session 4 economic impacts of a karst foundation wolf ......project benefits and lake level target...

39
7 7 7 th th th Annual Technical Forum Annual Technical Forum Annual Technical Forum Geohazards Geohazards Geohazards In Transportation In The Appalachian In Transportation In The Appalachian In Transportation In The Appalachian Region Region Region US Army Corps of US Army Corps of Engineers, Engineers, Nashville District Nashville District Session 4 Economic Session 4 Economic Impacts of a Impacts of a Karst Karst Foundation Wolf Foundation Wolf Creek Dam, Creek Dam,

Upload: others

Post on 18-Jun-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

777ththth Annual Technical ForumAnnual Technical ForumAnnual Technical ForumGeohazardsGeohazardsGeohazards In Transportation In The Appalachian In Transportation In The Appalachian In Transportation In The Appalachian

Region Region Region

US Army Corps of US Army Corps of Engineers, Engineers,

Nashville DistrictNashville District

Session 4 Economic Session 4 Economic Impacts of a Impacts of a KarstKarstFoundation Wolf Foundation Wolf

Creek Dam, Creek Dam,

Page 2: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

Outline of TopicsOutline of Topics

• Project Description.• General Background.• Reliability Studies. • Interim Risk Reduction Measures.• Operating Restrictions.• Economic Impacts.

Page 3: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

Project LocationProject Location

Page 4: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

Project FeaturesProject Features

Page 5: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

EMBANKMENT PLAN AND EMBANKMENT PLAN AND SECTIONSECTION

Cut Off Trench

Toe of Random Fill

Drainage Blanket

Page 6: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

Foundation Treatment Foundation Treatment ProblemsProblems

• Treatment techniques were inadequate for this geology

• Most of the alluvium left in place

•Except for cut-off trench, no embankment foundation treatment

•Cutoff trench design and construction inadequate

Page 7: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

Overhangs and loose rocks will only be removed where Overhangs and loose rocks will only be removed where they cross the line of the trench, since the they cross the line of the trench, since the earthfillearthfill in in the sides of the trench will have the function only of the sides of the trench will have the function only of stability and not of an absolutely uniform tight contact stability and not of an absolutely uniform tight contact with the trench walls. Tamping will with the trench walls. Tamping will supplimentsuppliment the the regular rolling of the fill as required under the regular rolling of the fill as required under the overhangs and irregular overhangs and irregular salientssalients..

Page 8: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

Foundation TreatmentFoundation Treatment

Cave

Cave

Solution Features

Page 9: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

1968 Sinkhole

Sinkhole

Switchyard

Page 10: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

19601960’’s and 70s and 70’’s s Remedial FeaturesRemedial Features

Concrete Dam

Earth Emb

Switchyard

Diaphragm Wall

Grout Lines

SwitchyarWall

Powerhouse

Diaphragm Wall

Switchyard Wall

Page 11: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

1

1

2

3

Post Wall Performance Post Wall Performance –– Wet AreasWet AreasMarch 2004March 2004

Existing Diaphragm Wall

Page 12: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

RiskRisk

Risk is defined as the probability of unsatisfactory performance times the consequences of the unsatisfactory performance.For Wolf Creek, based on a breach of the dam the estimated consequences are up to 350 lives lost and over $3 billion in damages.How do we establish the probability of unsatisfactory performance?It is especially difficult to predict the behavior in Karst.

Page 13: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

Reliability Analysis for Dams and Levees

Reliability Analysis for Dams and Reliability Analysis for Dams and LeveesLevees

Excerpts from a presentation by

Thomas F. Wolff, Ph.D., P.E.Michigan State University

Grand Rapids Branch ASCESeptember 2002

Page 14: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

General Approaches: Event TreeGeneral Approaches: General Approaches: Event TreeEvent Tree

Sand Boilp = 0.5

Carries materialp=0.3

Doesn’tp = 0.7

Close to leveep = 0.6

Notclosep = 0.4

0.09

0.06

0.35

Most problems of interest involve or could be represented by an event tree..

given some water level :

Page 15: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

Probabilities for the Event Tree - How?????Probabilities for the Probabilities for the Event TreeEvent Tree -- How?????How?????

