar.
Option 5 is the most expensive at $11,243,000.
Options 3 to 5 have the benefit of providing a means of servicing all properties between
Smith Point and Skidegate Landing with the pumped conveyance system at the outset of
construction. The disadvantage is the initial stage higher capital cost.
Not included in the cost estimates is the collector sewer system needed to service
properties between Skidegate Landing and Smith Point. This system will entail a series
of gravity collector sewers and small pump stations that discharge into the pumped
conveyance system forcemain.
In terms of treatment plant siting criteria for a Village owned plant; Site 1 is in a
residential area, Site 2 has a few homes in the area, Site 3 is undeveloped at present but is
subdivided into many small lots (presumably residential or highway commercial) and Site
4 is in an industrial area. Site 4 is best suited for a treatment plant. Should the Village
163.11 ©2010 Page 5-12
select a treatment plant site in a non-industrial area, then the OCP should make provision
to limit residential and public use development in the near vicinity of the treatment plant.
No archaeological impact assessment work has been done for this feasibility study. In
this regard, all options can be considered equal.
No oceanographic studies have been carried out for this report. Sites 3 and 4 at Skidegate
Landing will require a new outfall and its impact on the marine receiving environment
will need to be assessed. In principle, however, effluent discharge into Skidegate Inlet
should provide better opportunity for effluent dispersion than the existing outfall in the
more confined waters of Bearskin Bay. For Option 5, the required outfall expansion
would parallel the existing outfall which is understood to be well sited (DNA, 2010).
163.11 ©2010 Page 6-1
SEWAGE TREATMENT AND DISPOSAL – FEASIBILITY STUDY
6.0 SUMMARY, CONCLUSIONS AND RECOMMENDATIONS
A brief summary of the study findings, conclusions and recommendations are presented in this
section.
6.1 Summary and Conclusions
The Village presently houses about 960 people of which about 870 residents are serviced
with a sewage collection system. Raw sewage is discharged near Smith Point through an
outfall into Bearskin Bay. The unserviced area between Smith Point and Skidegate
Landing utilizes septic tanks and the ferry terminal a holding tank.
In 2009, Environment Canada issued an Inspector’s Direction under the Fisheries Act
which requires the Village to develop a plan for sewage treatment and disposal by
December 31, 2010.
The existing sewage collection system is well maintained and has adequate capacity for
present day needs. The flow records at the outfall Pump Station No. 5 are not reliable and
a flow meter should be installed.
Population in the Village has decreased from 1222 in 1996 to an estimated 960 in 2010.
The draft OCP projects a 25 year growth between 1250 and 2000 people. For the concept
designs in this study, a 20 year population of 1250 people (year 2030) has been used.
163.11 ©2010 Page 6-2
Current Provincial and Federal regulations require a secondary level of treatment for an
effluent discharge into marine waters. For this study, a sequencing batch reactor (SBR)
form of secondary treatment has been selected for development and evaluation of
treatment and disposal options.
Four site options for a Village owned treatment plant were identified. A fifth option
considered was joint treatment with the Skidegate Band.
The five options compare as follows:
TABLE 6-1 TREATMENT AND DISPOSAL COMPARISON – TOTAL COSTS
Option Capital Cost ($) Operating Cost ($) Life Cycle ($)
1. Smith Point Area 7,141,000 129,500 9,025,000
2. Central Area 7,625,000 130,100 9,246,000
3. Skidegate Landing West 7,770,000 127,100 9,354,000
4. Skidegate Landing East 7,803,000 115,300 9,240,000
5. Joint Treatment Skidegate Band
10,107,000 91,200 11,243,000
A Village owned treatment plant will cost between $7.4 to $7.8 million (depending on
treatment plant site location), relative to $10.1 million for joint treatment with the
Skidegate Band.
Considering treatment plant siting criteria, the Skidegate Landing East site followed by
the Central Area site are favoured.
6.2 Recommendations
A flow meter should be installed in Pump Station No. 5 to provide more accurate flow
data for future treatment plant design. Budget $15,000.
