seminar l b
TRANSCRIPT
-
8/8/2019 seminar L B
1/30
HIMANSHU VARUN CANDRAKAR
ROLL NO 214110019
04/10/2010 1
-
8/8/2019 seminar L B
2/30
` Introduction` Objectives
` Origin of line balancing
` Factors responsible for line balancing.
` Advantages and disadvantages.` Termonology
` Important parameters
` Steps of generalized algorithm
` Different method of line balancing problem
` Kilbridge and wester heuristics
` Solved example
` Balance of line in variety of ways
` References
04/10/2010 2
-
8/8/2019 seminar L B
3/30
` For smooth and efficient working of the assembly
line every work station should be assigned with
equal amount of work measured in terms of time
units, and this process of apportioning theassembly work among the operators is known as
assembly-line balancing.
` Line balancing is mainly associated with productlayout or flow shops.
04/10/2010 3
-
8/8/2019 seminar L B
4/30
04/10/2010 4
V1
-
8/8/2019 seminar L B
5/30
Slide 4
V1 V@RUN, 10/5/2010
-
8/8/2019 seminar L B
6/30
04/10/2010 5
-
8/8/2019 seminar L B
7/30
` To subdivide the station into several sub stations.
` Precedence relationships must be maintained
during allocating operations.
` To minimizes the total idle time.` To optimize the congestion.
` It ensures that the stages of production are co-
ordinated and bottleneck are avoided.
04/10/2010 6
-
8/8/2019 seminar L B
8/30
` Although the first assembly line was set up as early as
1913.
` Henry Ford was the pioneer in starting the first
assembly line for car manufacturing.` The line-balancing problem is probably the most
complicated problem faced by the engineer when
designing a production line.
` Recently this problem of line balancing has been
formulated analytically, and has drawn the attention of
those concerned with the science of management.
04/10/2010 7
-
8/8/2019 seminar L B
9/30
` If finished product is the result of many sequential
problem.
` Difference in production capacity of differentmachines.
` Cycle time required for workstation.
04/10/2010 8
-
8/8/2019 seminar L B
10/30
ADVANTAGES
` Uniform rate of production.
` Less work-in-process.
` Easy production control.
` Effective use of facilities.
` Less bottle necking.
DISADVANTAGES
` More capital intensive.` Low flexibility.
` Monotony of work for operators.
04/10/2010 9
-
8/8/2019 seminar L B
11/30
` Workstation
` Cycle time(C.T.)
C.T. =
` Work element
` Predecessor element
` Task time(t)- Standard time to perform
element task.` Station time(T)- Total standard work content
of specific workstation.
Productive time period
Production volume per period
04/10/2010 10
-
8/8/2019 seminar L B
12/30
04/10/2010 11
-
8/8/2019 seminar L B
13/30
` Line efficiency (L.E.)
L.E.= =
` Balance delay (B.D.)B.D. = 1 L.E.
total station time
C.T. no. of workstation
100 t
i=1
N
i
C.T. k
100
04/10/2010 12
-
8/8/2019 seminar L B
14/30
` Smoothness Index (S.I.)
S.I. = {(Max. station time station time of station i ) }
If S.I. = 0, means a perfect balance
k = total no of workstation
-
8/8/2019 seminar L B
15/30
Input: cycle time (C.T.),
precedence matrix,
total number of work elements(M),
work element times.
Initialize: unassigned cycle time(UACT) = CT,
station number (WS=1)
total number of assigned work element(N)=1
04/10/2010 14
-
8/8/2019 seminar L B
16/30
1) Print the station number(WS).
2) Initialize the total number of assigned work element counter to one, i.e. i=1.
3) If the i th work element is not assigned and all immediate precedors of the i
th work element are assigned or no immediate precedors, then go to step4,
otherwise go to step 6.
4) If the i th work element time is less than or equal to the unassigned cycle
time(UACT), then go to step5, otherwise go to step6.
5) Include the i th work element in the list A.
6) Increment the total number of assigned work elements counter by one, i.e. i
=i +1
7) Ifi M, then go to step 3; otherwise go to step 8.
8) If the number of work elements in the list A is more than 0,then go to step
10; otherwise go to step 9.
04/10/2010 15
-
8/8/2019 seminar L B
17/30
9) Perform the following and then go to step 2.a) Update UACT = CT
b) Update WS = WS+1
c) PrintWS
10) If the number of work element in the list A is equal to one, then assign that
work element to the current station; otherwise select a work element from
list A using a given HEURISTIC.
11) Subtract the recently assigned work element time from UACT and print the
recently assigned work elements number.
12) Update N =N +1
13) If N M, then go to step 2; otherwise go to step 14
14) Compute B.D. in percentage.15) Stop.
