sersa flash butt welding & destressing system presented by martin benkler member of the board...
TRANSCRIPT
Sersa Flash Butt Welding & Destressing System
Presented by
Martin Benkler
Member of the Board Sersa(UK)Ltd
Cost reductions and push for higher productivity
• High output industrial type approach
• Integration of individual processes
• Concentration of various activities in the same time slots
• Reduction of amount of possesions and better usage
• Introduction of high quality and repeatable processes
Solution
• Welding and Destressing in one process
Animation Serstar
Loosening the rail fasteners
Preparation of the joints
Positioning of the Joints
Welding machine
• Highly mobile Road/Rail machines
• Ready to weld within minutes
• Hight output (up to 8 welds per hour or more)
• High precision and fast alignment system
• Recording of welding parameters of each weld
Serstar Mobile Flash Butt Welding System
Serstar Mobile Flash Butt Welding System in Operation including rough grinding
Clamping and Alignment
Recording of weld parameters
Temperature measurement and calculation of required elongation
Calculation according to•the stressfree temperature•rail temperature•the lenght of rail to be destressed
Marking of the required elongation
Operation of Sersa Destressing Equipment
Passing over of Serstar mobile flash butt welder
Retightening of rail fasteners
Final grinding and marking of welds
Recording
• Weld Inspection Form
• Destressing FormFlashbuttWeldingInspectionformSersaUKLogo30-8-04.pdf
DestressingFormsSersaUK15-9-04.pdf
Personnel on worksite
Working teams
Amount of operators Responsibility Remarques
1 2 Loosening of rail fasteners and provisional clamps
1 Person in Charge for Destressing (SERSA) 2 Inspectors from the German Federal Railways (DB) for welding and destressing1 Lookout
Total Personnel on worksiteProductive Sersa 15+1Supervision German (DB) 3
2 2 Preparation of rail ends
3 2 Positioning of rails
4 2 Operation of Sersa Destressing Equipment
5 2 Flash butt welding and rough grinding
6 4 Retightening of fasteners
7 1 + Team 1 Final grinding and marking of welds
Average site productivity
Basis
• Rail Length 120m
• Rail Profile UIC 60 E 2 Grade 260
• Temperature Difference average 7 ° C
• Rail Fasteners Type Vossloh
• Monobloc concrete sleepers
• Track ballasted and tamped(at least first tamping)
Productivity
2,5 to 3 hours for
1 km of track welded and destressed
Conclusion
A high productivity and thus lower cost can be
achieved by
• a production line approach
• an integration of various processes
• Use of high output machinery and processes
• Use of reproducable and as much as possible operator independant processes
• Very precise & thorough site planning and organisation