163.11 ©2010 Page 6-3
The existing outfall should be dive inspected to determine its condition; particularly for
continued use. This task is included in 2011 Village budget.
The Village should meet again with the Skidegate Band to receive Band comments on the
joint treatment option, to review the contents of this final report and to determine the
Band’s position on the merits of joint treatment. Budget $2,500 if consultant attendance
is required.
The Village should initiate a public consultation process to obtain input on the treatment
and disposal options. Budget $5,000 if consultant attendance and illustrations are
required.
Following the public consultation process, the Village should select a favoured treatment
and disposal option. If a Village owned treatment plant option is selected, then the
Village should initiate the process for obtaining a treatment plant site. This process will
entail site inspection, geotechnical work, archaeological work, etc. to determine site
suitability. Once the site location is known, a budget can be developed to assist the
Village with the technical assessment of the site.
Finally, this report should be forwarded to Environment Canada prior to December 31,
2010 for their information and records.
VILLAGE OF QUEEN CHARLOTTE SEWAGE TREATMENT AND DISPOSAL – FEASIBILITY STUDY
APPENDIX 1 REFERENCES
(D&K 2000) Skeena Queen Charlotte Regional District, Queen Charlotte / Skidegate Landing
Management Committee, Long Term Water and Sewerage Plan for Queen Charlotte City, Dayton & Knight Ltd., December 6, 2000
(DNA 2004) Skidegate Band Council, Skidegate Sewage Treatment System, Design Brief,
David Nairne and Associates, January 2004. (DNA 2010) Personal Communication, Giorgio Caon, P.Eng., August 2010.
VILLAGE OF QUEEN CHARLOTTE SEWAGE TREATMENT AND DISPOSAL – FEASIBILITY STUDY
APPENDIX 2 ENVIRONMENT CANADA INSPECTORS DIRECTION
VILLAGE OF QUEEN CHARLOTTE SEWAGE TREATMENT AND DISPOSAL – FEASIBILITY STUDY
APPENDIX 3 COST ESTIMATES
163.11 ©2010 Page A3-1
VILLAGE OF QUEEN CHARLOTTE SEWAGE TREATMENT AND DISPOSAL – FEASIBILITY STUDY
OPTION 1 – SMITH POINT 1.
Capital Costs
• Upgrade P.S. No. 5; 2-10 HP $50,000 • Forcemain; 200 mm, 250 m x $275/m $69,000 • Land Outfall; 200 mm, 250 m x $200/m $50,000 • Highway Crossing, allowance $30,000 • Effluent P.S.; 2-10 HP
$499,000 $300,000
• 30% Engineering and Contingency
$150,000
TOTAL $649,000 2.
Operating Costs
• Power – 20 HP x 33% x $350/HP-year $2,300 • Labour - Daily – 0.5 hr x $50/hr x 260 days $6,500
- Quarterly – 8 hr x $100/hr x 4 days $3,200 • P.S. Annual Service $5,000 • Outfall – Dive Inspection, 5 year cycle
$1,000
TOTAL $18,000 /yr 3. Treatment Plant Site, allowance $500,000 OPTION 2 – BOAT LAUNCH 1.
Capital Costs
• Upgrade P.S. No. 5 and genset; 2-15 HP $75,000 • Forcemain; 200 mm, 1200 m x $275/m $330,000 • Land Outfall; 200 mm, 1200 m x $150/m $180,000 • Rock Excavation; 500 m3 x $100/m3
• Highway Crossing, allowance $30,000 $50,000
• Effluent P.S.; 2-10 HP $965,000
$300,000
• 30% Engineering and Contingency
$290,000
163.11 ©2010 Page A3-2
TOTAL $1,255,000 2.
Operating Costs
• Power – 25 HP x 33% x $350/HP-year $2,900 • Labour - Daily – 0.5 hr x $50/hr x 260 days $6,500
- Quarterly – 8 hr x $100/hr x 4 days $3,200 • P.S. Annual Service $5,000 • Outfall – Dive Inspection, 5 year cycle
$1,000
TOTAL $18,600 /yr 3. Treatment Plant Site, allowance $500,000 OPTION 3 – SKIDEGATE WEST 1.
