service installation specifications...3.homeowner / electrician to install "9s" meterbase...
TRANSCRIPT
SERVICE
INSTALLATION
SPECIFICATIONS
EFFECTIVE DATE: JANUARY 2020
P O Box 959 1009 East Main Street Brownsville, TN 38012
www.stemc.com Brownsville Jackson Covington Henderson Atoka
November 30, 2015
Dear STEMC Member and Contractors,
Over the years, STEMC has made many changes to its member requirements for new services and specifications associated
with those requirements. As a matter of consistency for members and contractors, STEMC has compiled and revised
several drawings used to aid members and their contractors installing facilities for new services.
ANY SPECIFICATION DRAWINGS OR DATED PRIOR TO SEPTEMBER 2015 WILL NOT BE HONORED.
In conjunction with this, STEMC has updated several OPERATIONAL PROCEDURES in an effort to bring STEMC more in-line
with other utility best practices. These revisions mutually benefit STEMC and the member.
OPERATING PROCEDURES WILL BECOME EFFECTIVE JANUARY 1, 2016.
If you have any questions regarding the changes, please contact myself or your local STEMC Engineering Coordinator.
Kind regards,
William V. Gordon, P.E. Vice President of Engineering SOUTHWEST TN EMC P.O. Box 959 | 1009 East Main Street Brownsville, TN 38012 (office) 731.585.0538 (fax) 731.772.103
Southwest TN EMC
Operating Procedure
Underground Residential Service
To: Engineering Coordinators
From: William V. Gordon
Date: November 30, 2015
Re: Underground Residential Service
Effective January 1, 2016, STEMC members (or their electrical contractor) shall install conduit to the
following specifications for underground secondary service. Remember to dial 811 three-days prior to any
digging.
Conduit shall be 3-inch PVC Schedule 80 above ground and PVC or HDPE Schedule 40 or 80
below ground. Conduit shall be installed at a minimum depth of 30-inches.
90s at STEMC point of feed and meterbase may be short sweeping (no plumbing fittings), but all
others shall be long sweeping. Two (2) 45s may be used at meterbase given a minimum 2-foot
section of straight conduit is installed between 45s. Conduit shall stop a minimum of 3-feet from
STEMCs point of feed (leave 90 and additional conduit on site) or contact STEMC to open point of
feed. Conduit shall have pull string installed throughout the entire length.
Contact your nearest STEMC office to schedule a ditch/conduit inspection. All conduits and
90s/45s shall be visible.
Point of feed may be considered a padmounted transformer, handhole, or pole.
If point of feed is pole, 1-stick of Schedule 80 PVC conduit shall be turned up at the pole
Southwest TN EMC
Operating Procedure
Underground Primary Extension
To: Engineering Coordinators
From: William V. Gordon
Date: November 30, 2015
Re: Underground Primary Extension
Effective January 1, 2016, STEMC members (or their electrical contractor) shall install 2-inch conduit for
the installation of primary cables. Conduit shall be installed per specification drawing TRD. Depending on
length of installation, STEMC may require placement of primary junction box to reduce pulling length. Direct
burial method may still be utilized at the discretion of STEMC Engineering.
Southwest TN EMC
Operating Procedure
Underground Secondaries for General Power Accounts
To: Engineering Coordinators
From: William V. Gordon
Date: November 30, 2015
Re: Underground Secondaries for General Power Accounts
Effective January 1, 2016, STEMC members (or their electrical contractor) shall install their own conduit
and secondary wiring to the point of feed (padmounted transformer, handhole, or pole) for general power
service. Conduit and secondary wiring shall be installed per specification drawing TDSEC. This includes
single and three-phase applications. For installations where point of feed is a padmounted transformer,
members (or their electrical contractor) shall be responsible for providing terminating lugs.
Single-phase general power accounts located on residential properties are exempt from providing
secondary wire to the point of feed, so long as they are not being used as a place of business. Example:
shops, gates, barns, pool houses are exempt.
