setting material baunces por temile wet processinginfohouse.p2ric.org/ref/31/30229.pdf · ·...
TRANSCRIPT
1
SETTING MATERIAL BAUNCES POR TEmILE WET PROCESSING
S- A . Tarabadkar,
Bombay Textile
S, Varadaraj'an and R. P . Kamble
Research Association, Bombay
INTRODUCTION
The textile industry uses large quantity of water for different
purposes. Much of this water is discharged with appreciable
quantities of organic and inorganic chemicals (dyes, pH control
agenta, lubricants, surfactants, auxiliaries), which require
extensive treatment of the waste water a8 it contributes to the
pollution problem associated with textile processing. Although
the establishment of direct effluent discharge standards for
industrial wastes has a major effect on the treatment and
discharge of textile waste water, the capital investment and
operating expenses associated with these standards require a
critical examination of all the available options for pollution
reduction and waste water treatment.
In the past, the problem of pollution resulting from textile
processing has generally been eased by construction of waste
treatment facilities. As requirements became more stringent, the
waste treatment plant was expanded or additional treatment
processes were added
however, has consumed
and has .increased the
to meet the standards. This approach,
large sums of non-income producing capital
operating costs of many textile plants. In
1.1
short, it has now become neceeeary to examine alternate methods of
textile wet processes for waste reduction and pollution control.
The introduction of the recent 'Environmental Audit' will
therefore be much helpful and enable the processor to take a
comprehensive look at the process to facilitate the understanding
of material flows and focus his attention on areas where waste
reduction is po~sible.
This paper discueses certain aspects of Betting up material
balance which is one of the key steps in the 'Environmental
Audit', for textile wet processes.
SEM'ING OF HATERIAL BALANCE
Material balance is one of the important steps in the
Environmental Audit designed to gain a better understanding of the
inputs and outputs, especially waste of any process/operation. It
may be defined as a precise account of the input8 and outputs of
an operation. The material balance enablee the proceseor to
identify major sources of waete, aseess the deviation# from the
norms in terms of waste production, identify areas of unexplained
l O s € ~ 3 0 and to pinpoint operations which contribute to flows that
exceed discharge regulations.
The principal steps involved in setting up material balance are :
0 Appraisal of process inputs :
- Determination of inputs
- Recording of waste usage
- Measurement of current levels of waste reuse/cycle
I1 . 2
0 Appraisal of proceess output8 :
- Quantificatiion of products/by-products
- Accounting for waste water
- Accounting for gaseous emission
. I .
?
Raw 1
Material
.
> Power OR >
Water/Air -3 PFtocESS
UNIT OPERATION
b -
- Accounting for off-site wastes
Product
including Wastee for
b By-pmduc ts
Recovery
From the above information of process inputs and outputs, a
preliminary material balance may be derived and subsequently
evaluated and refined for arriving at accurate material
balance. A schematic diagram illustrating the various steps
involved in setting up material balance is given below.
PIG. 1 : Typical Components of a Material Balance
1.3
A material balance may be prepared proceermiae e.g., desizing,
Bcouring, bleaching, dyeing and finishing, etc. at a scale
appropriate for the level of details required in the study.
The enqrgy input to a unit operation should be considered while
setting up material balance. However, energy u ~ e deserves a full
audit in its own right. For waste auditing purposes, it would
auffice to note the energy sources and whether waete reduction
could reduce energy costs. If energy usage is a particularly
prominent factor, separate energy audit should be undertaken.
O n e of the important steps for calculating material balance is
selection of appropriate tie compounds. For example, raw
materials such as water, cauatic soda, etc., may be taken for.
textile wet processing operations.
typical case studies exemplifying the steps involved in
setting material balance are gjven in the following.
CASE sTUDIES <
Study Study No.:
Material Balance in S i z i n g Section
A survey was carried out by BTRA in the eioing section of a mill
manufacturing grey fabric, to establieh a material balcnnce with
respect to the starch consumed in the sizing section.
