PHIN. SERA. Fabrication of a photo-injector for the CTF3 accelerator and for the NEPAL test stand. WP 4 of the JRA2 PHIN. Status of the construction of RF guns 2. Status of the construction of the NEPAL beamline. PHIN. SERA. 1.Status of the construction of the CTF3 photo-injector. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: SERA](https://reader035.vdocuments.us/reader035/viewer/2022062423/56814a8e550346895db79e82/html5/thumbnails/1.jpg)
PHINFabrication of a photo-injector
for the CTF3 acceleratorand for the NEPAL test stand
WP 4 of the JRA2 PHIN
1. Status of the construction of RF guns
2. Status of the construction of the NEPAL beamline
![Page 2: SERA](https://reader035.vdocuments.us/reader035/viewer/2022062423/56814a8e550346895db79e82/html5/thumbnails/2.jpg)
PHIN
1.Status of the construction of the CTF3 photo-injector
•Modification of the technical drawings of the gun upon a CERN requestdue to the insertion of photo-cathode transfer chamber (August)
All the cooling channels in the gun had to be re-designed
Makes difficult to support the gun
•Finalization of the technical drawings of the NEG envelop around the gun Strong collaboration with CERN is mandatory since the NEG coatingis done there=> drawings almost finished
![Page 3: SERA](https://reader035.vdocuments.us/reader035/viewer/2022062423/56814a8e550346895db79e82/html5/thumbnails/3.jpg)
PHIN
1. Status of the construction of the CTF3 photo-injector
•Modification of the magnetic design: 2 coils instead of 3No enough space for pumping with 3 coils
23
22
21
20
19
18
mm
mra
d)3000290028002700260025002400
Bz (G)
With a laser gaussian pulse
Solenoids ordered in June, one was modified in September taking into account the data of the CERN cooling system=> Should be delivered by the end of this month
![Page 4: SERA](https://reader035.vdocuments.us/reader035/viewer/2022062423/56814a8e550346895db79e82/html5/thumbnails/4.jpg)
PHINFabrication of a photo-injector
for the CTF3 acceleratorand for the NEPAL test stand
Ionic pump
Bucking coil
Focusing coil
Wave guide right RF gun output
![Page 5: SERA](https://reader035.vdocuments.us/reader035/viewer/2022062423/56814a8e550346895db79e82/html5/thumbnails/5.jpg)
PHINFabrication of a photo-injector
for the CTF3 acceleratorand for the NEPAL test stand
Modification from the initial drawing
1 Reduction of the cathode chamber
2 Migration of cooling pipes to the end of the gun
![Page 6: SERA](https://reader035.vdocuments.us/reader035/viewer/2022062423/56814a8e550346895db79e82/html5/thumbnails/6.jpg)
PHIN
1. Status of the construction of the CTF3 photo-injector
Construction of a cold model to valid RF simulations
History:• Ordered in March a test piece to check :-iris profile-roughness-mechanical accuracy• Test cavity received in AprilIris profile not satisfying, another item O.K.• Several tries later, order in beginning of June, foreseen delay: 8 W• Last piece received in November 4 th (the firm begins (we suspect) the work only in October)- Checking at LAL: general accuracy: 5 m, roughness: < 0,4 mRa , iris profile O.K.
Set up of the RF measurement apparatus begun the 14th
Duration: 2 months but we hope to order the final gun before the end of the year
![Page 7: SERA](https://reader035.vdocuments.us/reader035/viewer/2022062423/56814a8e550346895db79e82/html5/thumbnails/7.jpg)
PHIN
1. Status of the construction of the CTF3 photo-injector
Coupling aperture (before opening)
![Page 8: SERA](https://reader035.vdocuments.us/reader035/viewer/2022062423/56814a8e550346895db79e82/html5/thumbnails/8.jpg)
PHIN
1. Status of the construction of the CTF3 photo-injector
First half cavity with the holefor the photo-cathode
Central cavity
Last cavity with coupling holes
Cooling channels
![Page 9: SERA](https://reader035.vdocuments.us/reader035/viewer/2022062423/56814a8e550346895db79e82/html5/thumbnails/9.jpg)
PHIN
1. Status of the construction of the CTF3 photo-injector
Holes for NEG pumping
![Page 10: SERA](https://reader035.vdocuments.us/reader035/viewer/2022062423/56814a8e550346895db79e82/html5/thumbnails/10.jpg)
PHIN
2. Status of the construction of the NEPAL beam line
Laser :Ordered in JulyExpected at LAL in the end of this year
Preparation chamber :In progress in the LAL workshop
Beam-line : A possible design existA lot of drawing elements are readiesThe final studies are in expectation (lack of manpower)
![Page 11: SERA](https://reader035.vdocuments.us/reader035/viewer/2022062423/56814a8e550346895db79e82/html5/thumbnails/11.jpg)
PHINFabrication of a photo-injector
for the CTF3 acceleratorand for the NEPAL test stand
Short term program
1. RF measurements on the cold model final dimensions of cells and coupling holes
2. Ordered in December the two RF guns with a reserve on the final inner dimensions
3. NEG deposition Test of compatibility of SS/NEG (CERN specialists request) in the beginning of 06
3. First laser tests end of this year