sersa flash butt welding & destressing system presented by martin benkler member of the board...

21
Sersa Flash Butt Welding & Destressing System Presented by Martin Benkler Member of the Board Sersa(UK)Ltd

Upload: rachel-stewart

Post on 29-Dec-2015

218 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Sersa Flash Butt Welding & Destressing System Presented by Martin Benkler Member of the Board Sersa(UK)Ltd

Sersa Flash Butt Welding & Destressing System

Presented by

Martin Benkler

Member of the Board Sersa(UK)Ltd

Page 2: Sersa Flash Butt Welding & Destressing System Presented by Martin Benkler Member of the Board Sersa(UK)Ltd

Cost reductions and push for higher productivity

• High output industrial type approach

• Integration of individual processes

• Concentration of various activities in the same time slots

• Reduction of amount of possesions and better usage

• Introduction of high quality and repeatable processes

Page 3: Sersa Flash Butt Welding & Destressing System Presented by Martin Benkler Member of the Board Sersa(UK)Ltd

Solution

• Welding and Destressing in one process

Animation Serstar

Page 4: Sersa Flash Butt Welding & Destressing System Presented by Martin Benkler Member of the Board Sersa(UK)Ltd

Loosening the rail fasteners

Page 5: Sersa Flash Butt Welding & Destressing System Presented by Martin Benkler Member of the Board Sersa(UK)Ltd

Preparation of the joints

Page 6: Sersa Flash Butt Welding & Destressing System Presented by Martin Benkler Member of the Board Sersa(UK)Ltd

Positioning of the Joints

Page 7: Sersa Flash Butt Welding & Destressing System Presented by Martin Benkler Member of the Board Sersa(UK)Ltd

Welding machine

• Highly mobile Road/Rail machines

• Ready to weld within minutes

• Hight output (up to 8 welds per hour or more)

• High precision and fast alignment system

• Recording of welding parameters of each weld

Page 8: Sersa Flash Butt Welding & Destressing System Presented by Martin Benkler Member of the Board Sersa(UK)Ltd

Serstar Mobile Flash Butt Welding System

Page 9: Sersa Flash Butt Welding & Destressing System Presented by Martin Benkler Member of the Board Sersa(UK)Ltd

Serstar Mobile Flash Butt Welding System in Operation including rough grinding

Page 10: Sersa Flash Butt Welding & Destressing System Presented by Martin Benkler Member of the Board Sersa(UK)Ltd

Clamping and Alignment

Page 11: Sersa Flash Butt Welding & Destressing System Presented by Martin Benkler Member of the Board Sersa(UK)Ltd

Recording of weld parameters

Page 12: Sersa Flash Butt Welding & Destressing System Presented by Martin Benkler Member of the Board Sersa(UK)Ltd

Temperature measurement and calculation of required elongation

Calculation according to•the stressfree temperature•rail temperature•the lenght of rail to be destressed

Page 13: Sersa Flash Butt Welding & Destressing System Presented by Martin Benkler Member of the Board Sersa(UK)Ltd

Marking of the required elongation

Page 14: Sersa Flash Butt Welding & Destressing System Presented by Martin Benkler Member of the Board Sersa(UK)Ltd

Operation of Sersa Destressing Equipment

Page 15: Sersa Flash Butt Welding & Destressing System Presented by Martin Benkler Member of the Board Sersa(UK)Ltd

Passing over of Serstar mobile flash butt welder

Page 16: Sersa Flash Butt Welding & Destressing System Presented by Martin Benkler Member of the Board Sersa(UK)Ltd

Retightening of rail fasteners

Page 17: Sersa Flash Butt Welding & Destressing System Presented by Martin Benkler Member of the Board Sersa(UK)Ltd

Final grinding and marking of welds

Page 18: Sersa Flash Butt Welding & Destressing System Presented by Martin Benkler Member of the Board Sersa(UK)Ltd

Recording

• Weld Inspection Form

• Destressing FormFlashbuttWeldingInspectionformSersaUKLogo30-8-04.pdf

DestressingFormsSersaUK15-9-04.pdf

Page 19: Sersa Flash Butt Welding & Destressing System Presented by Martin Benkler Member of the Board Sersa(UK)Ltd

Personnel on worksite

Working teams

Amount of operators Responsibility Remarques

1 2 Loosening of rail fasteners and provisional clamps

1 Person in Charge for Destressing (SERSA) 2 Inspectors from the German Federal Railways (DB) for welding and destressing1 Lookout

Total Personnel on worksiteProductive Sersa 15+1Supervision German (DB) 3

2 2 Preparation of rail ends

3 2 Positioning of rails

4 2 Operation of Sersa Destressing Equipment

5 2 Flash butt welding and rough grinding

6 4 Retightening of fasteners

7 1 + Team 1 Final grinding and marking of welds

Page 20: Sersa Flash Butt Welding & Destressing System Presented by Martin Benkler Member of the Board Sersa(UK)Ltd

Average site productivity

Basis

• Rail Length 120m

• Rail Profile UIC 60 E 2 Grade 260

• Temperature Difference average 7 ° C

• Rail Fasteners Type Vossloh

• Monobloc concrete sleepers

• Track ballasted and tamped(at least first tamping)

Productivity

2,5 to 3 hours for

1 km of track welded and destressed

Page 21: Sersa Flash Butt Welding & Destressing System Presented by Martin Benkler Member of the Board Sersa(UK)Ltd

Conclusion

A high productivity and thus lower cost can be

achieved by

• a production line approach

• an integration of various processes

• Use of high output machinery and processes

• Use of reproducable and as much as possible operator independant processes

• Very precise & thorough site planning and organisation