CONTENTS
DRAWING TITLE (DESCRIPTION) PAGE
MBR SVC POLE ................................................................................................................................. 1
OH TEMP.......................................................................................................................................... 2
UG TEMP .......................................................................................................................................... 3
CT 1P ................................................................................................................................................ 4
CT 3P ................................................................................................................................................ 5
TD SEC .............................................................................................................................................. 6
TRD .................................................................................................................................................. 7
PM 1P SD ......................................................................................................................................... 8
PM 1P .............................................................................................................................................. 9
PM 3P 75-500 ................................................................................................................................ 10
PM 750-2500 ................................................................................................................................. 11
PBD ................................................................................................................................................ 12
PMC1 ............................................................................................................................................. 13
PMC2 ............................................................................................................................................. 14
TUCS .............................................................................................................................................. 15
URD STAKING ................................................................................................................................. 16
CONTACTS
ATOKA ENGINEERING ................................................................................................ (901) 622-0603
BROWNSVILLE ENGINEERING .................................................................................... (731) 585-0103
COVINGTON ENGINEERING ....................................................................................... (901) 622-0305
HENDERSON ENGINEERING ....................................................................................... (731) 520-0407
JACKSON ENGINEERING ............................................................................................ (731) 554-1206
5'-6"
SERVICE ENTRANCECONDUCTORS SHALL EXTEND 18"
FROM WEATHERHEAD WITHNEUTRAL MARKED IN WHITE.
5/8" x 8' GROUND RODBONDED TO GROUND WIRE
WITH CLAMP INSTALLEDBELOW GRADE.
EXIT CONDUIT LAYOUT WILLVARY BASED ON MEMBERNEEDS.
3000-PSI CONCRETE WITH MINIMUM48 HOUR CURE TIME.
16'
4'
DISCONNECT
METERBASE
CONDUIT STRAP
Southwest Tennessee ElectricMembership Corporation
A Touchstone Energy® Cooperative
MEMBER OWNED SERVICE POLE SPEC
JANUARY 2020 MBR SVC POLE
NOTES:1. Obtain approval for pole location and height from STEMC engineering prior to commencing work.
2. STEMC no longer issues permits. Contact local office for list of locations to obtain permits.
3. 20' pole with 6" minimum diameter shall be buried 4' below ground level. Any pole height other than 20'
must be approved by STEMC engineering.
4. Concrete shall be placed around pole, visible at ground level, and cured 48 hours.
5. Guy and anchor shall be set if service length is greater than 100', or as required by STEMC engineering.
6. Clearance to drip loop shall be a minimum of 12' above ground level. If service crosses driveways or public
streets minimum clearance could be extended up to 18'.
7. Service wire crossing a roof shall have minimum clearance of 8' where crossing.
8. STEMC provided eyebolt shall be installed 6" from top of pole.
ALL SERVICES SHALL MEET
NATIONAL ELECTRICAL CODE
STANDARDS.
1
36" RECOMMENDED MINIMUM
48" RECOMMENDED MINIMUM
GRADE
CONCRETE
GROUND ROD
60 AMP
MINIMUM
DISCONNECT
METERBASE
CONDUIT STRAP
SERVICE ENTRANCECONDUCTORS SHALL EXTEND 18"
FROM WEATHERHEAD WITHNEUTRAL MARKED IN WHITE.
Southwest Tennessee ElectricMembership Corporation
A Touchstone Energy® Cooperative
TEMPORARY OVERHEAD SERVICE DETAIL
JANUARY 2020 OH TEMP
NOTES:1. Use 3 - #6 service entrance conductors. must extend at least 18 inches from weatherhead.2. Minimum 1" conduit and weatherhead must extend to top of pole. Raceway may be rigid, EMT, IMC or
Schedule 40 PVC. EMT must have water tight fittings.3. A ground wire of #6 copper or larger shall be run, unspliced, from the meter socket to a driven ground
rod.4. A 6" x 6" square or 6" diameter (at top) round pole embed a minimum of 4 ft. below ground,
recommended with concrete placed around base. Minimum of 16' pole required.5. Point of attachement (eyebolt) must be of sufficient height ot provide proper clearance by NESC.6. Point of attachment must be mounted at or below weatherhead.7. Meter socket to be mounted not less than 5' and not more than 6' from ground.8. All 120/240 volt receptacles must be GFCI protected and have "in use" covers.9. An 8' x 5/8" ground rod bonded to ground wire with clamp sutiable for direct burial will be installed
below grade.
ALL SERVICES SHALL MEET
NATIONAL ELECTRICAL CODE
STANDARDS.
2
5'
8'
3'
6'
1 2 3 4
25
4' MAXIMUM
2'
DISCONNECT
METERBASE
Southwest Tennessee ElectricMembership Corporation
A Touchstone Energy® Cooperative
TEMP UNDERGROUND SERVICE DETAIL
JANUARY 2020 UG TEMP
NOTES:1. 8' Pole or timber with 4" minmum diameter shall be buried 3' below ground level.2. Backfill and tamp with clean native earth. Tamping shall provide sufficient support to set meter.