A) f (Uncertainty in parameter values) Reliability Index Methods (β)– Monte Carlo method– FOSM methods

point estimateTaylor’s Series

Mean ValueHasofer-Lind

B) Frequency Basis– Exponential, Weibull, or other lifetime distribution

C) Judgmental Values– Expert elicitation

Page 16: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

A) Pr(f) = Function of Parameter UncertaintyA) A) Pr(fPr(f) = Function of ) = Function of Parameter UncertaintyParameter Uncertainty

Identify performance function and limit state, typically ln(FS) = 0Identify random variables, X iCharacterize random variables,– E[X], σ x, ρ

Determine E[FS], σFSDetermine Reliability Index, βAssume Distribution and calculate Pr(f) = f(β)

Page 17: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

Pros and Cons of b, Pr(U)Pros and Cons of b, Pros and Cons of b, Pr(U)Pr(U)Advantages– “Plug and Chug”– fairly easy to

understand with some training

– provides some insight about the problem

Disadvantages– Still need better

practical tools for complex problems

– Non-unique, can be seriously in error

– No inherent time component

– only accounts for uncertainties related to parameter values and models

Page 18: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

B) Frequency-based ProbabilitiesB) FrequencyB) Frequency--based based ProbabilitiesProbabilities

Represent probability of event per timeperiodPoisson / exponential model well-recognized in floods and earthquakesWeibull model permits increasing or decreasing event rates as f(t), well developed in mechanical & electrical appliactionsSome application in material deteriorationRequires historical data to fit

Page 19: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

Pros and Cons of Frequency ModelsPros and Cons of Frequency Pros and Cons of Frequency ModelsModels

Advantages– Can be checked

against reality and history

– Can obtain confidence limits on the number of events

– Is compatible with economic analysis

Disadvantages– Need historical data– Uncertainty in extending

into future– Need “homogeneous”

or replicate data sets– Ignores site-specific

variations in structural condition

Page 20: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

C) Judgmental ProbabilitiesC) Judgmental C) Judgmental ProbabilitiesProbabilities

Mathematically equivalent to previous two, can be handled in same wayCan be obtained by Expert Elicitation– a systematic method of quantifying

individual judgments and developing some consensus, in the absence of means to quantify frequency data or parameter uncertainty

Page 21: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

Pros and Cons of Judgmental ProbabilitiesPros and Cons of Judgmental Pros and Cons of Judgmental ProbabilitiesProbabilities

Advantages– Gives you a number

when nothing else will– May be better reality

check than parameter uncertainty approach

– permits consideration of site-specific information

– Some experience in application to dams

Disadvantages– Distrusted by some

(including some within Federal Agencies)

– Some consider values “less accurate” than calculated ones

– Non-unique values– Who is an expert?

Page 22: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

1. Major Rehabilitation 1. Major Rehabilitation Report.Report.

1. Analysis from Major Rehabilitation Report (MRR)– Based on analysis of stress indicators– Limit State defined as condition that would require

operational restrictions. Limit State threshold selected by expert elicitation.

– Damage accumulation based on projection of instrumentation data coupled with historical pool stages using a Monte Carlo simulation.

– Reviewed by an independent panel of experts– Stress indicators show gradual change from 1984 to

present– Considered risk to be high– Analysis based on engineering judgment

Page 23: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

2. Screening Portfolio Risk 2. Screening Portfolio Risk AssessmentAssessment

2. Screening Portfolio Risk Assessment– In-house Corps expertise– Reviewed MRR and other data– Purpose to determine ranking in severity

of Corps dams– Placed Wolf Creek in the “Urgent and

Compelling” category

Page 24: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

3. Independent Peer 3. Independent Peer Review PanelReview Panel

3. Independent Peer Review Panel– Independent Consultants– Purpose to validate the SPRA process and

review projects in the “Urgent and Compelling”category

– Recommended immediate operating restrictions at Wolf Creek

– Considered risk to be high– Analysis based on engineering judgment

Page 25: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

Reliability ResultsReliability Results

All three studies conclude the project is deficient.Immediate measures should be taken to reduce the risk.Some of them can be implemented without serious negative impact.

Page 26: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

Risk Risk ReductionReduction

ActionsActions

Page 27: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

Interim Risk Mitigation Interim Risk Mitigation MeasuresMeasures

Dam Safety ProgramMonitoring 24/7Increased instrumentationEnhanced and aggressive EAP processPublic MeetingsIndependent Expert PanelStockpiling material

Page 28: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

Risk Reduction Risk Reduction ActionsActions

• Trigger Events that Would RequireEmergency Drawdown• Significant abnormal instrumentation readings• Sinkholes or settlement in the dam• Muddy flows• Slide in the dam slope

• Modified Lake Level Operation

Page 29: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

Operating RestrictionsOperating RestrictionsLower the Lake = Lower the RiskLower the Lake = Lower the Risk

This decision comes with a cost.The benefits derived from the project diminish as the lake is lowered.How do you make the decision which balances lowered risk with lost benefits.