Capital Costs
• Upgrade P.S. No. 5 and genset; 2-25 HP $150,000 • Forcemain; 200 mm, 3100 m x $275/m $853,000 • Land Outfall; 250 mm, 300 m x $325/m $98,000 • Rock Excavation; 1,300 m3 x $100/m3
• Highway Crossing, allowance $90,000 $130,000
• Marine Outfall; 250 mm, 400 m $1,621,000
$300,000
• 30% Engineering and Contingency
$487,000
TOTAL $2,108,000 2.
Operating Costs
• Power – 25 HP x 33% x $350/HP-year $2,900 • Labour - Daily – 0.5 hr x $50/hr x 260 days $6,500
- Quarterly – 8 hr x $100/hr x 4 days $3,200 • P.S. Annual Service $3,000 • Outfall – Dive Inspection, 5 year cycle
$1,000
TOTAL $16,600 /yr 3. Treatment Plant Site, allowance $500,000
163.11 ©2010 Page A3-3
OPTION 4 – SKIDEGATE EAST 1.
Capital Costs
• Upgrade P.S. No. 5 and genset; 2-40 HP $250,000 • Forcemain; 200 mm, 4200 m x $275/m $1,155,000 • Land Outfall; 250 mm, 250 m x $325/m $82,000 • Rock Excavation; 1,800 m3 x $100/m3
• Highway Crossing, allowance $150,000 $180,000
• Marine Outfall; 250 mm, 400 m $2,117,000
$300,000
• 30% Engineering and Contingency
$636,000
TOTAL $2,753,000 2.
Operating Costs
• Power – 40 HP x 33% x $350/HP-year $4,600 • Labour - Daily – 0.5 hr x $50/hr x 260 days $6,500
- Quarterly – 8 hr x $100/hr x 4 days $3,200 • P.S. Annual Service $3,500 • Outfall – Dive Inspection, 5 year cycle
$1,000
TOTAL $18,800 /yr 3. Treatment Plant Site, allowance $500,000 TREATMENT PLANT 1.
Design Criteria
• Population – 1250 • Design Flow – 1500 m3
• Effluent BOD/d
5
/TSS – 45 mg/L
2.
Capital Costs
• Site Works $750,000 • Head Works $250,000 • SBR/Digester Tanks $1,000,000 • Biosolids Dewatering $350,000 • Odour Control $100,000 • Control Building $750,000
163.11 ©2010 Page A3-4
• Electrical/Controls $3,500,000
$300,000
• 30% Engineering and Contingencies
$1,050,000
TOTAL $4,550,000 3.
Operating Costs
• Labour – Daily 3 hrs x $50/hr x 260 days $39,000 • Power – 50 HP x $350/HP-year $17,500 • Materials and Service, allowance $20,000 • Biosolids Disposal, allowance $15,000 • Administration
$5,000
TOTAL $96,500 /yr OPTION 5 – JOINT TREATMENT WITH SKIDEGATE BAND
Pumping Stations and Forcemain
1.
Capital Costs
• Upgrade P.S. No. 5 and genset; 2-50 HP $300,000 • New P.S. No. 6 and genset; 2-60 HP $450,000 • Forcemain; 200 mm, 11,000 m x $275/m $3,025,000 • Rock Excavation; 3,800 m3 x $100/m3
• Highway Crossing, allowance $380,000
$4,505,000 $350,000
• 30% Engineering and Contingency
$1,352,000
TOTAL $5,857,000 2.
Operating Costs
• Power – 110 HP x 33% x $350/HP-year $12,800 • Labour - Daily – 1.0 hr x $50/hr x 260 days $13,000
- Quarterly – 16 hr x $100/hr x 4 days $6,400 • P.S. Annual Service
$8,000
TOTAL $40,200 /yr