Unsecured temporaries will be truned down upon inspection.3. Service whip shall be a minimum of 6' in length when extended from pole. Whip shall be comprised of
flexible, non-metallic conduit, containing appropriately sized wire for disconnect.4. In addition to whip, conductor pigtail must extend 2 feet from end of flexible conduit.5. Coordinate transformer entry with local STEMC engineering.6. Temporary service pole must be set within 4 feet of existing STEMC padmount transformer.
ALL SERVICES SHALL MEET
NATIONAL ELECTRICAL CODE
STANDARDS.
3
CT "DOT TO THE POT/TRANSFORMER"
LINE SIDE
LOAD SIDE
36" MIN
36" MIN
1" NIPPLE
SERVICE ENTRANCE LAYOUT MAYVARY AS NEEDED.
CT
STEMC WILL PROVIDE SERVICE CONDUCTOR FORRESIDENTIAL MEMBERS. MEMBER TO PROVIDE CONDUIT.
Southwest Tennessee ElectricMembership Corporation
A Touchstone Energy® Cooperative
SINGLE PHASE 600 AMP INSTRUMENT RATED SERVICE
TYPICAL DETAIL
JANUARY 2020 CT 1P
NOTES:1. STEMC to provide "4s" meterbase and two "CTs."
2. Homeowner / Electrician to provide 36"x36"x12" minimum weatherproof enclosure with backplate and
locking provisions.
3. Homeowner / Electrician to install "4s" meterbase and 36" enclosure connected with 1 inch nipple.
4. Homeowner / Electrician to install CTs on backplate of 36" enclosure.
5. Polarity dot on CTs must be on line side of cable. See Figure 1.
6. Wiring from CTs to meter will be completed by STEMC.
7. OH or UG to be determined by load and transformer sizing per STEMC engineering.
8. Services larger than 600 amps will be required to be underground. These installations may need parallel
conduits and may need CTs to be placed at padmount transformer.
ALL SERVICES SHALL
MEET NATIONAL
ELECTRICAL CODE
STANDARDS.
FIGURE 1
4
PT
CT "DOT TO THE POT/TRANSFORMER"
LINE SIDE
LOAD SIDE
36" MIN
36" MIN
1" NIPPLE
SERVICE ENTRANCE LAYOUT MAYVARY AS NEEDED.
CT
PT
Southwest Tennessee ElectricMembership Corporation
A Touchstone Energy® Cooperative
THREE PHASE 600 AMP INSTRUMENT RATED SERVICE
TYPICAL DETAIL
JANUARY 2020 CT 3P
ALL SERVICES SHALL
MEET NATIONAL
ELECTRICAL CODE
STANDARDS.
NOTES:1. STEMC to provide "9s" Meterbase, 3 "CTs," and 3 "PTs" if necessary. (PTs only on 277/480 installations).
2. Homeowner / Electrician to provide 36"x36"x12" minimum weatherproof enclosure with backplate and
locking provisions.
3. Homeowner / Electrician to install "9s" meterbase and 36" enclosure connected with 1 inch nipple.
4. Homeowner / Electrician to install CTs on backplate of 36" enclosure.
5. Polarity dot on CTs must be on line side of cable. See Figure 1.
6. Wiring from CTs and PTs to meter will be completed by STEMC.
7. OH or UG to be determined by load and transformer sizing per STEMC engineering.
8. Services larger than 600 amps will be required to be underground. These Installations may need parallel
conduits and may need CT's to be placed at padmount.
FIGURE 1
5
GRADE
3" CONDUITQTY DETERMINED
BY MEMBERS NEEDS.
WARNINGTAPE
CLEAN FILL
FINAL
STEMC PRIMARY
SECTION A-A'
A
A'
COORDINATE FINAL INSTALL WITHSTEMC. OBSERVE APPLICABLE OSHAMINIMUM APPROACH STANDARDSAT ALL TIMES.
12"
18"
CONTRACTOR TO LEAVE6 FT. OF SECONDARY
(MINIMUM) FOR STEMCCONNECTION TO THE
TRANSFORMER
TELEPHONE ORCABLE TV
CONDUIT TO CONFORM TOLATEST NESC AND NEC
REQUIREMENTS.