The details of the survey are as follows :
Name of the Machine - West Point Sizing Machine 1.4
Sizing Recipes
A. Terry Catton Size ( 16 to 17% Liizse)
1. Fabrilose
2. Mutton Tallow
3. French Chalk
4. G U
5. CMC
6. Sapcotex
7. PVA
44
1.75
2.0
2.0
2.0
0.5
4.0
B. Cotton Siae (13 to 14%)
............................................................. Sr.No. Name of the Ingredient Quantity (kg)
1. Maize Starch 34
2. Fabr i lose 10
3. Mutton Tallow 2.5
4. Plasto Siae 5.0
1.5
June 5674
July 6807
32848
39827
August 77 16 43923
Table - 2 : For Terry Cotton
Apr i 1 2232 12156
May
June
July
August
September
1886
1421
1199
1932
2122
9934
6811
6256
'9404
10610
The following data wae used for working out the values of
starch conaumption on fabric and rstasch wastage, details of
which are given in the tabular form.
- 17% Pick-up for Terry Cotton Size
- 14% Pick-up for Cotton Size
- 10% Wastage of Starch due to Dusting
1.6
Table- 3 : For Terry Cotton (17% Size)
April 2232 12156 1633 223 376
May 1886 9934 1334 189 363
June 1421 6811 915 142 364
July 1199 6256 840 ” 120 239
August 1932 9404 1263 193 476
September 2122 10610 1423 212 487
Apr i 1 34884 6079 3980 ‘ 808 1491
MErY 28670 4832 327 1 483 1078
June I 32848 5674 3748 567 1359
*July 39827 8807 4544 68 1 1582
August 43923 7716 5012 772 1932
September 29279 5434 334 1 543 1550
--------------------____________c_______--------------------------
Average 34905 6090 3983 608 1499 ..................................................................
Thus based on the figures worked out, the material balance for
starch consumed works out as follows :
1.7
Conenamtion 7889 kg
V I + on Fabric __
5219 kg
Transport & Drainage Weighment 1420 kg 463 kg (18%) (6%)
7651 of the total starch consumption can be attributed to : the
starch of
dust. The remaining 24% of the starch, i.e., 1883 kg wae wasted
in the following operations :
consumed on the fabric and the starch lost in the f o r m
0 During Transportation
0
0 Drainage of Size
During Weighing and Preparation of Size
The size wastage can be avoided to a considerable extent by
implementing the following measure8 :
0 The hand washing8 after the weighing of sizing ingredients
should be done over empty size mixing tanka. .
o The size supply line valves mu& be checked regularly to stop
any size leakages.
1.8
Size should not be wasted alongwith the ateam condensate
during the recycling of size. It should be separately
collected in a bucket.
~
Better housekeeping measures must be implemented in storing
the size ingredient%,
Size overflow from the sow-box should be avoided. This ia
generally due to injection of excess ateam. It can be L
avoided by installing a dial type thermometer in every sow-
box.
Effect of Starch Wastage on Treatment Costs
The starch wastage of 1420 kg will exert on additional BOD load of
677 kg (477 g/kg of starch) which will ultimately add to the
treatment cost.
Case Study No.2
Haterial &lance in’ Mercerizil.ltg Section
The bleeached cotton fabric (4OS x 408 : 92 x 80) w a s mercerized
in a chain mercerizer. The details of the machine and proceas
were as follows :,
Average Machine Speed (m/min) : 60
No. of Impregnators : 2
Volume of Impregnators (1) : 1587 and i6ao No. of Pits under the Stenter : 5
Volume of Each Pit (1) : 2380
No. of Washing Tanks : 4
Volume of Each Tank (1) : 2083
1.9
Process Description
The bleached cotton fabric was padded with a solution of 300 g/l
caustic eoda and was passed through the stenter. The treated
fa was waahed in coun%ercurrent warrhing tanks for a period of
8 hr. During this period, 6000 kg of bleached fabric wars
mercerized. The caustic soda consumed wae 1980 kg for 6000 kg of
bleached fabric. The caustic soda content on the fabric after
~
impregnation was 33% and at the delivery end of the machine, it
was found to be 0.5%. Thus, cauetic soda
carried away by the fabric was ---------- i . e . 30 kg. 6000 x 0 .5
100
The caustic soda accumulated in the pitls and washers after the
successive washing operation was worked out a8 follows :
1. A t the iFsnd af &he Trial
(g/l) x (Volume in 1) = - 45
- 40
- 35
30
20
- -
10
6
4
2
- - c
-
X
X
X
X
X
X
X
X
X
2380
2380
2380
2380
2380
2083
2083
2083
2083
Total
1.10
(Weight in kJg)
107.1
96.2
83.3
71.4
47.6
20.83
12.5 .