04/10/2010 16
-
8/8/2019 seminar L B
18/30
7 8
9 12
1110
6
54
32
1
5
43
3 6
5 1
4 4
2 6
7
Work element
Element time
04/10/2010 17
-
8/8/2019 seminar L B
19/30
Station no. List A Work element assigned UACT
1 - - 11
1 1 6
2,4 4 32,5 2 0
2 - - 11
3,5 3 7
5,6 5 1
- - 1
3 - - 11
6 6 6
7,9,10 10 2
7,9,11 7 0
4 - - 11
8,9,11 8 5
9,11,12 11 1
9,12 9 0
5 - - 11
1) Print the station number(WS).
2) Initialize the total number of assigned work element counter to one, i.e. i=1.
3) If the i th work element is not assigned and all immediate precedors of the i
th work element are assigned or no immediate precedors, then go to step4,otherwise go to step 6.
4) If the i th work element time is less than or equal to the unassigned cycle
time(UACT), then go to step5, otherwise go to step6.
5) Include the i th work element in the list A.
6) Increment the total number of assigned work elements counter by one, i.e. i
=i +1
7) Ifi M, then go to step 3; otherwise go to step 8.
8) If the number of work elements in the list A is more than 0,then go to step
10; otherwise go to step 9.
9) Perform the following and then go to step 2.
a) Update UACT = CT
b) Update WS = WS+1
c) PrintWS
10) If the number of work element in the list A is equal to one, then assign that
work element to the current station; otherwise select a work element from
list A using a given HEURISTIC.
11) Subtract the recently assigned work element time from UACT and print the
recently assigned work elements number.
12) Update N =N +113) If N M, then go to step 2; otherwise go to step 14
14) Compute B.D. in percentage.
15) Stop.
04/10/2010 18
-
8/8/2019 seminar L B
20/30
04/10/2010 19
-
8/8/2019 seminar L B
21/30
04/10/2010 20
-
8/8/2019 seminar L B
22/30
7 8
9 12
1110
6
54
32
1
5
43
3 6
5 1
4 4
2 6
7
Work element
Element time
04/10/2010 21
-
8/8/2019 seminar L B
23/30
7 8
9 12
1110
6
54
32
1
5
43
3 6
5 1
4 4
2 6
7
1 2 3 4 5 6 7
04/10/2010 22
-
8/8/2019 seminar L B
24/30
t C.T. t
t = 7
t =5+3+4+3+6+5+2+6+1+4+4+7
= 50
7 C.T. 50
C.T. = =
=10.9 11
max
max
i=1
i=1
N
N
i
i
Productive time period
Production volume per period
8 60
44
04/10/2010 23
-
8/8/2019 seminar L B
25/30
7 8
9 12
1110
6
54
32
1
5
43
3 6
5 1
4 4
2 6
7
WS-1WS-2 WS-3 WS-4 WS-5
04/10/2010 24
-
8/8/2019 seminar L B
26/30
WORKSTATION 1 2 3 4 5
TIME (min) 11 10 11 11 7
Line efficiency = =
= 90.9%
Smoothness index = {(Max. station time station time of station i ) }
= { (11-11) + (11-10) + (11-11) + (11-11) + (11-7) }
= 4.123
t ii=1
N
C.T. k 100
11 5
50
1/22
i=1
k
2 2222 1/2
04/10/2010 25
-
8/8/2019 seminar L B
27/30
Balance delay = 1 L.E. = 1-O.909
= 0. 091
i.e. 9.1%
Idle time = (11-11) + (11-10) + (11-11) + (11-11) + (11-7)
= 5
Idle time % = (5/11) 100
= 45.45%
04/10/2010 26
-
8/8/2019 seminar L B
28/30
` Diamond star motor automobile manufacturing facility has achieved
balanced assembly lines through traditional analysis combined with a highly
automated material system.
` Sun micro system has expended production facility balances lines with a
more modular approach using torque conveyor to drive the materialhandling system.
` At asheville,Westinghouse has five separate assembly lines balanced by
one common feeder mini plant and one master storeroom.
04/10/2010 27
-
8/8/2019 seminar L B
29/30
` A Comparative Evaluation of Assembly Line BalancingHeuristics, by S. G Ponnambalam, P. Aravindan 2 and G.Mogileeswar Naidu.
` A survey on problems and methods in generalized assembly
line balancing, by Christian Becker and Armin Scholl.
` Industrial engineering and production management, bymartand telsang.
` Production and operation management, by R. paneerselvam.
` A Genetic Algorithm for Bin Packing and Line Balancing, byE.Falkenauer and A.Delchambre.
04/10/2010 28
-
8/8/2019 seminar L B
30/30
04/10/2010 29