STANDOFF BRACKETS, MACHINE BOLTS,WASHERS, LOCK NUTS , AND LAG SCREWS
PROVIDED BY STEMC (NOT PROVIDED IFSINGLE CONDUIT IS INSTALLED).
36" APPROX.
40" MINIMUM
Southwest Tennessee ElectricMembership Corporation
A Touchstone Energy® Cooperative
TRENCH AND RISER DETAIL FOR
MEMBER OWNED
UNDERGROUND SECONDARY
JANUARY 2020 TD SEC
NOTES:1. All conduit above final grade to be schedule 80 pvc or rigid steel.
2. All conduit below final grade to be pvc or hdpe (schedule 40 or 80).
3. Backfill with clean native earth and machine tamp.
4. The State of Tennessee requires a rough-in inspection on trench for member owned secondaries. This
applies to commercial general power accounts. This does not apply to STEMC installed residential
secondaries.
6
30"
(3) 2" CONDUIT
WARNING
TAPE
CLEAN
FILL
FINAL GRADE
42"
12"
A
A'
SECTION A-A'
STANDOFF BRACKET, MACHINE BOLT, WASHER,
LOCK NUT, AND LAG SCREW PROVIDED BY STEMC
(NOT PROVIDED IF A SINGLE CONDUIT IS INSTALLED).
FRONT VIEW
SIDE
VIEW
Southwest Tennessee ElectricMembership Corporation
A Touchstone Energy® Cooperative
TRENCH AND RISER DETAIL FOR 1Ø / 3Ø
PRIMARY CONDUIT INSTALLATION
JANUARY 2020 TRD
NOTES:1. Trench shall be inspected by STEMC engineering before backfilling.
2. Backfill with clean native earth and machine tamp.
3. Install string ("mule tape" preferred") with minimum rating of 2,500 lbs in conduit and cover ends to keep
out water.
4. Schedule 80 pvc conduit shall extend 10 feet above final grade, unless point of feed is an underground
device.
5. Conduit below final grade shall be pvc or hdpe (schedule 40 or 80).
6. Minimum 36 inch sweeping elbows shall be used. Rigid elbows may be required, as determined by STEMC
engineering.
7
44"
12"
27"
2" PRIMARY
FIBERGLASS TRANSFORMER PAD
STEMC PROVIDED MARKINGPOST FOR ELECTRICIAN CONNECTION
(SEE FIGURE 1).
20"
PROPERTY LINE
FRONT OF PAD
ROADSIDE
2" PRIMARY
3" SECONDARY SERVICE
3" SECON
DARY TO JU
NCTIO
N BO
X
UNGLUED CAP
6"
FIGURE 1
3" SECONDARY SERVICE
CON
DUIT M
ARKER WITH STEM
C STICKER
FRONT PROPERTY LINE
RESIDENTIAL / SUBDIVISIONS
BACK OF EASEMENT
Southwest Tennessee ElectricMembership Corporation
A Touchstone Energy® Cooperative
FIBERGLASS PAD DETAIL FOR SINGLE PHASE(1Ø)PAD-MOUNT TRANSFORMER
JANUARY 2020PM 1P SD(UF1.FG)
NOTES:1. Transformer pad is to be centered on property line at 2 feet from back of easement.2. Conduit is to be bundled at 3/4 distance from left side of conduit opening with primary conduits on the
left and secondary conduits on the right as shown above.3. Conduits markers will be provided by STEMC to mark the secondary conduit stubs.4. Install string ("mule tape" preferred") with minimum rating of 2,500 lbs in primary conduit and cover ends to
keep out water.
8
48"
52"
33"
12"
28"
6" MIN FINAL GRADE
#4 RE-BAR
SECTION A-A'
A'A
FRONT OF PAD
CONCRETE TRANSFORMER PAD
21"
3" SECONDARY SERVICE
2" PRIMARY
8' GROUND ROD
STEMC PROVIDED MARKINGPOST FOR ELECTRICIANCONNECTION
(SEE FIGURE 1).
UNGLUED CAP
6"
34" CHAMFER
CON
DUIT M
ARKER WITH STEM
C STICKER
FIGURE 1
COMMERCIAL / GENERAL POWER
Southwest Tennessee ElectricMembership Corporation
A Touchstone Energy® Cooperative
CONCRETE PAD DETAIL FOR SINGLE PHASE(1Ø)PAD-MOUNT TRANSFORMER
JANUARY 2020PM 1P(UF1-C)
NOTES:1. Pad shall be inspected by STEMC engineering before pouring concrete.