8.33
2. A t the Beginning of Trial
r Input
CaU8t iC soda 134 kg (6-72X) 1980 kg (loo%) F
AccupRlLATION
( d l ) x (Volume in 1) = 38 X 2380 - -
Cawtic Content on the Fabric A f t e r bheri- cation 90 kg ( 1 - 5 X )
8
30
22
16
12
Caustic
10
- Unaccounted
6
4
2
X
X
X
X
X
X
X
X
2380
2380
2380
2380
2083
2083
2083
2083
Total
(Weight in kg)
90.4
71.4
52.4
38.1
28.6
16.7
10.4
6.2
2.1
316 -------
Cautstic Soda Accumulation = 450 - 316 = 134 kg.
Haterial Balance
The dilute caustic soda eolution collected in the collection tanks
was 36,600 1 of 45 g/1 strength. Thus, the amount of caustic soda
collected by way of recovery waa ---------- = 1848 kp 36625 x 45
1000
1.11
Thus, based on the details available the material balance for
caustic soda works out as follow8 :
SCOUR WASHER , .
Fabric
bese Study No.3
Further
Haterial Balance in Scouring Razuge
J
*swiw P r o c e s s Detafls
T r e a t m e n t
Production Rate (m/min) : 70
Flow Rat8 (1) : 200-220
Percentage Moisture on Fabric : 80% pick-up
Water on Fabric (l/kg) : 15
Material (100% Cotton) : 100
Quantity (m/kg) : 5
r
Process water balance and chemical balance which are worked out
are given below; these are on the basis of 1000 kg of production.
1.12
Chemical Balance
Chemical Input Output % BOD Output (kg) BOD (kg)
NaOH 4 6 46 0 0
Detergent 1.3 1.3 50 0.65
Trisodium Phorphate
1.5 1.5 0 0
Chelate 0 . 4 0 . 4 50 0.2
Triethanol Amine ’ 0.7 0.7 50 0.4
Cotton Wax 30 30 50 15.0
Analytical Checks
BDD (ker) : 16.4
Total SS (kg) : 5
Total Dissolved Solids (kg) : 49.9
PH
Oil and Grease (kg)
: 12.5
: 30
Case Study No.4
Detection of Kerosene Vapour in a Curing Machine
At, t h e request from the mill, trial wap conducted to determine the
kerosene vapour content in a curing machine. This trial is a
classic example of meaerurement of kerosene vapour content in the
exhaust air in the absence of a direct ‘Read on’ type instrument
1.13
by establishing a material balance as an indirect method. The
kerosene vapours were eatimated by measuring the difference in the
weight of fabric before and after the curing operations and
estimating the weight of the air exhaueted. These two separately
eatimated values were combined and the percentage of kerosene
vapour in the exhaust air was calculated.
The details of the trial are as follows :
1. Details of Exhaust Air Flow
1.1 Maust duct No-1
Fan Installed (HP) : 5
Duct Size (in. x in.) : 20 x 16
Average Air Velocity (m/min) : 296
Average A i r Flow (m /min)
(Exhaust air flow was meaaursd with the help of 'Velometer')
Dampers Open ( % ) : 50
: 62 3
1.2 hkhauat duct No.2
Fan Installed (HP) : 2
Duct Size (in. x in.) : 8.5 x 8.5
Average Air Velocity (m/min) : 212
Average Air Flow (m /min) : 10 3
3 1.3 Total Air Flow : 1.1 + 1.2 = 62 + 10 = 72 m /min
2. Details of Estimation of Kerosene on Fabric
Machine Type 'Ham' Curing Machine
Width of Fabric (cm) : 89
Quality Number : 4218/90
Quantity ( m h g ) : 9
1.14
Consumption of Print Paste : About 0 kg/1000 m
Speed of Curing Machine : 26 MPN
Temperatugs of Curing : 148 Machine ( C)
h e 1 1 Time (min) : 4.4
Printing Coverage ( % ) : 80
Fabric Running (ends) : 2
Estimation of kerosene was carried out on two sets of fabric.
Set I
Before Curing 106.5 0.958263 111.14
set I1
Before Curing 109 I 5 1.0072 108.72
After .I_ determining the difference in weight of the fabric
before and after curing, the data was used in calculating the
composition of exhaust to find out the per cent volume of
kerosene in exhkust .
~.