Page 30: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

Project Benefits AndProject Benefits AndLake Level Target ZoneLake Level Target Zone

• Flood Control • Average annual flood damages prevented

= $34 million• Hydropower

• $77 million / year• Recreation

• 5 million visitors per year• $159 million impact on local economy

• Water Supply• Water Quality• Navigation

Page 31: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

4. Probability of Failure/ 4. Probability of Failure/ Operational RestrictionsOperational Restrictions

4. RAC Engineers and Economists Study (Operating Restrictions) Utah State U. Initiated before Peer Group.– Used risk assessment methodology to

determine effect on risk of various operating restrictions

– Preliminary ‘bounding analysis’ showed unacceptable level of risk

– Uses process similar to ‘expert elicitation’ to quantify engineering judgment

Page 32: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

Alluvium

Wolf Creek Dam Section

Damage Progression

Dam Cutoff Trench

Piezometers

Catheys Formation

Liepers Formation

Grout Curtain

Rap

id T

ailw

ater

Fluc

tuat

ions

Dur

ing

Pow

er G

ener

atio

n =

surg

ing

1967

& 6

8 M

uddy

flow

an

d si

nk h

ole

1968 Emergency grouting program

1979 Diaphragm Walls Complete

RAC First Failure Scenario

The Event Tree

1. Pipe begins in rock and expands to alluvium

2. Pipe continues US to wall

3. Secondary element in wall fails

4. Pipe expands rapidly upstream through aluvium

5. Breach and failure

Page 33: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

0.00001

0.0001

0.001

0.01

0.1

Top

SEPA

Curre

nt

OR.PF7

20

OR.PF7

10

OR.PF7

05

OR.PF7

00

OR.PF6

90

OR.680

OR.610a

OR.562a

OR.610b

OR.562b

Prob

abili

ty o

f Fai

lure

(/ye

ar)

20% Confidence of not being exceeded 50%80% 20%50% 80%Limit for Individual Risk & USBR Public Protection Guideline

Annualized Annualized Probability of FailureProbability of Failure

Page 34: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

What Does This Mean?What Does This Mean?

None of the operating restriction meet the criteria for tolerable risk except those that require structural modification of project.These restrictions result in loss of annual benefits totaling $200 million.There are severe environmental consequences to these restrictions.Unforeseen consequences?

Page 35: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

Where Are We NowWhere Are We Now

Decision based on previous risk studies + impacts that result and health and safety concerns for upstream residents. (Water Intakes). Corporate decision not solely District jurisdiction.Operate the pool at 680 – flat.Incremental approach. If distress indicators improve and grouting proceeds, evaluate new operating level. If not, consider more severe restrictions.

Page 36: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

Not very accurately (my opinion) --Many ill-defined links in process:– variations in deterministic and probabilistic models – different methods of characterizing soil parameters− φ - c strength envelopes are difficult– slope is a system of slip surfaces- distributions of permeability and permeability ratio– difficult to quantify spatial correlation in practice– difficult to account for length of embankments– difficult to account for independence vs correlation of

multiple monoliths, multiple footings, etc.

Thomas F. Wolff, Ph.D., P.E.Michigan State University

“How accurately can Pr(f) be calculated?”

Thomas F. Wolff, Ph.D., P.E.Thomas F. Wolff, Ph.D., P.E.Michigan State UniversityMichigan State University

““How accurately can Pr(f) How accurately can Pr(f) be calculated?be calculated?””

Page 37: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

Construction CostsConstruction Costs

First Emergency Grouting $15 millionComposite Cut Off Wall $ 90 millionCurrent Emergency Grouting $50 millionFuture Cut Off Wall $250 million ±

Page 38: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

Impact CostsImpact Costs

Lost hydropower generation = $70 millionCost of extending launching ramps = $ 165KCost of extending water intakes = $ several millionLost revenue from recreation = $65 millionFish hatchery modifications $750K +Others

Page 39: Session 4 Economic Impacts of a Karst Foundation Wolf ......Project Benefits And Lake Level Target Zone ... 0.0001 0.001 0.01 0.1 T op R SE P A r e nt O R. P 0 O R P F 5 O R P O R

QuestionsQuestionsQuestions

E FSFS E X E X

E Xn

[ ]( [ ], [ ],... [ ])

=

1

2Var FSFS

XFS

X FSX

i X

ij X X

XX

i

ij

ij

[ ]

,

= ⎛⎝⎜ ⎞

⎠⎟

+ ⎛

⎝⎜⎜ ⎞

⎠⎟⎟

∂∂ σ

∂ ∂ρ

σ σ

2

2

2∂∂

FSX FS X

FS XXX

i i

iii

≈−

−+

−+−

( )( )

Var FS FS XFS X

i

i

[ ]( )

( )

=−

⎛⎝⎜

⎞⎠⎟

+

∑2 2