2. Ground beneath the transformer pad shall be leveled and thoroughly compacted.
3. The primary and secondary wire shall be positioned as shown in the drawing.
4. Install 5\8" ground rod as indicated.
5. Bond # 4 solid copper to re-bar and ground rod.
6. Fiber reinforcement can be used in lieu of re-bar.
7. The concrete's minimum 28 day compressive strength shall be 2500 psi.
8. Install string ("mule tape" preferred") with minimum rating of 2,500 lbs in primary conduit and cover ends to
keep out water.
9
PRIMARY
CONDUITS
SECTION A-A'
A'A
SECONDARY
CONDUITS
8 FT. GROUND ROD
FINAL GRADE
72" SQUARE
12"15"18"
12" 48"
4" MAXIMUM HEIGHT
ON ANY CONDUIT
#4 RE-BAR
22"
6" MIN
1 2 3
4 5 6
FRONT OF PAD
CONCRETE TRANSFORMER PAD
12"
COMMERCIAL / GENERAL POWER
34 CHAMFER
GROUND ROD(NOTE 3)
SERVICECONDUITS(NOTE 2)
Southwest Tennessee ElectricMembership Corporation
A Touchstone Energy® Cooperative
CONCRETE PAD DETAIL FOR 75-500 kVA, THREE-PHASE(3Ø)PAD-MOUNT TRANSFORMER
JANUARY 2020PM 3P 75-500(UF3-C75-500)
NOTES:1. Pad shall be inspected by STEMC engineering before pouring concrete.2. Ground beneath the transformer pad shall be level and thoroughly compacted.3. Service conduit positions are numbered according to location preference.4. Three 5/8" x 8' copper ground rods (copperweld or equal) shall be installed; one in primary
compartment of transformer, and two on the back side of the transformer pad. a #4 copper wire shallbe installed between ground rods and attached to each ground rod with a ground rod clamp.
5. Bond #4 solid copper to rebar and ground rod.6. 3-2" primary conduit to have min. 36" radius elbows and to be extended beyond edge of pad in
direction indicated by engineering. rigid elbows may be required, as determined STEMC engineering.7. The concrete minimum 28 day compressive strength shall be 2500 p.s.i.8. Install string ("mule tape" preferred") with minimum rating of 2,500 lbs in primary conduit and cover ends
to keep out water.
10
#4 RE-BAR ON 18" CENTERS
9 10
7 1 2 5
6438
108" SQUARE
22" 24"
11"20"
A'A
SECTION A-A'
4" MAXIMUMHEIGHT ON ANY
CONDUIT
PRIMARYCONDUITS
SECONDARYCONDUITS
8 FT. GROUND ROD
FINAL GRADE
FRONT OF PAD
CONCRETE TRANSFORMER PAD GROUND ROD(NOTE 3)
SERVICECONDUITS(NOTE 2)
5"5"
5"
5"
5"
COMMERCIAL / GENERAL POWER
34 CHAMFER
24"
2"
Southwest Tennessee ElectricMembership Corporation
A Touchstone Energy® Cooperative
CONCRETE PAD DETAIL FOR 750-2500 kVA,THREE-PHASE(3Ø) PAD-MOUNT TRANSFORMER
JANUARY 2020PM 750-2500
(UF3-C750-2500)
NOTES:1. Pad shall be inspected by STEMC engineering before pouring concrete.2. Ground beneath the transformer pad shall be level and thoroughly compacted.3. Service conduit positions are numbered according to location preference.4. Three 5/8" x 8' copper ground rods (copperweld or equal) shall be installed; one in primary
compartment of transformer, and two on the back side of the transformer pad. a #4 copper wire shallbe installed between ground rods and attached to each ground rod with a ground rod clamp.
5. Bond #4 solid copper to rebar and ground rod.6. 3-2" primary conduit to have min. 36" radius elbows and to be extended beyond edge of pad in
direction indicated by engineering. rigid elbows may be required, as determined STEMC engineering.7. The concrete minimum 28 day compressive strength shall be 2500 p.s.i.8. Install string ("mule tape" preferred") with minimum rating of 2,500 lbs in primary conduit and cover ends
to keep out water.