1.15
3. "pos i t ion of Exhaust
3.1 #bight of Kerosene Evaporated :
For 1st rset (end) : difference in.weight x speed x width of f ab r i c
: 6.06 x 26 x 0.89 = 140.2 s h i n
For 2nd set (end) : 3-38 x 26 x 0.89 = 78.2 g/min
3.2 Total Weight of Kerosene : 140.2 + 78.2 = 218.4 Evaporated (g/min)
i .e. 0.2184 kg/min
3.3 Specif ic Volume of : 0.098 3 Vapour (m /kg)
3 . 4 Total Volume of Kerosene : 0.021
Vagour (m3/min
3.5 Total A i r Flow (m3/min) : 72
0.021 3.8 Composition of t h e - ----- x 100 = 0.03%
Exhauat (Volume 72 Percentage of Kerosene)
"hue based on t h e t r i a l conducted, the percentage of volume
was found t o be 0.03% of the exhaust.
Cam Study No.5
Water Con"ption &lance
In a Compoaite mill, it w a s found through surveys conducted; t h a t
of t he t o t a l w a t e r consumed, the e f f luen t generated was around 75-
80%. About 15-16% accounted for evaporative loasee and the rest
1.16
waa unaccounted. These un'accounted I *,
loseee were due to leakages in
pipee, trouqhs, improper fixture@, negligence in water U B W ~ S
pattern of the water consumed and 'the effluent
enerated is shown below.
Evaporative LOSEWS (15-16X)
'I' Input
Water Consumed %a1 Effluent (100%)
A survey wae carried out in one of the mille to establish the
water conmmption balance by measuring the effluent discharged.
The main purpose of carrying out the survey was to work out a
proper balance between the actual water consumption and the
effluent generated and also the various loasee.
Data obtained from .the mill showed that the total water
conaumptiop was around 1120 m3/day. The industrial effluent
discharged wae 762 m3/day (68%). The domestic and sanitary
effluent discharged amounted to 67 m /day (6%) considering (15%)
168 m3/day as evaporative losses, the unaccounted loases,
estimated were 11%.
3
1.17
InduetrialgECffluent
Dopllestic & sanitary ~
Effluent 67 m /day (6%)
762 BI /day (68%) ~
On detailed examination for the unaccounted losses it was revealed
that the -in contributing factors were negligent use o f water in
the mills, leakage8 in the pipes, leakages in waeh tanks, improper
fistureer, etc.
A general pattern of the water conewnption in a composite mill is
given below. Teble-1.5 givee an idea of the water consumption for
varioue, procseees. The mills can compare their results with this
Table to find out whether the water consumed for variouer processes
carried out ia within limite.
Dyeing 15 - 20 Printing 10 - 15 Boilers 0 - 12 Humidification 0 - 12
UTILITY OF MATERIAL BALANCE
These material balance studiea will give definite insight to the
wet processor regarding the process being followed in the mills
and will enable him to reduce the volume and toxicity of the
digcharges and also to think in terms of recycling and reusing ~~
useful constituents, such as water and colorant.
It is possible for a wet processor to reduce the waste volume in
order to get greater treatment efficiency on a "per kg of product"
basis, through these studies.
The following points may be considered for waste volume reduction.
0 Improved waaher designs. I
o
0 "Tailored rinses" - to fit particular shade, style or
Overflow v/er recirculating rinaes in package dyeing.
severity of treatment.
0 More careful control and testing to ensure that "over
rinsing" of fabric does not take place.
o Closed steam heating coils in dye becke, etc., rather than
open steam, to allow return of condensate.
o
0
U s e of counterflow principle on continuousj ranges.
Vacuum extract on package dye machines.
0 Inplant reuse of lightly contaminated rinse waters f o r other
"more concentrated" chemical processes.
Liquor ratio consideration in batch processes. 0
o Elimination of reworks by more careful control of processes
and greater automation.
0 Automatic cut-off on water losses.
1.19
Similarly, it is also possible to reduce the waste strength by
identifying the compounds which contribute to the pollution load
and replacing them with less polluting compounds and also reducing
the amount of unnecessary chemicals.
For example, chemicals such as sodium chloride, sodium sulphate,
sodium hydrosulphite, etc., are commonly used cheap Chemical6 in
t h e dyehouse. Since they are cheap, it is not unusual to see them
overused. These chemicals cannot be removed by biological methods
and management should therefore insist on minimum uee of these
chemicals;. Furthermore, sodium hydrosulghite has bean found to
contain residual zinc catalyet, a heavy toxic metal banned in
effluent discharges.
Many solvents contain phenols and many lubricating oils and
greaees contain substantial amount of zinc and lithium. H e m e it
is not advisable to pour these chemicals down the plant drain
after use.
1.20