11
FRONT OF PAD
REQUIRED BOLLARDS
POSSIBLE ADDITIONAL
BOLLARD LOCATIONS
(AS REQUIRED BY STEMC).
BOLLARD LOCATION
SECTION A-A'
A'A
BACKFILL HOLE
WITH CONCRETE.
72"
36"
36"
18"
18"
4" DIA. STEEL POST
FILLED WITH CONCRETE.
Southwest Tennessee ElectricMembership Corporation
A Touchstone Energy® Cooperative
PROTECTIVE BOLLARD DETAIL
JANUARY 2020 PBD 12
//
20'
15'
10'
10'
10'
6'
4'
4'
4'
Padmount Transformer
Southwest Tennessee ElectricMembership Corporation
A Touchstone Energy® Cooperative
CLEARANCE SPECIFICATIONS FOR PAD MOUNTEDTRANSFORMERS
JANUARY 2020 PMC1
NOTES:1. Clearances from padmout transformer to structures are measured from the nearest metal portion of
the transformer to the structure or any over hang.
13
X
X
X X X X X
FRONT OF PAD
TRANSFORMER PAD
FENCES OR OTHER OBSTACLES
OBS
TRU
CTIO
N
OBS
TRU
CTIO
N
BUILDING
8' MIN
4' MIN
4' MIN4' MIN
Southwest Tennessee ElectricMembership Corporation
A Touchstone Energy® Cooperative
CLEARANCE SPECIFICATIONS FOR PAD MOUNTEDTRANSFORMERS
JANUARY 2020 PMC2
NOTES:1. These clearances are STEMC minimums. Greater clearances may be requried by local codes, due to
building construction, type of operation, location of doors and windows, etc. Check with local inspection
authority.
14
VALLEY GUTTER
2'5.5'5'2.5'7'
℄SIDEWALKPGL=TOP OF CURB
WAT
ER
GAS
TELE
PHO
NE
(BO
TH S
IDES
)
TELE
PHO
NE
(BO
TH S
IDES
)
SEW
ERFO
RCE
MAI
N
ELEC
TRIC
42"
MIN
. CO
VERA
GE
ELEC
TRIC
42"
MIN
. CO
VERA
GE
2'
15' UTILITYEASEMENT
15' UTILITYEASEMENT50' ROW
31' B. TO B.26 PAVEMENT 5'4.5'
9.5'9.5'5' 4.5'
7'2.5'5'5.5'
STO
RMDR
AIN
AGE
SAN
ITAR
YSE
WER
VARIES
⅊⅊
IN GENERAL, ELECTRIC IS INSTALLED ALONG ONE SIDE OF THE
ROADWAY AT EVERY OTHER LOT LINE WITH SECONDARY VOLTAGE
CROSSING TO THE OTHER SIDE OF THE ROADWAY, IN SOME INSTANCES,
PRIMARY CABLE AND TRANSFORMERS WILL BE REQUIRED ON BOTH SIDES
OF THE ROADWAY. (WG 13-AUG-2013)
50' ROW WITH UTILITIES CROSS SECTIONNOT TO SCALE
PADMOUNTEDXFMR
1/4" /FT. (TYP.)
LIGH
TIN
G
2.5'
Southwest Tennessee ElectricMembership Corporation
A Touchstone Energy® Cooperative TYPICAL UTILITIES CROSS SECTION JANUARY 2020 TUCS
NOTES:1. If ROW is not 50 ft, adjust distance from curb using URD Staking drawing to maintain distances from
back of easment.
15
13'
9'
15'
"STREET NAME"
PROPERTY LINE
JUNCTION BOX STAKE (IF REQUIRED)
TRANSFORMER/ HANDHOLE STAKE
BACK OF UTILITY EASEMENT
PROPERTY CORNER
CURB
PROPERTY LINE (ROW)STREET LIGHT STAKE (IF REQUIRED)
2'
Southwest Tennessee ElectricMembership Corporation
A Touchstone Energy® Cooperative
UNDERGROUND ELECTRIC STAKING REQUIREMENTS
JANUARY 2020 URD STAKING
NOTES:1. Any requested street light locations shall be staked 2 feet away from the curb in line with the members
property line.
2. All junction boxes shall be staked 9 feet away from the property corner on the member's property line.
3. All transformers and handholes shall be staked 13 feet away from the property corner on the member's
property line.
4. Property line starts at edge of ROW. 50 foot ROW is typical, 25 foot from centerline of road.
16